28. CONTRACT VALUES HENRY HUDSON BRIDGE REHABILITATION BID VALUE: $84.3M CURRENT COST: $71.1M EST. FINAL COST: $85.5M (1.4%) % COMPLETION: 79.0% DURATION: 46 MONTHS APPROX. TIME EXT.: 1 MONTH CURRENTLY IN: 37 th MONTH START: NOV. 2006 COMPLETE: MAY 2010 (SC) STATUS: ON SCHEDULE
29. CONTRACT FACTS HENRY HUDSON BRIDGE REHABILITATION 76,000SF OF DECK REPLACEMENT (MAIN) 110 TONS OF STEEL REPAIR TO TOWERS TONS OF STEEL REPAIR TO STRUCTURE CY OF EXISTING CONCRETE REMOVAL CY OF NEW CONCRETE 100,000SF OF WORK PLATFORM INSTALLED 12,700SF OF DECK IN NORTH APPROACH SF OF NEW PAINTED STEEL OF RIVETS REPLACED WITH HS BOLTS