PLANNING AND COST
ANALYSIS OF THE
COMMERCIAL BUILDING
ABSTRACT
 In order to compete in the ever growing competent market it
is very important for a structural engineer to save time.
 As a sequel to this an attempt is made to planning by using
“Auto CAD” and Estimation, costing done by different
methods.
 Planning and cost analysis identifies the overall scope of
work involved in a construction/renovation project.
 For estimating and costing of commercial building can be
calculated by using different methods like Long wall-short
wall method, centre line method , partially centre line and
partially cross wall methods.
INTRODUCTION
 Buildings are important indicator of social
progress of the country.
 Daily new techniques are being developed for
the construction of buildings.
 The building subjected to both vertical and
horizontal loads. The horizontal loads are taken
as per IS 875-1987.And also the material
characteristics are taken from IS 456-2000.
SOFTWARES
 We are doing planning of Commercial Building by
using “AUTOCAD” software.
 In AutoCAD, the word ‘Auto’ came from “Auto desk
company”, and CAD stands for Computer Aided
Designing.
PLANNING
 Planning refers to the process of deciding what to do and
how to do it.
 We have done a planning of G+2 commercial building.
 The building which is used for functions.
The planning of G+2 commercial building can
be done by using “AUTO CAD”.
ESTIMATION
Estimation is the scientific way of working out the
approximate cost of an engineering project before execution
of the work.
Estimation requires a thorough knowledge of the
construction procedures and cost of materials & labour in
addition to the skill ,experience ,foresight etc.
TYPES OF ESTIMATES
 Approximate Estimate
 Model Estimate
 Comparison Estimate and
 Parametric Estimate
 Detailed Estimate
 Complete Estimate
APPROXIMATE ESTIMATE
Preliminary or approximate estimate is required for studies of
various aspects of work project and for its administrative approval.
The estimate is accompanied by a report duly explaining necessity
and utility of the project and with a site or layout plan.
Approximate estimate can be done by 2 parts ,
1.foundation including plinth
2.super structure
MODEL ESTIMATE
 This type of estimate is prepared is based on a modal
project estimate which is developed before .
 Preparing this type of estimate needs length and width of
building, size of base , floor height ,etc.,
 This type of estimate may prepare a details estimate of
whole project or a part of project depending on the
model project.
Comparison Estimate
In this method an estimator prepares a estimate of
proposed project by comparing similar completed
project.
After preparing the comparison estimate , estimator
makes adjustment for variation of proposed project
with the completed project.
Parametric Estimate
 In this type of estimate an estimator uses equations to
prepare the estimations .
 This equation is the relationship between “PARAMETERS”
and “COST “ of building project.
 This type of estimate is done for getting concept of
proposed project cost.
 Now-a-days there are many programmes available in the
market to make the estimation project easy.
Detailed Estimate
The preparation of detailed estimate consists of working out quantities
of various items of work and then determine the cost of each item.
It is the accurate estimate prepared by working out quantities of each
items of work.
This prepared in two stages:
 Details of measurements and calculation of quantities.
 Abstract of Estimated cost
REQUIREMENTS
1. Plans, Elevations, Section Drawings.
2. Specifications.
3. Rates.
Quantity Estimating Methods
The quantities like earth work, foundation concrete,
brickwork in plinth and super structure etc., can be
workout by any of following methods:
a) Long wall – Short wall method
 b) Centre line method
 c) Partly centre line and short wall method
Long wall – Short wall method
 In this method, measure the external length of walls out-to-out
running in the longitudinal direction.
 And also the internal lengths of walls running in the transverse
direction in-to-in i.e. of cross or short walls.
 Then the length of long wall, (out to out) may be calculated
after adding half breadth at each end to its centre line length.
 Thus the length of short wall measured into in and may be
found by deducting half breadth from its centre line length each
end.
Centre line method
 This method is suitable for walls of similar cross sections.
 Here the total centre line length is multiplied by breadth and
depth of respective item to get the total quantity at a time.
 Such junctions or joints are studied carefully while calculating
total centre line length.
 The estimates prepared by this method are most accurate and
quick.
Partly centre line and partly cross wall
method
 This method suits for different thicknesses of walls
and different level of foundations.
 In this external walls and internal walls have
different thicknesses.
 In such cases, center line method is applied to
external walls and Long wall-short wall method is used
for internal walls.
Rate Analysis
Definition:
This process of determining the rates of an item is termed
as analysis of rates or rate analysis.
The rates of items depends on,
1. Specification of works
2. Quantity and quality of materials
3. Cost of labors and their wages.
4. Location of site of work
5. Establishment charges.
6. Profit.
CONCLUSION
1.Planning by using software “AutoCAD”
reduces lot of time and work.
2.Analysis of each member and each material
is obtained from estimation and costing.
THANKYOU
-ila

