Feed-in Tariff Case Studies

Institute for Analysis of Solar Energy
Kickoff Symposium
“Solar Energy: A Solution to Energy and Environmental
Problems?”
                                       Karin Corfee
                                       April 24th, 2009

                                           Experience you can trust.
Agenda

• KEMA Overview
• Case Studies recent projects on Feed-in Tariffs
  – California
  – Hawaii
KEMA Services Cover the Entire Energy Value
Chain




• Consulting Services         • Customers in 70 countries
• Technical and Operational   • 1,700 employees, 50 offices in 20
Services                      countries
• Testing and Certification   • Incorporated in 1927

www.kema.com
What’s Happening in California?
California – Two State Agencies
Evaluating Feed-in Tariffs
• California Energy Commission (CEC)
  – Feed-in Tariff Docket (CEC Docket # 03-RPS-1078)


• California Public Utilities Commission
  – CPUC Feed-in Tariff OIR (08-08-009)
California Energy Commission (CEC)
 Activities on Feed-In Tariffs
• CEC Docket # 03-RPS-1078
  – 2 recent reports on the topic of Feed-In Tariffs
    • Exploring Feed-in Tariffs for California: Feed-in Tariff
       Design Issues and Options
       – Publication No. CEC-2008-003
     • California Feed-in Tariff Design and Policy Options
       – Publication No. CEC-2008-009D
  – KEMA supported development of both of these reports with
    support from Sustainable Energy Advantage, Wilson Rickerson
    and Exeter Associates
  – Both reports can be found on CEC website
    • http://www.energy.ca.gov/portfolio/documents
CA Feed-in Tariff Goals, Objectives &
  Policy Drivers
                                     CEC staff and Renewable Energy
Goals: e.g.                          Committee identified ‘Policy Drivers’
-reduce GHG                          for feed-in tariffs:
                  Objectives: e.g.
-Reduce fossil                       • High priority:
                  -20% RE by 2010
fuel use                                     Quantity of renewable energy
                  -33% RE by 2020
- manage                                     Financial security
ratepayer cost                       • Medium priority
& risk                                       Diversity ‘A’ = Diverse mix of
-Etc.                                      technology & operational
                                           characteristics
                                             Sustainable renewable
Subject to constraints…
   • Available transmission                energy
   • Siting/permitting                       Price stabilization
   • Feasible build-out time           Lower priority
   • Cost-effectiveness                      Diversity ‘B’ = other policy
   • Environmental/resource                objectives (e.g. biomass)
   sustainability

                                                        7
Key Benefits and Features of FITs
Identified
•   Guaranteed price
•   Guaranteed buyer
•   Long-term guaranteed revenue stream
•   Generally, unbounded market regardless of
    completion date
•   Minimizes transaction costs
•   Minimizes complexity of responding to solicitations
•   Few buyers with irregular shopping schedules
    (timing of market)
•   Reduces buyer credit or financing concerns
•   Generally, guaranteed interconnection
Feed-in Tariff Issues and Options




Source: Exploring Feed-in Tariffs for California: Feed-in Tariff Design and Implementation Issues and
Options (referred to herein as the Issues & Options Report, KEMA                                        9
Feed-in Tariff Design Issues and Options (2)




Source: Exploring Feed-in Tariffs for California: Feed-in Tariff Design and Implementation Issues and
Options (referred to herein as the Issues & Options Report, KEMA                                      10
FIT Design and Policy Options for CA
                                    #1                                  #2                            #3
                        Full-Market, unlimited size,     > 20 MW, undifferentiated       Differentiated Cost-based
                                                                                                CREZ-Only,
                      differentiated cost-based w/       value-based 3-yr pilot in 1
                                                                  utility                         > 1.5 MW
                         competitive benchmark,
                           conditional triggered
                    All                                All                               All
Resource Type
                                                       New + repowering                  New
                    New, separate price for
Vintage             repowering
                    No limit                           > 20                              >1.5
Size
                    If RPS<20% contracted by 2010,     Now (available for 3-year         automatically in 2010-11
Timing              start in 2012-13                   duration)                         (so projects developed with
                                                                                         transmission)
                    Full Market                        Pilot (limited time, 1 utility)   CREZ-Only
Scope
                                                                                         Cost-based
                    Cost-based with initial            Value Based (time & peak
Setting the Price   differentiated auction without     differentiated with CO2 & other
                                                       adders)
                    MPR to set competitive
                    benchmark for subsequent tariff
                    Long-term                          Long-term                         Long-term
Contract

Duration
                                                       Not Applicable
                    Differentiation by technology &                                      Wind by size, geothermal,
Tariff              size                                                                 biomass by size, solar by
                                                                                         technology
Differentiation
                                                       Uncapped
                    Capped at RPS targets; caps on                                       Capped at CREZ
                                                                                            11
Limits              more expensive technologies                                          Transmission limit
FIT Design and Policy Options for CA
                                         #4                         #5                           #6
                         Solar > net metering pilot   Sustainable biomass > 1.5    Full market < 20 MW cost-
                                                        MW only, cost-based
                          in 1 utility, cost-based                                  based differentiated by
                                                                                       technology & size
                             with competitive
                                benchmark
                         Solar                        Biomass (sustainable)        All
Resource Type

                         New                          New
Vintage                                                                            New, separate price for
                                                                                   repowering
                         > Net metering threshold     >1.5                         <20
Size

                         Now                          Now                          Now
Timing

                         Pilot within one utility     Full Market                  Full Market
Scope

                                                                                    Cost-based
Setting the Price        Cost-Based w/ Competitive    Cost-based, calculated to
                         benchmark                    consider sustainable yield of
                                                      local biomass sources
                         Long-term                    Short- or Medium Term        Long-term
Contract Duration

                         By size, type                By fuel and size
Tariff Differentiation                                                             Differentiation by technology
                                                                                   & size
                                                      Uncapped                     Uncapped
Limits                   Capacity limit will be
                                                                                         12
                         established for the
                         sponsoring utility.
CA IOU Contracted Capacity for
Renewable Generation
IOU Contracted Capacity - Contracts                                             IOU Contracted Capacity - MW




