Solar Photovoltaic Proposal Page 1
15 KVA/10kw ON GRID SOLAR PV SYSTEM
PROPOSAL
Ref: EXALTA-SOLAR/16-17/PV/869569
Date 04 Oct 16
Sub: Comprehensive Proposal for 15 KVA Solar PV System.
With referencetoyour query,wearepleasedtosubmitherewithourcomprehensiveproposaloftheTechnical&Commercialoverview,foryourkindp
A. System Definition
Size
10 KW total DC capacity
40 nos. 250-Wattpanels (To be procured globally from leading international vendors like Photon Energy, BP Solar, Solar Semiconductor, Waree ,Euro Solar etc .)
Energy Production
Site location: Rajkot
Site Co-ordinates:…56/87
Tilt Angle: South30.3o
Average dradiation:5.62 kW-hours/m2/day
Number of full production days assumed per year:330
PV System Based Statistics:-
Expected Annual production:1.5 MW-hours(As per simulations)
Note: Energy production projections are reason ably accurate estimates based on site’s solar data and our experience with similar
systems.Energy makes no guarantees as to actual production output from this system.
Grid/Load Interfacing
Solar system outputs shall be connected to a suitable load bus capable of taking the input. This input point’s hall be selected infield.
In consultation with client’s Executive Engineer.
Solar Photovoltaic Proposal Page 2
B. System Components
Solar Panels
Note: Subject to availability at installation time, a different panel from
a Leading vendor may be selected without affecting system size and
Performance.
Make: Solar Semiconductor/Euro/Waree/Silicon Taxim
Model: SSI-M6-250
Quantity: 40
Wattage: 250W No. of Cells:60 Voc:37.1V
Isc: 8.28 A
Vmp: 29.6V
Imp: 7.6A
Dimensions: 1660X990X42(mm)
Weight:10kg
Operating Conditions:- 40to+90CMaximum
SystemVoltage:600Vdc
Inverter
Note: Subject to availability at installation time, a different inverter may
Be selected without affecting system size and performance.
SMA Livint German - Ongrid Solar MPPT Inverter
Quantity:2
AC maximum output: 6 KW MPPT
Maximum current input DC/String:20A Maximum efficiency:>98.1%
Power connection : 3-phase
We may take any other reputed make with efficiency> 95%.
Mounting Structures Panels shall be mounted on galvanized frames inclined at 30.3degrees to the
South. The structure is designed in such a manner that module can be replaced eas
to install and service in future. The frames will be supported by angle legs of
Suitable length stop provide the pre-determined inclination. All fasteners, nut
and bolts are made of Stainlesssteel-SS304 5.4.6 PCC. The structures shall be
pre-engineered to meet special requirements of placing the modules on the
Corrugated roof tops.
FOUNDATION BASE: The legs of the structures made with GI angles
are made of fixed and grouted in the PCC foundation Columns made with
1:2:4 cement concrete.
Electrical Accessories Cables will conform to IS694 and shall be of 650V/1.1k V grade.
Inter connections, array to junction boxes,
junction boxes to DCDB, DCDB to PCU
etc will be selected to keep voltage drop and
losses to the minimum. The bright annealed
99.97% pure bare copper conductors offer low
Conductor resistance,
Solar Photovoltaic Proposal Page 3
Result in lower heating thereby increasing cable life and efficiency. These
Wires are insulated with a special grade PVC compound formulated and
Manufactured in-house.
Working voltage: up to 1100 V Temperature range:-15 deg Cto+70degC
Sizes: Suitable sizes
Color codes: Red, Yellow, Black, Blue, Green
Battery NO
Energy Meter The Inverter shall have a built-in meter that tracks energy production and
Display sit on a small LED screen. The display can be used to determine
Real-time production, daily production, and yearly production. For more
sophisticated analysis and visual data management, Solar Access modules
Can be included.
Remote Monitoring System(optional) The sunny web box continuously records and stores all avails able data of
about 50 inverters in real time, in addition the inverter parameter scan be
requested and modified. It provides you with various modern data
processing options for professional data Management .These are save din
conventional CSV or XML file formats. The ability to exchange data by
FTP allows you to easily transfer these values to your. To your PC you can
Just as easily use an SD card to save your data any such feature of remote
monitoring shall be made available through additional costs.
Stringing Design 4 strings of 10 panels each, however a detailed engineering might Change
the stringing design. Incase Inverter configuration needs any modifications,
based on its availability, the string layout may be Modified accordingly.
Solar Photovoltaic Proposal Page 4
C. Bill of Material
S.No. Component Type/Model No
Specifications
Quantity
1 PV Modules SSI-M6-250 40
2 SMA Livint German ongridf Solar Inverter 7.5 KVA 2
3 Mounting Structure Custom made
MShotdipIRON
1 Set
4 Solar Battery 150AH, C10 Exalta
IP65standards
20
5 Main Junction Box ABB Junction Boxes
IP65standards
As per stringing design
6 Earthling Kit Reputed make 1 set
7 AC & DC cables Conforming to BOS As per site requirements
D. Solar PV Plot Plan
Solar Photovoltaic Proposal Page 5
E. Installation Details
Area required:
The Total Area required for the System Installation shall be approx 600 sq feet, without any shades, facing south.
Structural Anchoring:
Panels shall be mounted on galvanized frames inclined at 30.3 degrees to the south or 6 degree in movable structure. The structure is designed in such a m
be replaced easily and in line with site requirements and it is easy to install and service in future. The frames will be Supported by angle legs of
suitable lengths to provide the pre-determined inclination. All fasteners, nutand bolts are made of Stainless steel-SS304 5.4.6 PCC.
Foundation Base:
The legs of the structures made with GI angles are made of fixed and grouted in the PCC foundation columns made with 1:2:4 Cement concrete.
Actual frame and other structural dimensions will be determined during a more detailed site visit by specialists during full design phase.
Inverter Installation
This space provides sample accessibility and good air circulation. The inverter is available in IP54housing, however, an enclosed Space has to be
Provided for the same. Actual installation location and methods will be determined during full design phase.
Electrical
Proposed fire hoses haft will be used for running electrical cables down to the electrical panel room. A detailed electrical design with Single-line
Diagram and specifications will be prepared during full design phase after receiving the PO, for the client’s approval.
Solar Photovoltaic Proposal Page 6
F. Scope of Work
1. We shall conduct a detailed site visit with specialists to take accurate measurements, photographs, another site-specific in Formation
for full design.
2. Prepare full system design to include civil, structural, electrical and mechanical components, with construction drawings and
Specifications.
3. Procure equipment and materials and deliver to site.
4. Perform complete system installation.
5. Test all electrical components in accordance with manufacturer instructions.
6. Commission the system to full operability.
G. Client Scope
Site-specific considerations will require assistance and cooperation from the client, as outlined below:
1. Provide access to work site for delivery of equipment and materials prior to and during project implementation.
2. Provide a suitable and secure space for storage of equipment and materials.
3. Facilitate access of work crew to the work site 7 days a week.
4. Facilitate interfacing with the client’s resident engineering staff for consultation as needed.
5. Separate electrical loads as discussed in Part A (Grid Interfacing)and connect solar output to building load system.
6. All the Statutory clearances, if any, required for the Project.
H. Delivery Schedule & Project Cost
Installation & Commissioning
All the Systems except Inverter will be installed within 1- 8weeks from the date of receipt of advance and approval of the “SLD”.
Warranty
The Solar modules are warranted by the solar panel manufacturer for a period of 25 years. The details areas below.
1. Panels:
Manufacturing Warrantee for the System: 3yrs after installation and commissioning. Performance Warrantee:
a. 90% efficiency up to 12 yrs
b. 80% efficiency up to 25 yrs
2. Inverter: 5yrs
3. Battery: NO
4. Balance of the Systems: Standard 12 months warrantee against manufacturing defects. We shall also ensure supply of Spares for
the System if required.
Solar Photovoltaic Proposal Page 7
The final system size and quotation shall be finalized based on site visit and load conditions.
• Prices: Price quoted are FOR at site Delhi or nearby Delhi. for other reason transportation charges will be extra.
• Freight & Insurance: Not Included
• System Installation: System will be supplied and same will be installed by us. Installation Charges included.
• Excise Duty/Service Tax: Currently, under present rules, Solar Photo Voltaic system is exempted from Excise Duty. However, rate
Prevalent at the time of dispatch will be applicable extra, at actual.
• Service Tax extra at Actual will be charged, Presently Applicable @NA
• Octroi: Any Octroi /Entry tax, if any, will be pay able will be extra
• Sales Tax: VAT @5% will be charged extra without Form-C OR CST@2%
• Delivery : Dispatch will be effected in 1-8 weeks from the date of acceptance of your Purchase order.(P.O) .System
• Installation will be completed in 3 week’s time from date of receipt of materials at site, provided site is ready for installation.
• Payment Terms:
Total cost of the project is :- 6 Lakh
- First delivery of Solar panels against amount paid in advance. i.e 4 Lakh
- Inverter and rest of the matterial against rest of the payment i.e 1.5 Lakh
- Remaining 50000/- cheque ,after successful installation.
Technical Director : Er. Ashutosh Verma
9999890192
Whatsapp No: 9807465570
Date: 4 Oct, 2016
Version:#1
Contact:
Address :- A117 Atul chok Dwarika Mor Delhi 110059
Registered Office:-D734 Kamla Nagar Agra-282005
E:sales@exalta.inW:www.exlata.in
www.exalta.co.in
EXALTA LED
Insparc Technologies Pvt Ltd