Weitere ähnliche Inhalte

Was ist angesagt?

Estimation and costing
Estimation and costingEstimation and costing
Estimation and costingGanesh Murugan
 
Principles of building construction, information and communication
Principles of building construction, information and communicationPrinciples of building construction, information and communication
Principles of building construction, information and communicationmichael mcewan
 
Design of residential building
Design of residential buildingDesign of residential building
Design of residential buildingK.MAHESH KUMAR
 
SITEWORKS & SETTING OUT
SITEWORKS & SETTING OUT SITEWORKS & SETTING OUT
SITEWORKS & SETTING OUT Saurav Shrestha
 
Site organization in Construction
Site organization in ConstructionSite organization in Construction
Site organization in ConstructionSamsonFemiAdesope
 
Setting out of building
Setting out of buildingSetting out of building
Setting out of buildingARUN KUMAR
 
estimation,its types and methods
estimation,its types and methodsestimation,its types and methods
estimation,its types and methodsgayu pandian
 
modular coordination
modular coordinationmodular coordination
modular coordinationShailja km
 
Lec 9 center line method
Lec 9 center line methodLec 9 center line method
Lec 9 center line methodmalang1214
 
Analysis and design of building
Analysis and design of buildingAnalysis and design of building
Analysis and design of buildingKrishnagnr
 
Prefabrication construction
Prefabrication constructionPrefabrication construction
Prefabrication constructionDivya Vishnoi
 
Estimating seminar presentation
Estimating seminar presentationEstimating seminar presentation
Estimating seminar presentationseenyeeyong
 

Was ist angesagt? (20)

Analysis of rates
Analysis of ratesAnalysis of rates
Analysis of rates
 
Estimation and costing
Estimation and costingEstimation and costing
Estimation and costing
 
Principles of building construction, information and communication
Principles of building construction, information and communicationPrinciples of building construction, information and communication
Principles of building construction, information and communication
 
Design of residential building
Design of residential buildingDesign of residential building
Design of residential building
 
Bills of quantities
Bills of quantitiesBills of quantities
Bills of quantities
 
Estimating and Costing
Estimating and CostingEstimating and Costing
Estimating and Costing
 
SITEWORKS & SETTING OUT
SITEWORKS & SETTING OUT SITEWORKS & SETTING OUT
SITEWORKS & SETTING OUT
 
Site organization in Construction
Site organization in ConstructionSite organization in Construction
Site organization in Construction
 
Building services
Building servicesBuilding services
Building services
 
Setting out of building
Setting out of buildingSetting out of building
Setting out of building
 
Preliminary estimate
Preliminary estimatePreliminary estimate
Preliminary estimate
 
Modular construction ppt
Modular construction pptModular construction ppt
Modular construction ppt
 
estimation,its types and methods
estimation,its types and methodsestimation,its types and methods
estimation,its types and methods
 
modular coordination
modular coordinationmodular coordination
modular coordination
 
ESTIMATING AND COSTING
ESTIMATING AND COSTINGESTIMATING AND COSTING
ESTIMATING AND COSTING
 
114 site layout
114 site layout114 site layout
114 site layout
 
Lec 9 center line method
Lec 9 center line methodLec 9 center line method
Lec 9 center line method
 
