Permen PU 01 2014 Standar Pelayanan Minimal Bidang Pekerjaan Umum dan Penataa...
Sanitation Development in Brunei Darussalam
1. ABOUT BRUNEI DARUSSALAM
BRUNEI PROFILE
GOVERNMENT : Malay Islamic
Monarchy, Independence on 1st
January 1984
LOCATION : North-West of
Borneo Island in South Eastern
Asia, Longitudes Between 114
deg 04’E & 115 deg 23’E And
Latitudes Between 4 deg 00’N &
5 deg 05’N
CAPITAL : Bandar Seri Begawan
AREA : 5,765 sq. km.
POPULATION : 398,000(mid-year
of 2008)
CLIMATE : Tropical Equatorial
1
2. TYPES OF SANITATION FACILITIES
SANITATION
IN BRUNEI
PIT LATRINES
CENTRALISED SEWERAGE
CENTRALISED SEWERAGE
DIRECT TO SYSTEM INCLUDING SEWAGE
SYSTEM INCLUDING SEWAGE
TREATMENT WORKS
TREATMENT WORKS
GROUND OR
WATERCOURSES
SEPTIC TANKS
EITHER TO
SOAKAWAY OR
DRAIN/RIVER
SEWERAGE
SYSTEM FOR
TREATMENT
AND/OR DISPOSAL
SEPTIC TANK WITH SOAKAWAY
SEPTIC TANK WITH SOAKAWAY PIT LATRINE
PIT LATRINE DIRECT DISCHARGE OF SEWAGE
DIRECT DISCHARGE OF SEWAGE
TO RIVER
TO RIVER
2
3. SANITATION COVERAGE IN BRUNEI
Estimated Estimated Estimated Estimated
Population No. of Houses No. of Urban Houses No. of Rural Houses
Septic Septic
Urban Rural Total 1 Urban Rural Total 2 Sewer Other Sewer Other
Tank Tank
National 236,984 95,860 332,844 43,204 12,492 55,696 49% 46% 5% 0% 65% 35%
Note:
1. Extracted from Table 1.6 Summary Tables of the population Census 2001 JPKE
2. Extracted from Table 13.1 Summary Tables of the population Census 2001 JPKE
POPULATION SEWER SYSTEM CONNECTIONS
90% Public Sewerage and Septic Tank
Public Sewerage system only with total length
40%
of sewer pipe 740km
3
4. SEWERAGE VACUUM SYSTEM
HOUSEHOLD HDPE VACUUM
VACUUM PUMP
SANITARY PIPES MAIN
STATION
VACUUM COLLECTION
POT/CHAMBER
SEWAGE TREATMENT
PLANT
SEWAGE TREATMENT PLANT
BOLKIAH ‘A’ AND ‘B’ WATER VILLAGES
4
5. SEWERAGE PROJECTS
NDP 2007-2012
Total of 20 projects with overall cost B$139,875,000.00 (US$97millions).
The projects are categorized into 5 groups which are as follows:
1. Upgrading of Sewage Treatment Plant (4 projects) - B$37M
2. Extension of Main Sewer line (2 projects) - B$14M
3. Sewer pipe connection to Main Sewer line (10 projects) - B$65.375M
4. New Sewerage Scheme (3 projects) - B$19M
5. Sewerage Asset Management - B$4.5M
Total : B$139.875M
(US$97millions)
5
6. SEWERAGE PROJECTS
NDP (2007-2012) 916-019
916-020 916-021
916-023
916-022
916-025
916-035 916-029 916-028 916-027 916-026
916-018
916-034 916-033 916-032
916-017 916-024
916-030 916-031
Legends:
Upgrading of Sewage Treatment Plant
Extension of Main Sewer line
Sewer pipe connection to the Main Sewer line
New Sewerage Scheme
6
7. STRATEGIC GOALS
TARGET DATES STRATEGY REMARKS
Greater access to high quality
sewerage system in line with
5% increase every NDP the Millennium Development Currently at 40% sewer.
Goal 7 (Ensure Environmental
Sustainability).
7