                                                                                                                                                                                               Right-of-way
                                                                                                         KE NTH O R P E WAY
1                                                                                                                             4
                               Half “Green
                     Street” Improvements
                     S
                                Stormwater                                                                                                                                                     Entry Plaza &
                             Detention Area                                1                                3                                                                                  Demonstration
                                                                                    2                                                                                                          Area
                                                                                                                                                                                               Plant Staff Roof
                            Flex-space for                                                                                               5                                                     Garden
                        Materials Laydown
                                                                                                     ADMIN/OPS                  REFURBISHED
                                                                                                      BUILDING                  OPS BUILDING                                          PA R K W A Y
                                                                                                                                                                            R I V E R PA



                                                                                               WW
                            Project Boundary                                                 EQUALIZA-
                                                                                              TION &                                      7             OZONE
                                                                                             RECOVERY                                                  GENERATOR
                                                                                6
17                                                                                             AREA                                                                               DEWATERING
                                                                                                                                                                                   BUILDING                   EXISTING
                                                                                                                 FILTERS                                                                                      LAGOONS                                                       7
                                                                                                                                                                                                                                                  Trail secured
                                                                                                                                                           CHEMICAL                                                                               access
                                                                                                                                                           BUILDING
                            Native Woodland
                                     Screen                                                                                           BALLASTED
                                                                       8                                                             FLOCCULATION                                   GRAVITY
                                                                                                                                                                                   THICKENERS
                                                                                                                                         9


                                                        Stormwater                                                                                                                            10
                                                     Detention Area
                                                                                                           ELECTRICAL/GEN-                                                                                               Native Woodland
16                                                                                                       ERATOR MAINTENANCE                         HSPS                                                                 Screen
                                                                                                              BUILDING     11
                                                                                                                                                                                                                         Emergency Access
                                                                                                                                                                                                                         Road/Public Trail

                                                                                                                                                                           12
                                                                                                                                               CLEARWELL
                                                 Decorative low wall                                                                                                                                                     Accent Tree Row
                                                 for Screening (from                                                                   13
                                                   re-used material)
                                                                                                                                                                      14                             15
                                                                                                                                                                                                                         Flowering Trees                                    8

                                                         Half “Green                                                                                                                                                     Road/Trail with secured access
                                               Street” Improvements
                                                                                                                     16
                                                                                           17
                                                        Right-of-way
                                                                                        M APLE TO N DR I V E                       Fresh water pipe                                         Raw water pipe
15                                                                                                                                                                                                                                                  0     20’   40’   80’




14                                   13                                        12                                                              11                                                                           10                                              9




     LAKE OSWEGO - TIGARD WTP EXPANSION PROJECT | Conceptual Site Plan
     West Linn, OR                                                                                                                                                                                                                                                              October 27, 2011
Kenthorpe Stormwater Garden                                                                             Water Treatment Plant Entry Area




 1                               2                  3       4 Existing View                              5                                 6          7                            8




                                                                                                                          A
                                                                              KE N T HO RPE WAY
                                                                                                                                                                                        11
                                                                                                                 9                             10




                                                                                                                          A’
                                                    4




                                     Stormwater
                                      detention
                                        area
                                                                                                                                                                          5
                                            1           3

                                                                                                                                                                       Stormwater swale
                                                                                   Existing tree
                                                                                                                                                                       Stormwater swale crossing
                                                                                   Steps                                                                               Ramp                     6
                                                                                   Tree preservation seat wall                                                         Water feature
              Vegetation
               Screen                                                              Picnic niche
                                                                                   Stormwater swale




                                                2                                                                                                                                                8
                                                                                                                                                           7




                                                                                                                      ADMIN/OPS BUILDING            REFURBISHED OPS BUILDING                 0   5’   10’     20’




Kenthorpe Way “Green” Street Improvements

                                      ROW




                                                                        9                                            10                             11 Existing View
SECTION   A


                LAKE OSWEGO - TIGARD WTP EXPANSION PROJECT | Focus Area | Kenthorpe Entry Area
                 West Linn, OR                                                                                                                                                                        October 27, 2011
Mapleton Orchard
                                                                                          EXISTING LAGOONS
                 BALLASTED FLOCCULATION                        GRAVITY
                                                              THICKENERS