Analysis and design of building
Analysis and design of buildingAnalysis and design of building
Analysis and design of building
 
Prefabrication construction
Prefabrication constructionPrefabrication construction
Prefabrication construction
 
Estimating seminar presentation
Estimating seminar presentationEstimating seminar presentation
Estimating seminar presentation
 

Andere mochten auch

Building Economics assaignment.
Building Economics assaignment.Building Economics assaignment.
Building Economics assaignment.Integrated Design
 
Hotel Design
Hotel DesignHotel Design
Hotel Designkylejanco
 
Building economics presentation 3 2
Building economics presentation 3 2Building economics presentation 3 2
Building economics presentation 3 2Syafiq Zariful
 
Building Economics Group Presentation Slides
Building Economics Group Presentation SlidesBuilding Economics Group Presentation Slides
Building Economics Group Presentation SlidesMelvin Lim
 
InMobi - The Economics of Building an Advertising Supported App Business
InMobi - The Economics of Building an Advertising Supported App BusinessInMobi - The Economics of Building an Advertising Supported App Business
InMobi - The Economics of Building an Advertising Supported App BusinessInMobi
 
Basic Economic Concepts
Basic Economic ConceptsBasic Economic Concepts
Basic Economic ConceptsDan Ewert
 

Andere mochten auch (6)

Building Economics assaignment.
Building Economics assaignment.Building Economics assaignment.
Building Economics assaignment.
 
Hotel Design
Hotel DesignHotel Design
Hotel Design
 
Building economics presentation 3 2
Building economics presentation 3 2Building economics presentation 3 2
Building economics presentation 3 2
 
Building Economics Group Presentation Slides
Building Economics Group Presentation SlidesBuilding Economics Group Presentation Slides
Building Economics Group Presentation Slides
 
InMobi - The Economics of Building an Advertising Supported App Business
InMobi - The Economics of Building an Advertising Supported App BusinessInMobi - The Economics of Building an Advertising Supported App Business
InMobi - The Economics of Building an Advertising Supported App Business
 
Basic Economic Concepts
Basic Economic ConceptsBasic Economic Concepts
Basic Economic Concepts
 

Ähnlich wie Planning and cost analysis of the commercial building

Quantity Surveying & valuation.ppt
Quantity Surveying & valuation.pptQuantity Surveying & valuation.ppt
Quantity Surveying & valuation.pptTauheedKhan45
 
Estimation and Costing
Estimation and Costing Estimation and Costing
Estimation and Costing Vijay325
 
Estimation Costing and Valuation Unit 2
Estimation Costing and Valuation Unit 2Estimation Costing and Valuation Unit 2
Estimation Costing and Valuation Unit 2Padmasinh Patil
 
Construction Planning and Scheduling of Residential Building by MS Project by...
Construction Planning and Scheduling of Residential Building by MS Project by...Construction Planning and Scheduling of Residential Building by MS Project by...
Construction Planning and Scheduling of Residential Building by MS Project by...Shabaz Khan
 
WHAT IS COST ESTIMATION IN PROJECT MANAGEMENT AND THEIR TYPES?
 WHAT IS COST ESTIMATION IN PROJECT MANAGEMENT AND THEIR TYPES? WHAT IS COST ESTIMATION IN PROJECT MANAGEMENT AND THEIR TYPES?
WHAT IS COST ESTIMATION IN PROJECT MANAGEMENT AND THEIR TYPES?MirzaNuman1
 
06 -Estimates, QS_CE, Mar 2021.pdf
06 -Estimates, QS_CE, Mar 2021.pdf06 -Estimates, QS_CE, Mar 2021.pdf
06 -Estimates, QS_CE, Mar 2021.pdfJunaidMughal34
 
Introduction to estimation
Introduction to estimationIntroduction to estimation
Introduction to estimationDhavalMithaiwala
 