Source: Energy Commission’s Database of Investor-Owned Utilities’ Contracts for Renewable Generation, Contracts Signed Towards Meeting the
California RPS Targets webpage, updated January 18, 2009, http://www.energy.ca.gov/portfolio/contracts_database.html.
Recommendation of CEC Staff
• Establish feed-in tariff initially for projects up to 20 MW
  –   Cost-based, must take tariff offering long-term contracts
  –   Open to all RPS-eligible resource types
  –   For new projects (separate tariff could be explored for repowering)
  –   No waiting
  –   Technology- and size-differentiated

• Consider recommended feed-in tariff as a potential
  bridge to broader scale implementation of feed-in tariffs
  for
  – Projects > 20 MW, Projects in CREZs
        • As greater experience is gained with smaller project feed-in
          tariffs
        • As transmission and other barriers are addressed
        • If conditions merit expansion
                                                         14
CPUC Feed-in Tariff Activities
• CPUC approved Feed-in Tariffs in February 2008 (Phase I)
   – Originally authorized by AB 1969 (Yee, 2006) for generators < 1.5 MW owned by
      public water and wastewater facilities
      •   Facilitates a streamlined interconnection process
   – Expanded to include “all customers” of the 3 IOUs
   – Statewide cumulative capacity up to 498 MW
   – Two contract choices depending upon customer choice
      •   Full scale production
      •   Excess sales (after on-site usage)
• CPUC R.08-08-009 is currently considering Phase II
   – Expansion of installation size cap between 1.5 and 20 MW
   – Expansion of FIT to 3rd party ownership of RPS eligible facilities
   – Counting excess sales toward program limits
   – Does not include modification of tariff structure
  Source: CPUC
CA Small Renewable Energy
 Generation Tariffs - Price
 • Rate is currently determined                                  15 year Annual Average
    by Market Price Referent                                     ($/MWh)
    (MPR) with Time of Delivery
    (TOD) adjustments                          IOU               MPR               Solar

    – Reference point of MPR is                                                    Estimate*

        set by law as a new                    PG&E              $0.09             $0.11

        Combined Cycle gas plant
                                               SCE               $0.09             $0.13
    – In AB 1969, the MPR (and
        annual #) is adjusted for              SDG&E             $0.09             $0.11

        season and time of delivery   * Solar produces largely on peak so receives a slightly higher average rate




Source: CPUC
CPUC
• SCE
 – Currently offers standard offer contracts for biomass projects up to 20 MW
   • Price set at MPR
   • 3 contracts offered (<1 MW, 1-5 MW, 5-20 MW)
        – 5-20 MW contracts include performance and development security
          requirements
 – SCE proposes in its RPS procurement plan to expand standard offer
   contracts to all renewable technologies
   • Two contracts will be offered: 1.5 -5 MW and 5-20 MW
• PG&E
 – Proposing a Feed-in Tariff Pilot Program for Feed-in Tariffs
   • Streamlined the contracting process for RE generators of all sizes
   • CPUC “pre-approved contract
   • Price at or below MPR
Note the

CPUC Energy Division Staff Proposal   project
                                      size cut-off
Hawaii
Hawaiian Clean Energy Initiative
Agreement (HCEI)
• Energy Agreement among the State of Hawaii, Division
  of Consumer Advocacy (CA) and the Hawaiian Electric
  Companies (HECO Companies)
• FIT Components to HCEI Agreement
  – PUC to determine the best design for FITs
    • March 2009
  – PUC to adopt a set of FITs and prices
    • July 2009
  – Utility PPA of RE made using the PUC approved FIT
    would be approved for rate recovery
  – Utility purchases of RE under the FIT would be
    counted towards the RPS
Hawaiian Public Utilities Commission
(PUC) Order
• Docket No. 2008-0273
  – Investigate the Implementation of Feed-in Tariffs
• Order Initiating Investigation
  – Filed on October 24, 2008
  – Required HECO Companies and the Consumer
    Advocate to file a Joint Proposal on FIT Program
    Design
• HECO Feed-In Tariff Program Plan
  – Developed by KEMA to support the development of
    the Joint Proposal
• The HECO Companies and the Consumer
  Advocate filed a Joint Proposal on FITs (HI FIT
  Proposal) on December 23, 2008
HI FIT Proposal – Key Design Objectives
            • A FIT is best suited for
               renewable energy projects that
               lend themselves to the use of
               standardized energy payment
               rates and power purchase
               contract terms and conditions,
               and which can be developed
               and interconnected to the utility
               grid in a relatively predictable
               and systematic manner
HI FIT Proposal – Key Elements
• Renewable resources initially targeted in the
      proposed FIT are those that:
  – Do not require complex environmental and land
       use permitting.
  –    Do not typically require extensive and lengthy
       interconnection studies or the need for significant
       interconnection requirements.
  –    Do not trigger complex financial accounting issues
       relative to utility power purchase contracts.
  –    Have already been, or are currently in the process
       of being implemented in Hawaii in commercial
       application.
FIT Program Eligibility


• Proposal is that a subset of
  renewable electricity
  technologies and project
  sizes will be targeted initially

                                                Hawaii
                           Oahu       Maui      Island      Lanai     Molokai
 PV Systems              ≤ 500 kW   ≤ 250 kW   ≤ 250 kW   ≤ 100 kW   ≤ 100 kW
 CSP Systems             ≤ 500 kW   ≤ 500 kW   ≤ 500 kW   ≤ 100 kW   ≤ 100 kW
 In-Line Hydro Systems   ≤ 100 kW   ≤ 100 kW   ≤ 100 kW   ≤ 100 kW   ≤ 100 kW
 Wind power systems      ≤ 100 kW   ≤ 100 kW   ≤ 100 kW   ≤ 100 kW   ≤ 100 kW

