SlideShare ist ein Scribd-Unternehmen logo
1 von 14
FIRE FIGHTING IN HIGH
VOLTAGE TRANSFORMERS
NEW IMPULSE TECHNOLOGIES
FIREFIGHTING IMPULSE STORM TECHNOLOGIES AND SYSTEMS
MARCH/2015
Problem
Solution
General Description
Operating Princíple
AGENDA
PROBLEM
Power utilities have installed power substations in their distribution grids to
accommodate the ever-increasing demand for dependable power with their rows
of large high voltage power transformers. Many precautions are taken to
safeguard them against failure because when all power fails, customers
complain, revenues are lost and medical emergencies can even happen.
One of the risks these large transformers are subjected to is fire. Although the
manufacturers of these oil filled transformers are building them with many
imbedded safety features, when they fail they often produce very large fires that
are very hard to extinguish and provoke environmental damages by the release of
thick black toxic smoke and spilling of transformer oil. This is why more and more
utilities are installing fire protection systems to protect their investment and to
prevent such fires. Containment curbs and runoff water catch basins are also
built around the transformers to prevent oil spills in case of problems.
When they are protected, most high voltage power transformers are with a
deluge sprinkler system and designers use NFPA-15 as a guide to design a
system that will cool off the transformer and eventually, extinguish the fire.
PROBLEM
Typical design calls for a grid of open type deluge/spray nozzles to be installed all
around the transformer. A typical system will use about 44 of them and will be
designed to spray about 500 gpm of water for a duration of one (1) hour.
That is a lot of water!
Example typical solution - use big amounts of water due
to flooding, cause collateral damage.
video
PROBLEM
NFPA-850 for Power Plant Design goes even farther, requesting water spray
duration to last a full two (2) hours! But minimum provisions for drainage are
specified to be only large enough to contain the spill from the largest single
container of any flammable or combustible liquid in the area and for fixed fire
suppression systems operating for a minimum of 10 minutes!
A lot of power substations are located in remote areas, or on the outskirts of
towns where water is often not readily available in these large quantities. Water
reservoirs have to be built (often underground) to accommodate this large
demand. They require an initial investment that is fairly high for the utility
company and they also need regular maintenance, factors that are rarely included
in the fire protection contractor's proposal.
Even when water is available in these quantities, powerful fire pumps will be
needed to provide water at a sufficiently high pressure to achieve the goals of the
fire protection system. Infrastructure costs for the utility company rise rapidly, to
the point where some of them don't protect their transformers at all and will simply
provide passive protection measures such as firewalls.
AGENDA
Problem
Solution
General Description
Operating Princíple
SOLUTION
The Impulse New Technologies has developed a solution to these problems:
System ISAS is designed for emergency cooling and extinguishing fires on
transformers using a technology spraying fine dispersed water. Neutral gas
generators are used to create the effect of fine water and water mist.
video
Solution
General Description
AGENDA
Problem
Operating Princíple
GENERAL DESCRIPTION
The system consists of special tanks (ISAS module) which contain not less than
7,500 liters of water and built-in neutral gas generators. Spraying is carried out
through a fine water pulverization system installed around the transformer.
GENERAL DESCRIPTION
ISAS modules must be located in the immediate vicinity from the transformer (the
place is determined together with the customer). ISAS module can be located on
the ground or can be completely hidden underground to create space around the
transformer. The location of the module does not affect its work.
Each ISAS module can operate in two modes:
- Emergency cooling mode, water consumption rate is from 20 to 200 liters per
second
- Fire extinguishing mode, water consumption rate is 300 liters per second.
Due to the possibility of ISAS system to support the constant pressure in the
pipelines during its operation, the levels and locations of pipelines and modules
do not affect the efficiency of the system and can be defined by the Customer to
achieve maximum comfort during operation and maintenance of transformers.
ISAS system has no electric valves and other electrical actuators. It is completely
independent on external power sources and eliminates the possibility of failure of
mechanisms that are bound to external electrical interference as a result of an
accident on the transformer.
GENERAL DESCRIPTION
The system can be adapted for extinguishing with foam.
ISAS system is guaranteed to execute:
1. Start water feed in a fire extinguishing mode not exceeding the timeframe of
five seconds after the fire source determination in an automatic mode. This
timeframe will not exceed 3 seconds in case of a manual start-up.
2. Execute fire extinguishing or emergency cooling at any time during 10 years
the least at the absence of external sources of electricity and water.
3. Perform its work in case of global disaster or accident at the transformers
station and electrical network with a large number of electrical interference.
Solution
Operating Princíple
AGENDA
Problem
General Description
OPERATING PRINCÍPLE
The launch of the ISAS module in the automatic mode is conducted by sending a
low power electrical signal or manually by pressing a button or pulling the
operation ring.
In the automatic mode, the signal to start the system is sent by special
autonomous thermal sensors that automatically generate an electrical signal.
Sensors are 100% independent on external sources of electricity. The sensor is
completely protected from external electrical noise.
After starting the pressure generator, neutral gas (fire aerosol) is supplied into
the module case and this starts the displacement of water into fine sprays or into
the water pipes. The capacity of gas and pressure in the housing is automatically
maintained at the same level regardless of the amount of displaced water. For
emergency pressure release, each ISAS module contains pressure release
valves.
The pressure level in the system during operation shall be determined during the
module charging procedure with pressure generators and can be any in the range
from 0.2 to 2 Mpa.
After starting the module all water is displaced and pressure generator resource
is completely consumed. Recharging the module is conducted by trained
personnel of the customer and it takes less than one hour.
IMPULSE-STORM.COM