                                                                                                           C
                                                                                            6




                                                                                                           C’
                                                                                                           Trail
                                                                                                           Emergency access route
                                                                                                           Stormwater detention area
                                                                                                                                                    1                            2
                                    HSPS                                                                   Security wall


                                                                                                                                                    Trail/Emergency Access
                                                                                                           Native Woodland




                                                                                                           Low site wall from re-used
                                 Clearwell                                                                 concrete
 Meadow
                               (Underground)


                                                                                                           Existing tree



                                                                                                           Accent tree



                                                                                                           Split-rail fence
      B’




                                       Vegetation
                                        Screen                                                             Secured Trail/Road Access                SECTION   C
                                                                                 5
                         2                                1                                                Stormwater swale
                                   3
                                                                                  4
      B




                              Fresh water pipe                           Raw water pipe         M APLE TO N DR I V E          0   10’   20’   40’



Mapleton Drive “Green” Street Improvements

                                                    ROW




                                                                      3                                  4 Existing View                             5                       6
SECTION   B


              LAKE OSWEGO - TIGARD WTP EXPANSION PROJECT | Focus Area | Mapleton Orchard
              West Linn, OR                                                                                                                                                          October 27, 2011
Front Entry Area




     LAKE OSWEGO - TIGARD WTP EXPANSION PROJECT | Vignettes
     West Linn, OR                                            October 27, 2011
Mapleton Trail/Emergency Access




    LAKE OSWEGO - TIGARD WTP EXPANSION PROJECT | Vignettes
     West Linn, OR                                           October 27, 2011
Kenthorpe Operations Entrance




    LAKE OSWEGO - TIGARD WTP EXPANSION PROJECT | Vignettes
     West Linn, OR                                           October 27, 2011
Kenthorpe Pedestrian Entrance




    LAKE OSWEGO - TIGARD WTP EXPANSION PROJECT | Vignettes
     West Linn, OR                                           October 27, 2011
Kenthorpe Stormwater Area




    LAKE OSWEGO - TIGARD WTP EXPANSION PROJECT | Vignettes
     West Linn, OR                                           October 27, 2011
Fencing                                                                                                                                   Walls + Screens




 1                                 2                View from Plant Side of Fence       3             View from Plant Side of Fence       4                                    5

Split-rail Fence                 Good Neighbor Fence                                Good Neighbor Fence w/ Security Mesh              High Site Wall + Gate                   Lumber Screen




                                                                                    7
                                                                                                                      4




                                                                    3               5




                                                                                                                                      2
                                                                                                                            6



                                                                                                          1




                                                                                                                                                               Not to Scale




 1                                1                                                     2                                                 6                                    7
Split-rail Fence                 Split-rail Fence                                   Good Neighbor Fence                               Re-used concrete for Low Site Wall      Dry-stacked stone for Tree Preservation Wall

           LAKE OSWEGO - TIGARD WTP EXPANSION PROJECT | Site Security + Screening
            West Linn, OR                                                                                                                                                                                   October 27, 2011
1                                                   2                                                      3                                              4
Stormwater Treatment - Vegetated Swale, Kenthorpe   Stormwater Detention Area                           Pervious Paving - with adjacent Vegetated Swale   Green Roof - Intensive Roof Garden



                                                                                                        1

                                                                                       2            3




                                                                                                            4
                                                                                                                5



                                                                                              6

                                                                                                                         7




                                                                                                                8




 5                                                   6                                                      7                                              8

Green Roof - Extensive                              Stormwater Treatment - Vegetated Swale, Grass       Stormwater Detention Area                         Stormwater Treatment - Vegetated Swale, Mapleton

          LAKE OSWEGO - TIGARD WTP EXPANSION PROJECT | Stormwater Design
           West Linn, OR                                                                                                                                                                          October 27, 2011
1                                                                                                    2
Kenthorpe Way Looking East                                                                            Kenthorpe Way Looking West



                                                                                              1           KENTHORPE WAY
                                                                                                                              2