Weitere ähnliche Inhalte

Was ist angesagt?

Engineering Drawings required for Solar Projects
Engineering Drawings required for Solar Projects Engineering Drawings required for Solar Projects
Engineering Drawings required for Solar Projects Gensol Engineering Limited
 
Drawings & Documents Required for Solar Projects
Drawings & Documents Required for Solar ProjectsDrawings & Documents Required for Solar Projects
Drawings & Documents Required for Solar ProjectsGensol Engineering Limited
 
Temelin power uprate
Temelin power uprateTemelin power uprate
Temelin power upratemyatom
 
Phases of Construction & Erection for Wind Power Project_03 09 2019
Phases of Construction & Erection for Wind Power Project_03 09 2019Phases of Construction & Erection for Wind Power Project_03 09 2019
Phases of Construction & Erection for Wind Power Project_03 09 2019Gensol Engineering Limited
 
Customer Success Story Bently Nevada* Asset Condition Monitoring
Customer Success Story Bently Nevada* Asset Condition MonitoringCustomer Success Story Bently Nevada* Asset Condition Monitoring
Customer Success Story Bently Nevada* Asset Condition MonitoringGE Measurement & Control
 
Key Projects List - DVLung
Key Projects List - DVLungKey Projects List - DVLung
Key Projects List - DVLungDarrin Lung
 
Nidec asi corporate energy efficient power solutions
Nidec asi corporate energy   efficient power solutionsNidec asi corporate energy   efficient power solutions
Nidec asi corporate energy efficient power solutionsNidec Corporation
 
Customer Success Story: Bently Nevada Asset Condition Monitoring
Customer Success Story: Bently Nevada Asset Condition MonitoringCustomer Success Story: Bently Nevada Asset Condition Monitoring
Customer Success Story: Bently Nevada Asset Condition MonitoringGE Measurement & Control
 
Nidec asi capability overview for oil&gas applications
Nidec asi capability overview for oil&gas applicationsNidec asi capability overview for oil&gas applications
Nidec asi capability overview for oil&gas applicationsNidec Corporation
 
Session 07 site assessment & planning
Session 07   site assessment & planningSession 07   site assessment & planning
Session 07 site assessment & planningChirag Jain
 
GEA31219 Wind_2.3-107_Brochure_LR
GEA31219 Wind_2.3-107_Brochure_LRGEA31219 Wind_2.3-107_Brochure_LR
GEA31219 Wind_2.3-107_Brochure_LRHarold Schnetzka
 
Ballasted Ground Mount Presentation 2014_optimized
Ballasted Ground Mount Presentation 2014_optimizedBallasted Ground Mount Presentation 2014_optimized
Ballasted Ground Mount Presentation 2014_optimizedDavid Lewenz
 
5kW on grid case study, Chennai, India
5kW on grid case study, Chennai, India 5kW on grid case study, Chennai, India
5kW on grid case study, Chennai, India giridaran123
 