Lec.1 Introduction to Estimation
Lec.1   Introduction to EstimationLec.1   Introduction to Estimation
Lec.1 Introduction to EstimationMuthanna Abbu
 
2 Presentation on Estimation and its Methods.pptx
2 Presentation on Estimation and its Methods.pptx2 Presentation on Estimation and its Methods.pptx
2 Presentation on Estimation and its Methods.pptxRaniVishwakarma15
 
ECONOMICS%20FOR%20ENGINEERS%20%5BHM-EE601%5D_removed.pdf
ECONOMICS%20FOR%20ENGINEERS%20%5BHM-EE601%5D_removed.pdfECONOMICS%20FOR%20ENGINEERS%20%5BHM-EE601%5D_removed.pdf
ECONOMICS%20FOR%20ENGINEERS%20%5BHM-EE601%5D_removed.pdfSURAJITDASBAURI
 
Unit 1 - General Items used for building
Unit 1 - General Items used for buildingUnit 1 - General Items used for building
Unit 1 - General Items used for buildingHimani762003
 
EJMCM_Volume 7_Issue 4_Pages 310-318.pdf
EJMCM_Volume 7_Issue 4_Pages 310-318.pdfEJMCM_Volume 7_Issue 4_Pages 310-318.pdf
EJMCM_Volume 7_Issue 4_Pages 310-318.pdfkripeshdubey1
 
م.80-مبادرة #تواصل_تطويرم.أحمد سعيد رفاعهى-دورة حياة تقدير التكلفة بمشروعات ا...
م.80-مبادرة #تواصل_تطويرم.أحمد سعيد رفاعهى-دورة حياة تقدير التكلفة بمشروعات ا...م.80-مبادرة #تواصل_تطويرم.أحمد سعيد رفاعهى-دورة حياة تقدير التكلفة بمشروعات ا...
م.80-مبادرة #تواصل_تطويرم.أحمد سعيد رفاعهى-دورة حياة تقدير التكلفة بمشروعات ا...Egyptian Engineers Association
 
Quantity Survey and Estimation basic terms
Quantity Survey and Estimation basic termsQuantity Survey and Estimation basic terms
Quantity Survey and Estimation basic termsmeghajain275
 
Project Proposal for Development Training
Project Proposal for Development TrainingProject Proposal for Development Training
Project Proposal for Development Trainingnipperb6
 
Aiet e&c lecture_notes
Aiet  e&c lecture_notesAiet  e&c lecture_notes
Aiet e&c lecture_notesDr.K.Mohan Das
 
chapter3-210122050220.pdf
chapter3-210122050220.pdfchapter3-210122050220.pdf
chapter3-210122050220.pdfDeepak37004
 

Ähnlich wie Planning and cost analysis of the commercial building (20)

Quantity Surveying & valuation.ppt
Quantity Surveying & valuation.pptQuantity Surveying & valuation.ppt
Quantity Surveying & valuation.ppt
 
Estimation and Costing
Estimation and Costing Estimation and Costing
Estimation and Costing
 
Estimation Costing and Valuation Unit 2
Estimation Costing and Valuation Unit 2Estimation Costing and Valuation Unit 2
Estimation Costing and Valuation Unit 2
 
Construction Planning and Scheduling of Residential Building by MS Project by...
Construction Planning and Scheduling of Residential Building by MS Project by...Construction Planning and Scheduling of Residential Building by MS Project by...
Construction Planning and Scheduling of Residential Building by MS Project by...
 
Ecv
EcvEcv
Ecv
 
WHAT IS COST ESTIMATION IN PROJECT MANAGEMENT AND THEIR TYPES?
 WHAT IS COST ESTIMATION IN PROJECT MANAGEMENT AND THEIR TYPES? WHAT IS COST ESTIMATION IN PROJECT MANAGEMENT AND THEIR TYPES?
WHAT IS COST ESTIMATION IN PROJECT MANAGEMENT AND THEIR TYPES?
 
