Session 9
Critical Chain
Single-Project Management
Reducing Project Duration by 25%
& Increasing Due Date Performance
Without Changes of Resource Capacity
Dr. Thomas Lechler Phone: (201) 216-8174
Babbio Center 416 FAX: (201) 216-5385
email: tlechler@stevens.edu
Date/reference/classification
2
© T. Lechler, Ph.D., 2013
1. Paradigm Question: Process Value
How much would your organization gain if over 90%
of the projects are finished in time?
How much would your organization gain if all new
projects starting next month finished 15-25% sooner?
• Reduced project cost?
• Faster time-to-market?
• Greater responsiveness to customers?
Date/reference/classification
3
© T. Lechler, Ph.D., 2013
1. Paradigm Question: Management Problems
Why is it so difficult to manage projects which
deliver on time, within budget and with the full
specification or scope intact ?
•__________________________________________________
•__________________________________________________
•__________________________________________________
•__________________________________________________
•__________________________________________________
Date/reference/classification
4
© T. Lechler, Ph.D., 2013
1. Paradigm Question: Project Manager’s Dilemma
• PRESSURE TO INCREASE SAFETY TIME - in order to complete projects on time
• PRESSURE TO REDUCE OVERALL PROJECT SCHEDULE - in order to meet the
customers need for shorter lead times
Be a good
Project Manager
Complete Projects
on time
(to be realistic)
Add protection
to tasks
Don’t add
protection to
tasks
PrerequisiteRequirement
Respond to
customers need for
short lead times
(quick response)
Objective
Date/reference/classification
5
© T. Lechler, Ph.D., 2013
1. Paradigm Question: CPM Management of Uncertainty
Often projects
have difficulty
staying within
budget
Often scope or
specifications are
cut from project
The Way We Manage
Uncertainty in
Projects
Often projects
have difficulty
finishing on time
YOU CAN’T IMPOSE CERTAINTY ON UNCERTAINTY
YOU MUST LEARN TO MANAGE THE UNCERTAINTY
Date/reference/classification
6
© T. Lechler, Ph.D., 2013
1. Paradigm Question: CPM Estimation
Average Work Uncertainty
Multitasking Set-up Time
Task Estimate - (Duration)
Basic Estimation Equation: W = U * D
W: Estimate of Work
U: Units of Resources
D: Duration
 Inflated Estimates!
Date/reference/classification
7
© T. Lechler, Ph.D., 2013
1. Paradigm Question: CPM Assumptions
Basic assumptions of the CPM paradigm:
1. Each task is scheduled with 90% likelihood thus the project is
scheduled with 90% likelihood. But:
Due date on a big project may be less than 10% likely even if the
single tasks are scheduled with 90%!
2. The critical path does not change. But:
The critical path changes in many projects!
3. Good and bad luck average out. But:
Good luck is wasted and bad luck accumulates because
- Scheduled tasks are started with delays (Student Syndrome)
- Early task finish is often not reported (Parkinson’s Law)
=> What are the consequences?
Date/reference/classification
8
© T. Lechler, Ph.D., 2013
1. Paradigm Question: CPM Assumption 1
Two scenarios:
1. All single tasks on the critical path are planned with 90%
accuracy: The probability to achieve the planned finish date is:
38% (=0.9 EXP 9)
2. One of the 9 tasks could be only planned with 80% accuracy and
one with 50%. The likelihood to achieve the planned finish date is:
18%!
Start
0d 9/1
(a) Initiate project
5d 9/1
(b) Assign PM
2d 9/8
(h) Design IPF
9d 9/12
(g) Conduct IPD
training
5d 9/28 (m) Conduct IPF
training
7d 10/5
(j) Prepare business
case
7d 10/5
(l) Finalize IPP
9d 10/18
(k) Write IPP
3d 10/13
(e) Develop project
schedule
10d 9/28
(i) Assign resources
1d 10/12
(d) Form PDT
12d 9/12
(f) Prepare expense
estimates
9d 9/28
Concept DCP
0d 10/28
(c) Establish
constraints
6d 9/8
(n) Reproduce
documents
8d 10/14
Date/reference/classification
9
© T. Lechler, Ph.D., 2013
1. Paradigm Question: CPM Assumption 2
Critical Path is not stable!
Determine budget
4 1d
Wed 6/1/94 Wed 6/1/94
Selection
6 120h
Thu 6/2/94 Wed 6/22/94
Theme
7 2d
Thu 6/2/94 Fri 6/3/94
Date
8 3d
Mon 6/6/94 Wed 6/8/94
Site
9 1w
Thu 6/9/94 Wed 6/15/94
Costumes
10 1w
Thu 6/16/94 Wed 6/22/94
Hire
11 168h
Thu 6/23/94 Thu 7/21/94
Caterer
12 2d
Thu 6/23/94 Fri 6/24/94
Entertainment
13 9d
Mon 6/27/94 Thu 7/7/94
Keynote speaker
14 2w
Fri 7/8/94 Thu 7/21/94
Public relations
15 88h
Fri 7/22/94 Fri 8/5/94
Rent Equipment
18 40h
Mon 8/8/94 Fri 8/12/94
Invitation list
5 1d
Wed 6/1/94 Wed 6/1/94
Date/reference/classification
10
© T. Lechler, Ph.D., 2013
1. Paradigm Question: CPM Assumption 3
– Finish early —
do we gain?
• Can the next task
start early?
• Good luck is
wasted.
– Finish late —
do we lose?
• The next task is
forced to delay
• Delays are
accumulated.
Good luck is wasted and bad luck accumulates!
Task1: 10 Days
Task2: 10 Days
Task3: 10 Days +2 D
Delay 2 Days
Due Date
Delay 2 Days
+2 D
Task1: 10 Days
Task2: 8 Days
Task3: 10 Days
2 D
Due Date Not
2 Days Earlier
2 Days Earlier
Date/reference/classification
11
© T. Lechler, Ph.D., 2013
1. Paradigm Question: CPM Assumption 3
Task safety wasted:
– as a student, did you start on assignments immediately?
– you had plenty of time, so you started later!
 Task safety is wasted right at the beginning
3
10
90%
A
B
wasted
7
70%student
syndrome
50% Task estimates include
safety, but what if we
start later?
Student Syndrome
Date/reference/classification
12
© T. Lechler, Ph.D., 2013
1. Paradigm Question: CPM Assumption 3
Report early finish after 5 days?
– There is always a bit more to do (polishing)
– The next person isn’t ready to start anyway
– Next time the estimate gets cut
 We erroneously report when we’re done
actual
50% 90%
1|0|0 |5 1|5
time
probability
5 ?
Task estimates include
safety, but what if we
get lucky, and finish
early?
Parkinson’s Law
Date/reference/classification
13
© T. Lechler, Ph.D., 2013
1. Paradigm Question: CPM Assumption 3
Slow starts and false finish reporting contaminate project metrics:
• Safety is systematically wasted!
• Initial expectations seem to be unrealistic…
expected
actual
B
3 2
student
syndrome
false finish
reporting
5
© 2000 ZULTNER & COMPANY
probability
Combined Effects of:
Student Syndrome and Parkinson’s Law
Date/reference/classification
14
© T. Lechler, Ph.D., 2013
1. Paradigm Question: CPM Limitations
Limitations of Critical Path Methods (CPM)
• CPM resource allocation leads to minimal single
project duration (local optimum)
• CPM does not explicitly take variation (risk) into
account
• CPM does not maximize the throughput of a multi-
project system (global optimum)
Critical Path Method leads to sub-optimal resource allocation!
Date/reference/classification
15
© T. Lechler, Ph.D., 2013
1. Paradigm Question: CPM Vicious Cycle
The Vicious Cycle of CPM
– More and more safety is added
over time
How to break the vicious cycle?
– Applying Critical Chain
Project
Is Late
Cut Schedule
“it’s just too long”
Add
Safety
Struggle
to Deadline
Blame
Assigned
Goldratt, Viewer Notebook, 1999, pp.75
Date/reference/classification
16
© T. Lechler, Ph.D., 2013
1. The Paradigm Question: System Problems
It’s the system, stupid!
“Pit a good person against a bad system and the system will
win all the time.”
(Rummler and Brache, 2002)
Deming’s 85/15
• 85% of faults are process related, and it is management’s
responsibility to solve them
• 15% of faults are the responsibility of individual
employee’s
• Most of the time management is focusing on the “15”
rather than the “85”, trying to find the guilty person rather
than to improve the process
Deming, W.E., “Out of the Crisis”, MIT, CIA, Massachussetts, 1986
Date/reference/classification
17
© T. Lechler, Ph.D., 2013
“If you do what you always
did, you’re gonna get what
you always got”
Yogi Berra
1. The Paradigm Question: Why change?
Date/reference/classification
18
© T. Lechler, Ph.D., 2013
1. The Future of Project Management
• Critical Chain allows to shorten your projects
• minimum 15-25% reduction