                                                                                11
                                                                                                                                            3




11                                                                              10                                                                                          3
Private Property on Northwestern Corner                                                                                                                                    View Along Eastern Side of Property
                                                                                                                                   5        4

                                                                                     9




                                                                                                  8                     7          6
                                                                                                             MAPLETON DRIVE
10                                                                                                                                                                          4

Wooded Area within Western Property Boundary                                                                                                                Not to Scale   View Out from East Property Corner




 9                                         8                                              7                                             6                                                       5
View from Private Property on West Side   Looking North from Southwest Corner            Looking West along Mapleton Drive             Southeast Property Corner                               View South along East Boundary


          LAKE OSWEGO - TIGARD WTP EXPANSION PROJECT | Surrounding Neighborhood
           West Linn, OR                                                                                                                                                                                         October 27, 2011
KENTHORP E WAY                                                KENTHORPE WAY




                              M A P LETON DRI VE                                           MAPLETON DRIVE

                                                                 Not to Scale                                Not to Scale




Existing                                                                        Proposed




      LAKE OSWEGO - TIGARD WTP EXPANSION PROJECT | Existing + Proposed Condition
       West Linn, OR                                                                                        October 27, 2011
VIEW LOOKING SOUTH AT MAIN PUBLIC ENTRY                    VIEW LOOKING WEST AT MAIN PUBLIC ENTRY




                                                                                           1            2                 3




                                                                                           4            5                 6




                                                                                                    PRIMARY MATERIALS MATRIX




                                          NON-PROCESS BUILDING STUDY
BIRDS EYE VIEW OF SOUTH EDGE OF     SOUTH EDGE BUILDING WALL ARTICULATION STUDY            VISUAL SCREEN CONCEPT
PLANT SHOWING GARDEN ROOFS




                                                                                  1         2                       4




                                                                             5        6                         8




                                                                                          PRIMARY MATERIALS MATRIX




                                  PROCESS BUILDING CONCEPT
EXISTING PLANT CONDITIONS                                                  NEIGHBORHOOD AESTHETIC CONTEXT




NORTH ELEVATION OF NEW OPERATIONS BUILDING
                                             REMODELED EXISTING BUILDING
Existing maintenance and truck
   loading area will now be located   S. Kenthorpe Way
   inside the plant, reducing
   associated impacts to neighbors.
                                                                            Dewatered solids loading
                                                                            will now be contained within
                                                                            a new Dewatering Building,
                                                                            reducing associated noise.




                                               All chemical deliveries are
                                               internal to plant facilities,
Where possible, all equipment                  screening associated visuals and
                                               noise. Delivery points are                     Existing basins will no longer
that is traditionally external to                                                             be used for solids drying.
buildings (HVAC fans, mixer                    designed with spill
                                               containment measures.                          Current noise associated with
motors, etc.) will be located                                                                 solids drying activities
within buildings to reduce                                                                    (engines, “backup” beeping,
external noise.                                                                               etc.) will no longer be needed
                                                                                              at the plant.

                                                                                              The remaining two lagoons
                                                                                              will only be used during
                                                                                              emergency operations.


                                        Mapleton Dr.
Current Treatment Process




                                                                                 TO WATER CUSTOMERS


                                   PUMP                                                                                    PUMP
                                                                                               CLEARWELL                  STATION
                                  STATION                                                       (UNDERGROUND)


                                                                     raw water




                                                                                   FLASH MIX
                SETTLING BASIN



                                   SETTLING BASIN



                                                    SETTLING BASIN




                                                                                                                FILTERS                        WASTE WATER
                                                                                 Coagulant and bleach                                           LAGOONS
                                                                                 are added.

                                                                                 CO2 and Powdered                               LIME SILO
                                                                                 Activated Carbon are
                                                                                                                                    Lime is
                                                                                 sometimes also added.
                                                                                                                                    added to
                                                                                                                                    regulate
                                                                                                                                    the pH.