                                                              24
HI FIT Proposal - Program Eligibility
• The FIT Update (Phase II) will examine adding:
  – Wave energy generating systems
  – Landfill gas generating systems
  – Sewage based digester gas generating systems
  – Biomass, including biomass crops, agricultural and
    animal wastes, and municipal solid waste
  – Liquid biofuel-fired systems




                                               25
HI FIT Proposal - Setting the Tariff Rate
• Tariffs should be based on cost of
   generation plus a reasonable profit
• The tariff rate should be based on the costs of
   developing a “typical” project
• All costs and operating estimates will be
   Hawaii specific due to Hawaii’s unique
   geography that affects cost of generation to the
   best extent possible
• Tariff rates should differentiate between:
  – Technology type
  – Project size
  – Project location
                                                      26
HI FIT Program Design Matrix
• Hypothetical Values

   Island “X”


                         Technical Attributes         Annual Quantity Target
                                      Expanded
                                  Voltage/Frequency                            FIT Rate,
                                    Ride Through                    2011
                   Curtailable                          2010                   ¢/kWh


    100 kW <PV≤       Yes             Required         8 MW         8 MW           22
      250 kW                          Required
                       …                               2 MW         2 MW           18


    30 kW ≤ PV ≤      Yes             Required         5 MW         5 MW           23
       100 kW                         Required
                       …                               2 MW         2 MW           19


                                         Yes
                       …                               3 MW         3 MW           24
     PV < 30 kW
                       …                  …            1 MW         1 MW           20


                                                                                 27
HI FIT Proposal - Contract Duration
• Contracts would be a standard length depending on the
  technology
  – New PV Systems – 20 years
  – New CSP – 10 years
  – Additional information is being gathered for in-line
      hydropower and small scale wind
• Following the initial contract term, projects could be
  allowed to extend, subject to a new FIT rate




                                              28
Interconnection




• Interconnection of eligible renewable generation to
  follow Rule 14.H technical standards
• Generators responsible for interconnection costs,
  consistent with current practices
• Reasonable FIT generator interconnection costs will
  be considered in the development of the tariff rates,
  as differentiated by technology and size 29
Thank you

Karin Corfee, KEMA Inc.

Senior Principal

Sustainable Market Strategies

Tel:   510-891-0446, x4112

karin.corfee@kema.com



Please visit our website www.kema.com
                                        Experience you can trust.

Weitere ähnliche Inhalte

Ähnlich wie Karin Corfee | Feed-in Tariff Case Studies

Evaluating the Development and Impact of Feed-In Tariffs
Evaluating the Development and Impact of Feed-In TariffsEvaluating the Development and Impact of Feed-In Tariffs
Evaluating the Development and Impact of Feed-In TariffsDirk Volkmann
 
Ninth Avenue Terminal Solar Proposal
Ninth Avenue Terminal Solar ProposalNinth Avenue Terminal Solar Proposal
Ninth Avenue Terminal Solar Proposalninthavenue
 
Clean Energy Trends – Costs, Policies and Initiatives - Steve Corneli, NRG En...
Clean Energy Trends – Costs, Policies and Initiatives - Steve Corneli, NRG En...Clean Energy Trends – Costs, Policies and Initiatives - Steve Corneli, NRG En...
Clean Energy Trends – Costs, Policies and Initiatives - Steve Corneli, NRG En...Energy Network marcus evans
 
General Carbon Newsletter - April 2011
General Carbon Newsletter - April 2011General Carbon Newsletter - April 2011
General Carbon Newsletter - April 2011Rameez Shaikh
 
Save on energy cost with a energy procurement reverse auction
Save on energy cost with a energy procurement reverse auctionSave on energy cost with a energy procurement reverse auction
Save on energy cost with a energy procurement reverse auctionmarussell624
 
GCCSI Financial Model Case Study
GCCSI Financial Model Case StudyGCCSI Financial Model Case Study
GCCSI Financial Model Case StudyGlobal CCS Institute
 
Carbon Financing Structures Accra Final
Carbon Financing Structures Accra FinalCarbon Financing Structures Accra Final
Carbon Financing Structures Accra Finalfbasoc
 
Flevy.com - Wireless Spend Sourcing Framework
Flevy.com - Wireless Spend Sourcing FrameworkFlevy.com - Wireless Spend Sourcing Framework
Flevy.com - Wireless Spend Sourcing FrameworkDavid Tracy
 
Course on Regulation and Sustainable Energy in Developing Countries - Session 4
Course on Regulation and Sustainable Energy in Developing Countries - Session 4Course on Regulation and Sustainable Energy in Developing Countries - Session 4
Course on Regulation and Sustainable Energy in Developing Countries - Session 4Leonardo ENERGY
 
Doe 1 dollar per watt roadmap dpw lushetsky
Doe 1 dollar per watt roadmap dpw lushetskyDoe 1 dollar per watt roadmap dpw lushetsky
Doe 1 dollar per watt roadmap dpw lushetskychandyGhosh
 
Jason Gifford REV 2012 Presentation - Drivers of Change for Distributed Resou...
Jason Gifford REV 2012 Presentation - Drivers of Change for Distributed Resou...Jason Gifford REV 2012 Presentation - Drivers of Change for Distributed Resou...
Jason Gifford REV 2012 Presentation - Drivers of Change for Distributed Resou...Chris Williams
 
Vant hof 2010
Vant hof 2010Vant hof 2010
Vant hof 2010Ngy Ea
 
Michael Keiths Professional Portfolio
Michael Keiths Professional PortfolioMichael Keiths Professional Portfolio
Michael Keiths Professional Portfoliobbascm
 
14.10.2019 proposed framework for real time market for electricity
14.10.2019 proposed framework for real time market for electricity14.10.2019 proposed framework for real time market for electricity
14.10.2019 proposed framework for real time market for electricityVijay Menghani
 
Role of Public Policies & Financing Techniques in Promoting Wind Energy
Role of Public Policies & Financing Techniques in Promoting Wind EnergyRole of Public Policies & Financing Techniques in Promoting Wind Energy
Role of Public Policies & Financing Techniques in Promoting Wind Energyswapnil_energy
 
