SlideShare ist ein Scribd-Unternehmen logo
1 von 26
Downloaden Sie, um offline zu lesen
+
We have lots data. Let’s use it create
more credible estimates to help tame
the growth beast
A Cure for Unanticipated
Cost and Schedule Growth
Thomas J. Coonce
Glen B. Alleman
+Why Are We Here?
n In spite the estimating community’s efforts to provide
credible estimates, government programs still seem to
deliver less than promised, cost more than planned, and
take longer than needed.
n Lots of reasons. Some well established; some hypothesized
n When estimates are consistently biased low
n Decisions of choice are distorted
n Cost growth causes more growth as programs are stretched out to
fund portfolios with fixed budgets
n Taxpayers become more cynical and negative about government
n The estimating community’s credibility is seriously
questioned
2
+Why are We Here? (Concluded)
n This presentation will
n Summarize many of the reasons documented and
hypothesized why programs deliver less, cost more and are
late;
n Provide a broad brush of what the community has done to
improve the imbalance;
n Assert that we can not solve all the root causes, but we can
effectively use historical experience (reference class
forecasting) to provide more credible estimates for future
systems; and
n Propose and discuss a number of changes needed in
estimating, acquisition, and the contracting communities to
restore balance and credibility and go a long way to tame the
growth beast
3
+Cost and Schedule Growth
4
Average Median
NASA in the 90s 36% 26% 78%
NASA in the 70s 43% 26% 75%
NASA in the 80s
(GAO) 83% 60% 89%
DoD RDT&E 45% 27% 76%
Cost/Budget Growth2
Study
Percent of Projects
Which Experienced
Growth
“In 1982, an unnamed witness at a House Armed Service Committee
stated, ‘Enough material has been written on the subject of cost
growth during the last ten years to fill a Minuteman silo’.
Unfortunately, cost growth is still with us. In a decade since that
testimony enough additional information on cost growth has been
written to fill a second minuteman silo”1
1. Cost Growth in DoD Major Programs:A Historical Perspective,Col.Harry Calcutt,
April 1993, http://www.dtic.mil/dtic/tr/fulltext/u2/a276950.pdf
2. Hamaker and Schaffer, NASA, 2004
+Cost & Schedule Growth Summary at NASA -
Combined 30 Mission Growth Average Over &
Above Reserves3
42%
29%
21%
0%
10%
20%
30%
40%
50%
60%
From
Phase B
Start
From
PDR
From
CDR
DevelopmentCostGrowth
29%
23%
19%
0%
10%
20%
30%
40%
50%
60%
From
Phase B
Start
From
PDR
From
CDR
PhaseB/C/DScheduleGrowth
5
3 Internal NASA Study,2009
Development Cost Growth* Schedule Growth
+Cost and Schedule Growth
(Continued)
n Many researcherhave tried to understandthe root
causes for growth.Here is a list from one study4
n Requirements related
n Poor initial requirement definition
n Poor performance/cost trade-off during development
n Changes in quantity requirements
n Estimating related
n Errors due to limitation is estimating procedures
n Failure to understand and account for technical risks
n Poor inflation estimates
n Top down pressure to reduce estimates
n Lack of valid independent cost estimates
6
4 Calcutt, April 1993
+Cost and Schedule Growth
(Continued)
n Program Management related
n Lack of program
management expertise
n Mismanagement/human
error
n Over optimism
n Schedule concurrency
n Program stretch outs to keep
production lines open
n Contracting related
n Lack of competition
n Contractor buy-in
n Use of wrong type of contract
n Inconsistent contract
management/admin procedures
n Too much contractor oversight
n Waste
n Excess profits
n Contractors overstaffed
n Contractor indirect costs
unreasonable
n Taking too long to resolve
undefinitized contracts
7
Root causes from Col. Calcutt’s study (continued)
+Cost and Schedule Growth
(Continued)
n Budget related
n Funding instabilities caused by trying to fund too many
programs
n Funding instabilities caused by congressional decisions
n Inefficient production rates due to stretching out programs
n Failure to fund for management reserves
n Failure to fund programs at most likely cost
8
Root causes from Col. Calcutt’s study (Concluded)
+Cost and Schedule Growth
(Concluded)
n Inception related
n Unrealistic performance expectations
n Unrealistic baseline estimates for cost or schedule
n Immature technologies or excessive manufacturing or
integration risk
n Execution related
n Unanticipated design, engineering mfg or technology
integration issues
n Changes in procurement quantities
n Inadequate program funding or funding instability
n Poor performance by government or contractor personnel
9
5 Report to Congress on Performance Assessment and Root Cause Analyses,Office of the Under Secretary of
Defense for Acquisition,Technology and Logistics,March 2014, p. 7, http://www.acq.osd.mil/parca/docs/2014-
parca-report-to-congress.pdf
Root causes cited by the Office of Program Assessment and Root
Cause Analysis (PARCA)5
+A Broad Brush Of What The Estimating
Community Has Done to Tame the Growth Beast
n Instituted independent estimating organizations at various
levels with DoD and civilian agencies