Solar Photovoltaic Power Plant: Best Practices
Solar Photovoltaic Power Plant: Best PracticesSolar Photovoltaic Power Plant: Best Practices
Solar Photovoltaic Power Plant: Best PracticesPuneet Jaggi
 

Was ist angesagt? (19)

Diosynth Electrical Upgrade
Diosynth Electrical UpgradeDiosynth Electrical Upgrade
Diosynth Electrical Upgrade
 
Engineering Drawings required for Solar Projects
Engineering Drawings required for Solar Projects Engineering Drawings required for Solar Projects
Engineering Drawings required for Solar Projects
 
Inspecting Photovoltaic (PV) Systems for Code Compliance
Inspecting Photovoltaic (PV) Systems for Code ComplianceInspecting Photovoltaic (PV) Systems for Code Compliance
Inspecting Photovoltaic (PV) Systems for Code Compliance
 
Drawings & Documents Required for Solar Projects
Drawings & Documents Required for Solar ProjectsDrawings & Documents Required for Solar Projects
Drawings & Documents Required for Solar Projects
 
Temelin power uprate
Temelin power uprateTemelin power uprate
Temelin power uprate
 
Phases of Construction & Erection for Wind Power Project_03 09 2019
Phases of Construction & Erection for Wind Power Project_03 09 2019Phases of Construction & Erection for Wind Power Project_03 09 2019
Phases of Construction & Erection for Wind Power Project_03 09 2019
 
Surmont 2 SAGD
Surmont 2 SAGDSurmont 2 SAGD
Surmont 2 SAGD
 
Guide to Solar Project Implementation
Guide to Solar Project ImplementationGuide to Solar Project Implementation
Guide to Solar Project Implementation
 
Customer Success Story Bently Nevada* Asset Condition Monitoring
Customer Success Story Bently Nevada* Asset Condition MonitoringCustomer Success Story Bently Nevada* Asset Condition Monitoring
Customer Success Story Bently Nevada* Asset Condition Monitoring
 
Key Projects List - DVLung
Key Projects List - DVLungKey Projects List - DVLung
Key Projects List - DVLung
 
Nidec asi corporate energy efficient power solutions
Nidec asi corporate energy   efficient power solutionsNidec asi corporate energy   efficient power solutions
Nidec asi corporate energy efficient power solutions
 
Customer Success Story: Bently Nevada Asset Condition Monitoring
Customer Success Story: Bently Nevada Asset Condition MonitoringCustomer Success Story: Bently Nevada Asset Condition Monitoring
Customer Success Story: Bently Nevada Asset Condition Monitoring
 
apratimkangkan
apratimkangkanapratimkangkan
apratimkangkan
 
Nidec asi capability overview for oil&gas applications
Nidec asi capability overview for oil&gas applicationsNidec asi capability overview for oil&gas applications
Nidec asi capability overview for oil&gas applications
 
Session 07 site assessment & planning
Session 07   site assessment & planningSession 07   site assessment & planning
Session 07 site assessment & planning
 
GEA31219 Wind_2.3-107_Brochure_LR
GEA31219 Wind_2.3-107_Brochure_LRGEA31219 Wind_2.3-107_Brochure_LR
GEA31219 Wind_2.3-107_Brochure_LR
 
Ballasted Ground Mount Presentation 2014_optimized
Ballasted Ground Mount Presentation 2014_optimizedBallasted Ground Mount Presentation 2014_optimized
Ballasted Ground Mount Presentation 2014_optimized
 
5kW on grid case study, Chennai, India
5kW on grid case study, Chennai, India 5kW on grid case study, Chennai, India
5kW on grid case study, Chennai, India
 
Solar Photovoltaic Power Plant: Best Practices
Solar Photovoltaic Power Plant: Best PracticesSolar Photovoltaic Power Plant: Best Practices
Solar Photovoltaic Power Plant: Best Practices
 

Andere mochten auch

Steps to a Successful Solar Request for Proposal
Steps to a Successful Solar Request for ProposalSteps to a Successful Solar Request for Proposal
Steps to a Successful Solar Request for ProposalThe Solar Foundation
 
Proposal for Installation of Solar PV system and Steam Cooking System.
Proposal for Installation of Solar PV system and Steam Cooking System.Proposal for Installation of Solar PV system and Steam Cooking System.
Proposal for Installation of Solar PV system and Steam Cooking System.Sridhar Sibi
 
Grid+connect+pv+install+and+supervise+guidelines+cec+issue+9Grid-Connected So...
Grid+connect+pv+install+and+supervise+guidelines+cec+issue+9Grid-Connected So...Grid+connect+pv+install+and+supervise+guidelines+cec+issue+9Grid-Connected So...
Grid+connect+pv+install+and+supervise+guidelines+cec+issue+9Grid-Connected So...JLanka Technologies (Pvt) Limited
 
Investment proposal for solar pv system training modules
Investment proposal for solar pv system training modulesInvestment proposal for solar pv system training modules
Investment proposal for solar pv system training modulesAli Ar-Ridha
 
Solar System proposal
Solar System proposalSolar System proposal
Solar System proposalSohail Azeem
 
Entrepreneurship, introduction to entrepreneurship, definition of entrepreneu...
Entrepreneurship, introduction to entrepreneurship, definition of entrepreneu...Entrepreneurship, introduction to entrepreneurship, definition of entrepreneu...
Entrepreneurship, introduction to entrepreneurship, definition of entrepreneu...Jorge Saguinsin
 

Andere mochten auch (10)

Exalta hybrid solar ac manual
Exalta hybrid solar ac manualExalta hybrid solar ac manual
Exalta hybrid solar ac manual
 
Steps to a Successful Solar Request for Proposal
Steps to a Successful Solar Request for ProposalSteps to a Successful Solar Request for Proposal
Steps to a Successful Solar Request for Proposal
 
Proposal for Installation of Solar PV system and Steam Cooking System.
Proposal for Installation of Solar PV system and Steam Cooking System.Proposal for Installation of Solar PV system and Steam Cooking System.
Proposal for Installation of Solar PV system and Steam Cooking System.
 
Solar petrol pump proposal
Solar petrol pump proposalSolar petrol pump proposal
Solar petrol pump proposal
 
Evaluation of new solar air conditioners
Evaluation of new solar air conditionersEvaluation of new solar air conditioners
Evaluation of new solar air conditioners
 
Grid+connect+pv+install+and+supervise+guidelines+cec+issue+9Grid-Connected So...
Grid+connect+pv+install+and+supervise+guidelines+cec+issue+9Grid-Connected So...Grid+connect+pv+install+and+supervise+guidelines+cec+issue+9Grid-Connected So...
Grid+connect+pv+install+and+supervise+guidelines+cec+issue+9Grid-Connected So...
 