Geo Epc Merrigan
Geo Epc MerriganGeo Epc Merrigan
Geo Epc MerriganConor Merrigan
 
Robin Duke Woolley Beecham Research Brl M2 M Forum 07 04 09
Robin Duke Woolley Beecham Research  Brl M2 M Forum 07 04 09Robin Duke Woolley Beecham Research  Brl M2 M Forum 07 04 09
Robin Duke Woolley Beecham Research Brl M2 M Forum 07 04 09GoWireless
 
Robin Duke Woolley Beecham Research Brl M2 M Forum 07 04 09
Robin Duke Woolley Beecham Research  Brl M2 M Forum 07 04 09Robin Duke Woolley Beecham Research  Brl M2 M Forum 07 04 09
Robin Duke Woolley Beecham Research Brl M2 M Forum 07 04 09GoWireless
 
The m2m market in the economic downturn - Robin Duke Woolley
The m2m market in the economic downturn - Robin Duke WoolleyThe m2m market in the economic downturn - Robin Duke Woolley
The m2m market in the economic downturn - Robin Duke WoolleyGoWireless
 

Ähnlich wie Karin Corfee | Feed-in Tariff Case Studies (20)

Evaluating the Development and Impact of Feed-In Tariffs
Evaluating the Development and Impact of Feed-In TariffsEvaluating the Development and Impact of Feed-In Tariffs
Evaluating the Development and Impact of Feed-In Tariffs
 
Ninth Avenue Terminal Solar Proposal
Ninth Avenue Terminal Solar ProposalNinth Avenue Terminal Solar Proposal
Ninth Avenue Terminal Solar Proposal
 
Clean Energy Trends – Costs, Policies and Initiatives - Steve Corneli, NRG En...
Clean Energy Trends – Costs, Policies and Initiatives - Steve Corneli, NRG En...Clean Energy Trends – Costs, Policies and Initiatives - Steve Corneli, NRG En...
Clean Energy Trends – Costs, Policies and Initiatives - Steve Corneli, NRG En...
 
General Carbon Newsletter - April 2011
General Carbon Newsletter - April 2011General Carbon Newsletter - April 2011
General Carbon Newsletter - April 2011
 
Save on energy cost with a energy procurement reverse auction
Save on energy cost with a energy procurement reverse auctionSave on energy cost with a energy procurement reverse auction
Save on energy cost with a energy procurement reverse auction
 
GCCSI Financial Model Case Study
GCCSI Financial Model Case StudyGCCSI Financial Model Case Study
GCCSI Financial Model Case Study
 
Carbon Financing Structures Accra Final
Carbon Financing Structures Accra FinalCarbon Financing Structures Accra Final
Carbon Financing Structures Accra Final
 
Flevy.com - Wireless Spend Sourcing Framework
Flevy.com - Wireless Spend Sourcing FrameworkFlevy.com - Wireless Spend Sourcing Framework
Flevy.com - Wireless Spend Sourcing Framework
 
Course on Regulation and Sustainable Energy in Developing Countries - Session 4
Course on Regulation and Sustainable Energy in Developing Countries - Session 4Course on Regulation and Sustainable Energy in Developing Countries - Session 4
Course on Regulation and Sustainable Energy in Developing Countries - Session 4
 
Doe 1 dollar per watt roadmap dpw lushetsky
Doe 1 dollar per watt roadmap dpw lushetskyDoe 1 dollar per watt roadmap dpw lushetsky
Doe 1 dollar per watt roadmap dpw lushetsky
 
Jason Gifford REV 2012 Presentation - Drivers of Change for Distributed Resou...
Jason Gifford REV 2012 Presentation - Drivers of Change for Distributed Resou...Jason Gifford REV 2012 Presentation - Drivers of Change for Distributed Resou...
Jason Gifford REV 2012 Presentation - Drivers of Change for Distributed Resou...
 
Vant hof 2010
Vant hof 2010Vant hof 2010
Vant hof 2010
 
Michael Keiths Professional Portfolio
Michael Keiths Professional PortfolioMichael Keiths Professional Portfolio
Michael Keiths Professional Portfolio
 
14.10.2019 proposed framework for real time market for electricity
14.10.2019 proposed framework for real time market for electricity14.10.2019 proposed framework for real time market for electricity
14.10.2019 proposed framework for real time market for electricity
 
Role of Public Policies & Financing Techniques in Promoting Wind Energy
Role of Public Policies & Financing Techniques in Promoting Wind EnergyRole of Public Policies & Financing Techniques in Promoting Wind Energy
Role of Public Policies & Financing Techniques in Promoting Wind Energy
 
Geo Epc Merrigan
Geo Epc MerriganGeo Epc Merrigan
Geo Epc Merrigan
 
Robin Duke Woolley Beecham Research Brl M2 M Forum 07 04 09
Robin Duke Woolley Beecham Research  Brl M2 M Forum 07 04 09Robin Duke Woolley Beecham Research  Brl M2 M Forum 07 04 09
Robin Duke Woolley Beecham Research Brl M2 M Forum 07 04 09
 
Robin Duke Woolley Beecham Research Brl M2 M Forum 07 04 09
Robin Duke Woolley Beecham Research  Brl M2 M Forum 07 04 09Robin Duke Woolley Beecham Research  Brl M2 M Forum 07 04 09
Robin Duke Woolley Beecham Research Brl M2 M Forum 07 04 09
 
The m2m market in the economic downturn - Robin Duke Woolley
The m2m market in the economic downturn - Robin Duke WoolleyThe m2m market in the economic downturn - Robin Duke Woolley
The m2m market in the economic downturn - Robin Duke Woolley
 
42918
4291842918
42918
 

Mehr von GW Solar Institute

Softer Solar Landings: Options to Avoid the Investment Tax Credit Cliff
Softer Solar Landings: Options to Avoid the Investment Tax Credit CliffSofter Solar Landings: Options to Avoid the Investment Tax Credit Cliff
Softer Solar Landings: Options to Avoid the Investment Tax Credit CliffGW Solar Institute
 