n Developed cost estimates using analogous historical data
(reference class forecasting)
n Required a Cost Analysis Requirements Description (CARD) to
ensure cost estimates are based on the agreed requirements
n Developed a variety of professional training and certification
programs, e.g., Certified Cost Estimator/Analyst (CCEA),
Certified Parametric Practitioner (CPP), AACE certifications,
and PMI
n Augmented independent estimating teams with program
management and scheduling personnel e.g., NASA and DoE
n Continued to collect historical cost and technical data to
improve parametric cost estimates
n Began to develop estimates using planned top-level schedules
and historical head counts (recognition that time and people
are big cost drivers)
n Another form of reference class forecasting
10
+A Broad Brush Of What The Estimating
Community Has Done (Concluded)
n Begun to set cost and schedule targets based on the
historical variability of cost and schedules
n The Weapon System Acquisition Reform Act (WSARA) of 2009
required DoD programs to be budgeted at the 80% cost
confidence level 6
n NASA requires programs to budgeted with a 70% probability
of meeting both cost and schedule targets
11
6 According to the FY 2011 Annual Report on Cost Assessment Activities by the Director,Cost Assessment
and Program Evaluation (CAPE),the WSARA requirement for confidence levels was eliminated in the
National Defense Authorization Act for Fiscal Year 2011, Public Law 111-383. “Today,the requirement is to
select a confidence level such that it provides a high degree of confidence that the program can be
completed without the need for significant adjustment to program budgets”.
http://www.pae.osd.mil/files/Reports/CA_AR_20120508.pdf
+So What?
n The estimatingcommunity is the best position to
understand,document and communicate the myriad
reasons for cost and schedule growth.
n We are the masters at collecting the data and evidence!
n But it is not our role to make the changes.We can
only advise
n We can,however,improve our estimates by usingour
historical data more effectively
n We can persuade government leadershipto require
contractors to do the same
12
+A Few Observations
n Our estimates are typically formed around a product-oriented
structure.We have great historical databases upon which to
develop credible estimates.
n We typically estimate individual WBS elements by developing
Cost Estimating Relationships (CERs) like this:
13
$
Cost Driver (Weight)
Cost = a + bXc
Input
variable
WBS Cost
Estimate
Historical data point
Cost estimating relationship
Standard percent error boundsTECHNICAL RISK
COMBINED COST MODELING
AND TECHNICAL RISK
COST MODELING
UNCERTAINTY
CER
+A Few Observations (Continued)
n But we have difficulty persuading government leadership to increase
their estimates that reflect the historical variances because they can’t
relate it to their implementation plans that look like this:
14
+ Uncertainty in the PM’s Plan Must be
Driven by Historical Data
15
U/C
Project
End
U/C
U/C
U/C
U/C
U/C
TD $
TD $ = Segment Duration X Burn Rate
U/C
U/C
U/C
TI $U/C
TI $U/C
TI $U/C
TI $U/C
TI $U/C
Task Duration
Burn Rate
Burn Rate Uncertainty
Duration Uncertainty
Risk
Probability
of
Occurrence
TI$ Uncertainty
TI = Time-Independent Cost: Does not change as schedule
slips. Example: Materials
TD = Time-Dependent Cost: Increases as schedule
slips. Example: LOE; ‘marching Army
+A Few Observations (Concluded)
16
PDF & CDF Integrated Master Schedule-Based
71.23%
0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1
1.1
0
0.05
0.1
0.15
0.2
0.25
0 5 10 15 20
CumulativeProbability
ProbabilityDensity
PDF & CDF CER-Based
=
71.23%
0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1
1.1
0
0.05
0.1
0.15
0.2
0.25
0 5 10 15 20
CumulativeProbability
ProbabilityDensity
Historical Cost Data
by WBS
Historical Activity
Durations and
Associated Costs
+Rationale for Budgeting at the 70
percent Joint Confidence Level
n Schedule drives a large component of cost
n We want programs to deliver on or before promised and
at or below the budgeted cost. This is the problem we are
trying to solve.
n We should have a better than 50/50 change of meeting
planned targets. (Don’t we owe this to the taxpayers?)
n There is no general consensus within the estimating
community about the right joint confidence level upon
which to set budgets
n Little empirical data (Too soon to tell if NASA’s experiment is
working)
n More research needed
n Until then, pick a “reasonably” high number and see if it
works.
17
+A Proposed Solution - Step 1: Program Office
Creates a Request for Information (RFI)
18
1.0
Develop
Draft
Integrated
Master Plan
(IMP)
Program Capabilities
(Requirements)
2.0
Develop
Summary
Level
Integrated
Master
Schedule
(IMS)
3.0
Develop
Summary-
Level
Baseline
Cost-Loaded
IMS
Historical Activity Durations and
Associated Costs
5.0
Create Joint
Probability
Distribution
4.0
Create Risk
Register
(RR)
Risk Register
6.0
Decide on
Target Cost
and
Completion
Date
7.0
Prepare RFI
Package with
IMS and RR
RFI to Industry
+A Proposed Solution - Step 2: Contractors
