The Accommodation Business Case and
the Role of the University
4th Annual Student Housing Forum
23 August 2013
Damien House & Leisl Harris
Introduction
Who is Social Infrastructure Solutions (SIS)?
PAST – full risk developers (FURTHER PAST…. architect, builder, financier, chartered accountant)
Some development projects include:
• Pharmacy Australia Centre of Excellence (PACE) University of Queensland Pharmacy School, Brisbane ($130m);
• Queensland University of Technology Health Faculty / Australian Red Cross Blood Service – Brisbane ($100m);
• Australian National University 2,500 student accommodation beds and ancillary facilities, ACT ($280m); and
• Twin Towns Services Club 260 key Short Stay Accommodation, Tweed Heads ($80m).
NOW – advisors to the university, government, semi-government , NFP and community sectors
Some advisory roles include:
• Mid West Development Commission – Geraldton Health Education &Training Accommodation Project Business Case
and Master Plan, WA;
• Goldfields – Esperance Development Commission – Tertiary Education Accommodation Business Case, WA;
• Private Developer, Student Accommodation Business Case, South East Queensland;
• Plus various Local and State Governments. – Redlands, Sunshine Coast, Victoria Government DEPI; and
• Community Sites – Stockland.
Introduction
How does an organisation whose core business is not accommodation
formulate and assess such a Business Case?
Damien
• Navigating the Business Case? Known knowns and known unknowns but what about unknown
unknowns?
• Definition of feasible / viable. Is the definition really contestable and what does it mean?
• Risk allocation, risk mitigation and risk gates.
Leisl
• Options for University involvement and role in the development of accommodation.
• Contracting, financial close and delivery.
• Classic breakdown points.
Introduction
How does an organisation whose core business is not accommodation
formulate and assess such a Business Case?
• In our experience - with difficulty, nervously, slowly and sometimes without a result (Decision!
Consensus!)
• Often our services to assist cannot be articulated and briefed with precision (telling)
• There are so many FUNDAMENTAL questions:
• How many beds?
• What mix of beds
• Budget and quality?
• Operations outsourcing?
• Timeframe?
• Whose money?
• What investment return?
• What price (rent)?
• On whose approval?
• Whose land?
• Amenity inclusions?
• Level of pastoral care?
• Delivery methodology?
• Under whose management and guidance?
• Private sector partnering?
• Uni underwriting - any/soft/hard?
• Ownership term (hold to prove up?)
• Profit maximisation?
Introduction
Context - Business Case
• Brief (not only the physical but the BC Brief)
• Quantitative aims
• Qualitative aims
• Measures of success (qualitative)
• Demand study
• Financial model
• Risk analysis
• Sensitivity Analysis
• Approval pathways
• Cost Benefit Analysis (qualitative issues)
• SROI Analysis
• How wide is the study? Project or University
And remember – GIGO - Garbage In Garbage Out!
Navigating the Business Case
Known knowns and known unknowns but what about unknown unknowns?
“Need to be an expert in areas we didn’t know we had to be experts in” Edwina, Day 1
“We don’t know what we don’t know…how do they sleep at night?” Damian, Day 1
• Risk navigation - various tools (see later)
• Simplification - paradoxically making things simple is very hard sometimes
• Unknown unknowns is expert assistance required? – tens of millions at stake
• Unis are some of the most fixed asset rich institutions on the planet
• Unis have a great deal of expertise in facility procurement
• But this is a separate asset class and potential commercial business stream
• Importantly it need not be a commercial business YET
• But can be established and structured to be in the future IF NECESSARY
Navigating the Business Case
Known knowns and known unknowns but what about unknown unknowns?
Feasibility context some examples…
Known knowns:
• Most of the pre-development expenses
• construction price and timing (market tested and mitigated by LDs)
• interest rate and margin (with hedging max 5-7 years)
• Warranties
• Operating costs (say 2/3s)
Known unknowns:
• Latent conditions (risk allocation)
• Demand (notwithstanding Demand Study)
• Price elasticity
• Operating costs (say 1/3)
Navigating the Business Case
Known knowns and known unknowns but what about unknown unknowns?
• Our team started out on one of the first (happy to be challenged here) BOOT student
accommodation developments in the country
• We had an englobo land agreement with a G8 university
• We also had:
• three experienced ex-project financiers in the development team
• experienced developers in each state
• a willing financial institution with UK PFI experience
• a tier one contractor
• a very nascent professional operator now one of the largest in the country then run by a
husband and wife team
• We pretty much started from scratch
Navigating the Business Case
Known knowns and known unknowns but what about unknown unknowns?
Frank admissions!
Unknown unknowns:
• Input tax credits!
• Now almost common knowledge but not when the GST was just introduced
• Ordinarily, the GST for construction costs CAN NOT be claimed back
• This is a complex area of law with some baffling case law precedents
• Most recently a successful challenge has been made but under specific circumstances
• Price point – always surprised how high!
• Rigorously test upside/aggressive assumptions
• Price elasticity (airport privatisation financial models explicitly modelled duty free spend)
Navigating the Business Case
Goods and Services Tax – Known Unknown!
Commencing working assumptions:
• input tax credits are NOT recovered for any and all capital costs
• input tax credits are NOT recovered for any and all operating costs
• GST is not charged on the accommodation rentals (and no remission to the ATO is required).