06 -Estimates, QS_CE, Mar 2021.pdf
06 -Estimates, QS_CE, Mar 2021.pdf06 -Estimates, QS_CE, Mar 2021.pdf
06 -Estimates, QS_CE, Mar 2021.pdf
 
Introduction to estimation
Introduction to estimationIntroduction to estimation
Introduction to estimation
 
Lec.1 Introduction to Estimation
Lec.1   Introduction to EstimationLec.1   Introduction to Estimation
Lec.1 Introduction to Estimation
 
2 Presentation on Estimation and its Methods.pptx
2 Presentation on Estimation and its Methods.pptx2 Presentation on Estimation and its Methods.pptx
2 Presentation on Estimation and its Methods.pptx
 
ECONOMICS%20FOR%20ENGINEERS%20%5BHM-EE601%5D_removed.pdf
ECONOMICS%20FOR%20ENGINEERS%20%5BHM-EE601%5D_removed.pdfECONOMICS%20FOR%20ENGINEERS%20%5BHM-EE601%5D_removed.pdf
ECONOMICS%20FOR%20ENGINEERS%20%5BHM-EE601%5D_removed.pdf
 
Unit 1 - General Items used for building
Unit 1 - General Items used for buildingUnit 1 - General Items used for building
Unit 1 - General Items used for building
 
EJMCM_Volume 7_Issue 4_Pages 310-318.pdf
EJMCM_Volume 7_Issue 4_Pages 310-318.pdfEJMCM_Volume 7_Issue 4_Pages 310-318.pdf
EJMCM_Volume 7_Issue 4_Pages 310-318.pdf
 
م.80-مبادرة #تواصل_تطويرم.أحمد سعيد رفاعهى-دورة حياة تقدير التكلفة بمشروعات ا...
م.80-مبادرة #تواصل_تطويرم.أحمد سعيد رفاعهى-دورة حياة تقدير التكلفة بمشروعات ا...م.80-مبادرة #تواصل_تطويرم.أحمد سعيد رفاعهى-دورة حياة تقدير التكلفة بمشروعات ا...
م.80-مبادرة #تواصل_تطويرم.أحمد سعيد رفاعهى-دورة حياة تقدير التكلفة بمشروعات ا...
 
Quantity Survey and Estimation basic terms
Quantity Survey and Estimation basic termsQuantity Survey and Estimation basic terms
Quantity Survey and Estimation basic terms
 
Quantity take off
Quantity take offQuantity take off
Quantity take off
 
Project Proposal for Development Training
Project Proposal for Development TrainingProject Proposal for Development Training
Project Proposal for Development Training
 
Aiet e&c lecture_notes
Aiet  e&c lecture_notesAiet  e&c lecture_notes
Aiet e&c lecture_notes
 
Estimation
EstimationEstimation
Estimation
 
chapter3-210122050220.pdf
chapter3-210122050220.pdfchapter3-210122050220.pdf
chapter3-210122050220.pdf
 

Mehr von ila vamsi krishna

COMPOSITION AND MANUFACTURING OF BRICKS.pptx
COMPOSITION AND MANUFACTURING OF BRICKS.pptxCOMPOSITION AND MANUFACTURING OF BRICKS.pptx
COMPOSITION AND MANUFACTURING OF BRICKS.pptxila vamsi krishna
 
CLASSIFICATION AND CHARACTERISTICS OF BRICK
CLASSIFICATION AND CHARACTERISTICS OF BRICKCLASSIFICATION AND CHARACTERISTICS OF BRICK
CLASSIFICATION AND CHARACTERISTICS OF BRICKila vamsi krishna
 
COST EFFECTIVE GEOPOLYMER BRICKS -1
COST EFFECTIVE GEOPOLYMER BRICKS -1COST EFFECTIVE GEOPOLYMER BRICKS -1
COST EFFECTIVE GEOPOLYMER BRICKS -1ila vamsi krishna
 