• on large projects, often more than 25%
• NO added resources (and less overtime!)
• NO sacrifice of value or features
• NO increase in risk
• NO cutting of quality
Date/reference/classification 19
Critical Chain
Performance Impact
Date/reference/classification
20
© T. Lechler, Ph.D., 2013
On-time performance N CPM N CC
Greater Than 90% 9 7% 8 53%
80% To 90% 12 10% 3 20%
70% To 80% 18 15% 1 7%
60% To 70% 20 17% 0 0
50% To 60% 18 15% 1 7%
40% To 50% 15 12% 0 0
Less Than 40% 27 22% 0 0
No Response 2 2% 2 14%
Results from: http://www.pdinstitute.com/surveys/surveyresults.htm
Question: On-time performance for the projects of my organization is:
CC promises higher due date performance!
2. Critical Chain Performance Impact: Average
Date/reference/classification
21
© T. Lechler, Ph.D., 2013
2. CC Performance Impact: Selected Cases
• Harris Corporation
• Microelectronics plant, Mountaintop, PA
• Project Goal: To be operational in 27 months
• Facility Construction:
• Critical Chain Plan: 18 months
• Result with CC: 13 months, 4% over budget
• Industry norm: 28-30 months
• Facility Operation:
• Result with CC : Full production in 21 months
• Industry norm 46-54 months total
Date/reference/classification
22
© T. Lechler, Ph.D., 2013
2. CC Performance Impact: Selected Cases
Lucent Technologies: Fiber Optic Cable Business Unit
Situation before CCM
• Product realization cycle for
Fiber Optic Cable was same as
its competitors.
• Designs based on tools took
longer time to come to market.
• Many designers were overloaded
and multi-tasking on several
projects simultaneously.
Situation After CCM
• Goals of implementation were
achieved.
• On-time delivery was markedly
improved
• The organizations capacity to
develop products markedly
increased.
• With no increase in staff, the
number of projects were
completed.
• The production introduction
interval was reduced by 50%.
Date/reference/classification
23
© T. Lechler, Ph.D., 2013
2. CC Performance Impact: Selected Cases
Successful Cases of Companies That Used Critical Chain
• (http://www.goldratt.com/success.htm)
• Seagate Technology
• F-22 Project Raptor
• Lucent Technologies
• The Clowes Group
• Valmount Industries
• BAE Systems (this article can be viewed
in(www.ets.news.com)
Date/reference/classification
24
© T. Lechler, Ph.D., 2013
CC-Project Before After
Warfighter Systems
Testing (US Air Force
Operational Test &
Evaluation Center)
18 projects in 6 months.
On time delivery unknown.
26 projects in 6 months.
75% projects on time;
30% reduction in cycle time.
Aircraft Repair and
Overhaul (US Naval
Aviation Depot, Cherry
Point)
Average turnaround time (TAT)
for H-46 aircraft was 225 days.
Throughput was 23 per year.
Reduced TAT to 167 days, a 25%
reduction while work scope was
increasing.
Throughput is 46 per year.
70% reduction in backlog
Submarine Maintenance
and Repair (US Naval
Shipyard, Pearl Harbor)
Job Completion Rate 94%
On-time delivery less than 60%.
Cost per job was $5,043.
Job Completion Rate now 98% On-time
delivery 95+%.
Cost per job reduced 33% Overtime
reduced by 49%
$9M saving in first year.
2. CC Performance Impact: Selected Cases
Date/reference/classification
25
© T. Lechler, Ph.D., 2013
2. CC Performance Impact: Summary
The Impact of CC across approx. 80 cases:
• Increased systems throughput ~ 20%
• Reduced project schedule ~ 15% - 40%
• Increased on-time delivery ~ 93%
• Reduced backlog ~ 30% - 70%
• Reduced overtime ~ 20% - 50%
CC shows dramatic performance improvements!
Date/reference/classification
26
© T. Lechler, Ph.D., 2013
3. What is CC? Critical Chain vs. CPM
Traditional PM scheduling problems:
• Resource conflicts
• Delays
• Uncertainty (scope change, context, resources)
CC offers a solution:
• Performance improvement with same resource base
• Reduces resource conflicts
• Reduces uncertainty
• Addresses multi-project environments
Date/reference/classification
27
© T. Lechler, Ph.D., 2013
3. What is CC? Critical Chain vs. CPM
Critical Chain three level approach:
1. Philosophical Level: Theory of Constraints
2. Single-Project Level: Managing Variation
3. Multi-Project Level: Systems Approach
Critical Path one level approach:
1. Single Project Level: Managing Due Date
• Does not account for variation
• Does not account for behaviors
• Does not account for multi-project system
Critical Chain promises advantages over CPM!
Date/reference/classification
28
© T. Lechler, Ph.D., 2013
3. What is CC? Philosophical Level: ToC
Theory of Constraints:
1. Systems perspective
2. Focus on the system’s bottle neck
3. Throughput mindset
4. Avoid sub-optimization
5. Use simple tools
Elyahu Goldratt, “The Goal,” 1988
Date/reference/classification
29
© T. Lechler, Ph.D., 2013
3. What is CC? Philosophical Level: ToC Steps
Theory of Constraints:
Step 1: Identify the system's constraint(s)
Step 2: Decide how to exploit the system’s constraint(s)
Step 3: Subordinate everything else to the above decision
Step 4: Elevate the system’s constraint(s)
Step 5: If in the previous step, a constraint has been broken go
back to step 1, but do not allow inertia to become the
system’s constraint
Elyahu Goldratt, “The Goal,” 1988
Date/reference/classification
30
© T. Lechler, Ph.D., 2013
3. What is CC? Philosophical Level: CC Estimation
Average Work
Touch
Time
Uncertainty
Buffers
Multitasking
Minimize
Set-up Time
Basic Estimation Equation: W = U * D
Date/reference/classification
31
© T. Lechler, Ph.D., 2013
• Realistic task estimates are 90% estimates.
• They include safety
– to assure on-time completion despite unknowns
In 90% of the cases the task will be finished EARLIER!
In 10% of the cases the task will be finished LATER!
55
50%
90%
1|0|0 |5 1|5
time
probability
10%
10
expected safety commitment
task duration
4. What is CC? Single-Project Level: Local vs. Global Safety
Date/reference/classification
32
© T. Lechler, Ph.D., 2013
4. What is CC? Single-Project Level: Local vs. Global Safety
Is trying to keep every task on-time an efficient way
to make the project deadline on time?
Probability of meeting the due date 73%!
5
50%
90%
5
50%
90%
5
50%
90%
105
5 10
105
traditional
committed
project
duration:
30 days
D
E
A
D
L
I
N
E
Date/reference/classification
33
© T. Lechler, Ph.D., 2013
4. What is CC? Single-Project Level: Buffer Sizing
55
25 75
8.665
25 25+ + =
project buffer
safety
take
square
root
square standard deviation
50% 90%
5 5
5
55
duration
55
safety
duration
duration
safety
Single-Project Level: Local vs. Global Safety
How much buffer is needed for a 90% Due Date estimate?
Goldratt’s Heuristic: Buffer Size = 50% of accumulated safety!
Date/reference/classification
34
© T. Lechler, Ph.D., 2013
4. What is CC? Single-Project Level: Buffer Sizing
An efficient way to manage risk:
– pool task variation in a project buffer,
– the project schedule is shorter,
– risk is not increased!
555
expected duration safety
8.66
50%
90%
project buffer
savings
15 6
© 2000 ZULTNER & COMPANY
Critical
Chain
committe
d project
duration:
24 days
D
E
A
D
L
I
N
E
Date/reference/classification
35
© T. Lechler, Ph.D., 2013
4. What is CC? Single-Project Level: Buffer Management
2|02|5 1|0 |0
9
5 5 5
-1 day
minimum buffer required
6 5 8
5
3 10
5
+2 days
5
10
-5 days
finished!
2
1
3
1|5 |53|0
8.6
7.1
5.0
actual buffer
+1 buffer-days
+5 buffer-days
+5 buffer-days
BUFFER STATUS
How many buffer-days
are needed to meet the
due date with 90%
probability?
How could good and
bad luck averaged
out?
Buffers absorb risks
CC Buffer Metric: Actual Buffer/Minimum Buffer Required
Date/reference/classification
36
© T. Lechler, Ph.D., 2013
6:Prog 3:HW
5:HW
Feeding Buffer
2:CS
6:Prog 3:HW
3:Eng 5:HW4:CS 2:CS Project Buffer
Resource Leveled Critical Path (in Red)
Critical Chain (in Red) Buffered Schedule
Individual activities are scheduled at their average durations (no safety
margin) 15%-25% decrease of project duration
4:CS 3:Eng
CPM Network
CC Network
4. What is CC? Single-Project Level: Feeding & Project Buffers
Due Date