Assumes accommodation is “input taxed” - consistent with ATO guidance.
However, there is recent case law precedent that may “unlock” the input tax credit by treating the
accommodation as “Commercial Residential”.
This particular area of indirect tax is a complex area of law with some very contentious and seemingly
conflicting decisions in recent cases.
Navigating the Business Case
Price Point - Disincentives/barriers to private house rental:
• lack of single bed accommodation
• product not designed for purpose of shared accommodation (ie lacking locks and ensuites)
• finding partners to share with for multi bed accommodation
• financial commitment for multi bed (underwriting your partners!)
• refusal to rent to students
• language barriers
• term of student lease may not fit market
• general logistical difficulty for a young person (never done it)
• lawn and garden maintenance costs (if a house)
• travel - lack of proximity to campus
• safety
• lack of student community (if communal amenity is provided)
• lack of “house rules”
• predatory landlords
THESE ITEMS WILL BE VALUED BY STUDENTS IN LONG RUN
Definition of Feasible / Viable
Is the definition really contestable and what does it mean?
• Yes absolutely - it can mean different things to different people
• Last two accommodation BC had vastly different starting points and feasibility criteria
• One was for a commercial off campus facility incorporating both a refurb of existing and new
accommodation development in Brisbane. This needed to meet hurdle rates of return for the
transaction term and at specific points through the life of the transaction for equity and debt.
• Our last assignment was for an agency of the WA Government in a health education and training
precinct.
• The feasibility criterion for this project was operationally breakeven. No return ON or OF capital
required
• NFP providers. What are their criteria? Service mission but how is capital decision made?????
• Clearly, the starting point is critical to navigating a successful outcome
Definition of Feasible / Viable
Solutions Targeting
• Solve rent – Base Case assumptions but allowing rent to fluctuate to solve for a xx%pa equity IRR.
• Solve capex – Base Case but allowing construction costs to fluctuate to solve for a xx% pa equity IRR.
• Solve opex - Base Case assumptions but allowing opex costs to fluctuate to solve for a xx% pa equity IRR.
• Solve land price – ditto
• Solve break even – for rent, capex, opex (and operationally breakeven)
• Solve concession term
• Other critical criteria - Project IRR, Equity yield by year, DSCR, ICR, Gearing, Payback
• Sinking fund allowance of xx% of revenue treated as cash outflow
• Later explicitly model lifecycle costs
• General comment
• Risk free rates, risk premium, debt tenor, AUD, yield play – all augur well
• Qualitative – student experience, VFM, regional WA nurses community vs built environment)
The Future….
Hertfordshire University Accomodation – GBP 190m (AUD 300m+)
Debt funding via an index-linked unwrapped private bond placement with a maturity of 41 years, one of the longest maturities
to be raised for greenfield infrastructure projects.
The bond has been rated A- by S&P. The high rating reflects the fact that despite demand risk to which the SPV is exposed, the
University is guaranteeing occupancy during construction. The University has also taken credit risk on students, meaning that it
will pay if they do not, which provided a significant enhancement in terms of revenue risk.
Gearing is 75:25, which also contributed to the high rating.
Project details
The project is for the DBFO of student accommodation totalling 3,000 bedrooms and associated spaces. Construction involves
the development of over 2,500 new bedrooms.
Derwent Living’s provision of asset management and facilities management services for the new and existing units will be
worth more than GBP 200m over the lifetime of the contract. Derwent Living will also refurbish the existing 500 bedrooms over
the next three years.
The scheme will be delivered in three phases with the first phase scheduled to be completed in September 2014.
Issue amount:GBP 143.5m
Maturity: 31 July 2054
Issue price: 100
Coupon: 2.057%
Spread: 235bps versus UK 2035 Inflation linked
Frequency: Semi-Annual
Rating: S&P A-
Understanding Risk
Risk allocation, risk mitigation and risk gates.
• Risk allocation at a broad level is a function of the delivery and operations model
• Accommodation need not be delivered under a BOOT model
• Our team helped deliver under BOOT and under direct ownership with a third party operator
• Much of the completion risk is contained within the building contract and usually for circa 80%+ of
cost
• Our team has developed several template style RAMMs for different style developments (example)
• We also developed a detailed risk capital gate model that ensures appropriate risk taking and
expenditure commitment during the critical early phase investigations and through project life
(example)
The Role of the University
What options are available for the University’s involvement and role in the
development of accommodation?
Consider
Student Accommodation – Core University Business or to Support Core University Business?
“The Universities do not necessarily recognise the benefit and value that accommodation brings to the students” Laura, Day 1
Just another University asset? Is accommodation the same as an academic / faculty building?
“Whose responsibility is it to provide student accommodation – Property and Facilities, Student Services, Others?” Day 1
Discussion
What is the best use of limited University capital?
Round 5 of NRAS closed 6th August – Secondary market?
“We have to more with less, in a more efficient way” Edwina, Day 1
Resources – expertise and capacity
Specialist user requirements – design and operations - capital versus operations – lifecycle costs