Weitere ähnliche Inhalte

Was ist angesagt?

Insulation resistance test
Insulation resistance testInsulation resistance test
Insulation resistance testDonald Stephen
 
Electrical wiring domestic and industries
Electrical wiring domestic and industriesElectrical wiring domestic and industries
Electrical wiring domestic and industriesPavan Kumar Mallepoola
 
Presentation_Power_Transformers-1
Presentation_Power_Transformers-1Presentation_Power_Transformers-1
Presentation_Power_Transformers-1Nageswar Rao
 
Vacuum circuit breaker
Vacuum circuit breakerVacuum circuit breaker
Vacuum circuit breakeropjit88
 
Electric Heat Tracing - Installation Procedures (Thermon Cables)
Electric Heat Tracing - Installation Procedures (Thermon Cables)Electric Heat Tracing - Installation Procedures (Thermon Cables)
Electric Heat Tracing - Installation Procedures (Thermon Cables)Thorne & Derrick UK
 
Buku Pintar MIGAS INDONESIA - Sertifikasi lokasi berbahaya untuk peralatan li...
Buku Pintar MIGAS INDONESIA - Sertifikasi lokasi berbahaya untuk peralatan li...Buku Pintar MIGAS INDONESIA - Sertifikasi lokasi berbahaya untuk peralatan li...
Buku Pintar MIGAS INDONESIA - Sertifikasi lokasi berbahaya untuk peralatan li...Ariyandi Yuda Prahara
 
Understanding Arc Flash
Understanding Arc FlashUnderstanding Arc Flash
Understanding Arc Flashmichaeljmack
 
Survey report on house wiring
Survey report on house wiringSurvey report on house wiring
Survey report on house wiringChandan Garg
 
CIRCUIT BREAKER ON GSS
CIRCUIT BREAKER ON GSSCIRCUIT BREAKER ON GSS
CIRCUIT BREAKER ON GSSDilip kumar
 
Testing and Condition Monitoring of Substation Equipments
Testing and Condition Monitoring of Substation EquipmentsTesting and Condition Monitoring of Substation Equipments
Testing and Condition Monitoring of Substation EquipmentsSumeet Ratnawat
 
Earth Leakage Circuit Breaker
Earth Leakage Circuit BreakerEarth Leakage Circuit Breaker
Earth Leakage Circuit Breakermilanpatel007
 
Testing of circuit breakers
Testing of circuit breakersTesting of circuit breakers
Testing of circuit breakersKabilesh K
 
Switchgear Installation Precomissioning Inspection.PPT
Switchgear Installation  Precomissioning Inspection.PPTSwitchgear Installation  Precomissioning Inspection.PPT
Switchgear Installation Precomissioning Inspection.PPTAbdullah Al Dushaishi
 

Was ist angesagt? (20)

Circuit breaker
Circuit breakerCircuit breaker
Circuit breaker
 
Insulation resistance test
Insulation resistance testInsulation resistance test
Insulation resistance test
 
Electrical wiring domestic and industries
Electrical wiring domestic and industriesElectrical wiring domestic and industries
Electrical wiring domestic and industries
 
Panel check-list
Panel check-listPanel check-list
Panel check-list
 
Presentation_Power_Transformers-1
Presentation_Power_Transformers-1Presentation_Power_Transformers-1
Presentation_Power_Transformers-1
 
Fundamentals of Fire Alarm System
Fundamentals of Fire Alarm SystemFundamentals of Fire Alarm System
Fundamentals of Fire Alarm System
 
Vacuum circuit breaker
Vacuum circuit breakerVacuum circuit breaker
Vacuum circuit breaker
 
Vcb ppt.
Vcb ppt.Vcb ppt.
Vcb ppt.
 