Date/reference/classification
37
© T. Lechler, Ph.D., 2013
4. What is CC? Single-Project Level: Resource Buffers
For Relay Runners
– resources get a countdown
– assure the resource can start immediately
– activities start as soon as possible
NOT when the schedule says
3
10
A
B
Resource
Buffer
7
start!
10
current task next task
3
10
2
1
three days to go
two days to go
one day to go
good luck strikes—early finish
the plan
Date/reference/classification
38
© T. Lechler, Ph.D., 2013
4. What is CC? Single-Project Level: Relay Runner Effects
Resources seem to be working “faster” but
• Overtime goes down
• Speed may go down
• Throughput goes way up
• Quality goes up (slightly to a lot)
• Projects take much less time
• Resources will be idle more often
• Resource utilization goes down
Date/reference/classification
39
© T. Lechler, Ph.D., 2013
4. What is CC? Single-Project Level: Computation Steps
Critical Chain computation steps for single project schedule:
• Compute baseline schedule using average activity durations and ALAP
• Aggregate safety margins into Project Buffer
• Identify Critical Chain (CC)
• Protect CC using Feeding Buffers
• Try to keep baseline schedule and CC fixed during execution
• Use buffers as proactive warning system during execution
Date/reference/classification
40
© T. Lechler, Ph.D., 2013
7. What is CC? Summary
CC (1996):
• Feeding Buffer
• Resource Buffer
• Project Buffer
CC Metrics
• Actual Buffer/ Minimum required buffer
• Due date performance (% of milestones finished or mean project
duration and its standard dev.
• Operating expenses (# of hours invested)
• Inventory (amount of work in process not finished yet, hours invested
in unfinished work orders/activities)
• Project Quality (# development cycles and # of changes)
Date/reference/classification
41
© T. Lechler, Ph.D., 2013
7. What is CC? Summary
Critical Chain Advantages (CC)
• Provides a systems approach for managing multiple
projects sharing a set of resources
• Improved system throughput (global optimum)
• Explicitly takes variation (risk) into account
• Efficiently! (reduces time to market)
• Provides a visible, and powerful way to manage risk and
likelihood of on-time delivery
• A base for real risk management (reduces % of late
projects)
Critical Chain promises advantages over CPM!
Date/reference/classification
42
© T. Lechler, Ph.D., 2013
Date/reference/classification
43
© T. Lechler, Ph.D., 2013
Implementing CC: Creating a Project Schedule
The Five Focusing Steps of ToC
1. Identify the constraint
2. Exploit the constraint
3. Subordinate everything else to the above decision
4. Elevate the constraint
5. Don’t let inertia become the constraint
(If the constraint is broken, go to 1)
Date/reference/classification
44
© T. Lechler, Ph.D., 2013
Implementing CC: Step 0
Before creating the CC project schedule
• Define the project and its purpose
• Define the fundamental measurements for the project
Date/reference/classification
45
© T. Lechler, Ph.D., 2013
Implementing CC: Step 1
1. Identify the Critical Chain
A. Lay out the project network with all tasks as late as possible
(latest completion time of tasks)
B. Working backwards, identify the contention (usually resource) to
address next
C. Remove the contention by adding more resources, or moving
tasks earlier
D. Continue until all conflicts are resolved
E. Identify the longest dependent chain
Date/reference/classification
46
© T. Lechler, Ph.D., 2013
Implementing CC: Step 2-4
2. Exploit the Critical Chain
Use 50% task times and a project buffer
3. Subordinate everything else
• Protect the CC with feeding buffers
• Resolve new conflicts from buffers by moving tasks earlier
4. Elevate (shorten) the Critical Chain
Add resources, change procedures, etc.
Date/reference/classification
47
© T. Lechler, Ph.D., 2013
Implementing CC: Step 5
5. Go back to step 1. Do not allow inertia to become the constraint!
We have now applied the Five Focusing steps of Theory of Constraints
(ToC) to schedule a project
Date/reference/classification
48
© T. Lechler, Ph.D., 2013
Implementing CC: Case 1
• Variation…
– Non-critical path
• if it slips, could impact the critical path
– Protect the critical path — with a feeding buffer
• absorbs non-critical path variation
• prevents the critical path from shifting
10 10 16
20
1616
A
5 5 8
FB 1188
C
PB 1410
CPM Project Plan
CC Project Plan
Date/reference/classification
49
© T. Lechler, Ph.D., 2013
20 60
20 40 20
60
Airframe
+10
Component
Aircraft
Complete
20 30
30
Implementing CC: Case 2
Let’s establish a Critical Chain Schedule
Aircraft Project – Traditional Schedule
Engine
+20
Critical Path: 140 Months
Aircraft
Start
Date/reference/classification
50
© T. Lechler, Ph.D., 2013
10 30
10 20 10
30
Airframe
Engine
Component
Aircraft
Complete
10 15
15
Implementing CC: Case 2
Cut task estimates by 50%
Aircraft
Start
Date/reference/classification
51
© T. Lechler, Ph.D., 2013
10 30
10 20 10
30
Airframe
Engine
Component
Aircraft
Complete
10 15
15
Implementing CC: Case 2
Push all tasks to start as late as possible.
Date/reference/classification
52
© T. Lechler, Ph.D., 2013
10 30
10 20 10
30
Airframe
Engine
Component
Aircraft
Complete
10 15
15
Implementing CC: Case 2
Eliminate Resource Contention
Date/reference/classification
53
© T. Lechler, Ph.D., 2013
10 30
10 20 10
30
Airframe
Engine
Component Aircraft
Complete
10 15
15
Implementing CC: Case 2
Resource contention eliminated by moving
Component branch 15 months backward.
+15
Date/reference/classification
54
© T. Lechler, Ph.D., 2013
10 30
10 20 10
30
Airframe
Engine
Component Aircraft
Complete
10 15
15
Implementing CC: Case 2
Eliminate Resource Contention
+15
Date/reference/classification
55
© T. Lechler, Ph.D., 2013
10 30
10 20 10
30
Airframe
Engine
Component
Aircraft
Complete
10 15
15
Implementing CC: Case 2
Resource contention eliminated by moving
Engine branch 5 months backward.
+5
+15
Date/reference/classification
56
© T. Lechler, Ph.D., 2013
10 30
10 20 10
30
Airframe
Engine
Component Aircraft
Complete
10 15
15
Implementing CC: Case 2
Eliminate Resource Contention
+5
+15
Date/reference/classification
57
© T. Lechler, Ph.D., 2013
10 30
10 20 10
30
Airframe
Engine
Component Aircraft
Complete
10 15
15
Implementing CC: Case 2
Resource contention eliminated by moving
Airframe branch 5 months backward.
+5
+5
Aircraft
Start
+15
Date/reference/classification
58
© T. Lechler, Ph.D., 2013
10 30
10 20 10
30
Airframe
Engine
Component Aircraft
Complete
10 15
15
Implementing CC: Case 2
The longest path through the network considering both
TASK and RESOURCE DEPENDENCIES is the Critical
Chain (CC = 70 months).
+5
+5
Aircraft
Start
CC
+15
Date/reference/classification
59
© T. Lechler, Ph.D., 2013
10 30
10 20 10
30
Airframe
Engine
Component Aircraft
Complete
10 15
15
Implementing CC: Buffer Management (Project Buffer)
Using Buffer Management: Project Buffer
Project Buffer = 38.08 months (accurate calculation)
Total project duration = 108 months
+5
+5
Aircraft
Start
Project Buffer
CC
+15
Date/reference/classification
60
© T. Lechler, Ph.D., 2013
10 30
10 20 10
30
Airframe
Engine
Component Aircraft
Complete
10 15
15
Implementing CC: Buffer Management (Feeding Buffer)
Using Buffer Management: Feeding Buffers
Locations of feeding buffers
+5
+5
Project Buffer
+15
Date/reference/classification
61
© T. Lechler, Ph.D., 2013
10
10 20 10
30
Airframe
Engine
Component Aircraft
Complete
10
Implementing CC: Buffer Management (Feeding Buffer)
Using Buffer Management: Feeding Buffers
Durations of feeding buffers moves project start to an
earlier start date!
Total project duration: 129 months
15
30
15 PB=38FB=26.5
FB=30
FB=10
Date/reference/classification
62
© T. Lechler, Ph.D., 2013
Implementing CC: Conclusions
10 30
10 20 10
30
Airframe
Engine
Component Aircraft
Complete
10
Use Project Buffer
Use “Float” as “quasi feeding buffers”
Total project duration = 108 months compared to
Standard schedule with 140 months
Aircraft
Start
Project Buffer
CC
15
15FB=5
FB=5