Investment proposal for solar pv system training modules
Investment proposal for solar pv system training modulesInvestment proposal for solar pv system training modules
Investment proposal for solar pv system training modules
 
Proposal solar
Proposal solarProposal solar
Proposal solar
 
Solar System proposal
Solar System proposalSolar System proposal
Solar System proposal
 
Entrepreneurship, introduction to entrepreneurship, definition of entrepreneu...
Entrepreneurship, introduction to entrepreneurship, definition of entrepreneu...Entrepreneurship, introduction to entrepreneurship, definition of entrepreneu...
Entrepreneurship, introduction to entrepreneurship, definition of entrepreneu...
 

Ähnlich wie Exalta Quotation 10 kw_ongrid_rajkot_std

DPR - 500KWp Solar PV Grid Connected Plant for CUJ june 2023.pdf
DPR - 500KWp Solar PV Grid Connected Plant for CUJ june 2023.pdfDPR - 500KWp Solar PV Grid Connected Plant for CUJ june 2023.pdf
DPR - 500KWp Solar PV Grid Connected Plant for CUJ june 2023.pdfsmsksolar
 
Design & Analysis of Grid Connected Photovoltaic System
Design & Analysis of Grid Connected Photovoltaic SystemDesign & Analysis of Grid Connected Photovoltaic System
Design & Analysis of Grid Connected Photovoltaic SystemSulaman Muhammad
 
Solar rooftop projects primotech
Solar rooftop projects primotechSolar rooftop projects primotech
Solar rooftop projects primotechvimalranaprimotech
 
Guidetosolarprojectimplementation 140323073210-phpapp01
Guidetosolarprojectimplementation 140323073210-phpapp01Guidetosolarprojectimplementation 140323073210-phpapp01
Guidetosolarprojectimplementation 140323073210-phpapp01Kiran Singh
 
Inspecting pv systems_for_code_compliance
Inspecting pv systems_for_code_complianceInspecting pv systems_for_code_compliance
Inspecting pv systems_for_code_complianceAnkit Saxena
 
Solar PV Codes and Standards
Solar PV Codes and StandardsSolar PV Codes and Standards
Solar PV Codes and StandardsSolar Reference
 
Specifications of Solar Power system (Issue-II).pdf
Specifications of Solar Power system (Issue-II).pdfSpecifications of Solar Power system (Issue-II).pdf
Specifications of Solar Power system (Issue-II).pdfAmjiShah
 
New Mexico Statewide Standards for Solar PV and Solar Thermal
New Mexico Statewide Standards for Solar PV and Solar Thermal New Mexico Statewide Standards for Solar PV and Solar Thermal
New Mexico Statewide Standards for Solar PV and Solar Thermal KristyDyer
 
Coxwell Substation.docx
Coxwell Substation.docxCoxwell Substation.docx
Coxwell Substation.docxPranav Godse
 
IC Adapters & Interposers | Interconnect Systems ISI - a Molex company
IC Adapters & Interposers | Interconnect Systems ISI - a Molex companyIC Adapters & Interposers | Interconnect Systems ISI - a Molex company
IC Adapters & Interposers | Interconnect Systems ISI - a Molex companyPeter Ivas
 
Solar latest jmv products and services information with seci specication sola...
Solar latest jmv products and services information with seci specication sola...Solar latest jmv products and services information with seci specication sola...
Solar latest jmv products and services information with seci specication sola...Mahesh Chandra Manav
 
Presentation for Final Year Students about Solar.pptx
Presentation for Final Year Students about Solar.pptxPresentation for Final Year Students about Solar.pptx
Presentation for Final Year Students about Solar.pptxHafizAsimKhayyam
 
Solar Driven Asia Proposal
Solar Driven Asia Proposal Solar Driven Asia Proposal
Solar Driven Asia Proposal Maurice Williams
 
Solar street light technical specification solar lighting & street lamp man...
Solar street light technical specification   solar lighting & street lamp man...Solar street light technical specification   solar lighting & street lamp man...
Solar street light technical specification solar lighting & street lamp man...Eric Cao Solar
 

Ähnlich wie Exalta Quotation 10 kw_ongrid_rajkot_std (20)

DPR - 500KWp Solar PV Grid Connected Plant for CUJ june 2023.pdf
DPR - 500KWp Solar PV Grid Connected Plant for CUJ june 2023.pdfDPR - 500KWp Solar PV Grid Connected Plant for CUJ june 2023.pdf
DPR - 500KWp Solar PV Grid Connected Plant for CUJ june 2023.pdf
 
Mohamed Abou mesalem updated CV
Mohamed Abou mesalem  updated CVMohamed Abou mesalem  updated CV
Mohamed Abou mesalem updated CV
 
SORALITE POWER
SORALITE POWERSORALITE POWER
SORALITE POWER
 
Designing Solar PV Systems ( Utility Scale)
Designing Solar PV Systems ( Utility Scale)Designing Solar PV Systems ( Utility Scale)
Designing Solar PV Systems ( Utility Scale)
 
Design & Analysis of Grid Connected Photovoltaic System
Design & Analysis of Grid Connected Photovoltaic SystemDesign & Analysis of Grid Connected Photovoltaic System
Design & Analysis of Grid Connected Photovoltaic System
 
Solar rooftop projects primotech
Solar rooftop projects primotechSolar rooftop projects primotech
Solar rooftop projects primotech
 
Guidetosolarprojectimplementation 140323073210-phpapp01
Guidetosolarprojectimplementation 140323073210-phpapp01Guidetosolarprojectimplementation 140323073210-phpapp01
Guidetosolarprojectimplementation 140323073210-phpapp01
 
BOQ _UN.pptx
BOQ _UN.pptxBOQ _UN.pptx
BOQ _UN.pptx
 
Inspecting pv systems_for_code_compliance
Inspecting pv systems_for_code_complianceInspecting pv systems_for_code_compliance
Inspecting pv systems_for_code_compliance
 
Solar PV Codes and Standards
Solar PV Codes and StandardsSolar PV Codes and Standards
Solar PV Codes and Standards
 