Review and Submit Revised Plan
n Is the top-level plan logical given the technical challenges and
capabilities required? If no,
n What other activities should be included or dropped?
n What changes in logic are required?
n Are activities durations “consistent” (within family) of your
experience?
n Are the costs “consistent” (within family) of your experience?
n Is the PMO’s perspective on risks realistic? If not,
n Which risks are overstated?
n Which risks are understated?
n Which risks were missed? And what is your assessment of probabilities
and consequences for those risks?
n Revise and submit contractor-modified high level cost-level
plan, updated Risk Register, and Probability Assessment
19
+A Proposed Solution - Step 3: Program Office
Uses the Responses to RFIs to Improve an RFP
20
8.0
Assess
Responsesto
RFI
Updated Risk
Register(RR)
Updated Program Capabilities
(Requirements)
10.0
Re-create
Joint
Probability
Distribution
Updated Cost-LoadedIMS
11.0
Decide on
Targeted Cost
and
Completion
Date
Multiple responses
12.0
Create
Request for
Proposal
(RFP)
9.0
Update IMP/
IMS, Risk
Register,
and/or
Modify
Rqmts
+A Proposed Solution - Step 4: Bidders Prepare
Responses to Proposals
21
13.0
Create
Contractor
Version of
IMP
14.0
Develop
Summary
Level IMS
15.0
Develop
Detailed
Cost or
Resource-
Loaded
IMS
ContractorHistorical Activity
Durationsand Associated Costs
17.0
Create Joint
Probability
Distribution
16.0
Create
Updated
Risk
Register
(RR)
ContractorRisk
Register(RR)
18.0
Specify Joint
Confidence Level of
Targeted Cost and
Completion Date
19.0
Complete
Preparation of
Proposal
Response to RFP
Updated Program
Capabilities
(Requirements)
+A Proposed Solution - Step 5: Program Office
Evaluates and Oversees the Contractors
n Government program offices should:
n Award contracts based on the “credibility” of the historical
uncertainty data used and discrete risks for the joint cost and
schedules proposed
n Hold requirements stable after contract awards
n Require contractors to submit updated Risk Registers, and
probability statements associated with Best Case,Worse
Case and Mostly Likely Estimates at Complete in Format 5 of
the Integrated Program Management Reports (IPMRs) every
six months (What gets measured, gets managed)
22
+A Proposed Solution - Step 6: Contractors
Execute to the Plan
n Winningcontractors should:
n Set Program Management Baselines (PMBs)
n Using more detailed cost or resource-loaded Integrated
Master Schedules (IMSes)
n With at least a 50% joint probability of meeting cost and
schedule targets
n Set up objective measures of progress at IBRs that are
directly connected back to user-desired capabilities through
appropriate Technical Performance Measures (TPMs)
n Record progress (Budgeted Cost of Work Performed) using
the pre-defined set of progress criteria
n Maintain risk registers and use them to provide probability
statements of cost and completion dates every six months
23
+More on Why
n We don’t really need to understand why we have cost and schedule
growth; we just need to estimate future programs using all the historical
experience
n We need to speak the same language that the government PM speaks.
Independent product-oriented estimates based on historical data are
“right” if the probabilities are set right, but government program
managers have difficulty relating these estimates to their plans or potential
bidders’ plans
n Activity-based estimates that are grounded with historical data help
government PMs to revise their plans based on well communicated
reasons for the cost and schedule variations, i.e., what happened to similar
programs in the past
n Initial government probabilistic estimates that are based on a program’s
activity-based plan that recognize the “natural variation” of cost and
schedule performance of historical projects, should tame the growth beast
if the joint probabilities are greater than 70 percent
n Estimates that are activity-based aid government PMs and contractors to
manage the contracts during execution. The language is the same and the
focus is on their plan (the PMB) and the risks!
24
+Some How Challenges
n Estimating community needs to start collecting common development activity duration
data and associated costs
n Some of this may already be available from the schedule data contained in the Earned Value
Management Central Repository (EVM-CR)
n Government program office have to step up their game
n Need to think through the development of the system capabilities and document those in an IMP
n Need to create a notional summary-level cost-loaded activity-based plan
n Need to get help on the historical variation of activity durations and associated costs
n Need to coordinate with the acquisition community on the RFI and follow-on RFP
process
n Integrate Program Management Report (IPMR) Data Item Description (DID) would need
to be updated
n Require the Integrated Master Plan (IMP) as part of the RFP submission
n Add submission of the contractor’s Risk Register and instrumented native probability models
every six months
n Others?
25
+Discussion/Questions
26

