This document outlines the schedule and progress of a media studies advanced portfolio project. It includes tasks such as completing research, planning, rough cuts, final cuts, album covers, and posters. Deadlines are assigned to each task, and actual completion dates are tracked. The schedule also allows marking the progress of tasks as incomplete or completed. The final deadline for handing in the project is December 1st, 2009.
2. Outline of Project Schedule and
Progression Record
Task Predicted Date Actual Date
Completion Completed
Complete Research 24th July 2009
Complete Planning 10th September 2009
Complete Rough Cut 20th September 2009
Complete Final Cut 1st October 2009
Complete Album cover and Poster 15th October 2009
Final Album cover and Poster 31st October 2009
Audience Feedback 10th November 2009
Revisions & Corrections 20th November 2009
Evaluation 30th November 2009
First Hand In 1st December 2009
3. Research (completion date – 24th July 2009)
Task
Incomplete Completed
Survey / Questionnaire on the kind
of music avenue to peruse
Digipack research understanding
wide spectrum of methods used.
Research on the kinds of ways to
research target audiences and to
present data.
11. Evaluation
30th November 2009
Task
Incomplete Completed
12. First Hand In Checklist
1st December 2009
Task Predicted Date Actual Date
Completion Completed
Complete Research 24th July 2009
Complete Planning 10th September 2009
Complete Rough Cut 20th September 2009
Complete Final Cut 1st October 2009
Complete Album cover and Poster 15th October 2009
Final Album cover and Poster 31st October 2009
Audience Feedback 10th November 2009
Revisions & Corrections 20th November 2009
Evaluation 30th November 2009
Ready to hand in ? 1st December 2009
13. Review Changes From
1st December 2009 marking
Review Tasks Incomplete Completed
14. Final Deadline Checklist and
Additions Of Possible Extras For
Moderation ()
Task Predicted Date Actual Date
Completion Completed
Complete Research 24th July 2009
Complete Planning 10th September 2009
Complete Rough Cut 20th September 2009
Complete Final Cut 1st October 2009
Complete Album cover and Poster 15th October 2009
Final Album cover and Poster 31st October 2009
Audience Feedback 10th November 2009
Revisions & Corrections 20th November 2009
Evaluation 30th November 2009
First Hand In 1st December 2009