ANALYSIS AND DESIGN OF HIGH RISE BUILDING BY USING ETABS
ANALYSIS AND DESIGN OF HIGH RISE BUILDING BY USING ETABSANALYSIS AND DESIGN OF HIGH RISE BUILDING BY USING ETABS
ANALYSIS AND DESIGN OF HIGH RISE BUILDING BY USING ETABSila vamsi krishna
 
Results of ETABS on HIGH RISE RESIDENTIAL BUILDINGS
Results of ETABS on HIGH RISE RESIDENTIAL BUILDINGSResults of ETABS on HIGH RISE RESIDENTIAL BUILDINGS
Results of ETABS on HIGH RISE RESIDENTIAL BUILDINGSila vamsi krishna
 
Calculating quantity of cement in m20 grade concrete
Calculating quantity of cement in m20 grade concreteCalculating quantity of cement in m20 grade concrete
Calculating quantity of cement in m20 grade concreteila vamsi krishna
 
Planning and cost analysis of the commercial building
Planning and cost analysis of the commercial buildingPlanning and cost analysis of the commercial building
Planning and cost analysis of the commercial buildingila vamsi krishna
 
Experimental investigation of ohns surface property and process parameter on ...
Experimental investigation of ohns surface property and process parameter on ...Experimental investigation of ohns surface property and process parameter on ...
Experimental investigation of ohns surface property and process parameter on ...ila vamsi krishna
 
Preliminary design of column
Preliminary design of columnPreliminary design of column
Preliminary design of columnila vamsi krishna
 
ANALYSIS AND DESIGN OF G+4 RESIDENTIAL BUILDING contents
ANALYSIS AND DESIGN OF G+4 RESIDENTIAL BUILDING contentsANALYSIS AND DESIGN OF G+4 RESIDENTIAL BUILDING contents
ANALYSIS AND DESIGN OF G+4 RESIDENTIAL BUILDING contentsila vamsi krishna
 
residential buliding by stadd pro
residential buliding by stadd proresidential buliding by stadd pro
residential buliding by stadd proila vamsi krishna
 
COMPRESSIVE STRENGTH OF CONCRETE BY USING WASTE MATERIALS
COMPRESSIVE STRENGTH OF CONCRETE BY USING WASTE MATERIALSCOMPRESSIVE STRENGTH OF CONCRETE BY USING WASTE MATERIALS
COMPRESSIVE STRENGTH OF CONCRETE BY USING WASTE MATERIALSila vamsi krishna
 
Surplus weir when flood discharge known
Surplus weir when flood discharge knownSurplus weir when flood discharge known
Surplus weir when flood discharge knownila vamsi krishna
 
Sloping glacis weir OR canal drop
Sloping glacis weir OR canal dropSloping glacis weir OR canal drop
Sloping glacis weir OR canal dropila vamsi krishna
 

Mehr von ila vamsi krishna (20)

COMPOSITION AND MANUFACTURING OF BRICKS.pptx
COMPOSITION AND MANUFACTURING OF BRICKS.pptxCOMPOSITION AND MANUFACTURING OF BRICKS.pptx
COMPOSITION AND MANUFACTURING OF BRICKS.pptx
 
CLASSIFICATION AND CHARACTERISTICS OF BRICK
CLASSIFICATION AND CHARACTERISTICS OF BRICKCLASSIFICATION AND CHARACTERISTICS OF BRICK
CLASSIFICATION AND CHARACTERISTICS OF BRICK
 
COST EFFECTIVE GEOPOLYMER BRICKS -1
COST EFFECTIVE GEOPOLYMER BRICKS -1COST EFFECTIVE GEOPOLYMER BRICKS -1
COST EFFECTIVE GEOPOLYMER BRICKS -1
 
ANALYSIS AND DESIGN OF HIGH RISE BUILDING BY USING ETABS
ANALYSIS AND DESIGN OF HIGH RISE BUILDING BY USING ETABSANALYSIS AND DESIGN OF HIGH RISE BUILDING BY USING ETABS
ANALYSIS AND DESIGN OF HIGH RISE BUILDING BY USING ETABS
 