Certainty of outcomes – short (delivery) and long term (operations)
Brand – preservation, enhancement and value
How does the University ‘stay safe’ throughout the process - from project inception to operations?
The Role of the University
What options are available for the University’s involvement and role in the
development of accommodation?
Role Responsibility
‘ON CAMPUS’ Design (fit
for intended
purpose)
Funding
(Debt &
Equity)
Construction
(Delivery)
Occupancy Operator Maintenance
and Capex
Comments / Other
Developer & Operator D&C or
construct
only?
Full responsibility in all areas
(Monash BVN example)
Developer Only Operator may or may not take occupancy risk if not
the developer. Example: Third party operator takes
existing facility.
Equity Investor Only Financial returns through term and asset reversion
at the end of the term (BOOT example).
Partner
(with Private Sector)
May or may not be required to underwrite
minimum occupancy level and may benefit from
increased occupancy level. Branding is important
to operations. Design guidelines versus operator
requirements.
Land Owner Only
(Contribution via
Ground Lease)
Certain level of control over design (maybe design
guidelines), development or operational outcomes.
Brand protection is important. Asset may revert to
University at end of life under Ground Lease.
Brand Contribution Brand recognition to students (marketing tool) and
ease of booking when choosing accommodation is
critical and therefore assists occupancy levels.
The Role of the University
Contracting, Financial Close and Delivery – let’s start building….??
Need
Use
Market
Site
Investment
Strategic
Stakeholder
Needs
Schematic /
Concept Design
Planning
Parameters
Assumptions
• Development
Costs
• Revenue
• Operations
• Funding – debt
and equity
‘Solve for’
Sensitivities
Market testing /
Demand Study
Support Feasibility
Assumptions
Commercial
Positions /
Options and
Recommendation
Delivery Options
and
Recommendation
Certainty
Planning
Design Risk – fit for
purpose?
Construction Risk?
Budget
Management
Programme / Time
Management
Commercial /
Funding Structure
Design Development
Planning Approval
Negotiation and
Execution of Contracts
Financial Close /
Construction
Commencement
Development /
Project Management
Handover
Operations
Opportunity
Identification
Concept
Creation
Feasibility Business Case
Validation
Choose Delivery
Option
Implementation
(Predevelopment and
Delivery)
Iterative process
The Role of the University
Role evolution and adaptability…
Accommodation Projects 1&2
UNIVERSITY ROLE: Equity Investor Only
• Two other equity participants (Financier and Developer) – aligned objectives – University kept safe
• Developer undertook design and delivery risk as well as development management role –
University kept safe
• Third party operator – University kept safe with no occupancy, maintenance or capex risk
Projects 3 &4
UNIVERSITY ROLE: Developer
• Market changed (market failure)
• The ‘template’ had been tested
• Confidence in implementation
• University undertook development with development manager and operator
The Role of the University
Contracting, Financial Close and Delivery – some examples…
Builder
PACE Project (Developer SPV)
The University of Queensland
(Landowner and Tenant)
Completion G’tee /
Performance Bond
Development Manager
Bond Proceeds
PACE Finance
(Debt Financier)
1. Facility Agreement (Loan)
2. Development Agreement
(including Ground (Head) and Tenancy
(Sub) Leases
3. Development Management
Agreement
4. D&C
Contract
Additional PACE Project (Developer)
Documentation
• Principal’s Project Requirements
(PPR)
• Ground Lease / Head Lease
• Superintendent Deed
• Completion Guarantee
• Deed of Assignment of Rents
and Termination Value
• Deed of Assignment of Ground
and Sublease
• Deed of consent to assignment
• Multi-party Deed
• UQ Superintendent Deed
• Precinct Agreement
In addition to the above, some 30
finance documents were also required
for the bond components
University of Queensland, Pharmacy Australia Centre of Excellence (PACE)
The Role of the University
Contracting, Financial Close and Delivery – some examples…
Various
Lease Terms
Terms
3rd party
COMMERCIAL AND
RETAIL TENANTS
DEVELOPER RISK
QUT
as LANDOWNER
ING HEALTHCARE as END OWNER
ground lease conditions
controlled how the developer
can use the land and sets rules
for future (re)development.
ground lease payments in return
for using the QUT land.
ARCBS as pre-
committed
TENANT –
7900sqm
80 year
lease term
Upfront
NPV lease
payment
DEVELOPER
Development, delivery and financial risk minimised to a level
acceptable to QUT & ARCBS
The Development Agreement
ensured that QUT and ARCBS were
shielded from risk and it clearly
detailed the developer’s
development and delivery
obligations.
Developer takes development risk and
provides equity as necessary
QUT as pre-
committed
TENANT –
8300sqm
25 year
lease term
Monthly
lease
paymentsDeveloper negotiates and enters into agreements with:
• D&C contractor
• Development consultants
• Sales agreement with building owner
• Financier (ING Bank)
• Agreements to Lease (under Development Agreement)
• Others as necessary
Lease Payments
Queensland University of Technology and Australian Red Cross Blood Service, Combined Facility
What could possibly go wrong?
Classic Breakdown Points
Translation of the ‘need or idea’ into ‘reality’…
Making the project ‘viable’ – under what definition?
Risk allocation and acceptance
Decision making – who is responsible?
University approvals process (particularly if third party delivery)
Delivery options consideration and comfort level – University through to third party provider
The Principal’s Project Requirements (Design Brief or the ‘glue’) – prescription or performance?
Demand Study Outcomes
Market appetite or even market failure (if third party involvement)
Too many false starts – market becomes wary
Questions?