Weitere ähnliche Inhalte

Andere mochten auch

Week10 slides
Week10 slidesWeek10 slides
Week10 slideshenry KKK
 
Reading week08 shah_ahp_case
Reading week08 shah_ahp_caseReading week08 shah_ahp_case
Reading week08 shah_ahp_casehenry KKK
 
Week06 slides
Week06 slidesWeek06 slides
Week06 slideshenry KKK
 
Reading week08 saaty_ahp_prediction
Reading week08 saaty_ahp_predictionReading week08 saaty_ahp_prediction
Reading week08 saaty_ahp_predictionhenry KKK
 
Week02 slides spring_2013
Week02 slides spring_2013Week02 slides spring_2013
Week02 slides spring_2013henry KKK
 
Week03 reading lechler_pm_mindset
Week03 reading lechler_pm_mindsetWeek03 reading lechler_pm_mindset
Week03 reading lechler_pm_mindsethenry KKK
 

Andere mochten auch (6)

Week10 slides
Week10 slidesWeek10 slides
Week10 slides
 
Reading week08 shah_ahp_case
Reading week08 shah_ahp_caseReading week08 shah_ahp_case
Reading week08 shah_ahp_case
 
Week06 slides
Week06 slidesWeek06 slides
Week06 slides
 
Reading week08 saaty_ahp_prediction
Reading week08 saaty_ahp_predictionReading week08 saaty_ahp_prediction
Reading week08 saaty_ahp_prediction
 
Week02 slides spring_2013
Week02 slides spring_2013Week02 slides spring_2013
Week02 slides spring_2013
 
Week03 reading lechler_pm_mindset
Week03 reading lechler_pm_mindsetWeek03 reading lechler_pm_mindset
Week03 reading lechler_pm_mindset
 

Ähnlich wie Week09 cc single_project_slides_v1

Week10 slides
Week10 slidesWeek10 slides
Week10 slideshenry KKK
 
Critical Chain Basics
Critical Chain BasicsCritical Chain Basics
Critical Chain BasicsJakub Linhart
 
The Future of Oilsands Projects – Productivity Improvement & the Role o...
The Future of Oilsands  Projects – Productivity Improvement  & the Role o...The Future of Oilsands  Projects – Productivity Improvement  & the Role o...
The Future of Oilsands Projects – Productivity Improvement & the Role o...Nick Anderson
 
Effective Program Management
Effective Program ManagementEffective Program Management
Effective Program ManagementKaushik Shah
 
Contractor management sect 2 unit 3
Contractor management sect 2 unit 3Contractor management sect 2 unit 3
Contractor management sect 2 unit 3Michael Shellshear
 
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...IRJET Journal
 
Green Wulf - Sustainable Gym on Campus / Project Management at SKEMA Business...
Green Wulf - Sustainable Gym on Campus / Project Management at SKEMA Business...Green Wulf - Sustainable Gym on Campus / Project Management at SKEMA Business...
Green Wulf - Sustainable Gym on Campus / Project Management at SKEMA Business...Caroline Bilet
 
Week11 slides
Week11 slidesWeek11 slides
Week11 slideshenry KKK
 
Why Is New Software Always Late
Why Is New Software Always LateWhy Is New Software Always Late
Why Is New Software Always LateAlex Beston
 
VeeShell presentation
VeeShell presentationVeeShell presentation
VeeShell presentationCherniak Soft
 
Interview questions-answers-for-planning-engineers-r.00
Interview questions-answers-for-planning-engineers-r.00Interview questions-answers-for-planning-engineers-r.00
Interview questions-answers-for-planning-engineers-r.00Praveen Krishna
 
Major Projects - Faster Better Cheaper
Major Projects - Faster Better CheaperMajor Projects - Faster Better Cheaper
Major Projects - Faster Better CheaperIan Heptinstall
 
SPE London 'Geomechanics: Quo Vadis?' Event Talk - 27Oct15
SPE London 'Geomechanics: Quo Vadis?' Event Talk - 27Oct15 SPE London 'Geomechanics: Quo Vadis?' Event Talk - 27Oct15
SPE London 'Geomechanics: Quo Vadis?' Event Talk - 27Oct15 Glen Burridge
 
SPE London - 'Geomechanics: Quo Vadis?' Event Talk - 27Oct15
SPE London - 'Geomechanics: Quo Vadis?' Event Talk - 27Oct15SPE London - 'Geomechanics: Quo Vadis?' Event Talk - 27Oct15
SPE London - 'Geomechanics: Quo Vadis?' Event Talk - 27Oct15Glen Burridge
 
Spe london geomech quo vadis - 27 oct15 - external
Spe london   geomech quo vadis - 27 oct15 - externalSpe london   geomech quo vadis - 27 oct15 - external
Spe london geomech quo vadis - 27 oct15 - externalRichard Lamb
 
Team 4, Team PMP”IT Installation of the Adelphi V.docx
Team 4, Team PMP”IT Installation of the Adelphi V.docxTeam 4, Team PMP”IT Installation of the Adelphi V.docx
Team 4, Team PMP”IT Installation of the Adelphi V.docxmattinsonjanel
 
Project management
Project managementProject management
Project managementsmumbahelp
 
Reduce Release Cycle Time: Nine Months to a Week - Nice!
Reduce Release Cycle Time: Nine Months to a Week - Nice!Reduce Release Cycle Time: Nine Months to a Week - Nice!
Reduce Release Cycle Time: Nine Months to a Week - Nice!TechWell
 
IT Operations Consulting
IT Operations Consulting  IT Operations Consulting
IT Operations Consulting Anubhav Lal
 

Ähnlich wie Week09 cc single_project_slides_v1 (20)

Week10 slides
Week10 slidesWeek10 slides
Week10 slides
 
Critical Chain Basics
Critical Chain BasicsCritical Chain Basics
Critical Chain Basics
 
The Future of Oilsands Projects – Productivity Improvement & the Role o...
The Future of Oilsands  Projects – Productivity Improvement  & the Role o...The Future of Oilsands  Projects – Productivity Improvement  & the Role o...
The Future of Oilsands Projects – Productivity Improvement & the Role o...
 
Effective Program Management
Effective Program ManagementEffective Program Management
Effective Program Management
 
Contractor management sect 2 unit 3
Contractor management sect 2 unit 3Contractor management sect 2 unit 3
Contractor management sect 2 unit 3
 
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
 
Green Wulf - Sustainable Gym on Campus / Project Management at SKEMA Business...
Green Wulf - Sustainable Gym on Campus / Project Management at SKEMA Business...Green Wulf - Sustainable Gym on Campus / Project Management at SKEMA Business...
Green Wulf - Sustainable Gym on Campus / Project Management at SKEMA Business...
 