Gensol - EPC Services
Gensol - EPC ServicesGensol - EPC Services
Gensol - EPC Services
 
structure
structurestructure
structure
 
Specifications of Solar Power system (Issue-II).pdf
Specifications of Solar Power system (Issue-II).pdfSpecifications of Solar Power system (Issue-II).pdf
Specifications of Solar Power system (Issue-II).pdf
 
New Mexico Statewide Standards for Solar PV and Solar Thermal
New Mexico Statewide Standards for Solar PV and Solar Thermal New Mexico Statewide Standards for Solar PV and Solar Thermal
New Mexico Statewide Standards for Solar PV and Solar Thermal
 
Coxwell Substation.docx
Coxwell Substation.docxCoxwell Substation.docx
Coxwell Substation.docx
 
IC Adapters & Interposers | Interconnect Systems ISI - a Molex company
IC Adapters & Interposers | Interconnect Systems ISI - a Molex companyIC Adapters & Interposers | Interconnect Systems ISI - a Molex company
IC Adapters & Interposers | Interconnect Systems ISI - a Molex company
 
Solar latest jmv products and services information with seci specication sola...
Solar latest jmv products and services information with seci specication sola...Solar latest jmv products and services information with seci specication sola...
Solar latest jmv products and services information with seci specication sola...
 
Presentation for Final Year Students about Solar.pptx
Presentation for Final Year Students about Solar.pptxPresentation for Final Year Students about Solar.pptx
Presentation for Final Year Students about Solar.pptx
 
Solar Driven Asia Proposal
Solar Driven Asia Proposal Solar Driven Asia Proposal
Solar Driven Asia Proposal
 
Solar street light technical specification solar lighting & street lamp man...
Solar street light technical specification   solar lighting & street lamp man...Solar street light technical specification   solar lighting & street lamp man...
Solar street light technical specification solar lighting & street lamp man...
 

Kürzlich hochgeladen

Abortion pills in Jeddah +966572737505 <> buy cytotec <> unwanted kit Saudi A...
Abortion pills in Jeddah +966572737505 <> buy cytotec <> unwanted kit Saudi A...Abortion pills in Jeddah +966572737505 <> buy cytotec <> unwanted kit Saudi A...
Abortion pills in Jeddah +966572737505 <> buy cytotec <> unwanted kit Saudi A...samsungultra782445
 
一比一定(购)国立南方理工学院毕业证(Southern毕业证)成绩单学位证
一比一定(购)国立南方理工学院毕业证(Southern毕业证)成绩单学位证一比一定(购)国立南方理工学院毕业证(Southern毕业证)成绩单学位证
一比一定(购)国立南方理工学院毕业证(Southern毕业证)成绩单学位证wpkuukw
 
一比一定(购)UNITEC理工学院毕业证(UNITEC毕业证)成绩单学位证
一比一定(购)UNITEC理工学院毕业证(UNITEC毕业证)成绩单学位证一比一定(购)UNITEC理工学院毕业证(UNITEC毕业证)成绩单学位证
一比一定(购)UNITEC理工学院毕业证(UNITEC毕业证)成绩单学位证wpkuukw
 
怎样办理圣芭芭拉分校毕业证(UCSB毕业证书)成绩单留信认证
怎样办理圣芭芭拉分校毕业证(UCSB毕业证书)成绩单留信认证怎样办理圣芭芭拉分校毕业证(UCSB毕业证书)成绩单留信认证
怎样办理圣芭芭拉分校毕业证(UCSB毕业证书)成绩单留信认证ehyxf
 
怎样办理维多利亚大学毕业证(UVic毕业证书)成绩单留信认证
怎样办理维多利亚大学毕业证(UVic毕业证书)成绩单留信认证怎样办理维多利亚大学毕业证(UVic毕业证书)成绩单留信认证
怎样办理维多利亚大学毕业证(UVic毕业证书)成绩单留信认证tufbav
 
Top profile Call Girls In Ratlam [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Ratlam [ 7014168258 ] Call Me For Genuine Models We...Top profile Call Girls In Ratlam [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Ratlam [ 7014168258 ] Call Me For Genuine Models We...nirzagarg
 
LANDSLIDE MONITORING AND ALERT SYSTEM FINAL YEAR PROJECT BROCHURE
LANDSLIDE MONITORING AND ALERT SYSTEM FINAL YEAR PROJECT BROCHURELANDSLIDE MONITORING AND ALERT SYSTEM FINAL YEAR PROJECT BROCHURE
LANDSLIDE MONITORING AND ALERT SYSTEM FINAL YEAR PROJECT BROCHUREF2081syahirahliyana
 
Top profile Call Girls In Palghar [ 7014168258 ] Call Me For Genuine Models W...
Top profile Call Girls In Palghar [ 7014168258 ] Call Me For Genuine Models W...Top profile Call Girls In Palghar [ 7014168258 ] Call Me For Genuine Models W...
Top profile Call Girls In Palghar [ 7014168258 ] Call Me For Genuine Models W...gajnagarg
 
怎样办理斯威本科技大学毕业证(SUT毕业证书)成绩单留信认证
怎样办理斯威本科技大学毕业证(SUT毕业证书)成绩单留信认证怎样办理斯威本科技大学毕业证(SUT毕业证书)成绩单留信认证
怎样办理斯威本科技大学毕业证(SUT毕业证书)成绩单留信认证tufbav
 
CRISIS COMMUNICATION presentation=-Rishabh(11195)-group ppt (4).pptx
CRISIS COMMUNICATION presentation=-Rishabh(11195)-group ppt (4).pptxCRISIS COMMUNICATION presentation=-Rishabh(11195)-group ppt (4).pptx
CRISIS COMMUNICATION presentation=-Rishabh(11195)-group ppt (4).pptxRishabh332761
 
Abort pregnancy in research centre+966_505195917 abortion pills in Kuwait cyt...
Abort pregnancy in research centre+966_505195917 abortion pills in Kuwait cyt...Abort pregnancy in research centre+966_505195917 abortion pills in Kuwait cyt...
Abort pregnancy in research centre+966_505195917 abortion pills in Kuwait cyt...drmarathore
 