                                                                                     Future Treatment Process




                                   PUMP
                                  STATION
    raw water




                                                                                                                                                      FILTERS

                                 SEDIMENT REMOVAL


                                                                                                                                             pH
                                                                                                                          BLEACH         ADJUSTMENT


COAGULANT


                                                     PUMP
TO WATER CUSTOMERS                                  STATION                                    CLEARWELL
                                                                                                 (UNDERGROUND)                                        MECHANICAL SOLIDS
                                                                                                                                                         DEWATERING
Benefits for West Linn

West Linn’s Water Supply

    Oregon City and West Linn jointly own South Fork Water Board (serves
                                                                       s
    54,000 people).

    Drinking water source: Clackamas River

    Treatment plant located in Oregon City in the Park Place
    Neighborhood. (Recently extensively upgraded and expanded).

    Water delivered through a 24-inch transmission main suspended on
    the I-205 Bridge.


Benefits of Partnership

    Lake Oswego’s water treatment plant serves as West Linn’s sole
    emergency and backup water source.

    The water treatment plant cannot deliver emergency supply year-round unless it is expanded through
    the partnership with Tigard.

    West Linn’s Water Master Plan (2008) explains West Linn does not currently have adequate storage to
    meet system-wide needs under emergency conditions.

    Improving the intertie with Lake Oswego is identified as the least expensive option to meet storage
    supply needs.

    West Linn ratepayers would save millions of dollars by avoiding construction of a new 8.4 million gallon
    reservoir.

    A larger underground reservoir for treated water (a clearwell) at the plant will allow water to be fully
    treated before it leaves the treatment plant – a key to providing high quality potable water to West Linn
    residents when needed.


                    West Linn Water System Master Plan (2008)
                    Table 6.3 System Wide Performance Requirement Summary
                    Year            Maximum     Fire       Total      Normal       Emergency     Normal     Emergency
                                    Daily       Flow       Supply     Supply       Supply        Supply     Supply
                                    Demand      (mg)       Need       Capacity     Capacity*     Deficit    Deficit (mg)
                                    (mg)                   (mg)       (mg)         (mg)          (mg)
                    Current         8.1         0.5        8.6        9.5          0             (0.9)      8.6
                    2015            8.6         0.5        9.1        9.5          0             (0.4)      9.1
                    2030            9.7         0.5        10.2       9.5          0             0.7        10.2
                    Saturation      10          0.5        10.5       9.5          0             1.0        10.5
                    Development


                    *Emergency supply capacity is the total available capacity of the City’s Lake Oswego Emergency
                     Intertie Pump Station, assumed to be 0 under maximum daily demand conditions.




Learn More!
South Fork Water Board: http://www.sfwb.org

Information about the emergency water intertie with Lake Oswego:
http://westlinnoregon.gov/publicworks/information-about-emergency-water-intertie-lake-oswego-water-system
Water Treatment Plant Project Timeline

GNP Development Period . . . . . . . . . . . . . . . . . . . . . . . . . . . Oct. 2010 – Dec. 2011

WTP Design Open House               . . . . . . . . . . . . . . . . . . . . . . . . . . . Oct. 27, 2011

Required Land Use Application Public Meeting . . . . . . . . . Nov. 10, 2011
Land Use Application Submittal                . . . . . . . . . . . . . . . . . . . . . Jan. 2012

Planning Commission Hearing . . . . . . . . . . . . . . . . . . . . . . . . Spring, 2012

Project Design        . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Spring 2011 – Spring 2013
Construction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Spring 2013 – Summer 2015



                                                                                             Lake Oswego · Tigard
                                                                                             Water Partnership
                                                                                             sharing water · connecting communities

Weitere ähnliche Inhalte

Andere mochten auch

BFM Directive S Murphy Week 3 2011
BFM Directive S Murphy Week 3 2011BFM Directive S Murphy Week 3 2011
BFM Directive S Murphy Week 3 2011wmpeed
 
Google Display nettverket for folkehøyskoler.
Google Display nettverket for folkehøyskoler. Google Display nettverket for folkehøyskoler.
Google Display nettverket for folkehøyskoler. Brede Ohnstad
 
תרשים לשון תת תפקודית
תרשים לשון תת תפקודיתתרשים לשון תת תפקודית
תרשים לשון תת תפקודיתנטע שפיר
 
