MET 401 Chapter 10 -_economics_of_power_generation_-_a._rezk
1. MET401 Power Plant Engineering
Economics of Power
Generation
DR. TAIB ISKANDAR & DR. AHMED REZK
2. Introduction
2
Why do we need economic analysis?
The main purpose of design and operation of a power
plant is to bring the cost of energy produced to
minimum.
Thermal efficiency of a plant is one of the important
factors in determining energy cost.
The most thermally efficient plant is not the most
economics.
3. Types of power plants
3
Thermal
fossil fuels, coal, fuel oil & natural gas.
• Similar in cycle
80% of world electricity. • Similar in structure
Nuclear • Use steam as a working fluid
Geothermal
Hydraulic
Multipurpose plants (generating power, flood control, etc..)
Gas turbine plants
They run for a short time to meet the peak load demand
They are used in the combined steam power plant.
5. Production rate
5
Electricity production, E dE
Ei
Annual fractional dt
E
increase rate, i (%) ln i (t to )
Eo
Eo=electricity production i(t to )
E Eoe
at year t0
tD t2 t1
E2
2
To find time required for E1
electricity production to ln 2 it D
be doubled, we define tD 0 . 693
tD
as doubling time i
6. Planning a new power plant
6
When planning a new power plant there are two
considered factors.
Total power output to be installed (kWinst)
First demand (kWmax).
Growth of demand.
Reserve capacity required.
500MW plant
Size of generating units
Load variation during 24hr
Total capacity of units connected to grid
Minimum start up and shut down periods
Maintenance program Unit 1 Unit 2 Unit 3
Plant efficiency
Price and space per kW vs. unit
8. Electricity supply industry factors
8
Load factor (m)
average load over a time interval
m
peak load during the same interval
kWh ave
m " one year 24 * 365 8760"
kW max x 8760
Capacity factor / plant factor (n)
average load
n
rated capacity of plant
kWhr gen
kWhr gen
n
kW inst x 24 x 365 kW inst x 8760
9. Electricity supply industry factors
9
Reserve factor (r)
kW inst m
r
kW max n
load factor
r
capacity factor
Demand factor (dem)
actual maximum demand
dem
total connected demand
kW max
dem
kW connected
10. Electricity supply industry factors
10
Diversity factor (div)
sum of invidual consumer groups
div
actual peak load of system
a b c
div
kW peak
Use factor (u)
kWh gen
u
kW inst x operating hours
11. Example 1
11
A steam power plant have a peak load of 65 MW.
Connected to it are five loads having maximum
demands of 20 MW, 15 MW, 10 MW, 10 MW and 5
MW each. Plant capacity is 90MW and annual load
factor is 0.60. Determine,
a) the average load on the power plant
b) the energy supplied annually
c) the demand factor
d) the diversity factor
e) the use factor if plant only operate 8000 hrs per year
f) What do you think about this plant economically?
12. Power plants location
12
For thermal power plant
Availability of cooling water
Availability of fuel
Distance from center of load demand
Land cost and characteristics
Wind direction & water stream
Disposal of fuel waste and ashes
Staff accommodations
Rail and road connections
Security
For hydraulic power plant
Availability of water and water head
13. Power plant economics
13
The cost per kWhnet is determined by
Fixed cost (FC)
Interest (I)
Depend on capital invest
Depreciation (D)
(construction cost)
Taxes and insurance (T)
Operation and maintenance (O&M) covering
Salaries and wages
Overhauling of equipment
Repairs including spare parts, lubricants, miscellaneous, etc..
Fuel cost
kWhrnet sent out
14. Power plant economics
14
Total annual cost
I D T
Ct Cc (W R M ) C f
100
Cc – construction cost
W – wages
R – repairs and maintenance
M – miscellaneous.
Cf – fuel cost
Annual amount of electricity sent out
L aux
kWh net
kW inst x 8760 x 1 x n
100
Laux = power consumption by auxiliaries
n = plant capacity factor
15. Cost reduction
15
The costs have a continuous upward mainly due to
monetary inflation, rising fuel prices. It can be reduced
by applying the following:
Select equipment with longer life and proper capacity
Run at high load factor
Increase power plant efficiency
Proper maintenance to reduce breakdown
Keep a proper supervision
Simple design (less dependent on highly skilled worker)
16. Example 2
16
Connected Demand
A new housing development is to be added Store or service
load (kW) factor (d) %
to the lines of a public electrical network 1- laundry 25 0.66
There are 2500 apartments each having a 3-mosques 12 each 0.58
1-resturant 60 0.50
connected load of 6 kW, with the 1-bookstore 8 0.68
commercial load shown. The demand factor 2-drugsstores 10 each 0.77
of the apartments is 55%. The group 2-grocery stores 5 each 0.75
1-shoe store 2 0.69
diversity factor of the residential load is 2.5, 1-cloting store 6 0.56
and the peak diversity factor is 1.5, and the 1-theater 95 0.45
commercial – load group diversity factor is
1.6 and the peak diversity factor is 1.1.
Find the maximum demand of each group and the system peak
demand.