National Solar Jobs Census 2013
National Solar Jobs Census 2013National Solar Jobs Census 2013
National Solar Jobs Census 2013GW Solar Institute
 
Fitting Clean Energy into a Reformed Tax Code
Fitting Clean Energy into a Reformed Tax CodeFitting Clean Energy into a Reformed Tax Code
Fitting Clean Energy into a Reformed Tax CodeGW Solar Institute
 
Consensus Recommendations on How to Catalyze Low-Income Solar in DC
Consensus Recommendations on How to Catalyze Low-Income Solar in DCConsensus Recommendations on How to Catalyze Low-Income Solar in DC
Consensus Recommendations on How to Catalyze Low-Income Solar in DCGW Solar Institute
 
Economic Potential of Low-Income Solar in DC
Economic Potential of Low-Income Solar in DCEconomic Potential of Low-Income Solar in DC
Economic Potential of Low-Income Solar in DCGW Solar Institute
 
Bridging the Solar Income Gap Working Paper
Bridging the Solar Income Gap Working PaperBridging the Solar Income Gap Working Paper
Bridging the Solar Income Gap Working PaperGW Solar Institute
 
National Solar Jobs Census 2014 Report
National Solar Jobs Census 2014 ReportNational Solar Jobs Census 2014 Report
National Solar Jobs Census 2014 ReportGW Solar Institute
 
Tax Reform, a Looming Threat to a Booming Solar Industry
Tax Reform, a Looming Threat to a Booming Solar IndustryTax Reform, a Looming Threat to a Booming Solar Industry
Tax Reform, a Looming Threat to a Booming Solar IndustryGW Solar Institute
 
Low-Income Solar Roundtable Whitepaper
Low-Income Solar Roundtable WhitepaperLow-Income Solar Roundtable Whitepaper
Low-Income Solar Roundtable WhitepaperGW Solar Institute
 
Capital Partners Solar Project FAQ
Capital Partners Solar Project FAQCapital Partners Solar Project FAQ
Capital Partners Solar Project FAQGW Solar Institute
 
Bringing the Light of Solar Wealth to Low-Income Families
Bringing the Light of Solar Wealth to Low-Income FamiliesBringing the Light of Solar Wealth to Low-Income Families
Bringing the Light of Solar Wealth to Low-Income FamiliesGW Solar Institute
 
A Solar Boom, But Not For All
A Solar Boom, But Not For AllA Solar Boom, But Not For All
A Solar Boom, But Not For AllGW Solar Institute
 
Rhone Resch | Trends in Solar Energy Technology and Costs | 2014 Solar Symposium
Rhone Resch | Trends in Solar Energy Technology and Costs | 2014 Solar SymposiumRhone Resch | Trends in Solar Energy Technology and Costs | 2014 Solar Symposium
Rhone Resch | Trends in Solar Energy Technology and Costs | 2014 Solar SymposiumGW Solar Institute
 
Jon Hillis | Innovation Showcase | 2014 Solar Symposium
Jon Hillis | Innovation Showcase | 2014 Solar SymposiumJon Hillis | Innovation Showcase | 2014 Solar Symposium
Jon Hillis | Innovation Showcase | 2014 Solar SymposiumGW Solar Institute
 
Hannah Masterjohn | Innovation Showcase | 2014 Solar Symposium
Hannah Masterjohn | Innovation Showcase | 2014 Solar SymposiumHannah Masterjohn | Innovation Showcase | 2014 Solar Symposium
Hannah Masterjohn | Innovation Showcase | 2014 Solar SymposiumGW Solar Institute
 
Bracken Hendricks | Innovation Showcase | 2014 Solar Symposium
Bracken Hendricks | Innovation Showcase | 2014 Solar SymposiumBracken Hendricks | Innovation Showcase | 2014 Solar Symposium
Bracken Hendricks | Innovation Showcase | 2014 Solar SymposiumGW Solar Institute
 
Annie Harper | Innovation Showcase | 2014 Solar Symposium
Annie Harper | Innovation Showcase | 2014 Solar SymposiumAnnie Harper | Innovation Showcase | 2014 Solar Symposium
Annie Harper | Innovation Showcase | 2014 Solar SymposiumGW Solar Institute
 
Beth Galante | Innovation Showcase | 2014 Solar Symposium
Beth Galante | Innovation Showcase | 2014 Solar SymposiumBeth Galante | Innovation Showcase | 2014 Solar Symposium
Beth Galante | Innovation Showcase | 2014 Solar SymposiumGW Solar Institute
 
Planet Forward Infographic: A Big Deal for Solar in the District
Planet Forward Infographic: A Big Deal for Solar in the DistrictPlanet Forward Infographic: A Big Deal for Solar in the District
Planet Forward Infographic: A Big Deal for Solar in the DistrictGW Solar Institute
 
18th Annual US-China Legal Exchange
18th Annual US-China Legal Exchange18th Annual US-China Legal Exchange
18th Annual US-China Legal ExchangeGW Solar Institute
 

Mehr von GW Solar Institute (20)

Softer Solar Landings: Options to Avoid the Investment Tax Credit Cliff
Softer Solar Landings: Options to Avoid the Investment Tax Credit CliffSofter Solar Landings: Options to Avoid the Investment Tax Credit Cliff
Softer Solar Landings: Options to Avoid the Investment Tax Credit Cliff
 
National Solar Jobs Census 2013
National Solar Jobs Census 2013National Solar Jobs Census 2013
National Solar Jobs Census 2013
 
Fitting Clean Energy into a Reformed Tax Code
Fitting Clean Energy into a Reformed Tax CodeFitting Clean Energy into a Reformed Tax Code
Fitting Clean Energy into a Reformed Tax Code
 
Consensus Recommendations on How to Catalyze Low-Income Solar in DC
Consensus Recommendations on How to Catalyze Low-Income Solar in DCConsensus Recommendations on How to Catalyze Low-Income Solar in DC
Consensus Recommendations on How to Catalyze Low-Income Solar in DC
 
Economic Potential of Low-Income Solar in DC
Economic Potential of Low-Income Solar in DCEconomic Potential of Low-Income Solar in DC
Economic Potential of Low-Income Solar in DC
 