Weitere ähnliche Inhalte

Andere mochten auch

Avoid software project horror stories - check the reality value of the estima...
Avoid software project horror stories - check the reality value of the estima...Avoid software project horror stories - check the reality value of the estima...
Avoid software project horror stories - check the reality value of the estima...Harold van Heeringen
 
Physical Percent Complete - june 2010 (6)
Physical Percent Complete - june 2010 (6)Physical Percent Complete - june 2010 (6)
Physical Percent Complete - june 2010 (6)Glen Alleman
 
Pedir lo mismo de diferentes maneras
Pedir lo mismo de diferentes manerasPedir lo mismo de diferentes maneras
Pedir lo mismo de diferentes manerasAntonio Salvadores
 
Cure for cost and schedule growth
Cure for cost and schedule growthCure for cost and schedule growth
Cure for cost and schedule growthGlen Alleman
 
Architectured Centered Design
Architectured Centered DesignArchitectured Centered Design
Architectured Centered DesignGlen Alleman
 
Establishing the performance measurement baseline (pmi fort worth)(v4)
Establishing the performance measurement baseline (pmi fort worth)(v4)Establishing the performance measurement baseline (pmi fort worth)(v4)
Establishing the performance measurement baseline (pmi fort worth)(v4)Glen Alleman
 
Inversion of Control
Inversion of ControlInversion of Control
Inversion of ControlGlen Alleman
 
Immutable Principles Of Project Management (V7 Final Cmu)
Immutable Principles Of Project Management (V7 Final Cmu)Immutable Principles Of Project Management (V7 Final Cmu)
Immutable Principles Of Project Management (V7 Final Cmu)Glen Alleman
 
