11. Outreach and scaling up No. of VWSCs -13980 (75% of total villages) Total funds allocated to villages – Rs. 882.54 mn. Projects completed -4109 Community contribution – Rs. 83.83 mn. No of projects in progress – 3800 No. of women headed committees - 2800 Tariff structures institutionalised -3123 No. of women in the committees – 42,700
12.
13.
14.
15. Diversion of rain water in tubewell benefitted water supply to five villages of Rapar taluka Village pond area: 26550 Sq. M Village pond capacity: 31860 M 3 Recharging tube wells: 2 x 53 M depth, 250 mm dia Diversion wall: 355 m length Total cost of works: Rs. 6,97,000/- Case Study: Village Ramvav, Taluka Rapar, Kutch