ELSA Belgium (Partnership Presentation)
ELSA Belgium (Partnership Presentation)ELSA Belgium (Partnership Presentation)
ELSA Belgium (Partnership Presentation)belgiec
 

Andere mochten auch (7)

BFM Directive S Murphy Week 3 2011
BFM Directive S Murphy Week 3 2011BFM Directive S Murphy Week 3 2011
BFM Directive S Murphy Week 3 2011
 
Google Display nettverket for folkehøyskoler.
Google Display nettverket for folkehøyskoler. Google Display nettverket for folkehøyskoler.
Google Display nettverket for folkehøyskoler.
 
תרשים לשון תת תפקודית
תרשים לשון תת תפקודיתתרשים לשון תת תפקודית
תרשים לשון תת תפקודית
 
People
PeoplePeople
People
 
Jagannadham t smc
Jagannadham t smcJagannadham t smc
Jagannadham t smc
 
Housing
HousingHousing
Housing
 
ELSA Belgium (Partnership Presentation)
ELSA Belgium (Partnership Presentation)ELSA Belgium (Partnership Presentation)
ELSA Belgium (Partnership Presentation)
 

Ähnlich wie Robinwood Neighborhood Open House Presentation

Palm Springs Golf Guide
Palm Springs Golf GuidePalm Springs Golf Guide
Palm Springs Golf GuideEdwin Guerra
 
Sk 1020 terrace_(b)_page 01
Sk 1020 terrace_(b)_page 01Sk 1020 terrace_(b)_page 01
Sk 1020 terrace_(b)_page 01Radzuan Yaakob
 
20120904 oakland global petition photographic addendum
20120904 oakland global petition photographic addendum20120904 oakland global petition photographic addendum
20120904 oakland global petition photographic addendumCorrie Messinger
 
Source To Exhaust A4
Source To Exhaust A4Source To Exhaust A4
Source To Exhaust A4BarryMcLeod
 
Matthew Petrie - Partial Portfolio
Matthew Petrie - Partial PortfolioMatthew Petrie - Partial Portfolio
Matthew Petrie - Partial Portfoliomatthewcpetrie
 
Krisna portfolio2012
Krisna portfolio2012Krisna portfolio2012
Krisna portfolio2012putrimamesah
 
Bridgeport Multi-Magnet High School
Bridgeport Multi-Magnet High SchoolBridgeport Multi-Magnet High School
Bridgeport Multi-Magnet High Schooljlaposta
 

Ähnlich wie Robinwood Neighborhood Open House Presentation (9)

Palm Springs Golf Guide
Palm Springs Golf GuidePalm Springs Golf Guide
Palm Springs Golf Guide
 
Sk 1020 terrace_(b)_page 01
Sk 1020 terrace_(b)_page 01Sk 1020 terrace_(b)_page 01
Sk 1020 terrace_(b)_page 01
 
20120904 oakland global petition photographic addendum
20120904 oakland global petition photographic addendum20120904 oakland global petition photographic addendum
20120904 oakland global petition photographic addendum
 
Source To Exhaust A4
Source To Exhaust A4Source To Exhaust A4
Source To Exhaust A4
 
A.Mittman_Portfolio
A.Mittman_PortfolioA.Mittman_Portfolio
A.Mittman_Portfolio
 
Matthew Petrie - Partial Portfolio
Matthew Petrie - Partial PortfolioMatthew Petrie - Partial Portfolio
Matthew Petrie - Partial Portfolio
 
Krisna portfolio2012
Krisna portfolio2012Krisna portfolio2012
Krisna portfolio2012
 
Mapa folia
Mapa foliaMapa folia
Mapa folia
 
Bridgeport Multi-Magnet High School
Bridgeport Multi-Magnet High SchoolBridgeport Multi-Magnet High School
Bridgeport Multi-Magnet High School
 

Kürzlich hochgeladen

FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756dollysharma2066
 
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptxB.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptxpriyanshujha201
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒anilsa9823
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear RegressionRavindra Nath Shukla
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableDipal Arora
 
Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxWorkforce Group
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdfRenandantas16
 