Results of ETABS on HIGH RISE RESIDENTIAL BUILDINGS
Results of ETABS on HIGH RISE RESIDENTIAL BUILDINGSResults of ETABS on HIGH RISE RESIDENTIAL BUILDINGS
Results of ETABS on HIGH RISE RESIDENTIAL BUILDINGS
 
Calculating quantity of cement in m20 grade concrete
Calculating quantity of cement in m20 grade concreteCalculating quantity of cement in m20 grade concrete
Calculating quantity of cement in m20 grade concrete
 
Self compaction concrete
Self compaction concreteSelf compaction concrete
Self compaction concrete
 
Planning and cost analysis of the commercial building
Planning and cost analysis of the commercial buildingPlanning and cost analysis of the commercial building
Planning and cost analysis of the commercial building
 
Experimental investigation of ohns surface property and process parameter on ...
Experimental investigation of ohns surface property and process parameter on ...Experimental investigation of ohns surface property and process parameter on ...
Experimental investigation of ohns surface property and process parameter on ...
 
Preliminary design of slab
Preliminary design of slabPreliminary design of slab
Preliminary design of slab
 
Preliminary design of beam
Preliminary design of beamPreliminary design of beam
Preliminary design of beam
 
Preliminary design of column
Preliminary design of columnPreliminary design of column
Preliminary design of column
 
design of stair case
design of stair casedesign of stair case
design of stair case
 
ANALYSIS AND DESIGN OF G+4 RESIDENTIAL BUILDING contents
ANALYSIS AND DESIGN OF G+4 RESIDENTIAL BUILDING contentsANALYSIS AND DESIGN OF G+4 RESIDENTIAL BUILDING contents
ANALYSIS AND DESIGN OF G+4 RESIDENTIAL BUILDING contents
 
residential buliding by stadd pro
residential buliding by stadd proresidential buliding by stadd pro
residential buliding by stadd pro
 
COMPRESSIVE STRENGTH OF CONCRETE BY USING WASTE MATERIALS
COMPRESSIVE STRENGTH OF CONCRETE BY USING WASTE MATERIALSCOMPRESSIVE STRENGTH OF CONCRETE BY USING WASTE MATERIALS
COMPRESSIVE STRENGTH OF CONCRETE BY USING WASTE MATERIALS
 
Tank sluice with tower head
Tank sluice with tower headTank sluice with tower head
Tank sluice with tower head
 
Surplus weir when flood discharge known
Surplus weir when flood discharge knownSurplus weir when flood discharge known
Surplus weir when flood discharge known
 
Sloping glacis weir OR canal drop
Sloping glacis weir OR canal dropSloping glacis weir OR canal drop
Sloping glacis weir OR canal drop
 
Canal regulator
Canal regulatorCanal regulator
Canal regulator
 

Kürzlich hochgeladen

power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and usesDevarapalliHaritha
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxvipinkmenon1
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 

Kürzlich hochgeladen (20)

power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and uses
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptx
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 