Bridging the Solar Income Gap Working Paper
Bridging the Solar Income Gap Working PaperBridging the Solar Income Gap Working Paper
Bridging the Solar Income Gap Working Paper
 
National Solar Jobs Census 2014 Report
National Solar Jobs Census 2014 ReportNational Solar Jobs Census 2014 Report
National Solar Jobs Census 2014 Report
 
Tax Reform, a Looming Threat to a Booming Solar Industry
Tax Reform, a Looming Threat to a Booming Solar IndustryTax Reform, a Looming Threat to a Booming Solar Industry
Tax Reform, a Looming Threat to a Booming Solar Industry
 
Low-Income Solar Roundtable Whitepaper
Low-Income Solar Roundtable WhitepaperLow-Income Solar Roundtable Whitepaper
Low-Income Solar Roundtable Whitepaper
 
Capital Partners Solar Project FAQ
Capital Partners Solar Project FAQCapital Partners Solar Project FAQ
Capital Partners Solar Project FAQ
 
Bringing the Light of Solar Wealth to Low-Income Families
Bringing the Light of Solar Wealth to Low-Income FamiliesBringing the Light of Solar Wealth to Low-Income Families
Bringing the Light of Solar Wealth to Low-Income Families
 
A Solar Boom, But Not For All
A Solar Boom, But Not For AllA Solar Boom, But Not For All
A Solar Boom, But Not For All
 
Rhone Resch | Trends in Solar Energy Technology and Costs | 2014 Solar Symposium
Rhone Resch | Trends in Solar Energy Technology and Costs | 2014 Solar SymposiumRhone Resch | Trends in Solar Energy Technology and Costs | 2014 Solar Symposium
Rhone Resch | Trends in Solar Energy Technology and Costs | 2014 Solar Symposium
 
Jon Hillis | Innovation Showcase | 2014 Solar Symposium
Jon Hillis | Innovation Showcase | 2014 Solar SymposiumJon Hillis | Innovation Showcase | 2014 Solar Symposium
Jon Hillis | Innovation Showcase | 2014 Solar Symposium
 
Hannah Masterjohn | Innovation Showcase | 2014 Solar Symposium
Hannah Masterjohn | Innovation Showcase | 2014 Solar SymposiumHannah Masterjohn | Innovation Showcase | 2014 Solar Symposium
Hannah Masterjohn | Innovation Showcase | 2014 Solar Symposium
 
Bracken Hendricks | Innovation Showcase | 2014 Solar Symposium
Bracken Hendricks | Innovation Showcase | 2014 Solar SymposiumBracken Hendricks | Innovation Showcase | 2014 Solar Symposium
Bracken Hendricks | Innovation Showcase | 2014 Solar Symposium
 
Annie Harper | Innovation Showcase | 2014 Solar Symposium
Annie Harper | Innovation Showcase | 2014 Solar SymposiumAnnie Harper | Innovation Showcase | 2014 Solar Symposium
Annie Harper | Innovation Showcase | 2014 Solar Symposium
 
Beth Galante | Innovation Showcase | 2014 Solar Symposium
Beth Galante | Innovation Showcase | 2014 Solar SymposiumBeth Galante | Innovation Showcase | 2014 Solar Symposium
Beth Galante | Innovation Showcase | 2014 Solar Symposium
 
Planet Forward Infographic: A Big Deal for Solar in the District
Planet Forward Infographic: A Big Deal for Solar in the DistrictPlanet Forward Infographic: A Big Deal for Solar in the District
Planet Forward Infographic: A Big Deal for Solar in the District
 
18th Annual US-China Legal Exchange
18th Annual US-China Legal Exchange18th Annual US-China Legal Exchange
18th Annual US-China Legal Exchange
 

KĂźrzlich hochgeladen

Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...apidays
 
Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...
Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...
Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...gurkirankumar98700
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationRadu Cotescu
 
A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024Results
 
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Igalia
 
🐬 The future of MySQL is Postgres 🐘
🐬  The future of MySQL is Postgres   🐘🐬  The future of MySQL is Postgres   🐘
🐬 The future of MySQL is Postgres 🐘RTylerCroy
 
2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...Martijn de Jong
 
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...Neo4j
 
Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024The Digital Insurer
 
Breaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountBreaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountPuma Security, LLC
 
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...Neo4j
 
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Miguel AraĂşjo
 
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc
 
Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024The Digital Insurer
 
Factors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptxFactors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptxKatpro Technologies
 
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationFrom Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationSafe Software
 
Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024The Digital Insurer
 
Unblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen FramesUnblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen FramesSinan KOZAK
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationMichael W. Hawkins
 
Salesforce Community Group Quito, Salesforce 101
Salesforce Community Group Quito, Salesforce 101Salesforce Community Group Quito, Salesforce 101
Salesforce Community Group Quito, Salesforce 101Paola De la Torre
 

KĂźrzlich hochgeladen (20)

Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
 
Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...
Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...
Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organization
 
A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024
 
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
 
🐬 The future of MySQL is Postgres 🐘
🐬  The future of MySQL is Postgres   🐘🐬  The future of MySQL is Postgres   🐘
🐬 The future of MySQL is Postgres 🐘
 
2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...
 