How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityEric T. Tung
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...anilsa9823
 
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfDr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfAdmir Softic
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesDipal Arora
 
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyThe Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyEthan lee
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Dave Litwiller
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayNZSG
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMANIlamathiKannappan
 
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Dipal Arora
 
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...Any kyc Account
 
RSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataRSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataExhibitors Data
 

Kürzlich hochgeladen (20)

FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
 
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptxB.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear Regression
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
 
Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptx
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
 
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
 
How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League City
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
 
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfDr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
 
Mifty kit IN Salmiya (+918133066128) Abortion pills IN Salmiyah Cytotec pills
Mifty kit IN Salmiya (+918133066128) Abortion pills IN Salmiyah Cytotec pillsMifty kit IN Salmiya (+918133066128) Abortion pills IN Salmiyah Cytotec pills
Mifty kit IN Salmiya (+918133066128) Abortion pills IN Salmiyah Cytotec pills
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
 
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyThe Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 May
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMAN
 
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
 
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
 
RSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataRSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors Data
 

Robinwood Neighborhood Open House Presentation

  • 1.
  • 2. 2 3 4 5 6 Right-of-way KE NTH O R P E WAY 1 4 Half “Green Street” Improvements S Stormwater Entry Plaza & Detention Area 1 3 Demonstration 2 Area Plant Staff Roof Flex-space for 5 Garden Materials Laydown ADMIN/OPS REFURBISHED BUILDING OPS BUILDING PA R K W A Y R I V E R PA WW Project Boundary EQUALIZA- TION & 7 OZONE RECOVERY GENERATOR 6 17 AREA DEWATERING BUILDING EXISTING FILTERS LAGOONS 7 Trail secured CHEMICAL access BUILDING Native Woodland Screen BALLASTED 8 FLOCCULATION GRAVITY THICKENERS 9 Stormwater 10 Detention Area ELECTRICAL/GEN- Native Woodland 16 ERATOR MAINTENANCE HSPS Screen BUILDING 11 Emergency Access Road/Public Trail 12 CLEARWELL Decorative low wall Accent Tree Row for Screening (from 13 re-used material) 14 15 Flowering Trees 8 Half “Green Road/Trail with secured access Street” Improvements 16 17 Right-of-way M APLE TO N DR I V E Fresh water pipe Raw water pipe 15 0 20’ 40’ 80’ 14 13 12 11 10 9 LAKE OSWEGO - TIGARD WTP EXPANSION PROJECT | Conceptual Site Plan West Linn, OR October 27, 2011
  • 3. Kenthorpe Stormwater Garden Water Treatment Plant Entry Area 1 2 3 4 Existing View 5 6 7 8 A KE N T HO RPE WAY 11 9 10 A’ 4 Stormwater detention area 5 1 3 Stormwater swale Existing tree Stormwater swale crossing Steps Ramp 6 Tree preservation seat wall Water feature Vegetation Screen Picnic niche Stormwater swale 2 8 7 ADMIN/OPS BUILDING REFURBISHED OPS BUILDING 0 5’ 10’ 20’ Kenthorpe Way “Green” Street Improvements ROW 9 10 11 Existing View SECTION A LAKE OSWEGO - TIGARD WTP EXPANSION PROJECT | Focus Area | Kenthorpe Entry Area West Linn, OR October 27, 2011