Week11 slides
Week11 slidesWeek11 slides
Week11 slides
 
Why Is New Software Always Late
Why Is New Software Always LateWhy Is New Software Always Late
Why Is New Software Always Late
 
Lean Project Leadership
Lean Project LeadershipLean Project Leadership
Lean Project Leadership
 
VeeShell presentation
VeeShell presentationVeeShell presentation
VeeShell presentation
 
Interview questions-answers-for-planning-engineers-r.00
Interview questions-answers-for-planning-engineers-r.00Interview questions-answers-for-planning-engineers-r.00
Interview questions-answers-for-planning-engineers-r.00
 
Major Projects - Faster Better Cheaper
Major Projects - Faster Better CheaperMajor Projects - Faster Better Cheaper
Major Projects - Faster Better Cheaper
 
SPE London 'Geomechanics: Quo Vadis?' Event Talk - 27Oct15
SPE London 'Geomechanics: Quo Vadis?' Event Talk - 27Oct15 SPE London 'Geomechanics: Quo Vadis?' Event Talk - 27Oct15
SPE London 'Geomechanics: Quo Vadis?' Event Talk - 27Oct15
 
SPE London - 'Geomechanics: Quo Vadis?' Event Talk - 27Oct15
SPE London - 'Geomechanics: Quo Vadis?' Event Talk - 27Oct15SPE London - 'Geomechanics: Quo Vadis?' Event Talk - 27Oct15
SPE London - 'Geomechanics: Quo Vadis?' Event Talk - 27Oct15
 
Spe london geomech quo vadis - 27 oct15 - external
Spe london   geomech quo vadis - 27 oct15 - externalSpe london   geomech quo vadis - 27 oct15 - external
Spe london geomech quo vadis - 27 oct15 - external
 
Team 4, Team PMP”IT Installation of the Adelphi V.docx
Team 4, Team PMP”IT Installation of the Adelphi V.docxTeam 4, Team PMP”IT Installation of the Adelphi V.docx
Team 4, Team PMP”IT Installation of the Adelphi V.docx
 
Project management
Project managementProject management
Project management
 
Reduce Release Cycle Time: Nine Months to a Week - Nice!
Reduce Release Cycle Time: Nine Months to a Week - Nice!Reduce Release Cycle Time: Nine Months to a Week - Nice!
Reduce Release Cycle Time: Nine Months to a Week - Nice!
 
IT Operations Consulting
IT Operations Consulting  IT Operations Consulting
IT Operations Consulting
 

Mehr von henry KKK

Yiheng deng hw3
Yiheng deng hw3Yiheng deng hw3
Yiheng deng hw3henry KKK
 
Yiheng deng hw2
Yiheng deng hw2Yiheng deng hw2
Yiheng deng hw2henry KKK
 
Yiheng deng hw1
Yiheng deng hw1Yiheng deng hw1
Yiheng deng hw1henry KKK
 
Examples of smart_objective_attributes
Examples of smart_objective_attributesExamples of smart_objective_attributes
Examples of smart_objective_attributeshenry KKK
 
Week09 cc single_project_slides_v1
Week09 cc single_project_slides_v1Week09 cc single_project_slides_v1
Week09 cc single_project_slides_v1henry KKK
 
Week12 slides
Week12 slidesWeek12 slides
Week12 slideshenry KKK
 
Week08 slides
Week08 slidesWeek08 slides
Week08 slideshenry KKK
 
Week07 slides 2013_s
Week07 slides 2013_sWeek07 slides 2013_s
Week07 slides 2013_shenry KKK
 
Week05 spc single_case
Week05 spc single_caseWeek05 spc single_case
Week05 spc single_casehenry KKK
 
Week05 slides
Week05 slidesWeek05 slides
Week05 slideshenry KKK
 
Week05 reading
Week05 readingWeek05 reading
Week05 readinghenry KKK
 
Week05 exercise
Week05 exerciseWeek05 exercise
Week05 exercisehenry KKK
 
Week03 slides spring_2013
Week03 slides spring_2013Week03 slides spring_2013
Week03 slides spring_2013henry KKK
 
Week02 reading lechler_plan_and_changing
Week02 reading lechler_plan_and_changingWeek02 reading lechler_plan_and_changing
Week02 reading lechler_plan_and_changinghenry KKK
 
Week01 slides spring_2013
Week01 slides spring_2013Week01 slides spring_2013
Week01 slides spring_2013henry KKK
 
Toc evaporating cloud
Toc evaporating cloudToc evaporating cloud
Toc evaporating cloudhenry KKK
 
Toc evaporating cloud
Toc evaporating cloudToc evaporating cloud
Toc evaporating cloudhenry KKK
 
Syllabus mgt610 2013_s
Syllabus mgt610 2013_sSyllabus mgt610 2013_s
Syllabus mgt610 2013_shenry KKK
 
Reading week09 lechler_cc
Reading week09 lechler_ccReading week09 lechler_cc
Reading week09 lechler_cchenry KKK
 
Reading week08 shah_ahp_case
Reading week08 shah_ahp_caseReading week08 shah_ahp_case
Reading week08 shah_ahp_casehenry KKK
 

Mehr von henry KKK (20)

Yiheng deng hw3
Yiheng deng hw3Yiheng deng hw3
Yiheng deng hw3
 
Yiheng deng hw2
Yiheng deng hw2Yiheng deng hw2
Yiheng deng hw2
 
Yiheng deng hw1
Yiheng deng hw1Yiheng deng hw1
Yiheng deng hw1
 
Examples of smart_objective_attributes
Examples of smart_objective_attributesExamples of smart_objective_attributes
Examples of smart_objective_attributes
 
Week09 cc single_project_slides_v1
Week09 cc single_project_slides_v1Week09 cc single_project_slides_v1
Week09 cc single_project_slides_v1
 
Week12 slides
Week12 slidesWeek12 slides
Week12 slides
 
Week08 slides
Week08 slidesWeek08 slides
Week08 slides
 
Week07 slides 2013_s
Week07 slides 2013_sWeek07 slides 2013_s
Week07 slides 2013_s
 
Week05 spc single_case
Week05 spc single_caseWeek05 spc single_case
Week05 spc single_case
 
Week05 slides
Week05 slidesWeek05 slides
Week05 slides
 
Week05 reading
Week05 readingWeek05 reading
Week05 reading
 
Week05 exercise
Week05 exerciseWeek05 exercise
Week05 exercise
 
Week03 slides spring_2013
Week03 slides spring_2013Week03 slides spring_2013
Week03 slides spring_2013
 
Week02 reading lechler_plan_and_changing
Week02 reading lechler_plan_and_changingWeek02 reading lechler_plan_and_changing
Week02 reading lechler_plan_and_changing
 
Week01 slides spring_2013
Week01 slides spring_2013Week01 slides spring_2013
Week01 slides spring_2013
 
Toc evaporating cloud
Toc evaporating cloudToc evaporating cloud
Toc evaporating cloud
 
Toc evaporating cloud
Toc evaporating cloudToc evaporating cloud
Toc evaporating cloud
 
Syllabus mgt610 2013_s
Syllabus mgt610 2013_sSyllabus mgt610 2013_s
Syllabus mgt610 2013_s
 
Reading week09 lechler_cc
Reading week09 lechler_ccReading week09 lechler_cc
Reading week09 lechler_cc
 
Reading week08 shah_ahp_case
Reading week08 shah_ahp_caseReading week08 shah_ahp_case
Reading week08 shah_ahp_case
 

Kürzlich hochgeladen

👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...rajveerescorts2022
 
How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityEric T. Tung
 
Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st CenturyFamous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Centuryrwgiffor
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableDipal Arora
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdfRenandantas16
 
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...lizamodels9
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayNZSG
 
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLSeo
 
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...Aggregage
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMANIlamathiKannappan
 
HONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael HawkinsHONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael HawkinsMichael W. Hawkins
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...anilsa9823
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...amitlee9823
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Neil Kimberley
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756dollysharma2066
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMRavindra Nath Shukla
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...lizamodels9
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.Aaiza Hassan
 

Kürzlich hochgeladen (20)

👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
 
How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League City
 
Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st CenturyFamous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Century
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
 
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 May
 
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
 
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
 
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMAN
 
HONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael HawkinsHONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael Hawkins
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023
 
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabiunwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSM
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.
 