Systems Engineering in One Picture
Systems Engineering in One PictureSystems Engineering in One Picture
Systems Engineering in One PictureGlen Alleman
 
Risk management processes
Risk management processesRisk management processes
Risk management processesGlen Alleman
 
iOS 7 Human Interface Guidelines
iOS 7 Human Interface GuidelinesiOS 7 Human Interface Guidelines
iOS 7 Human Interface GuidelinesEvgeny Belyaev
 
PM Chapter on Agile IT Project Management Methods
PM Chapter on Agile IT Project Management MethodsPM Chapter on Agile IT Project Management Methods
PM Chapter on Agile IT Project Management MethodsGlen Alleman
 
UX for Lean Startups Sep 15
UX for Lean Startups Sep 15UX for Lean Startups Sep 15
UX for Lean Startups Sep 15Lane Goldstone
 
4 PM Anti-Patterns
4 PM Anti-Patterns4 PM Anti-Patterns
4 PM Anti-PatternsBert Heymans
 
search.com or Google: Why we suck at naming products and companies (PCA13)
search.com or Google: Why we suck at naming products and companies (PCA13)search.com or Google: Why we suck at naming products and companies (PCA13)
search.com or Google: Why we suck at naming products and companies (PCA13)Roger Cauvin
 
Agile Girl Scouts Presentation
Agile Girl Scouts PresentationAgile Girl Scouts Presentation
Agile Girl Scouts PresentationDave Prior
 
Increasing The Probability Of Success For Your Project
Increasing The Probability Of Success For Your ProjectIncreasing The Probability Of Success For Your Project
Increasing The Probability Of Success For Your ProjectGlen Alleman
 
Moe mop tpm connections
Moe mop tpm connectionsMoe mop tpm connections
Moe mop tpm connectionsGlen Alleman
 
Improving DOE Project Performance Using the DOD Integrated Master Plan
Improving DOE Project Performance Using the DOD Integrated Master PlanImproving DOE Project Performance Using the DOD Integrated Master Plan
Improving DOE Project Performance Using the DOD Integrated Master PlanGlen Alleman
 

Andere mochten auch (20)

Avoid software project horror stories - check the reality value of the estima...
Avoid software project horror stories - check the reality value of the estima...Avoid software project horror stories - check the reality value of the estima...
Avoid software project horror stories - check the reality value of the estima...
 
Physical Percent Complete - june 2010 (6)
Physical Percent Complete - june 2010 (6)Physical Percent Complete - june 2010 (6)
Physical Percent Complete - june 2010 (6)
 
Pedir lo mismo de diferentes maneras
Pedir lo mismo de diferentes manerasPedir lo mismo de diferentes maneras
Pedir lo mismo de diferentes maneras
 
Cure for cost and schedule growth
Cure for cost and schedule growthCure for cost and schedule growth
Cure for cost and schedule growth
 
Architectured Centered Design
Architectured Centered DesignArchitectured Centered Design
Architectured Centered Design
 
Universidades
Universidades Universidades
Universidades
 
Establishing the performance measurement baseline (pmi fort worth)(v4)
Establishing the performance measurement baseline (pmi fort worth)(v4)Establishing the performance measurement baseline (pmi fort worth)(v4)
Establishing the performance measurement baseline (pmi fort worth)(v4)
 
Inversion of Control
Inversion of ControlInversion of Control
Inversion of Control
 
Immutable Principles Of Project Management (V7 Final Cmu)
Immutable Principles Of Project Management (V7 Final Cmu)Immutable Principles Of Project Management (V7 Final Cmu)
Immutable Principles Of Project Management (V7 Final Cmu)
 
Systems Engineering in One Picture
Systems Engineering in One PictureSystems Engineering in One Picture
Systems Engineering in One Picture
 
Risk management processes
Risk management processesRisk management processes
Risk management processes
 
iOS 7 Human Interface Guidelines
iOS 7 Human Interface GuidelinesiOS 7 Human Interface Guidelines
iOS 7 Human Interface Guidelines
 