  • 4. Mapleton Orchard EXISTING LAGOONS BALLASTED FLOCCULATION GRAVITY THICKENERS C 6 C’ Trail Emergency access route Stormwater detention area 1 2 HSPS Security wall Trail/Emergency Access Native Woodland Low site wall from re-used Clearwell concrete Meadow (Underground) Existing tree Accent tree Split-rail fence B’ Vegetation Screen Secured Trail/Road Access SECTION C 5 2 1 Stormwater swale 3 4 B Fresh water pipe Raw water pipe M APLE TO N DR I V E 0 10’ 20’ 40’ Mapleton Drive “Green” Street Improvements ROW 3 4 Existing View 5 6 SECTION B LAKE OSWEGO - TIGARD WTP EXPANSION PROJECT | Focus Area | Mapleton Orchard West Linn, OR October 27, 2011
  • 5. Front Entry Area LAKE OSWEGO - TIGARD WTP EXPANSION PROJECT | Vignettes West Linn, OR October 27, 2011
  • 6. Mapleton Trail/Emergency Access LAKE OSWEGO - TIGARD WTP EXPANSION PROJECT | Vignettes West Linn, OR October 27, 2011
  • 7. Kenthorpe Operations Entrance LAKE OSWEGO - TIGARD WTP EXPANSION PROJECT | Vignettes West Linn, OR October 27, 2011
  • 8. Kenthorpe Pedestrian Entrance LAKE OSWEGO - TIGARD WTP EXPANSION PROJECT | Vignettes West Linn, OR October 27, 2011
  • 9. Kenthorpe Stormwater Area LAKE OSWEGO - TIGARD WTP EXPANSION PROJECT | Vignettes West Linn, OR October 27, 2011
  • 10. Fencing Walls + Screens 1 2 View from Plant Side of Fence 3 View from Plant Side of Fence 4 5 Split-rail Fence Good Neighbor Fence Good Neighbor Fence w/ Security Mesh High Site Wall + Gate Lumber Screen 7 4 3 5 2 6 1 Not to Scale 1 1 2 6 7 Split-rail Fence Split-rail Fence Good Neighbor Fence Re-used concrete for Low Site Wall Dry-stacked stone for Tree Preservation Wall LAKE OSWEGO - TIGARD WTP EXPANSION PROJECT | Site Security + Screening West Linn, OR October 27, 2011
  • 11. 1 2 3 4 Stormwater Treatment - Vegetated Swale, Kenthorpe Stormwater Detention Area Pervious Paving - with adjacent Vegetated Swale Green Roof - Intensive Roof Garden 1 2 3 4 5 6 7 8 5 6 7 8 Green Roof - Extensive Stormwater Treatment - Vegetated Swale, Grass Stormwater Detention Area Stormwater Treatment - Vegetated Swale, Mapleton LAKE OSWEGO - TIGARD WTP EXPANSION PROJECT | Stormwater Design West Linn, OR October 27, 2011
  • 12. 1 2 Kenthorpe Way Looking East Kenthorpe Way Looking West 1 KENTHORPE WAY 2 11 3 11 10 3 Private Property on Northwestern Corner View Along Eastern Side of Property 5 4 9 8 7 6 MAPLETON DRIVE 10 4 Wooded Area within Western Property Boundary Not to Scale View Out from East Property Corner 9 8 7 6 5 View from Private Property on West Side Looking North from Southwest Corner Looking West along Mapleton Drive Southeast Property Corner View South along East Boundary LAKE OSWEGO - TIGARD WTP EXPANSION PROJECT | Surrounding Neighborhood West Linn, OR October 27, 2011
  • 13. KENTHORP E WAY KENTHORPE WAY M A P LETON DRI VE MAPLETON DRIVE Not to Scale Not to Scale Existing Proposed LAKE OSWEGO - TIGARD WTP EXPANSION PROJECT | Existing + Proposed Condition West Linn, OR October 27, 2011
  • 14. VIEW LOOKING SOUTH AT MAIN PUBLIC ENTRY VIEW LOOKING WEST AT MAIN PUBLIC ENTRY 1 2 3 4 5 6 PRIMARY MATERIALS MATRIX NON-PROCESS BUILDING STUDY
  • 15. BIRDS EYE VIEW OF SOUTH EDGE OF SOUTH EDGE BUILDING WALL ARTICULATION STUDY VISUAL SCREEN CONCEPT PLANT SHOWING GARDEN ROOFS 1 2 4 5 6 8 PRIMARY MATERIALS MATRIX PROCESS BUILDING CONCEPT
  • 16. EXISTING PLANT CONDITIONS NEIGHBORHOOD AESTHETIC CONTEXT NORTH ELEVATION OF NEW OPERATIONS BUILDING REMODELED EXISTING BUILDING