Week09 cc single_project_slides_v1

  • 1. Date/reference/classification 1 Session 9 Critical Chain Single-Project Management Reducing Project Duration by 25% & Increasing Due Date Performance Without Changes of Resource Capacity Dr. Thomas Lechler Phone: (201) 216-8174 Babbio Center 416 FAX: (201) 216-5385 email: tlechler@stevens.edu
  • 2. Date/reference/classification 2 © T. Lechler, Ph.D., 2013 1. Paradigm Question: Process Value How much would your organization gain if over 90% of the projects are finished in time? How much would your organization gain if all new projects starting next month finished 15-25% sooner? • Reduced project cost? • Faster time-to-market? • Greater responsiveness to customers?
  • 3. Date/reference/classification 3 © T. Lechler, Ph.D., 2013 1. Paradigm Question: Management Problems Why is it so difficult to manage projects which deliver on time, within budget and with the full specification or scope intact ? •__________________________________________________ •__________________________________________________ •__________________________________________________ •__________________________________________________ •__________________________________________________
  • 4. Date/reference/classification 4 © T. Lechler, Ph.D., 2013 1. Paradigm Question: Project Manager’s Dilemma • PRESSURE TO INCREASE SAFETY TIME - in order to complete projects on time • PRESSURE TO REDUCE OVERALL PROJECT SCHEDULE - in order to meet the customers need for shorter lead times Be a good Project Manager Complete Projects on time (to be realistic) Add protection to tasks Don’t add protection to tasks PrerequisiteRequirement Respond to customers need for short lead times (quick response) Objective
  • 5. Date/reference/classification 5 © T. Lechler, Ph.D., 2013 1. Paradigm Question: CPM Management of Uncertainty Often projects have difficulty staying within budget Often scope or specifications are cut from project The Way We Manage Uncertainty in Projects Often projects have difficulty finishing on time YOU CAN’T IMPOSE CERTAINTY ON UNCERTAINTY YOU MUST LEARN TO MANAGE THE UNCERTAINTY
  • 6. Date/reference/classification 6 © T. Lechler, Ph.D., 2013 1. Paradigm Question: CPM Estimation Average Work Uncertainty Multitasking Set-up Time Task Estimate - (Duration) Basic Estimation Equation: W = U * D W: Estimate of Work U: Units of Resources D: Duration  Inflated Estimates!
  • 7. Date/reference/classification 7 © T. Lechler, Ph.D., 2013 1. Paradigm Question: CPM Assumptions Basic assumptions of the CPM paradigm: 1. Each task is scheduled with 90% likelihood thus the project is scheduled with 90% likelihood. But: Due date on a big project may be less than 10% likely even if the single tasks are scheduled with 90%! 2. The critical path does not change. But: The critical path changes in many projects! 3. Good and bad luck average out. But: Good luck is wasted and bad luck accumulates because - Scheduled tasks are started with delays (Student Syndrome) - Early task finish is often not reported (Parkinson’s Law) => What are the consequences?
  • 8. Date/reference/classification 8 © T. Lechler, Ph.D., 2013 1. Paradigm Question: CPM Assumption 1 Two scenarios: 1. All single tasks on the critical path are planned with 90% accuracy: The probability to achieve the planned finish date is: 38% (=0.9 EXP 9) 2. One of the 9 tasks could be only planned with 80% accuracy and one with 50%. The likelihood to achieve the planned finish date is: 18%! Start 0d 9/1 (a) Initiate project 5d 9/1 (b) Assign PM 2d 9/8 (h) Design IPF 9d 9/12 (g) Conduct IPD training 5d 9/28 (m) Conduct IPF training 7d 10/5 (j) Prepare business case 7d 10/5 (l) Finalize IPP 9d 10/18 (k) Write IPP 3d 10/13 (e) Develop project schedule 10d 9/28 (i) Assign resources 1d 10/12 (d) Form PDT 12d 9/12 (f) Prepare expense estimates 9d 9/28 Concept DCP 0d 10/28 (c) Establish constraints 6d 9/8 (n) Reproduce documents 8d 10/14
  • 9. Date/reference/classification 9 © T. Lechler, Ph.D., 2013 1. Paradigm Question: CPM Assumption 2 Critical Path is not stable! Determine budget 4 1d Wed 6/1/94 Wed 6/1/94 Selection 6 120h Thu 6/2/94 Wed 6/22/94 Theme 7 2d Thu 6/2/94 Fri 6/3/94 Date 8 3d Mon 6/6/94 Wed 6/8/94 Site 9 1w Thu 6/9/94 Wed 6/15/94 Costumes 10 1w Thu 6/16/94 Wed 6/22/94 Hire 11 168h Thu 6/23/94 Thu 7/21/94 Caterer 12 2d Thu 6/23/94 Fri 6/24/94 Entertainment 13 9d Mon 6/27/94 Thu 7/7/94 Keynote speaker 14 2w Fri 7/8/94 Thu 7/21/94 Public relations 15 88h Fri 7/22/94 Fri 8/5/94 Rent Equipment 18 40h Mon 8/8/94 Fri 8/12/94 Invitation list 5 1d Wed 6/1/94 Wed 6/1/94
  • 10. Date/reference/classification 10 © T. Lechler, Ph.D., 2013 1. Paradigm Question: CPM Assumption 3 – Finish early — do we gain? • Can the next task start early? • Good luck is wasted. – Finish late — do we lose? • The next task is forced to delay • Delays are accumulated. Good luck is wasted and bad luck accumulates! Task1: 10 Days Task2: 10 Days Task3: 10 Days +2 D Delay 2 Days Due Date Delay 2 Days +2 D Task1: 10 Days Task2: 8 Days Task3: 10 Days 2 D Due Date Not 2 Days Earlier 2 Days Earlier
  • 11. Date/reference/classification 11 © T. Lechler, Ph.D., 2013 1. Paradigm Question: CPM Assumption 3 Task safety wasted: – as a student, did you start on assignments immediately? – you had plenty of time, so you started later!  Task safety is wasted right at the beginning 3 10 90% A B wasted 7 70%student syndrome 50% Task estimates include safety, but what if we start later? Student Syndrome
  • 12. Date/reference/classification 12 © T. Lechler, Ph.D., 2013 1. Paradigm Question: CPM Assumption 3 Report early finish after 5 days? – There is always a bit more to do (polishing) – The next person isn’t ready to start anyway – Next time the estimate gets cut  We erroneously report when we’re done actual 50% 90% 1|0|0 |5 1|5 time probability 5 ? Task estimates include safety, but what if we get lucky, and finish early? Parkinson’s Law
  • 13. Date/reference/classification 13 © T. Lechler, Ph.D., 2013 1. Paradigm Question: CPM Assumption 3 Slow starts and false finish reporting contaminate project metrics: • Safety is systematically wasted! • Initial expectations seem to be unrealistic… expected actual B 3 2 student syndrome false finish reporting 5 © 2000 ZULTNER & COMPANY probability Combined Effects of: Student Syndrome and Parkinson’s Law
  • 14. Date/reference/classification 14 © T. Lechler, Ph.D., 2013 1. Paradigm Question: CPM Limitations Limitations of Critical Path Methods (CPM) • CPM resource allocation leads to minimal single project duration (local optimum) • CPM does not explicitly take variation (risk) into account • CPM does not maximize the throughput of a multi- project system (global optimum) Critical Path Method leads to sub-optimal resource allocation!
  • 15. Date/reference/classification 15 © T. Lechler, Ph.D., 2013 1. Paradigm Question: CPM Vicious Cycle The Vicious Cycle of CPM – More and more safety is added over time How to break the vicious cycle? – Applying Critical Chain Project Is Late Cut Schedule “it’s just too long” Add Safety Struggle to Deadline Blame Assigned Goldratt, Viewer Notebook, 1999, pp.75
  • 16. Date/reference/classification 16 © T. Lechler, Ph.D., 2013 1. The Paradigm Question: System Problems It’s the system, stupid! “Pit a good person against a bad system and the system will win all the time.” (Rummler and Brache, 2002) Deming’s 85/15 • 85% of faults are process related, and it is management’s responsibility to solve them • 15% of faults are the responsibility of individual employee’s • Most of the time management is focusing on the “15” rather than the “85”, trying to find the guilty person rather than to improve the process Deming, W.E., “Out of the Crisis”, MIT, CIA, Massachussetts, 1986
  • 17. Date/reference/classification 17 © T. Lechler, Ph.D., 2013 “If you do what you always did, you’re gonna get what you always got” Yogi Berra 1. The Paradigm Question: Why change?