Weitere ähnliche Inhalte

Ähnlich wie Damien House and Leisl Harris

Pitching the Plan and Financial Projections
Pitching the Plan and Financial ProjectionsPitching the Plan and Financial Projections
Pitching the Plan and Financial ProjectionsThe Capital Network
 
Investing in Commercial Property
 Investing in Commercial Property Investing in Commercial Property
Investing in Commercial PropertyFinancial Poise
 
Offshoring devlearn10
Offshoring devlearn10Offshoring devlearn10
Offshoring devlearn10devlearn10
 
Pitching the Plan (Venture Fast Track preparation)
Pitching the Plan (Venture Fast Track preparation)Pitching the Plan (Venture Fast Track preparation)
Pitching the Plan (Venture Fast Track preparation)The Capital Network
 
Browne Jacobson - Education Law Conference 2016 - Workshop stream 1, Efficien...
Browne Jacobson - Education Law Conference 2016 - Workshop stream 1, Efficien...Browne Jacobson - Education Law Conference 2016 - Workshop stream 1, Efficien...
Browne Jacobson - Education Law Conference 2016 - Workshop stream 1, Efficien...Browne Jacobson LLP
 
Economic Development Financing 101
Economic Development Financing 101Economic Development Financing 101
Economic Development Financing 101MBEDC, LLC
 
SMART International Symposium for Next Generation Infrastructure: Cost Benefi...
SMART International Symposium for Next Generation Infrastructure: Cost Benefi...SMART International Symposium for Next Generation Infrastructure: Cost Benefi...
SMART International Symposium for Next Generation Infrastructure: Cost Benefi...SMART Infrastructure Facility
 
Payel_Banik_resume
Payel_Banik_resumePayel_Banik_resume
Payel_Banik_resumePAYEL BANIK
 
Facility Management Trends Presentation final_1
Facility Management Trends Presentation final_1Facility Management Trends Presentation final_1
Facility Management Trends Presentation final_1Hugh Swan
 
Stanford CS 007-08 (2021): Personal Finance for Engineers / Financial Plannin...
Stanford CS 007-08 (2021): Personal Finance for Engineers / Financial Plannin...Stanford CS 007-08 (2021): Personal Finance for Engineers / Financial Plannin...
Stanford CS 007-08 (2021): Personal Finance for Engineers / Financial Plannin...Adam Nash
 
Stanford CS 007-08: Personal Finance for Engineers / Financial Planning & Goals
Stanford CS 007-08: Personal Finance for Engineers / Financial Planning & GoalsStanford CS 007-08: Personal Finance for Engineers / Financial Planning & Goals
Stanford CS 007-08: Personal Finance for Engineers / Financial Planning & GoalsAdam Nash
 
Stanford CS 007-08 (2018): Personal Finance for Engineers / Financial Plannin...
Stanford CS 007-08 (2018): Personal Finance for Engineers / Financial Plannin...Stanford CS 007-08 (2018): Personal Finance for Engineers / Financial Plannin...
Stanford CS 007-08 (2018): Personal Finance for Engineers / Financial Plannin...Adam Nash
 
On bill presentation for ny utilities
On bill presentation for ny utilitiesOn bill presentation for ny utilities
On bill presentation for ny utilitiesJeremy Epstein
 

Ähnlich wie Damien House and Leisl Harris (20)

Pitching the Plan and Financial Projections
Pitching the Plan and Financial ProjectionsPitching the Plan and Financial Projections
Pitching the Plan and Financial Projections
 
Investing in Commercial Property
 Investing in Commercial Property Investing in Commercial Property
Investing in Commercial Property
 
Pitching the plan
Pitching the planPitching the plan
Pitching the plan
 
Offshoring devlearn10
Offshoring devlearn10Offshoring devlearn10
Offshoring devlearn10
 
Pitching the Plan (Venture Fast Track preparation)
Pitching the Plan (Venture Fast Track preparation)Pitching the Plan (Venture Fast Track preparation)
Pitching the Plan (Venture Fast Track preparation)
 
Are SMSFs close to their 'use by date'?
Are SMSFs close to their 'use by date'?Are SMSFs close to their 'use by date'?
Are SMSFs close to their 'use by date'?
 
dan palmer
dan palmerdan palmer
dan palmer
 
Browne Jacobson - Education Law Conference 2016 - Workshop stream 1, Efficien...
Browne Jacobson - Education Law Conference 2016 - Workshop stream 1, Efficien...Browne Jacobson - Education Law Conference 2016 - Workshop stream 1, Efficien...
Browne Jacobson - Education Law Conference 2016 - Workshop stream 1, Efficien...
 