Electric Heat Tracing - Installation Procedures (Thermon Cables)
Electric Heat Tracing - Installation Procedures (Thermon Cables)Electric Heat Tracing - Installation Procedures (Thermon Cables)
Electric Heat Tracing - Installation Procedures (Thermon Cables)
 
Buku Pintar MIGAS INDONESIA - Sertifikasi lokasi berbahaya untuk peralatan li...
Buku Pintar MIGAS INDONESIA - Sertifikasi lokasi berbahaya untuk peralatan li...Buku Pintar MIGAS INDONESIA - Sertifikasi lokasi berbahaya untuk peralatan li...
Buku Pintar MIGAS INDONESIA - Sertifikasi lokasi berbahaya untuk peralatan li...
 
Understanding Arc Flash
Understanding Arc FlashUnderstanding Arc Flash
Understanding Arc Flash
 
Survey report on house wiring
Survey report on house wiringSurvey report on house wiring
Survey report on house wiring
 
Nfpa coods list2
Nfpa coods list2Nfpa coods list2
Nfpa coods list2
 
CIRCUIT BREAKER ON GSS
CIRCUIT BREAKER ON GSSCIRCUIT BREAKER ON GSS
CIRCUIT BREAKER ON GSS
 
Testing and Condition Monitoring of Substation Equipments
Testing and Condition Monitoring of Substation EquipmentsTesting and Condition Monitoring of Substation Equipments
Testing and Condition Monitoring of Substation Equipments
 
Vacuum circuit breaker
Vacuum circuit breakerVacuum circuit breaker
Vacuum circuit breaker
 
Earth Leakage Circuit Breaker
Earth Leakage Circuit BreakerEarth Leakage Circuit Breaker
Earth Leakage Circuit Breaker
 
Testing of circuit breakers
Testing of circuit breakersTesting of circuit breakers
Testing of circuit breakers
 
Switchgear Installation Precomissioning Inspection.PPT
Switchgear Installation  Precomissioning Inspection.PPTSwitchgear Installation  Precomissioning Inspection.PPT
Switchgear Installation Precomissioning Inspection.PPT
 
BUS BAR PROTECTION PPT BY:-R.K.PANDIT
BUS BAR  PROTECTION PPT BY:-R.K.PANDITBUS BAR  PROTECTION PPT BY:-R.K.PANDIT
BUS BAR PROTECTION PPT BY:-R.K.PANDIT
 

Ähnlich wie ISAS system for transformer fire fighting

Inplant training about 110kv/11kv substation
Inplant training about 110kv/11kv substationInplant training about 110kv/11kv substation
Inplant training about 110kv/11kv substationshivashankar307
 
Presentation training
Presentation trainingPresentation training
Presentation trainingSrajan Raj
 
RELINK - benefit of micro inverters
RELINK - benefit of micro invertersRELINK - benefit of micro inverters
RELINK - benefit of micro invertersMarco Achilli
 
TotalEcoEnergy Smart homebuilding solutions
TotalEcoEnergy Smart homebuilding solutionsTotalEcoEnergy Smart homebuilding solutions
TotalEcoEnergy Smart homebuilding solutionsAzi Col
 
Seminar report theory
Seminar report theorySeminar report theory
Seminar report theoryRanjan kumar
 
Transformerless inverters with thin film technology-Danfoss thin film and pid...
Transformerless inverters with thin film technology-Danfoss thin film and pid...Transformerless inverters with thin film technology-Danfoss thin film and pid...
Transformerless inverters with thin film technology-Danfoss thin film and pid...Andreas ILIOU - Elektro- Solar
 