  • 18. Date/reference/classification 18 © T. Lechler, Ph.D., 2013 1. The Future of Project Management • Critical Chain allows to shorten your projects • minimum 15-25% reduction • on large projects, often more than 25% • NO added resources (and less overtime!) • NO sacrifice of value or features • NO increase in risk • NO cutting of quality
  • 20. Date/reference/classification 20 © T. Lechler, Ph.D., 2013 On-time performance N CPM N CC Greater Than 90% 9 7% 8 53% 80% To 90% 12 10% 3 20% 70% To 80% 18 15% 1 7% 60% To 70% 20 17% 0 0 50% To 60% 18 15% 1 7% 40% To 50% 15 12% 0 0 Less Than 40% 27 22% 0 0 No Response 2 2% 2 14% Results from: http://www.pdinstitute.com/surveys/surveyresults.htm Question: On-time performance for the projects of my organization is: CC promises higher due date performance! 2. Critical Chain Performance Impact: Average
  • 21. Date/reference/classification 21 © T. Lechler, Ph.D., 2013 2. CC Performance Impact: Selected Cases • Harris Corporation • Microelectronics plant, Mountaintop, PA • Project Goal: To be operational in 27 months • Facility Construction: • Critical Chain Plan: 18 months • Result with CC: 13 months, 4% over budget • Industry norm: 28-30 months • Facility Operation: • Result with CC : Full production in 21 months • Industry norm 46-54 months total
  • 22. Date/reference/classification 22 © T. Lechler, Ph.D., 2013 2. CC Performance Impact: Selected Cases Lucent Technologies: Fiber Optic Cable Business Unit Situation before CCM • Product realization cycle for Fiber Optic Cable was same as its competitors. • Designs based on tools took longer time to come to market. • Many designers were overloaded and multi-tasking on several projects simultaneously. Situation After CCM • Goals of implementation were achieved. • On-time delivery was markedly improved • The organizations capacity to develop products markedly increased. • With no increase in staff, the number of projects were completed. • The production introduction interval was reduced by 50%.
  • 23. Date/reference/classification 23 © T. Lechler, Ph.D., 2013 2. CC Performance Impact: Selected Cases Successful Cases of Companies That Used Critical Chain • (http://www.goldratt.com/success.htm) • Seagate Technology • F-22 Project Raptor • Lucent Technologies • The Clowes Group • Valmount Industries • BAE Systems (this article can be viewed in(www.ets.news.com)
  • 24. Date/reference/classification 24 © T. Lechler, Ph.D., 2013 CC-Project Before After Warfighter Systems Testing (US Air Force Operational Test & Evaluation Center) 18 projects in 6 months. On time delivery unknown. 26 projects in 6 months. 75% projects on time; 30% reduction in cycle time. Aircraft Repair and Overhaul (US Naval Aviation Depot, Cherry Point) Average turnaround time (TAT) for H-46 aircraft was 225 days. Throughput was 23 per year. Reduced TAT to 167 days, a 25% reduction while work scope was increasing. Throughput is 46 per year. 70% reduction in backlog Submarine Maintenance and Repair (US Naval Shipyard, Pearl Harbor) Job Completion Rate 94% On-time delivery less than 60%. Cost per job was $5,043. Job Completion Rate now 98% On-time delivery 95+%. Cost per job reduced 33% Overtime reduced by 49% $9M saving in first year. 2. CC Performance Impact: Selected Cases
  • 25. Date/reference/classification 25 © T. Lechler, Ph.D., 2013 2. CC Performance Impact: Summary The Impact of CC across approx. 80 cases: • Increased systems throughput ~ 20% • Reduced project schedule ~ 15% - 40% • Increased on-time delivery ~ 93% • Reduced backlog ~ 30% - 70% • Reduced overtime ~ 20% - 50% CC shows dramatic performance improvements!
  • 26. Date/reference/classification 26 © T. Lechler, Ph.D., 2013 3. What is CC? Critical Chain vs. CPM Traditional PM scheduling problems: • Resource conflicts • Delays • Uncertainty (scope change, context, resources) CC offers a solution: • Performance improvement with same resource base • Reduces resource conflicts • Reduces uncertainty • Addresses multi-project environments
  • 27. Date/reference/classification 27 © T. Lechler, Ph.D., 2013 3. What is CC? Critical Chain vs. CPM Critical Chain three level approach: 1. Philosophical Level: Theory of Constraints 2. Single-Project Level: Managing Variation 3. Multi-Project Level: Systems Approach Critical Path one level approach: 1. Single Project Level: Managing Due Date • Does not account for variation • Does not account for behaviors • Does not account for multi-project system Critical Chain promises advantages over CPM!
  • 28. Date/reference/classification 28 © T. Lechler, Ph.D., 2013 3. What is CC? Philosophical Level: ToC Theory of Constraints: 1. Systems perspective 2. Focus on the system’s bottle neck 3. Throughput mindset 4. Avoid sub-optimization 5. Use simple tools Elyahu Goldratt, “The Goal,” 1988
  • 29. Date/reference/classification 29 © T. Lechler, Ph.D., 2013 3. What is CC? Philosophical Level: ToC Steps Theory of Constraints: Step 1: Identify the system's constraint(s) Step 2: Decide how to exploit the system’s constraint(s) Step 3: Subordinate everything else to the above decision Step 4: Elevate the system’s constraint(s) Step 5: If in the previous step, a constraint has been broken go back to step 1, but do not allow inertia to become the system’s constraint Elyahu Goldratt, “The Goal,” 1988
  • 30. Date/reference/classification 30 © T. Lechler, Ph.D., 2013 3. What is CC? Philosophical Level: CC Estimation Average Work Touch Time Uncertainty Buffers Multitasking Minimize Set-up Time Basic Estimation Equation: W = U * D
  • 31. Date/reference/classification 31 © T. Lechler, Ph.D., 2013 • Realistic task estimates are 90% estimates. • They include safety – to assure on-time completion despite unknowns In 90% of the cases the task will be finished EARLIER! In 10% of the cases the task will be finished LATER! 55 50% 90% 1|0|0 |5 1|5 time probability 10% 10 expected safety commitment task duration 4. What is CC? Single-Project Level: Local vs. Global Safety
  • 32. Date/reference/classification 32 © T. Lechler, Ph.D., 2013 4. What is CC? Single-Project Level: Local vs. Global Safety Is trying to keep every task on-time an efficient way to make the project deadline on time? Probability of meeting the due date 73%! 5 50% 90% 5 50% 90% 5 50% 90% 105 5 10 105 traditional committed project duration: 30 days D E A D L I N E
  • 33. Date/reference/classification 33 © T. Lechler, Ph.D., 2013 4. What is CC? Single-Project Level: Buffer Sizing 55 25 75 8.665 25 25+ + = project buffer safety take square root square standard deviation 50% 90% 5 5 5 55 duration 55 safety duration duration safety Single-Project Level: Local vs. Global Safety How much buffer is needed for a 90% Due Date estimate? Goldratt’s Heuristic: Buffer Size = 50% of accumulated safety!
  • 34. Date/reference/classification 34 © T. Lechler, Ph.D., 2013 4. What is CC? Single-Project Level: Buffer Sizing An efficient way to manage risk: – pool task variation in a project buffer, – the project schedule is shorter, – risk is not increased! 555 expected duration safety 8.66 50% 90% project buffer savings 15 6 © 2000 ZULTNER & COMPANY Critical Chain committe d project duration: 24 days D E A D L I N E
  • 35. Date/reference/classification 35 © T. Lechler, Ph.D., 2013 4. What is CC? Single-Project Level: Buffer Management 2|02|5 1|0 |0 9 5 5 5 -1 day minimum buffer required 6 5 8 5 3 10 5 +2 days 5 10 -5 days finished! 2 1 3 1|5 |53|0 8.6 7.1 5.0 actual buffer +1 buffer-days +5 buffer-days +5 buffer-days BUFFER STATUS How many buffer-days are needed to meet the due date with 90% probability? How could good and bad luck averaged out? Buffers absorb risks CC Buffer Metric: Actual Buffer/Minimum Buffer Required
  • 36. Date/reference/classification 36 © T. Lechler, Ph.D., 2013 6:Prog 3:HW 5:HW Feeding Buffer 2:CS 6:Prog 3:HW 3:Eng 5:HW4:CS 2:CS Project Buffer Resource Leveled Critical Path (in Red) Critical Chain (in Red) Buffered Schedule Individual activities are scheduled at their average durations (no safety margin) 15%-25% decrease of project duration 4:CS 3:Eng CPM Network CC Network 4. What is CC? Single-Project Level: Feeding & Project Buffers Due Date