一比一原版(USYD毕业证书)澳洲悉尼大学毕业证如何办理
一比一原版(USYD毕业证书)澳洲悉尼大学毕业证如何办理一比一原版(USYD毕业证书)澳洲悉尼大学毕业证如何办理
一比一原版(USYD毕业证书)澳洲悉尼大学毕业证如何办理uodye
 
怎样办理伍伦贡大学毕业证(UOW毕业证书)成绩单留信认证
怎样办理伍伦贡大学毕业证(UOW毕业证书)成绩单留信认证怎样办理伍伦贡大学毕业证(UOW毕业证书)成绩单留信认证
怎样办理伍伦贡大学毕业证(UOW毕业证书)成绩单留信认证ehyxf
 
Low Cost Patna Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top Class Call Gi...
Low Cost Patna Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top Class Call Gi...Low Cost Patna Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top Class Call Gi...
Low Cost Patna Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top Class Call Gi...vershagrag
 
一比一维多利亚大学毕业证(victoria毕业证)成绩单学位证如何办理
一比一维多利亚大学毕业证(victoria毕业证)成绩单学位证如何办理一比一维多利亚大学毕业证(victoria毕业证)成绩单学位证如何办理
一比一维多利亚大学毕业证(victoria毕业证)成绩单学位证如何办理uodye
 
Hilti's Latest Battery - Hire Depot.pptx
Hilti's Latest Battery - Hire Depot.pptxHilti's Latest Battery - Hire Depot.pptx
Hilti's Latest Battery - Hire Depot.pptxhiredepot6
 
一比一定(购)坎特伯雷大学毕业证(UC毕业证)成绩单学位证
一比一定(购)坎特伯雷大学毕业证(UC毕业证)成绩单学位证一比一定(购)坎特伯雷大学毕业证(UC毕业证)成绩单学位证
一比一定(购)坎特伯雷大学毕业证(UC毕业证)成绩单学位证wpkuukw
 
在线制作(ANU毕业证书)澳大利亚国立大学毕业证成绩单原版一比一
在线制作(ANU毕业证书)澳大利亚国立大学毕业证成绩单原版一比一在线制作(ANU毕业证书)澳大利亚国立大学毕业证成绩单原版一比一
在线制作(ANU毕业证书)澳大利亚国立大学毕业证成绩单原版一比一ougvy
 
怎样办理昆士兰大学毕业证(UQ毕业证书)成绩单留信认证
怎样办理昆士兰大学毕业证(UQ毕业证书)成绩单留信认证怎样办理昆士兰大学毕业证(UQ毕业证书)成绩单留信认证
怎样办理昆士兰大学毕业证(UQ毕业证书)成绩单留信认证ehyxf
 

Kürzlich hochgeladen (20)

Abortion pills in Jeddah +966572737505 <> buy cytotec <> unwanted kit Saudi A...
Abortion pills in Jeddah +966572737505 <> buy cytotec <> unwanted kit Saudi A...Abortion pills in Jeddah +966572737505 <> buy cytotec <> unwanted kit Saudi A...
Abortion pills in Jeddah +966572737505 <> buy cytotec <> unwanted kit Saudi A...
 
一比一定(购)国立南方理工学院毕业证(Southern毕业证)成绩单学位证
一比一定(购)国立南方理工学院毕业证(Southern毕业证)成绩单学位证一比一定(购)国立南方理工学院毕业证(Southern毕业证)成绩单学位证
一比一定(购)国立南方理工学院毕业证(Southern毕业证)成绩单学位证
 
一比一定(购)UNITEC理工学院毕业证(UNITEC毕业证)成绩单学位证
一比一定(购)UNITEC理工学院毕业证(UNITEC毕业证)成绩单学位证一比一定(购)UNITEC理工学院毕业证(UNITEC毕业证)成绩单学位证
一比一定(购)UNITEC理工学院毕业证(UNITEC毕业证)成绩单学位证
 
怎样办理圣芭芭拉分校毕业证(UCSB毕业证书)成绩单留信认证
怎样办理圣芭芭拉分校毕业证(UCSB毕业证书)成绩单留信认证怎样办理圣芭芭拉分校毕业证(UCSB毕业证书)成绩单留信认证
怎样办理圣芭芭拉分校毕业证(UCSB毕业证书)成绩单留信认证
 
怎样办理维多利亚大学毕业证(UVic毕业证书)成绩单留信认证
怎样办理维多利亚大学毕业证(UVic毕业证书)成绩单留信认证怎样办理维多利亚大学毕业证(UVic毕业证书)成绩单留信认证
怎样办理维多利亚大学毕业证(UVic毕业证书)成绩单留信认证
 
Top profile Call Girls In Ratlam [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Ratlam [ 7014168258 ] Call Me For Genuine Models We...Top profile Call Girls In Ratlam [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Ratlam [ 7014168258 ] Call Me For Genuine Models We...
 
LANDSLIDE MONITORING AND ALERT SYSTEM FINAL YEAR PROJECT BROCHURE
LANDSLIDE MONITORING AND ALERT SYSTEM FINAL YEAR PROJECT BROCHURELANDSLIDE MONITORING AND ALERT SYSTEM FINAL YEAR PROJECT BROCHURE
LANDSLIDE MONITORING AND ALERT SYSTEM FINAL YEAR PROJECT BROCHURE
 
Top profile Call Girls In Palghar [ 7014168258 ] Call Me For Genuine Models W...
Top profile Call Girls In Palghar [ 7014168258 ] Call Me For Genuine Models W...Top profile Call Girls In Palghar [ 7014168258 ] Call Me For Genuine Models W...
Top profile Call Girls In Palghar [ 7014168258 ] Call Me For Genuine Models W...
 
怎样办理斯威本科技大学毕业证(SUT毕业证书)成绩单留信认证
怎样办理斯威本科技大学毕业证(SUT毕业证书)成绩单留信认证怎样办理斯威本科技大学毕业证(SUT毕业证书)成绩单留信认证
怎样办理斯威本科技大学毕业证(SUT毕业证书)成绩单留信认证
 
CRISIS COMMUNICATION presentation=-Rishabh(11195)-group ppt (4).pptx
CRISIS COMMUNICATION presentation=-Rishabh(11195)-group ppt (4).pptxCRISIS COMMUNICATION presentation=-Rishabh(11195)-group ppt (4).pptx
CRISIS COMMUNICATION presentation=-Rishabh(11195)-group ppt (4).pptx
 
Abort pregnancy in research centre+966_505195917 abortion pills in Kuwait cyt...
Abort pregnancy in research centre+966_505195917 abortion pills in Kuwait cyt...Abort pregnancy in research centre+966_505195917 abortion pills in Kuwait cyt...
Abort pregnancy in research centre+966_505195917 abortion pills in Kuwait cyt...
 