Planning and cost analysis of the commercial building

  • 1. PLANNING AND COST ANALYSIS OF THE COMMERCIAL BUILDING
  • 2. ABSTRACT  In order to compete in the ever growing competent market it is very important for a structural engineer to save time.  As a sequel to this an attempt is made to planning by using “Auto CAD” and Estimation, costing done by different methods.  Planning and cost analysis identifies the overall scope of work involved in a construction/renovation project.  For estimating and costing of commercial building can be calculated by using different methods like Long wall-short wall method, centre line method , partially centre line and partially cross wall methods.
  • 3. INTRODUCTION  Buildings are important indicator of social progress of the country.  Daily new techniques are being developed for the construction of buildings.  The building subjected to both vertical and horizontal loads. The horizontal loads are taken as per IS 875-1987.And also the material characteristics are taken from IS 456-2000.
  • 4. SOFTWARES  We are doing planning of Commercial Building by using “AUTOCAD” software.  In AutoCAD, the word ‘Auto’ came from “Auto desk company”, and CAD stands for Computer Aided Designing.
  • 5. PLANNING  Planning refers to the process of deciding what to do and how to do it.  We have done a planning of G+2 commercial building.  The building which is used for functions. The planning of G+2 commercial building can be done by using “AUTO CAD”.
  • 6.
  • 7.
  • 8.
  • 9.
  • 10. ESTIMATION Estimation is the scientific way of working out the approximate cost of an engineering project before execution of the work. Estimation requires a thorough knowledge of the construction procedures and cost of materials & labour in addition to the skill ,experience ,foresight etc.
  • 11. TYPES OF ESTIMATES  Approximate Estimate  Model Estimate  Comparison Estimate and  Parametric Estimate  Detailed Estimate  Complete Estimate
  • 12. APPROXIMATE ESTIMATE Preliminary or approximate estimate is required for studies of various aspects of work project and for its administrative approval. The estimate is accompanied by a report duly explaining necessity and utility of the project and with a site or layout plan. Approximate estimate can be done by 2 parts , 1.foundation including plinth 2.super structure
  • 13. MODEL ESTIMATE  This type of estimate is prepared is based on a modal project estimate which is developed before .  Preparing this type of estimate needs length and width of building, size of base , floor height ,etc.,  This type of estimate may prepare a details estimate of whole project or a part of project depending on the model project.
  • 14. Comparison Estimate In this method an estimator prepares a estimate of proposed project by comparing similar completed project. After preparing the comparison estimate , estimator makes adjustment for variation of proposed project with the completed project.
  • 15. Parametric Estimate  In this type of estimate an estimator uses equations to prepare the estimations .  This equation is the relationship between “PARAMETERS” and “COST “ of building project.  This type of estimate is done for getting concept of proposed project cost.  Now-a-days there are many programmes available in the market to make the estimation project easy.
  • 16. Detailed Estimate The preparation of detailed estimate consists of working out quantities of various items of work and then determine the cost of each item. It is the accurate estimate prepared by working out quantities of each items of work. This prepared in two stages:  Details of measurements and calculation of quantities.  Abstract of Estimated cost
  • 17.
  • 18. REQUIREMENTS 1. Plans, Elevations, Section Drawings. 2. Specifications. 3. Rates.
  • 19. Quantity Estimating Methods The quantities like earth work, foundation concrete, brickwork in plinth and super structure etc., can be workout by any of following methods: a) Long wall – Short wall method  b) Centre line method  c) Partly centre line and short wall method
  • 20. Long wall – Short wall method  In this method, measure the external length of walls out-to-out running in the longitudinal direction.  And also the internal lengths of walls running in the transverse direction in-to-in i.e. of cross or short walls.  Then the length of long wall, (out to out) may be calculated after adding half breadth at each end to its centre line length.  Thus the length of short wall measured into in and may be found by deducting half breadth from its centre line length each end.
  • 21. Centre line method  This method is suitable for walls of similar cross sections.  Here the total centre line length is multiplied by breadth and depth of respective item to get the total quantity at a time.  Such junctions or joints are studied carefully while calculating total centre line length.  The estimates prepared by this method are most accurate and quick.
  • 22. Partly centre line and partly cross wall method  This method suits for different thicknesses of walls and different level of foundations.  In this external walls and internal walls have different thicknesses.  In such cases, center line method is applied to external walls and Long wall-short wall method is used for internal walls.
  • 23.
  • 24. Rate Analysis Definition: This process of determining the rates of an item is termed as analysis of rates or rate analysis. The rates of items depends on, 1. Specification of works 2. Quantity and quality of materials 3. Cost of labors and their wages. 4. Location of site of work 5. Establishment charges. 6. Profit.
  • 25. CONCLUSION 1.Planning by using software “AutoCAD” reduces lot of time and work. 2.Analysis of each member and each material is obtained from estimation and costing.