PM Chapter on Agile IT Project Management Methods
PM Chapter on Agile IT Project Management MethodsPM Chapter on Agile IT Project Management Methods
PM Chapter on Agile IT Project Management Methods
 
UX for Lean Startups Sep 15
UX for Lean Startups Sep 15UX for Lean Startups Sep 15
UX for Lean Startups Sep 15
 
4 PM Anti-Patterns
4 PM Anti-Patterns4 PM Anti-Patterns
4 PM Anti-Patterns
 
search.com or Google: Why we suck at naming products and companies (PCA13)
search.com or Google: Why we suck at naming products and companies (PCA13)search.com or Google: Why we suck at naming products and companies (PCA13)
search.com or Google: Why we suck at naming products and companies (PCA13)
 
Agile Girl Scouts Presentation
Agile Girl Scouts PresentationAgile Girl Scouts Presentation
Agile Girl Scouts Presentation
 
Increasing The Probability Of Success For Your Project
Increasing The Probability Of Success For Your ProjectIncreasing The Probability Of Success For Your Project
Increasing The Probability Of Success For Your Project
 
Moe mop tpm connections
Moe mop tpm connectionsMoe mop tpm connections
Moe mop tpm connections
 
Improving DOE Project Performance Using the DOD Integrated Master Plan
Improving DOE Project Performance Using the DOD Integrated Master PlanImproving DOE Project Performance Using the DOD Integrated Master Plan
Improving DOE Project Performance Using the DOD Integrated Master Plan
 

Ähnlich wie A possible cure 2014 may9

Cure for cost and schedule growth (submitted)
Cure for cost and schedule growth (submitted)Cure for cost and schedule growth (submitted)
Cure for cost and schedule growth (submitted)Glen Alleman
 
Cure for Cost and Schedule Growth
Cure for Cost and Schedule GrowthCure for Cost and Schedule Growth
Cure for Cost and Schedule GrowthGlen Alleman
 
Hembree.mike
Hembree.mikeHembree.mike
Hembree.mikeNASAPMC
 
Coast estimating and assessment guide
Coast estimating and assessment guideCoast estimating and assessment guide
Coast estimating and assessment guideBudi Santony
 
Portfolio management and the ppbe process at the department of energy white p...
Portfolio management and the ppbe process at the department of energy white p...Portfolio management and the ppbe process at the department of energy white p...
Portfolio management and the ppbe process at the department of energy white p...p6academy
 
C:\documents and settings\ckampschulte\desktop\in sync risk range analysis
C:\documents and settings\ckampschulte\desktop\in sync risk range analysisC:\documents and settings\ckampschulte\desktop\in sync risk range analysis
C:\documents and settings\ckampschulte\desktop\in sync risk range analysisInSync Conference
 
Zimmerman.marybeth
Zimmerman.marybethZimmerman.marybeth
Zimmerman.marybethNASAPMC
 
Federal Project Management - Line of Sight
Federal Project Management - Line of SightFederal Project Management - Line of Sight
Federal Project Management - Line of SightLine of Sight
 
1st APR-URP Presentation
1st APR-URP Presentation 1st APR-URP Presentation
1st APR-URP Presentation ShamsulArefin75
 
Calculations1. Net present valueEstimated investment of the la
Calculations1. Net present valueEstimated investment of the laCalculations1. Net present valueEstimated investment of the la
Calculations1. Net present valueEstimated investment of the laTawnaDelatorrejs
 
Capital and infrastructure solution brochure Single FINAL
Capital and infrastructure solution brochure Single FINALCapital and infrastructure solution brochure Single FINAL
Capital and infrastructure solution brochure Single FINALChristopher Matthews
 
NASA 2015 Summary Brief
NASA 2015 Summary BriefNASA 2015 Summary Brief
NASA 2015 Summary BriefKeenan Brugh
 
Towardsatransformedoyostate minofepb-120820151350-phpapp02
Towardsatransformedoyostate minofepb-120820151350-phpapp02Towardsatransformedoyostate minofepb-120820151350-phpapp02
Towardsatransformedoyostate minofepb-120820151350-phpapp02Oyo State Government Nigeria
 