一比一原版(USYD毕业证书)澳洲悉尼大学毕业证如何办理
一比一原版(USYD毕业证书)澳洲悉尼大学毕业证如何办理一比一原版(USYD毕业证书)澳洲悉尼大学毕业证如何办理
一比一原版(USYD毕业证书)澳洲悉尼大学毕业证如何办理
 
怎样办理伍伦贡大学毕业证(UOW毕业证书)成绩单留信认证
怎样办理伍伦贡大学毕业证(UOW毕业证书)成绩单留信认证怎样办理伍伦贡大学毕业证(UOW毕业证书)成绩单留信认证
怎样办理伍伦贡大学毕业证(UOW毕业证书)成绩单留信认证
 
Abortion pills in Dammam +966572737505 Buy Cytotec
Abortion pills in Dammam +966572737505 Buy CytotecAbortion pills in Dammam +966572737505 Buy Cytotec
Abortion pills in Dammam +966572737505 Buy Cytotec
 
Low Cost Patna Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top Class Call Gi...
Low Cost Patna Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top Class Call Gi...Low Cost Patna Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top Class Call Gi...
Low Cost Patna Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top Class Call Gi...
 
一比一维多利亚大学毕业证(victoria毕业证)成绩单学位证如何办理
一比一维多利亚大学毕业证(victoria毕业证)成绩单学位证如何办理一比一维多利亚大学毕业证(victoria毕业证)成绩单学位证如何办理
一比一维多利亚大学毕业证(victoria毕业证)成绩单学位证如何办理
 
Hilti's Latest Battery - Hire Depot.pptx
Hilti's Latest Battery - Hire Depot.pptxHilti's Latest Battery - Hire Depot.pptx
Hilti's Latest Battery - Hire Depot.pptx
 
一比一定(购)坎特伯雷大学毕业证(UC毕业证)成绩单学位证
一比一定(购)坎特伯雷大学毕业证(UC毕业证)成绩单学位证一比一定(购)坎特伯雷大学毕业证(UC毕业证)成绩单学位证
一比一定(购)坎特伯雷大学毕业证(UC毕业证)成绩单学位证
 
在线制作(ANU毕业证书)澳大利亚国立大学毕业证成绩单原版一比一
在线制作(ANU毕业证书)澳大利亚国立大学毕业证成绩单原版一比一在线制作(ANU毕业证书)澳大利亚国立大学毕业证成绩单原版一比一
在线制作(ANU毕业证书)澳大利亚国立大学毕业证成绩单原版一比一
 
怎样办理昆士兰大学毕业证(UQ毕业证书)成绩单留信认证
怎样办理昆士兰大学毕业证(UQ毕业证书)成绩单留信认证怎样办理昆士兰大学毕业证(UQ毕业证书)成绩单留信认证
怎样办理昆士兰大学毕业证(UQ毕业证书)成绩单留信认证
 