FIRE PREVENTION & FIRE FIGHTING EQUIPMENT-N PPT.pptx
FIRE PREVENTION & FIRE FIGHTING EQUIPMENT-N PPT.pptxFIRE PREVENTION & FIRE FIGHTING EQUIPMENT-N PPT.pptx
FIRE PREVENTION & FIRE FIGHTING EQUIPMENT-N PPT.pptxNeerajTiwari965955
 
Over/Under Voltage Protection Circuit
Over/Under Voltage Protection CircuitOver/Under Voltage Protection Circuit
Over/Under Voltage Protection CircuitMuhammadFazilMemon
 
3 phase transformer protection
3 phase transformer protection3 phase transformer protection
3 phase transformer protectionHimanshu Paghdal
 
Minimax power plant
Minimax power plantMinimax power plant
Minimax power plantFaiz Husein
 
AUTOMATIC RAIN ALARM SENSOR/ CONTINUITY TESTER
    AUTOMATIC RAIN ALARM SENSOR/ CONTINUITY TESTER    AUTOMATIC RAIN ALARM SENSOR/ CONTINUITY TESTER
AUTOMATIC RAIN ALARM SENSOR/ CONTINUITY TESTERFAIZAN SHAFI
 

Ähnlich wie ISAS system for transformer fire fighting (20)

Power backups
Power backupsPower backups
Power backups
 
Subtech profile
Subtech profile Subtech profile
Subtech profile
 
Inplant training about 110kv/11kv substation
Inplant training about 110kv/11kv substationInplant training about 110kv/11kv substation
Inplant training about 110kv/11kv substation
 
Presentation training
Presentation trainingPresentation training
Presentation training
 
RELINK - benefit of micro inverters
RELINK - benefit of micro invertersRELINK - benefit of micro inverters
RELINK - benefit of micro inverters
 
Feigin Electric Co. Ltd.
Feigin Electric Co. Ltd.Feigin Electric Co. Ltd.
Feigin Electric Co. Ltd.
 
Hybrid Cooler
Hybrid CoolerHybrid Cooler
Hybrid Cooler
 
ISAS-F
ISAS-FISAS-F
ISAS-F
 
TotalEcoEnergy Smart homebuilding solutions
TotalEcoEnergy Smart homebuilding solutionsTotalEcoEnergy Smart homebuilding solutions
TotalEcoEnergy Smart homebuilding solutions
 
Seminar report theory
Seminar report theorySeminar report theory
Seminar report theory
 
Moisture controller report total
Moisture controller report totalMoisture controller report total
Moisture controller report total
 
Service solahart bogor 081313462267
Service solahart bogor 081313462267Service solahart bogor 081313462267
Service solahart bogor 081313462267
 
Transformerless inverters with thin film technology-Danfoss thin film and pid...
Transformerless inverters with thin film technology-Danfoss thin film and pid...Transformerless inverters with thin film technology-Danfoss thin film and pid...
Transformerless inverters with thin film technology-Danfoss thin film and pid...
 
PMG Newsletter (Volume 03. Issue 10).pdf
PMG Newsletter (Volume 03. Issue 10).pdfPMG Newsletter (Volume 03. Issue 10).pdf
PMG Newsletter (Volume 03. Issue 10).pdf
 
FIRE PREVENTION & FIRE FIGHTING EQUIPMENT-N PPT.pptx
FIRE PREVENTION & FIRE FIGHTING EQUIPMENT-N PPT.pptxFIRE PREVENTION & FIRE FIGHTING EQUIPMENT-N PPT.pptx
FIRE PREVENTION & FIRE FIGHTING EQUIPMENT-N PPT.pptx
 
Over/Under Voltage Protection Circuit
Over/Under Voltage Protection CircuitOver/Under Voltage Protection Circuit
Over/Under Voltage Protection Circuit
 
3 phase transformer protection
3 phase transformer protection3 phase transformer protection
3 phase transformer protection
 
Final Presentation.pptx
Final Presentation.pptxFinal Presentation.pptx
Final Presentation.pptx
 
Minimax power plant
Minimax power plantMinimax power plant
Minimax power plant
 
AUTOMATIC RAIN ALARM SENSOR/ CONTINUITY TESTER
    AUTOMATIC RAIN ALARM SENSOR/ CONTINUITY TESTER    AUTOMATIC RAIN ALARM SENSOR/ CONTINUITY TESTER
AUTOMATIC RAIN ALARM SENSOR/ CONTINUITY TESTER
 

