This document outlines the quality assurance kick-off meeting for Rapid Legal's new Orange County eFiling and eService product. It discusses the QA goals of ensuring the product performs as expected and delivers customer satisfaction. It then details the various testing tasks like unit, integration, regression, and user acceptance testing that will be performed on the customer portal, gateway, and corporate website. Responsibilities are assigned and the testing environments, processes, and project timeline are defined. The goal is to start testing on December 10th and complete all testing before the planned go-live date of December 31st.
1. December 10, 2012
Interim QA Lead: Joe Richards
Quality Assurance Kick-off Meeting
for the Orange County eFiling and eService Product
2. Agenda
• Quality Assurance Goal
• Tasks and Test Areas
• Team Roles and Responsibilities
• Testing Environment
• Test Processes
• Details and Project Snapshot
3. Goal
External Goal:
Ensure Rapid Legal’s OC eFiling and eService product
performs as expected and delivers customer
satisfaction.
Internal Goal:
Ensure quality assurance testing is performed with
excellence by the project team.
8. Test Processes and Confirmation
• Test Cases
– QA will define and distribute each teams detailed test cases.
• Test Procedure
– Perform test cases defined, using your own test case copy, track
your results.
• Problem Reporting
– Report errors using Team Foundation Server bug reporting.
Provide detailed steps taken to produce bug and if needed,
screen shots. When bug has been resolved, you will be
prompted to test functionality.
9. Details
• When does this QA Plan start? Today
• When do I get testing documents? Today
• Daily Expectation? 10 to 15 orders per day
• When does it end? Beyond our go Live date: 12/31/2012
10. Project Snapshot
Task Team Start Date End Date
Unit Testing Unit Testing 12/03/2012 12/11/2012
OC eFiling / eService Testing Customer Service 12/10/2012 12/28/2012
Existing Product Testing Operations 12/10/2012 12/28/2012
Corporate Website Testing Products Customer Service/Operations 12/12/2012 12/28/2012
Corporate Website Testing Content Stakeholders 12/12/2012 12/28/2012
Customer Testing Customer Service 12/17/2012 12/21/2012
Regression Testing Team 12/20/2012 12/21/2012
Smoke Testing Pre-Push Team 12/26/2012 12/28/2012
Smoke Testing Post-Push Team 12/29/2012 12/30/2012
Product Verification Team 12/29/2012 01/04/2013