Colleges and Institutes Canada, June 2020 Presentation
Colleges and Institutes Canada, June 2020 PresentationColleges and Institutes Canada, June 2020 Presentation
Colleges and Institutes Canada, June 2020 Presentation
 
Economic Development Financing 101
Economic Development Financing 101Economic Development Financing 101
Economic Development Financing 101
 
SMART International Symposium for Next Generation Infrastructure: Cost Benefi...
SMART International Symposium for Next Generation Infrastructure: Cost Benefi...SMART International Symposium for Next Generation Infrastructure: Cost Benefi...
SMART International Symposium for Next Generation Infrastructure: Cost Benefi...
 
Payel_Banik_resume
Payel_Banik_resumePayel_Banik_resume
Payel_Banik_resume
 
Facility Management Trends Presentation final_1
Facility Management Trends Presentation final_1Facility Management Trends Presentation final_1
Facility Management Trends Presentation final_1
 
Stanford CS 007-08 (2021): Personal Finance for Engineers / Financial Plannin...
Stanford CS 007-08 (2021): Personal Finance for Engineers / Financial Plannin...Stanford CS 007-08 (2021): Personal Finance for Engineers / Financial Plannin...
Stanford CS 007-08 (2021): Personal Finance for Engineers / Financial Plannin...
 
bpa8_1
bpa8_1bpa8_1
bpa8_1
 
Stanford CS 007-08: Personal Finance for Engineers / Financial Planning & Goals
Stanford CS 007-08: Personal Finance for Engineers / Financial Planning & GoalsStanford CS 007-08: Personal Finance for Engineers / Financial Planning & Goals
Stanford CS 007-08: Personal Finance for Engineers / Financial Planning & Goals
 
Stanford CS 007-08 (2018): Personal Finance for Engineers / Financial Plannin...
Stanford CS 007-08 (2018): Personal Finance for Engineers / Financial Plannin...Stanford CS 007-08 (2018): Personal Finance for Engineers / Financial Plannin...
Stanford CS 007-08 (2018): Personal Finance for Engineers / Financial Plannin...
 
On bill presentation for ny utilities
On bill presentation for ny utilitiesOn bill presentation for ny utilities
On bill presentation for ny utilities
 
Mike Furniss - CV
Mike Furniss - CVMike Furniss - CV
Mike Furniss - CV
 
Mike furniss cv
Mike furniss   cvMike furniss   cv
Mike furniss cv
 

Mehr von Informa Australia (10)

Tom Jordan
Tom JordanTom Jordan
Tom Jordan
 
Colin Marshall
Colin MarshallColin Marshall
Colin Marshall
 
Bec Pannell
Bec PannellBec Pannell
Bec Pannell
 
Renata Matyear
Renata MatyearRenata Matyear
Renata Matyear
 
Introducing the complex
Introducing the complexIntroducing the complex
Introducing the complex
 
Jason Ashton
Jason AshtonJason Ashton
Jason Ashton
 
Student housing conference aug13 bvn_final
Student housing conference aug13 bvn_finalStudent housing conference aug13 bvn_final
Student housing conference aug13 bvn_final
 
Paul Yeates
Paul YeatesPaul Yeates
Paul Yeates
 
Focus session
Focus sessionFocus session
Focus session
 
Liz Cameron
Liz CameronLiz Cameron
Liz Cameron
 

Kürzlich hochgeladen

Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityGeoBlogs
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13Steve Thomason
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformChameera Dedduwage
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxmanuelaromero2013
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactPECB
 
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991RKavithamani
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104misteraugie
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...Marc Dusseiller Dusjagr
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingTechSoup
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdfQucHHunhnh
 
Privatization and Disinvestment - Meaning, Objectives, Advantages and Disadva...
Privatization and Disinvestment - Meaning, Objectives, Advantages and Disadva...Privatization and Disinvestment - Meaning, Objectives, Advantages and Disadva...
Privatization and Disinvestment - Meaning, Objectives, Advantages and Disadva...RKavithamani
 
URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppCeline George
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfsanyamsingh5019
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfchloefrazer622
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdfQucHHunhnh
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxNirmalaLoungPoorunde1
 
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxRoyAbrique
 

Kürzlich hochgeladen (20)

Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activity
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy Reform
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptx
 
Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global Impact
 
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy Consulting
 
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdf
 
Privatization and Disinvestment - Meaning, Objectives, Advantages and Disadva...
Privatization and Disinvestment - Meaning, Objectives, Advantages and Disadva...Privatization and Disinvestment - Meaning, Objectives, Advantages and Disadva...
Privatization and Disinvestment - Meaning, Objectives, Advantages and Disadva...
 
URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website App
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdf
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdf
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdf
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptx
 
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
 

Damien House and Leisl Harris

  • 1. The Accommodation Business Case and the Role of the University 4th Annual Student Housing Forum 23 August 2013 Damien House & Leisl Harris
  • 2. Introduction Who is Social Infrastructure Solutions (SIS)? PAST – full risk developers (FURTHER PAST…. architect, builder, financier, chartered accountant) Some development projects include: • Pharmacy Australia Centre of Excellence (PACE) University of Queensland Pharmacy School, Brisbane ($130m); • Queensland University of Technology Health Faculty / Australian Red Cross Blood Service – Brisbane ($100m); • Australian National University 2,500 student accommodation beds and ancillary facilities, ACT ($280m); and • Twin Towns Services Club 260 key Short Stay Accommodation, Tweed Heads ($80m). NOW – advisors to the university, government, semi-government , NFP and community sectors Some advisory roles include: • Mid West Development Commission – Geraldton Health Education &Training Accommodation Project Business Case and Master Plan, WA; • Goldfields – Esperance Development Commission – Tertiary Education Accommodation Business Case, WA; • Private Developer, Student Accommodation Business Case, South East Queensland; • Plus various Local and State Governments. – Redlands, Sunshine Coast, Victoria Government DEPI; and • Community Sites – Stockland.
  • 3. Introduction How does an organisation whose core business is not accommodation formulate and assess such a Business Case? Damien • Navigating the Business Case? Known knowns and known unknowns but what about unknown unknowns? • Definition of feasible / viable. Is the definition really contestable and what does it mean? • Risk allocation, risk mitigation and risk gates. Leisl • Options for University involvement and role in the development of accommodation. • Contracting, financial close and delivery. • Classic breakdown points.
  • 4. Introduction How does an organisation whose core business is not accommodation formulate and assess such a Business Case? • In our experience - with difficulty, nervously, slowly and sometimes without a result (Decision! Consensus!) • Often our services to assist cannot be articulated and briefed with precision (telling) • There are so many FUNDAMENTAL questions: • How many beds? • What mix of beds • Budget and quality? • Operations outsourcing? • Timeframe? • Whose money? • What investment return? • What price (rent)? • On whose approval? • Whose land? • Amenity inclusions? • Level of pastoral care? • Delivery methodology? • Under whose management and guidance? • Private sector partnering? • Uni underwriting - any/soft/hard? • Ownership term (hold to prove up?) • Profit maximisation?
  • 5. Introduction Context - Business Case • Brief (not only the physical but the BC Brief) • Quantitative aims • Qualitative aims • Measures of success (qualitative) • Demand study • Financial model • Risk analysis • Sensitivity Analysis • Approval pathways • Cost Benefit Analysis (qualitative issues) • SROI Analysis • How wide is the study? Project or University And remember – GIGO - Garbage In Garbage Out!
  • 6. Navigating the Business Case Known knowns and known unknowns but what about unknown unknowns? “Need to be an expert in areas we didn’t know we had to be experts in” Edwina, Day 1 “We don’t know what we don’t know…how do they sleep at night?” Damian, Day 1 • Risk navigation - various tools (see later) • Simplification - paradoxically making things simple is very hard sometimes • Unknown unknowns is expert assistance required? – tens of millions at stake • Unis are some of the most fixed asset rich institutions on the planet • Unis have a great deal of expertise in facility procurement • But this is a separate asset class and potential commercial business stream • Importantly it need not be a commercial business YET • But can be established and structured to be in the future IF NECESSARY
  • 7. Navigating the Business Case Known knowns and known unknowns but what about unknown unknowns? Feasibility context some examples… Known knowns: • Most of the pre-development expenses • construction price and timing (market tested and mitigated by LDs) • interest rate and margin (with hedging max 5-7 years) • Warranties • Operating costs (say 2/3s) Known unknowns: • Latent conditions (risk allocation) • Demand (notwithstanding Demand Study) • Price elasticity • Operating costs (say 1/3)
  • 8. Navigating the Business Case Known knowns and known unknowns but what about unknown unknowns? • Our team started out on one of the first (happy to be challenged here) BOOT student accommodation developments in the country • We had an englobo land agreement with a G8 university • We also had: • three experienced ex-project financiers in the development team • experienced developers in each state • a willing financial institution with UK PFI experience • a tier one contractor • a very nascent professional operator now one of the largest in the country then run by a husband and wife team • We pretty much started from scratch
  • 9. Navigating the Business Case Known knowns and known unknowns but what about unknown unknowns? Frank admissions! Unknown unknowns: • Input tax credits! • Now almost common knowledge but not when the GST was just introduced • Ordinarily, the GST for construction costs CAN NOT be claimed back • This is a complex area of law with some baffling case law precedents • Most recently a successful challenge has been made but under specific circumstances • Price point – always surprised how high! • Rigorously test upside/aggressive assumptions • Price elasticity (airport privatisation financial models explicitly modelled duty free spend)