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
 
Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024
 
Breaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountBreaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path Mount
 
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
 
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
 
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
 
Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024
 
Factors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptxFactors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptx
 
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationFrom Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
 
Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024
 
Unblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen FramesUnblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen Frames
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day Presentation
 
Salesforce Community Group Quito, Salesforce 101
Salesforce Community Group Quito, Salesforce 101Salesforce Community Group Quito, Salesforce 101
Salesforce Community Group Quito, Salesforce 101
 

Karin Corfee | Feed-in Tariff Case Studies

  • 1. Feed-in Tariff Case Studies Institute for Analysis of Solar Energy Kickoff Symposium “Solar Energy: A Solution to Energy and Environmental Problems?” Karin Corfee April 24th, 2009 Experience you can trust.
  • 2. Agenda • KEMA Overview • Case Studies recent projects on Feed-in Tariffs – California – Hawaii
  • 3. KEMA Services Cover the Entire Energy Value Chain • Consulting Services • Customers in 70 countries • Technical and Operational • 1,700 employees, 50 offices in 20 Services countries • Testing and Certification • Incorporated in 1927 www.kema.com
  • 5. California – Two State Agencies Evaluating Feed-in Tariffs • California Energy Commission (CEC) – Feed-in Tariff Docket (CEC Docket # 03-RPS-1078) • California Public Utilities Commission – CPUC Feed-in Tariff OIR (08-08-009)
  • 6. California Energy Commission (CEC) Activities on Feed-In Tariffs • CEC Docket # 03-RPS-1078 – 2 recent reports on the topic of Feed-In Tariffs • Exploring Feed-in Tariffs for California: Feed-in Tariff Design Issues and Options – Publication No. CEC-2008-003 • California Feed-in Tariff Design and Policy Options – Publication No. CEC-2008-009D – KEMA supported development of both of these reports with support from Sustainable Energy Advantage, Wilson Rickerson and Exeter Associates – Both reports can be found on CEC website • http://www.energy.ca.gov/portfolio/documents
  • 7. CA Feed-in Tariff Goals, Objectives & Policy Drivers CEC staff and Renewable Energy Goals: e.g. Committee identified ‘Policy Drivers’ -reduce GHG for feed-in tariffs: Objectives: e.g. -Reduce fossil • High priority: -20% RE by 2010 fuel use Quantity of renewable energy -33% RE by 2020 - manage Financial security ratepayer cost • Medium priority & risk Diversity ‘A’ = Diverse mix of -Etc. technology & operational characteristics Sustainable renewable Subject to constraints… • Available transmission energy • Siting/permitting Price stabilization • Feasible build-out time Lower priority • Cost-effectiveness Diversity ‘B’ = other policy • Environmental/resource objectives (e.g. biomass) sustainability 7
  • 8. Key Benefits and Features of FITs Identified • Guaranteed price • Guaranteed buyer • Long-term guaranteed revenue stream • Generally, unbounded market regardless of completion date • Minimizes transaction costs • Minimizes complexity of responding to solicitations • Few buyers with irregular shopping schedules (timing of market) • Reduces buyer credit or financing concerns • Generally, guaranteed interconnection
  • 9. Feed-in Tariff Issues and Options Source: Exploring Feed-in Tariffs for California: Feed-in Tariff Design and Implementation Issues and Options (referred to herein as the Issues & Options Report, KEMA 9
  • 10. Feed-in Tariff Design Issues and Options (2) Source: Exploring Feed-in Tariffs for California: Feed-in Tariff Design and Implementation Issues and Options (referred to herein as the Issues & Options Report, KEMA 10
  • 11. FIT Design and Policy Options for CA #1 #2 #3 Full-Market, unlimited size, > 20 MW, undifferentiated Differentiated Cost-based CREZ-Only, differentiated cost-based w/ value-based 3-yr pilot in 1 utility > 1.5 MW competitive benchmark, conditional triggered All All All Resource Type New + repowering New New, separate price for Vintage repowering No limit > 20 >1.5 Size If RPS<20% contracted by 2010, Now (available for 3-year automatically in 2010-11 Timing start in 2012-13 duration) (so projects developed with transmission) Full Market Pilot (limited time, 1 utility) CREZ-Only Scope Cost-based Cost-based with initial Value Based (time & peak Setting the Price differentiated auction without differentiated with CO2 & other adders) MPR to set competitive benchmark for subsequent tariff Long-term Long-term Long-term Contract Duration Not Applicable Differentiation by technology & Wind by size, geothermal, Tariff size biomass by size, solar by technology Differentiation Uncapped Capped at RPS targets; caps on Capped at CREZ 11 Limits more expensive technologies Transmission limit
  • 12. FIT Design and Policy Options for CA #4 #5 #6 Solar > net metering pilot Sustainable biomass > 1.5 Full market < 20 MW cost- MW only, cost-based in 1 utility, cost-based based differentiated by technology & size with competitive benchmark Solar Biomass (sustainable) All Resource Type New New Vintage New, separate price for repowering > Net metering threshold >1.5 <20 Size Now Now Now Timing Pilot within one utility Full Market Full Market Scope Cost-based Setting the Price Cost-Based w/ Competitive Cost-based, calculated to benchmark consider sustainable yield of local biomass sources Long-term Short- or Medium Term Long-term Contract Duration By size, type By fuel and size Tariff Differentiation Differentiation by technology & size Uncapped Uncapped Limits Capacity limit will be 12 established for the sponsoring utility.
  • 13. CA IOU Contracted Capacity for Renewable Generation IOU Contracted Capacity - Contracts IOU Contracted Capacity - MW Source: Energy Commission’s Database of Investor-Owned Utilities’ Contracts for Renewable Generation, Contracts Signed Towards Meeting the California RPS Targets webpage, updated January 18, 2009, http://www.energy.ca.gov/portfolio/contracts_database.html.