Mehr von Valeriy Ivanov

Presentation Impulse Storm technologies
Presentation Impulse Storm technologiesPresentation Impulse Storm technologies
Presentation Impulse Storm technologiesValeriy Ivanov
 
New generation technology for firefighting oil tank 80 000 m3
New generation technology for firefighting oil tank 80 000 m3New generation technology for firefighting oil tank 80 000 m3
New generation technology for firefighting oil tank 80 000 m3Valeriy Ivanov
 
Presentation ird direct
Presentation ird directPresentation ird direct
Presentation ird directValeriy Ivanov
 
Supercompressed foam ISAS
Supercompressed foam ISASSupercompressed foam ISAS
Supercompressed foam ISASValeriy Ivanov
 
Mobile ISAS firefighting system
Mobile ISAS firefighting systemMobile ISAS firefighting system
Mobile ISAS firefighting systemValeriy Ivanov
 

Mehr von Valeriy Ivanov (7)

Presentation Impulse Storm technologies
Presentation Impulse Storm technologiesPresentation Impulse Storm technologies
Presentation Impulse Storm technologies
 
New generation technology for firefighting oil tank 80 000 m3
New generation technology for firefighting oil tank 80 000 m3New generation technology for firefighting oil tank 80 000 m3
New generation technology for firefighting oil tank 80 000 m3
 
Tunnels firefighting
Tunnels firefightingTunnels firefighting
Tunnels firefighting
 
Presentation ird direct
Presentation ird directPresentation ird direct
Presentation ird direct
 
Fire tunnels
Fire tunnelsFire tunnels
Fire tunnels
 
Supercompressed foam ISAS
Supercompressed foam ISASSupercompressed foam ISAS
Supercompressed foam ISAS
 
Mobile ISAS firefighting system
Mobile ISAS firefighting systemMobile ISAS firefighting system
Mobile ISAS firefighting system
 

Kürzlich hochgeladen

Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdfKamal Acharya
 
Bridge Jacking Design Sample Calculation.pptx
Bridge Jacking Design Sample Calculation.pptxBridge Jacking Design Sample Calculation.pptx
Bridge Jacking Design Sample Calculation.pptxnuruddin69
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptDineshKumar4165
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapRishantSharmaFr
 
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills KuwaitKuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwaitjaanualu31
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfJiananWang21
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VDineshKumar4165
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"mphochane1998
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptxJIT KUMAR GUPTA
 
kiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal loadkiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal loadhamedmustafa094
 
Rums floating Omkareshwar FSPV IM_16112021.pdf
Rums floating Omkareshwar FSPV IM_16112021.pdfRums floating Omkareshwar FSPV IM_16112021.pdf
Rums floating Omkareshwar FSPV IM_16112021.pdfsmsksolar
 
2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projectssmsksolar
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . pptDineshKumar4165
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueBhangaleSonal
 
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Call Girls Mumbai
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTbhaskargani46
 
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...soginsider
 

Kürzlich hochgeladen (20)

Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdf
 
Bridge Jacking Design Sample Calculation.pptx
Bridge Jacking Design Sample Calculation.pptxBridge Jacking Design Sample Calculation.pptx
Bridge Jacking Design Sample Calculation.pptx
 
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills KuwaitKuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
 
kiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal loadkiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal load
 
Rums floating Omkareshwar FSPV IM_16112021.pdf
Rums floating Omkareshwar FSPV IM_16112021.pdfRums floating Omkareshwar FSPV IM_16112021.pdf
Rums floating Omkareshwar FSPV IM_16112021.pdf
 