  • 10. Navigating the Business Case Goods and Services Tax – Known Unknown! Commencing working assumptions: • input tax credits are NOT recovered for any and all capital costs • input tax credits are NOT recovered for any and all operating costs • GST is not charged on the accommodation rentals (and no remission to the ATO is required). Assumes accommodation is “input taxed” - consistent with ATO guidance. However, there is recent case law precedent that may “unlock” the input tax credit by treating the accommodation as “Commercial Residential”. This particular area of indirect tax is a complex area of law with some very contentious and seemingly conflicting decisions in recent cases.
  • 11. Navigating the Business Case Price Point - Disincentives/barriers to private house rental: • lack of single bed accommodation • product not designed for purpose of shared accommodation (ie lacking locks and ensuites) • finding partners to share with for multi bed accommodation • financial commitment for multi bed (underwriting your partners!) • refusal to rent to students • language barriers • term of student lease may not fit market • general logistical difficulty for a young person (never done it) • lawn and garden maintenance costs (if a house) • travel - lack of proximity to campus • safety • lack of student community (if communal amenity is provided) • lack of “house rules” • predatory landlords THESE ITEMS WILL BE VALUED BY STUDENTS IN LONG RUN
  • 12. Definition of Feasible / Viable Is the definition really contestable and what does it mean? • Yes absolutely - it can mean different things to different people • Last two accommodation BC had vastly different starting points and feasibility criteria • One was for a commercial off campus facility incorporating both a refurb of existing and new accommodation development in Brisbane. This needed to meet hurdle rates of return for the transaction term and at specific points through the life of the transaction for equity and debt. • Our last assignment was for an agency of the WA Government in a health education and training precinct. • The feasibility criterion for this project was operationally breakeven. No return ON or OF capital required • NFP providers. What are their criteria? Service mission but how is capital decision made????? • Clearly, the starting point is critical to navigating a successful outcome
  • 13. Definition of Feasible / Viable Solutions Targeting • Solve rent – Base Case assumptions but allowing rent to fluctuate to solve for a xx%pa equity IRR. • Solve capex – Base Case but allowing construction costs to fluctuate to solve for a xx% pa equity IRR. • Solve opex - Base Case assumptions but allowing opex costs to fluctuate to solve for a xx% pa equity IRR. • Solve land price – ditto • Solve break even – for rent, capex, opex (and operationally breakeven) • Solve concession term • Other critical criteria - Project IRR, Equity yield by year, DSCR, ICR, Gearing, Payback • Sinking fund allowance of xx% of revenue treated as cash outflow • Later explicitly model lifecycle costs • General comment • Risk free rates, risk premium, debt tenor, AUD, yield play – all augur well • Qualitative – student experience, VFM, regional WA nurses community vs built environment)
  • 14. The Future…. Hertfordshire University Accomodation – GBP 190m (AUD 300m+) Debt funding via an index-linked unwrapped private bond placement with a maturity of 41 years, one of the longest maturities to be raised for greenfield infrastructure projects. The bond has been rated A- by S&P. The high rating reflects the fact that despite demand risk to which the SPV is exposed, the University is guaranteeing occupancy during construction. The University has also taken credit risk on students, meaning that it will pay if they do not, which provided a significant enhancement in terms of revenue risk. Gearing is 75:25, which also contributed to the high rating. Project details The project is for the DBFO of student accommodation totalling 3,000 bedrooms and associated spaces. Construction involves the development of over 2,500 new bedrooms. Derwent Living’s provision of asset management and facilities management services for the new and existing units will be worth more than GBP 200m over the lifetime of the contract. Derwent Living will also refurbish the existing 500 bedrooms over the next three years. The scheme will be delivered in three phases with the first phase scheduled to be completed in September 2014. Issue amount:GBP 143.5m Maturity: 31 July 2054 Issue price: 100 Coupon: 2.057% Spread: 235bps versus UK 2035 Inflation linked Frequency: Semi-Annual Rating: S&P A-
  • 15. Understanding Risk Risk allocation, risk mitigation and risk gates. • Risk allocation at a broad level is a function of the delivery and operations model • Accommodation need not be delivered under a BOOT model • Our team helped deliver under BOOT and under direct ownership with a third party operator • Much of the completion risk is contained within the building contract and usually for circa 80%+ of cost • Our team has developed several template style RAMMs for different style developments (example) • We also developed a detailed risk capital gate model that ensures appropriate risk taking and expenditure commitment during the critical early phase investigations and through project life (example)
  • 16. The Role of the University What options are available for the University’s involvement and role in the development of accommodation? Consider Student Accommodation – Core University Business or to Support Core University Business? “The Universities do not necessarily recognise the benefit and value that accommodation brings to the students” Laura, Day 1 Just another University asset? Is accommodation the same as an academic / faculty building? “Whose responsibility is it to provide student accommodation – Property and Facilities, Student Services, Others?” Day 1 Discussion What is the best use of limited University capital? Round 5 of NRAS closed 6th August – Secondary market? “We have to more with less, in a more efficient way” Edwina, Day 1 Resources – expertise and capacity Specialist user requirements – design and operations - capital versus operations – lifecycle costs Certainty of outcomes – short (delivery) and long term (operations) Brand – preservation, enhancement and value How does the University ‘stay safe’ throughout the process - from project inception to operations?