  • 17. Existing maintenance and truck loading area will now be located S. Kenthorpe Way inside the plant, reducing associated impacts to neighbors. Dewatered solids loading will now be contained within a new Dewatering Building, reducing associated noise. All chemical deliveries are internal to plant facilities, Where possible, all equipment screening associated visuals and noise. Delivery points are Existing basins will no longer that is traditionally external to be used for solids drying. buildings (HVAC fans, mixer designed with spill containment measures. Current noise associated with motors, etc.) will be located solids drying activities within buildings to reduce (engines, “backup” beeping, external noise. etc.) will no longer be needed at the plant. The remaining two lagoons will only be used during emergency operations. Mapleton Dr.
  • 18. Current Treatment Process TO WATER CUSTOMERS PUMP PUMP CLEARWELL STATION STATION (UNDERGROUND) raw water FLASH MIX SETTLING BASIN SETTLING BASIN SETTLING BASIN FILTERS WASTE WATER Coagulant and bleach LAGOONS are added. CO2 and Powdered LIME SILO Activated Carbon are Lime is sometimes also added. added to regulate the pH. Future Treatment Process PUMP STATION raw water FILTERS SEDIMENT REMOVAL pH BLEACH ADJUSTMENT COAGULANT PUMP TO WATER CUSTOMERS STATION CLEARWELL (UNDERGROUND) MECHANICAL SOLIDS DEWATERING
  • 19. Benefits for West Linn West Linn’s Water Supply Oregon City and West Linn jointly own South Fork Water Board (serves s 54,000 people). Drinking water source: Clackamas River Treatment plant located in Oregon City in the Park Place Neighborhood. (Recently extensively upgraded and expanded). Water delivered through a 24-inch transmission main suspended on the I-205 Bridge. Benefits of Partnership Lake Oswego’s water treatment plant serves as West Linn’s sole emergency and backup water source. The water treatment plant cannot deliver emergency supply year-round unless it is expanded through the partnership with Tigard. West Linn’s Water Master Plan (2008) explains West Linn does not currently have adequate storage to meet system-wide needs under emergency conditions. Improving the intertie with Lake Oswego is identified as the least expensive option to meet storage supply needs. West Linn ratepayers would save millions of dollars by avoiding construction of a new 8.4 million gallon reservoir. A larger underground reservoir for treated water (a clearwell) at the plant will allow water to be fully treated before it leaves the treatment plant – a key to providing high quality potable water to West Linn residents when needed. West Linn Water System Master Plan (2008) Table 6.3 System Wide Performance Requirement Summary Year Maximum Fire Total Normal Emergency Normal Emergency Daily Flow Supply Supply Supply Supply Supply Demand (mg) Need Capacity Capacity* Deficit Deficit (mg) (mg) (mg) (mg) (mg) (mg) Current 8.1 0.5 8.6 9.5 0 (0.9) 8.6 2015 8.6 0.5 9.1 9.5 0 (0.4) 9.1 2030 9.7 0.5 10.2 9.5 0 0.7 10.2 Saturation 10 0.5 10.5 9.5 0 1.0 10.5 Development *Emergency supply capacity is the total available capacity of the City’s Lake Oswego Emergency Intertie Pump Station, assumed to be 0 under maximum daily demand conditions. Learn More! South Fork Water Board: http://www.sfwb.org Information about the emergency water intertie with Lake Oswego: http://westlinnoregon.gov/publicworks/information-about-emergency-water-intertie-lake-oswego-water-system
  • 20. Water Treatment Plant Project Timeline GNP Development Period . . . . . . . . . . . . . . . . . . . . . . . . . . . Oct. 2010 – Dec. 2011 WTP Design Open House . . . . . . . . . . . . . . . . . . . . . . . . . . . Oct. 27, 2011 Required Land Use Application Public Meeting . . . . . . . . . Nov. 10, 2011 Land Use Application Submittal . . . . . . . . . . . . . . . . . . . . . Jan. 2012 Planning Commission Hearing . . . . . . . . . . . . . . . . . . . . . . . . Spring, 2012 Project Design . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Spring 2011 – Spring 2013 Construction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Spring 2013 – Summer 2015 Lake Oswego · Tigard Water Partnership sharing water · connecting communities