2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
 

ISAS system for transformer fire fighting

  • 1. FIRE FIGHTING IN HIGH VOLTAGE TRANSFORMERS NEW IMPULSE TECHNOLOGIES FIREFIGHTING IMPULSE STORM TECHNOLOGIES AND SYSTEMS MARCH/2015
  • 3. PROBLEM Power utilities have installed power substations in their distribution grids to accommodate the ever-increasing demand for dependable power with their rows of large high voltage power transformers. Many precautions are taken to safeguard them against failure because when all power fails, customers complain, revenues are lost and medical emergencies can even happen. One of the risks these large transformers are subjected to is fire. Although the manufacturers of these oil filled transformers are building them with many imbedded safety features, when they fail they often produce very large fires that are very hard to extinguish and provoke environmental damages by the release of thick black toxic smoke and spilling of transformer oil. This is why more and more utilities are installing fire protection systems to protect their investment and to prevent such fires. Containment curbs and runoff water catch basins are also built around the transformers to prevent oil spills in case of problems. When they are protected, most high voltage power transformers are with a deluge sprinkler system and designers use NFPA-15 as a guide to design a system that will cool off the transformer and eventually, extinguish the fire.
  • 4. PROBLEM Typical design calls for a grid of open type deluge/spray nozzles to be installed all around the transformer. A typical system will use about 44 of them and will be designed to spray about 500 gpm of water for a duration of one (1) hour. That is a lot of water! Example typical solution - use big amounts of water due to flooding, cause collateral damage. video
  • 5. PROBLEM NFPA-850 for Power Plant Design goes even farther, requesting water spray duration to last a full two (2) hours! But minimum provisions for drainage are specified to be only large enough to contain the spill from the largest single container of any flammable or combustible liquid in the area and for fixed fire suppression systems operating for a minimum of 10 minutes! A lot of power substations are located in remote areas, or on the outskirts of towns where water is often not readily available in these large quantities. Water reservoirs have to be built (often underground) to accommodate this large demand. They require an initial investment that is fairly high for the utility company and they also need regular maintenance, factors that are rarely included in the fire protection contractor's proposal. Even when water is available in these quantities, powerful fire pumps will be needed to provide water at a sufficiently high pressure to achieve the goals of the fire protection system. Infrastructure costs for the utility company rise rapidly, to the point where some of them don't protect their transformers at all and will simply provide passive protection measures such as firewalls.
  • 7. SOLUTION The Impulse New Technologies has developed a solution to these problems: System ISAS is designed for emergency cooling and extinguishing fires on transformers using a technology spraying fine dispersed water. Neutral gas generators are used to create the effect of fine water and water mist. video
  • 9. GENERAL DESCRIPTION The system consists of special tanks (ISAS module) which contain not less than 7,500 liters of water and built-in neutral gas generators. Spraying is carried out through a fine water pulverization system installed around the transformer.
  • 10. GENERAL DESCRIPTION ISAS modules must be located in the immediate vicinity from the transformer (the place is determined together with the customer). ISAS module can be located on the ground or can be completely hidden underground to create space around the transformer. The location of the module does not affect its work. Each ISAS module can operate in two modes: - Emergency cooling mode, water consumption rate is from 20 to 200 liters per second - Fire extinguishing mode, water consumption rate is 300 liters per second. Due to the possibility of ISAS system to support the constant pressure in the pipelines during its operation, the levels and locations of pipelines and modules do not affect the efficiency of the system and can be defined by the Customer to achieve maximum comfort during operation and maintenance of transformers. ISAS system has no electric valves and other electrical actuators. It is completely independent on external power sources and eliminates the possibility of failure of mechanisms that are bound to external electrical interference as a result of an accident on the transformer.
  • 11. GENERAL DESCRIPTION The system can be adapted for extinguishing with foam. ISAS system is guaranteed to execute: 1. Start water feed in a fire extinguishing mode not exceeding the timeframe of five seconds after the fire source determination in an automatic mode. This timeframe will not exceed 3 seconds in case of a manual start-up. 2. Execute fire extinguishing or emergency cooling at any time during 10 years the least at the absence of external sources of electricity and water. 3. Perform its work in case of global disaster or accident at the transformers station and electrical network with a large number of electrical interference.
  • 13. OPERATING PRINCÍPLE The launch of the ISAS module in the automatic mode is conducted by sending a low power electrical signal or manually by pressing a button or pulling the operation ring. In the automatic mode, the signal to start the system is sent by special autonomous thermal sensors that automatically generate an electrical signal. Sensors are 100% independent on external sources of electricity. The sensor is completely protected from external electrical noise. After starting the pressure generator, neutral gas (fire aerosol) is supplied into the module case and this starts the displacement of water into fine sprays or into the water pipes. The capacity of gas and pressure in the housing is automatically maintained at the same level regardless of the amount of displaced water. For emergency pressure release, each ISAS module contains pressure release valves. The pressure level in the system during operation shall be determined during the module charging procedure with pressure generators and can be any in the range from 0.2 to 2 Mpa. After starting the module all water is displaced and pressure generator resource is completely consumed. Recharging the module is conducted by trained personnel of the customer and it takes less than one hour.