  • 17. The Role of the University What options are available for the University’s involvement and role in the development of accommodation? Role Responsibility ‘ON CAMPUS’ Design (fit for intended purpose) Funding (Debt & Equity) Construction (Delivery) Occupancy Operator Maintenance and Capex Comments / Other Developer & Operator D&C or construct only? Full responsibility in all areas (Monash BVN example) Developer Only Operator may or may not take occupancy risk if not the developer. Example: Third party operator takes existing facility. Equity Investor Only Financial returns through term and asset reversion at the end of the term (BOOT example). Partner (with Private Sector) May or may not be required to underwrite minimum occupancy level and may benefit from increased occupancy level. Branding is important to operations. Design guidelines versus operator requirements. Land Owner Only (Contribution via Ground Lease) Certain level of control over design (maybe design guidelines), development or operational outcomes. Brand protection is important. Asset may revert to University at end of life under Ground Lease. Brand Contribution Brand recognition to students (marketing tool) and ease of booking when choosing accommodation is critical and therefore assists occupancy levels.
  • 18. The Role of the University Contracting, Financial Close and Delivery – let’s start building….?? Need Use Market Site Investment Strategic Stakeholder Needs Schematic / Concept Design Planning Parameters Assumptions • Development Costs • Revenue • Operations • Funding – debt and equity ‘Solve for’ Sensitivities Market testing / Demand Study Support Feasibility Assumptions Commercial Positions / Options and Recommendation Delivery Options and Recommendation Certainty Planning Design Risk – fit for purpose? Construction Risk? Budget Management Programme / Time Management Commercial / Funding Structure Design Development Planning Approval Negotiation and Execution of Contracts Financial Close / Construction Commencement Development / Project Management Handover Operations Opportunity Identification Concept Creation Feasibility Business Case Validation Choose Delivery Option Implementation (Predevelopment and Delivery) Iterative process
  • 19. The Role of the University Role evolution and adaptability… Accommodation Projects 1&2 UNIVERSITY ROLE: Equity Investor Only • Two other equity participants (Financier and Developer) – aligned objectives – University kept safe • Developer undertook design and delivery risk as well as development management role – University kept safe • Third party operator – University kept safe with no occupancy, maintenance or capex risk Projects 3 &4 UNIVERSITY ROLE: Developer • Market changed (market failure) • The ‘template’ had been tested • Confidence in implementation • University undertook development with development manager and operator
  • 20. The Role of the University Contracting, Financial Close and Delivery – some examples… Builder PACE Project (Developer SPV) The University of Queensland (Landowner and Tenant) Completion G’tee / Performance Bond Development Manager Bond Proceeds PACE Finance (Debt Financier) 1. Facility Agreement (Loan) 2. Development Agreement (including Ground (Head) and Tenancy (Sub) Leases 3. Development Management Agreement 4. D&C Contract Additional PACE Project (Developer) Documentation • Principal’s Project Requirements (PPR) • Ground Lease / Head Lease • Superintendent Deed • Completion Guarantee • Deed of Assignment of Rents and Termination Value • Deed of Assignment of Ground and Sublease • Deed of consent to assignment • Multi-party Deed • UQ Superintendent Deed • Precinct Agreement In addition to the above, some 30 finance documents were also required for the bond components University of Queensland, Pharmacy Australia Centre of Excellence (PACE)
  • 21. The Role of the University Contracting, Financial Close and Delivery – some examples… Various Lease Terms Terms 3rd party COMMERCIAL AND RETAIL TENANTS DEVELOPER RISK QUT as LANDOWNER ING HEALTHCARE as END OWNER ground lease conditions controlled how the developer can use the land and sets rules for future (re)development. ground lease payments in return for using the QUT land. ARCBS as pre- committed TENANT – 7900sqm 80 year lease term Upfront NPV lease payment DEVELOPER Development, delivery and financial risk minimised to a level acceptable to QUT & ARCBS The Development Agreement ensured that QUT and ARCBS were shielded from risk and it clearly detailed the developer’s development and delivery obligations. Developer takes development risk and provides equity as necessary QUT as pre- committed TENANT – 8300sqm 25 year lease term Monthly lease paymentsDeveloper negotiates and enters into agreements with: • D&C contractor • Development consultants • Sales agreement with building owner • Financier (ING Bank) • Agreements to Lease (under Development Agreement) • Others as necessary Lease Payments Queensland University of Technology and Australian Red Cross Blood Service, Combined Facility
  • 22. What could possibly go wrong? Classic Breakdown Points Translation of the ‘need or idea’ into ‘reality’… Making the project ‘viable’ – under what definition? Risk allocation and acceptance Decision making – who is responsible? University approvals process (particularly if third party delivery) Delivery options consideration and comfort level – University through to third party provider The Principal’s Project Requirements (Design Brief or the ‘glue’) – prescription or performance? Demand Study Outcomes Market appetite or even market failure (if third party involvement) Too many false starts – market becomes wary