Exalta Quotation 10 kw_ongrid_rajkot_std

  • 1. Solar Photovoltaic Proposal Page 1 15 KVA/10kw ON GRID SOLAR PV SYSTEM PROPOSAL Ref: EXALTA-SOLAR/16-17/PV/869569 Date 04 Oct 16 Sub: Comprehensive Proposal for 15 KVA Solar PV System. With referencetoyour query,wearepleasedtosubmitherewithourcomprehensiveproposaloftheTechnical&Commercialoverview,foryourkindp A. System Definition Size 10 KW total DC capacity 40 nos. 250-Wattpanels (To be procured globally from leading international vendors like Photon Energy, BP Solar, Solar Semiconductor, Waree ,Euro Solar etc .) Energy Production Site location: Rajkot Site Co-ordinates:…56/87 Tilt Angle: South30.3o Average dradiation:5.62 kW-hours/m2/day Number of full production days assumed per year:330 PV System Based Statistics:- Expected Annual production:1.5 MW-hours(As per simulations) Note: Energy production projections are reason ably accurate estimates based on site’s solar data and our experience with similar systems.Energy makes no guarantees as to actual production output from this system. Grid/Load Interfacing Solar system outputs shall be connected to a suitable load bus capable of taking the input. This input point’s hall be selected infield. In consultation with client’s Executive Engineer.
  • 2. Solar Photovoltaic Proposal Page 2 B. System Components Solar Panels Note: Subject to availability at installation time, a different panel from a Leading vendor may be selected without affecting system size and Performance. Make: Solar Semiconductor/Euro/Waree/Silicon Taxim Model: SSI-M6-250 Quantity: 40 Wattage: 250W No. of Cells:60 Voc:37.1V Isc: 8.28 A Vmp: 29.6V Imp: 7.6A Dimensions: 1660X990X42(mm) Weight:10kg Operating Conditions:- 40to+90CMaximum SystemVoltage:600Vdc Inverter Note: Subject to availability at installation time, a different inverter may Be selected without affecting system size and performance. SMA Livint German - Ongrid Solar MPPT Inverter Quantity:2 AC maximum output: 6 KW MPPT Maximum current input DC/String:20A Maximum efficiency:>98.1% Power connection : 3-phase We may take any other reputed make with efficiency> 95%. Mounting Structures Panels shall be mounted on galvanized frames inclined at 30.3degrees to the South. The structure is designed in such a manner that module can be replaced eas to install and service in future. The frames will be supported by angle legs of Suitable length stop provide the pre-determined inclination. All fasteners, nut and bolts are made of Stainlesssteel-SS304 5.4.6 PCC. The structures shall be pre-engineered to meet special requirements of placing the modules on the Corrugated roof tops. FOUNDATION BASE: The legs of the structures made with GI angles are made of fixed and grouted in the PCC foundation Columns made with 1:2:4 cement concrete. Electrical Accessories Cables will conform to IS694 and shall be of 650V/1.1k V grade. Inter connections, array to junction boxes, junction boxes to DCDB, DCDB to PCU etc will be selected to keep voltage drop and losses to the minimum. The bright annealed 99.97% pure bare copper conductors offer low Conductor resistance,
  • 3. Solar Photovoltaic Proposal Page 3 Result in lower heating thereby increasing cable life and efficiency. These Wires are insulated with a special grade PVC compound formulated and Manufactured in-house. Working voltage: up to 1100 V Temperature range:-15 deg Cto+70degC Sizes: Suitable sizes Color codes: Red, Yellow, Black, Blue, Green Battery NO Energy Meter The Inverter shall have a built-in meter that tracks energy production and Display sit on a small LED screen. The display can be used to determine Real-time production, daily production, and yearly production. For more sophisticated analysis and visual data management, Solar Access modules Can be included. Remote Monitoring System(optional) The sunny web box continuously records and stores all avails able data of about 50 inverters in real time, in addition the inverter parameter scan be requested and modified. It provides you with various modern data processing options for professional data Management .These are save din conventional CSV or XML file formats. The ability to exchange data by FTP allows you to easily transfer these values to your. To your PC you can Just as easily use an SD card to save your data any such feature of remote monitoring shall be made available through additional costs. Stringing Design 4 strings of 10 panels each, however a detailed engineering might Change the stringing design. Incase Inverter configuration needs any modifications, based on its availability, the string layout may be Modified accordingly.
  • 4. Solar Photovoltaic Proposal Page 4 C. Bill of Material S.No. Component Type/Model No Specifications Quantity 1 PV Modules SSI-M6-250 40 2 SMA Livint German ongridf Solar Inverter 7.5 KVA 2 3 Mounting Structure Custom made MShotdipIRON 1 Set 4 Solar Battery 150AH, C10 Exalta IP65standards 20 5 Main Junction Box ABB Junction Boxes IP65standards As per stringing design 6 Earthling Kit Reputed make 1 set 7 AC & DC cables Conforming to BOS As per site requirements D. Solar PV Plot Plan
  • 5. Solar Photovoltaic Proposal Page 5 E. Installation Details Area required: The Total Area required for the System Installation shall be approx 600 sq feet, without any shades, facing south. Structural Anchoring: Panels shall be mounted on galvanized frames inclined at 30.3 degrees to the south or 6 degree in movable structure. The structure is designed in such a m be replaced easily and in line with site requirements and it is easy to install and service in future. The frames will be Supported by angle legs of suitable lengths to provide the pre-determined inclination. All fasteners, nutand bolts are made of Stainless steel-SS304 5.4.6 PCC. Foundation Base: The legs of the structures made with GI angles are made of fixed and grouted in the PCC foundation columns made with 1:2:4 Cement concrete. Actual frame and other structural dimensions will be determined during a more detailed site visit by specialists during full design phase. Inverter Installation This space provides sample accessibility and good air circulation. The inverter is available in IP54housing, however, an enclosed Space has to be Provided for the same. Actual installation location and methods will be determined during full design phase. Electrical Proposed fire hoses haft will be used for running electrical cables down to the electrical panel room. A detailed electrical design with Single-line Diagram and specifications will be prepared during full design phase after receiving the PO, for the client’s approval.
  • 6. Solar Photovoltaic Proposal Page 6 F. Scope of Work 1. We shall conduct a detailed site visit with specialists to take accurate measurements, photographs, another site-specific in Formation for full design. 2. Prepare full system design to include civil, structural, electrical and mechanical components, with construction drawings and Specifications. 3. Procure equipment and materials and deliver to site. 4. Perform complete system installation. 5. Test all electrical components in accordance with manufacturer instructions. 6. Commission the system to full operability. G. Client Scope Site-specific considerations will require assistance and cooperation from the client, as outlined below: 1. Provide access to work site for delivery of equipment and materials prior to and during project implementation. 2. Provide a suitable and secure space for storage of equipment and materials. 3. Facilitate access of work crew to the work site 7 days a week. 4. Facilitate interfacing with the client’s resident engineering staff for consultation as needed. 5. Separate electrical loads as discussed in Part A (Grid Interfacing)and connect solar output to building load system. 6. All the Statutory clearances, if any, required for the Project. H. Delivery Schedule & Project Cost Installation & Commissioning All the Systems except Inverter will be installed within 1- 8weeks from the date of receipt of advance and approval of the “SLD”. Warranty The Solar modules are warranted by the solar panel manufacturer for a period of 25 years. The details areas below. 1. Panels: Manufacturing Warrantee for the System: 3yrs after installation and commissioning. Performance Warrantee: a. 90% efficiency up to 12 yrs b. 80% efficiency up to 25 yrs 2. Inverter: 5yrs 3. Battery: NO 4. Balance of the Systems: Standard 12 months warrantee against manufacturing defects. We shall also ensure supply of Spares for the System if required.
  • 7. Solar Photovoltaic Proposal Page 7 The final system size and quotation shall be finalized based on site visit and load conditions. • Prices: Price quoted are FOR at site Delhi or nearby Delhi. for other reason transportation charges will be extra. • Freight & Insurance: Not Included • System Installation: System will be supplied and same will be installed by us. Installation Charges included. • Excise Duty/Service Tax: Currently, under present rules, Solar Photo Voltaic system is exempted from Excise Duty. However, rate Prevalent at the time of dispatch will be applicable extra, at actual. • Service Tax extra at Actual will be charged, Presently Applicable @NA • Octroi: Any Octroi /Entry tax, if any, will be pay able will be extra • Sales Tax: VAT @5% will be charged extra without Form-C OR CST@2% • Delivery : Dispatch will be effected in 1-8 weeks from the date of acceptance of your Purchase order.(P.O) .System • Installation will be completed in 3 week’s time from date of receipt of materials at site, provided site is ready for installation. • Payment Terms: Total cost of the project is :- 6 Lakh - First delivery of Solar panels against amount paid in advance. i.e 4 Lakh - Inverter and rest of the matterial against rest of the payment i.e 1.5 Lakh - Remaining 50000/- cheque ,after successful installation. Technical Director : Er. Ashutosh Verma 9999890192 Whatsapp No: 9807465570 Date: 4 Oct, 2016 Version:#1 Contact: Address :- A117 Atul chok Dwarika Mor Delhi 110059 Registered Office:-D734 Kamla Nagar Agra-282005 E:sales@exalta.inW:www.exlata.in www.exalta.co.in EXALTA LED Insparc Technologies Pvt Ltd