  • 37. Date/reference/classification 37 © T. Lechler, Ph.D., 2013 4. What is CC? Single-Project Level: Resource Buffers For Relay Runners – resources get a countdown – assure the resource can start immediately – activities start as soon as possible NOT when the schedule says 3 10 A B Resource Buffer 7 start! 10 current task next task 3 10 2 1 three days to go two days to go one day to go good luck strikes—early finish the plan
  • 38. Date/reference/classification 38 © T. Lechler, Ph.D., 2013 4. What is CC? Single-Project Level: Relay Runner Effects Resources seem to be working “faster” but • Overtime goes down • Speed may go down • Throughput goes way up • Quality goes up (slightly to a lot) • Projects take much less time • Resources will be idle more often • Resource utilization goes down
  • 39. Date/reference/classification 39 © T. Lechler, Ph.D., 2013 4. What is CC? Single-Project Level: Computation Steps Critical Chain computation steps for single project schedule: • Compute baseline schedule using average activity durations and ALAP • Aggregate safety margins into Project Buffer • Identify Critical Chain (CC) • Protect CC using Feeding Buffers • Try to keep baseline schedule and CC fixed during execution • Use buffers as proactive warning system during execution
  • 40. Date/reference/classification 40 © T. Lechler, Ph.D., 2013 7. What is CC? Summary CC (1996): • Feeding Buffer • Resource Buffer • Project Buffer CC Metrics • Actual Buffer/ Minimum required buffer • Due date performance (% of milestones finished or mean project duration and its standard dev. • Operating expenses (# of hours invested) • Inventory (amount of work in process not finished yet, hours invested in unfinished work orders/activities) • Project Quality (# development cycles and # of changes)
  • 41. Date/reference/classification 41 © T. Lechler, Ph.D., 2013 7. What is CC? Summary Critical Chain Advantages (CC) • Provides a systems approach for managing multiple projects sharing a set of resources • Improved system throughput (global optimum) • Explicitly takes variation (risk) into account • Efficiently! (reduces time to market) • Provides a visible, and powerful way to manage risk and likelihood of on-time delivery • A base for real risk management (reduces % of late projects) Critical Chain promises advantages over CPM!
  • 43. Date/reference/classification 43 © T. Lechler, Ph.D., 2013 Implementing CC: Creating a Project Schedule The Five Focusing Steps of ToC 1. Identify the constraint 2. Exploit the constraint 3. Subordinate everything else to the above decision 4. Elevate the constraint 5. Don’t let inertia become the constraint (If the constraint is broken, go to 1)
  • 44. Date/reference/classification 44 © T. Lechler, Ph.D., 2013 Implementing CC: Step 0 Before creating the CC project schedule • Define the project and its purpose • Define the fundamental measurements for the project
  • 45. Date/reference/classification 45 © T. Lechler, Ph.D., 2013 Implementing CC: Step 1 1. Identify the Critical Chain A. Lay out the project network with all tasks as late as possible (latest completion time of tasks) B. Working backwards, identify the contention (usually resource) to address next C. Remove the contention by adding more resources, or moving tasks earlier D. Continue until all conflicts are resolved E. Identify the longest dependent chain
  • 46. Date/reference/classification 46 © T. Lechler, Ph.D., 2013 Implementing CC: Step 2-4 2. Exploit the Critical Chain Use 50% task times and a project buffer 3. Subordinate everything else • Protect the CC with feeding buffers • Resolve new conflicts from buffers by moving tasks earlier 4. Elevate (shorten) the Critical Chain Add resources, change procedures, etc.
  • 47. Date/reference/classification 47 © T. Lechler, Ph.D., 2013 Implementing CC: Step 5 5. Go back to step 1. Do not allow inertia to become the constraint! We have now applied the Five Focusing steps of Theory of Constraints (ToC) to schedule a project
  • 48. Date/reference/classification 48 © T. Lechler, Ph.D., 2013 Implementing CC: Case 1 • Variation… – Non-critical path • if it slips, could impact the critical path – Protect the critical path — with a feeding buffer • absorbs non-critical path variation • prevents the critical path from shifting 10 10 16 20 1616 A 5 5 8 FB 1188 C PB 1410 CPM Project Plan CC Project Plan
  • 49. Date/reference/classification 49 © T. Lechler, Ph.D., 2013 20 60 20 40 20 60 Airframe +10 Component Aircraft Complete 20 30 30 Implementing CC: Case 2 Let’s establish a Critical Chain Schedule Aircraft Project – Traditional Schedule Engine +20 Critical Path: 140 Months Aircraft Start
  • 50. Date/reference/classification 50 © T. Lechler, Ph.D., 2013 10 30 10 20 10 30 Airframe Engine Component Aircraft Complete 10 15 15 Implementing CC: Case 2 Cut task estimates by 50% Aircraft Start
  • 51. Date/reference/classification 51 © T. Lechler, Ph.D., 2013 10 30 10 20 10 30 Airframe Engine Component Aircraft Complete 10 15 15 Implementing CC: Case 2 Push all tasks to start as late as possible.
  • 52. Date/reference/classification 52 © T. Lechler, Ph.D., 2013 10 30 10 20 10 30 Airframe Engine Component Aircraft Complete 10 15 15 Implementing CC: Case 2 Eliminate Resource Contention
  • 53. Date/reference/classification 53 © T. Lechler, Ph.D., 2013 10 30 10 20 10 30 Airframe Engine Component Aircraft Complete 10 15 15 Implementing CC: Case 2 Resource contention eliminated by moving Component branch 15 months backward. +15
  • 54. Date/reference/classification 54 © T. Lechler, Ph.D., 2013 10 30 10 20 10 30 Airframe Engine Component Aircraft Complete 10 15 15 Implementing CC: Case 2 Eliminate Resource Contention +15
  • 55. Date/reference/classification 55 © T. Lechler, Ph.D., 2013 10 30 10 20 10 30 Airframe Engine Component Aircraft Complete 10 15 15 Implementing CC: Case 2 Resource contention eliminated by moving Engine branch 5 months backward. +5 +15
  • 56. Date/reference/classification 56 © T. Lechler, Ph.D., 2013 10 30 10 20 10 30 Airframe Engine Component Aircraft Complete 10 15 15 Implementing CC: Case 2 Eliminate Resource Contention +5 +15
  • 57. Date/reference/classification 57 © T. Lechler, Ph.D., 2013 10 30 10 20 10 30 Airframe Engine Component Aircraft Complete 10 15 15 Implementing CC: Case 2 Resource contention eliminated by moving Airframe branch 5 months backward. +5 +5 Aircraft Start +15
  • 58. Date/reference/classification 58 © T. Lechler, Ph.D., 2013 10 30 10 20 10 30 Airframe Engine Component Aircraft Complete 10 15 15 Implementing CC: Case 2 The longest path through the network considering both TASK and RESOURCE DEPENDENCIES is the Critical Chain (CC = 70 months). +5 +5 Aircraft Start CC +15
  • 59. Date/reference/classification 59 © T. Lechler, Ph.D., 2013 10 30 10 20 10 30 Airframe Engine Component Aircraft Complete 10 15 15 Implementing CC: Buffer Management (Project Buffer) Using Buffer Management: Project Buffer Project Buffer = 38.08 months (accurate calculation) Total project duration = 108 months +5 +5 Aircraft Start Project Buffer CC +15
  • 60. Date/reference/classification 60 © T. Lechler, Ph.D., 2013 10 30 10 20 10 30 Airframe Engine Component Aircraft Complete 10 15 15 Implementing CC: Buffer Management (Feeding Buffer) Using Buffer Management: Feeding Buffers Locations of feeding buffers +5 +5 Project Buffer +15
  • 61. Date/reference/classification 61 © T. Lechler, Ph.D., 2013 10 10 20 10 30 Airframe Engine Component Aircraft Complete 10 Implementing CC: Buffer Management (Feeding Buffer) Using Buffer Management: Feeding Buffers Durations of feeding buffers moves project start to an earlier start date! Total project duration: 129 months 15 30 15 PB=38FB=26.5 FB=30 FB=10
  • 62. Date/reference/classification 62 © T. Lechler, Ph.D., 2013 Implementing CC: Conclusions 10 30 10 20 10 30 Airframe Engine Component Aircraft Complete 10 Use Project Buffer Use “Float” as “quasi feeding buffers” Total project duration = 108 months compared to Standard schedule with 140 months Aircraft Start Project Buffer CC 15 15FB=5 FB=5