  • 14. Recommendation of CEC Staff • Establish feed-in tariff initially for projects up to 20 MW – Cost-based, must take tariff offering long-term contracts – Open to all RPS-eligible resource types – For new projects (separate tariff could be explored for repowering) – No waiting – Technology- and size-differentiated • Consider recommended feed-in tariff as a potential bridge to broader scale implementation of feed-in tariffs for – Projects > 20 MW, Projects in CREZs • As greater experience is gained with smaller project feed-in tariffs • As transmission and other barriers are addressed • If conditions merit expansion 14
  • 15. CPUC Feed-in Tariff Activities • CPUC approved Feed-in Tariffs in February 2008 (Phase I) – Originally authorized by AB 1969 (Yee, 2006) for generators < 1.5 MW owned by public water and wastewater facilities • Facilitates a streamlined interconnection process – Expanded to include “all customers” of the 3 IOUs – Statewide cumulative capacity up to 498 MW – Two contract choices depending upon customer choice • Full scale production • Excess sales (after on-site usage) • CPUC R.08-08-009 is currently considering Phase II – Expansion of installation size cap between 1.5 and 20 MW – Expansion of FIT to 3rd party ownership of RPS eligible facilities – Counting excess sales toward program limits – Does not include modification of tariff structure Source: CPUC
  • 16. CA Small Renewable Energy Generation Tariffs - Price • Rate is currently determined 15 year Annual Average by Market Price Referent ($/MWh) (MPR) with Time of Delivery (TOD) adjustments IOU MPR Solar – Reference point of MPR is Estimate* set by law as a new PG&E $0.09 $0.11 Combined Cycle gas plant SCE $0.09 $0.13 – In AB 1969, the MPR (and annual #) is adjusted for SDG&E $0.09 $0.11 season and time of delivery * Solar produces largely on peak so receives a slightly higher average rate Source: CPUC
  • 17. CPUC • SCE – Currently offers standard offer contracts for biomass projects up to 20 MW • Price set at MPR • 3 contracts offered (<1 MW, 1-5 MW, 5-20 MW) – 5-20 MW contracts include performance and development security requirements – SCE proposes in its RPS procurement plan to expand standard offer contracts to all renewable technologies • Two contracts will be offered: 1.5 -5 MW and 5-20 MW • PG&E – Proposing a Feed-in Tariff Pilot Program for Feed-in Tariffs • Streamlined the contracting process for RE generators of all sizes • CPUC “pre-approved contract • Price at or below MPR
  • 18. Note the CPUC Energy Division Staff Proposal project size cut-off
  • 20. Hawaiian Clean Energy Initiative Agreement (HCEI) • Energy Agreement among the State of Hawaii, Division of Consumer Advocacy (CA) and the Hawaiian Electric Companies (HECO Companies) • FIT Components to HCEI Agreement – PUC to determine the best design for FITs • March 2009 – PUC to adopt a set of FITs and prices • July 2009 – Utility PPA of RE made using the PUC approved FIT would be approved for rate recovery – Utility purchases of RE under the FIT would be counted towards the RPS
  • 21. Hawaiian Public Utilities Commission (PUC) Order • Docket No. 2008-0273 – Investigate the Implementation of Feed-in Tariffs • Order Initiating Investigation – Filed on October 24, 2008 – Required HECO Companies and the Consumer Advocate to file a Joint Proposal on FIT Program Design • HECO Feed-In Tariff Program Plan – Developed by KEMA to support the development of the Joint Proposal • The HECO Companies and the Consumer Advocate filed a Joint Proposal on FITs (HI FIT Proposal) on December 23, 2008
  • 22. HI FIT Proposal – Key Design Objectives • A FIT is best suited for renewable energy projects that lend themselves to the use of standardized energy payment rates and power purchase contract terms and conditions, and which can be developed and interconnected to the utility grid in a relatively predictable and systematic manner
  • 23. HI FIT Proposal – Key Elements • Renewable resources initially targeted in the proposed FIT are those that: – Do not require complex environmental and land use permitting. – Do not typically require extensive and lengthy interconnection studies or the need for significant interconnection requirements. – Do not trigger complex financial accounting issues relative to utility power purchase contracts. – Have already been, or are currently in the process of being implemented in Hawaii in commercial application.
  • 24. FIT Program Eligibility • Proposal is that a subset of renewable electricity technologies and project sizes will be targeted initially Hawaii Oahu Maui Island Lanai Molokai PV Systems ≤ 500 kW ≤ 250 kW ≤ 250 kW ≤ 100 kW ≤ 100 kW CSP Systems ≤ 500 kW ≤ 500 kW ≤ 500 kW ≤ 100 kW ≤ 100 kW In-Line Hydro Systems ≤ 100 kW ≤ 100 kW ≤ 100 kW ≤ 100 kW ≤ 100 kW Wind power systems ≤ 100 kW ≤ 100 kW ≤ 100 kW ≤ 100 kW ≤ 100 kW 24
  • 25. HI FIT Proposal - Program Eligibility • The FIT Update (Phase II) will examine adding: – Wave energy generating systems – Landfill gas generating systems – Sewage based digester gas generating systems – Biomass, including biomass crops, agricultural and animal wastes, and municipal solid waste – Liquid biofuel-fired systems 25
  • 26. HI FIT Proposal - Setting the Tariff Rate • Tariffs should be based on cost of generation plus a reasonable profit • The tariff rate should be based on the costs of developing a “typical” project • All costs and operating estimates will be Hawaii specific due to Hawaii’s unique geography that affects cost of generation to the best extent possible • Tariff rates should differentiate between: – Technology type – Project size – Project location 26
  • 27. HI FIT Program Design Matrix • Hypothetical Values Island “X” Technical Attributes Annual Quantity Target Expanded Voltage/Frequency FIT Rate, Ride Through 2011 Curtailable 2010 ¢/kWh 100 kW <PV≤ Yes Required 8 MW 8 MW 22 250 kW Required … 2 MW 2 MW 18 30 kW ≤ PV ≤ Yes Required 5 MW 5 MW 23 100 kW Required … 2 MW 2 MW 19 Yes … 3 MW 3 MW 24 PV < 30 kW … … 1 MW 1 MW 20 27
  • 28. HI FIT Proposal - Contract Duration • Contracts would be a standard length depending on the technology – New PV Systems – 20 years – New CSP – 10 years – Additional information is being gathered for in-line hydropower and small scale wind • Following the initial contract term, projects could be allowed to extend, subject to a new FIT rate 28
  • 29. Interconnection • Interconnection of eligible renewable generation to follow Rule 14.H technical standards • Generators responsible for interconnection costs, consistent with current practices • Reasonable FIT generator interconnection costs will be considered in the development of the tariff rates, as differentiated by technology and size 29
  • 30. Thank you Karin Corfee, KEMA Inc. Senior Principal Sustainable Market Strategies Tel: 510-891-0446, x4112 karin.corfee@kema.com Please visit our website www.kema.com Experience you can trust.