Dwayne Davis resume June 2016
Dwayne Davis resume June 2016Dwayne Davis resume June 2016
Dwayne Davis resume June 2016Dwayne Davis
 
The Programme Certainty Paradox
The Programme Certainty ParadoxThe Programme Certainty Paradox
The Programme Certainty ParadoxHKA
 
Pipeline_Management_2014_06.pptx
Pipeline_Management_2014_06.pptxPipeline_Management_2014_06.pptx
Pipeline_Management_2014_06.pptxwikig2
 
Portfolio management in the government sector....the ONS journey by Nicky Blo...
Portfolio management in the government sector....the ONS journey by Nicky Blo...Portfolio management in the government sector....the ONS journey by Nicky Blo...
Portfolio management in the government sector....the ONS journey by Nicky Blo...Association for Project Management
 

Ähnlich wie A possible cure 2014 may9 (20)

Cure for cost and schedule growth (submitted)
Cure for cost and schedule growth (submitted)Cure for cost and schedule growth (submitted)
Cure for cost and schedule growth (submitted)
 
Cure for Cost and Schedule Growth
Cure for Cost and Schedule GrowthCure for Cost and Schedule Growth
Cure for Cost and Schedule Growth
 
Hembree.mike
Hembree.mikeHembree.mike
Hembree.mike
 
Coast estimating and assessment guide
Coast estimating and assessment guideCoast estimating and assessment guide
Coast estimating and assessment guide
 
Shinn
ShinnShinn
Shinn
 
Portfolio management and the ppbe process at the department of energy white p...
Portfolio management and the ppbe process at the department of energy white p...Portfolio management and the ppbe process at the department of energy white p...
Portfolio management and the ppbe process at the department of energy white p...
 
C:\documents and settings\ckampschulte\desktop\in sync risk range analysis
C:\documents and settings\ckampschulte\desktop\in sync risk range analysisC:\documents and settings\ckampschulte\desktop\in sync risk range analysis
C:\documents and settings\ckampschulte\desktop\in sync risk range analysis
 
Zimmerman.marybeth
Zimmerman.marybethZimmerman.marybeth
Zimmerman.marybeth
 
Federal Project Management - Line of Sight
Federal Project Management - Line of SightFederal Project Management - Line of Sight
Federal Project Management - Line of Sight
 
1st APR-URP Presentation
1st APR-URP Presentation 1st APR-URP Presentation
1st APR-URP Presentation
 
Calculations1. Net present valueEstimated investment of the la
Calculations1. Net present valueEstimated investment of the laCalculations1. Net present valueEstimated investment of the la
Calculations1. Net present valueEstimated investment of the la
 
Capital and infrastructure solution brochure Single FINAL
Capital and infrastructure solution brochure Single FINALCapital and infrastructure solution brochure Single FINAL
Capital and infrastructure solution brochure Single FINAL
 
NASA 2015 Summary Brief
NASA 2015 Summary BriefNASA 2015 Summary Brief
NASA 2015 Summary Brief
 
Towardsatransformedoyostate minofepb-120820151350-phpapp02
Towardsatransformedoyostate minofepb-120820151350-phpapp02Towardsatransformedoyostate minofepb-120820151350-phpapp02
Towardsatransformedoyostate minofepb-120820151350-phpapp02
 
Dwayne Davis resume June 2016
Dwayne Davis resume June 2016Dwayne Davis resume June 2016
Dwayne Davis resume June 2016
 
CMFA 12.11.15
CMFA 12.11.15CMFA 12.11.15
CMFA 12.11.15
 
The Programme Certainty Paradox
The Programme Certainty ParadoxThe Programme Certainty Paradox
The Programme Certainty Paradox
 
Session 6 gdas pmp study group presentation
Session 6   gdas pmp study group presentationSession 6   gdas pmp study group presentation
Session 6 gdas pmp study group presentation
 
Pipeline_Management_2014_06.pptx
Pipeline_Management_2014_06.pptxPipeline_Management_2014_06.pptx
Pipeline_Management_2014_06.pptx
 
Portfolio management in the government sector....the ONS journey by Nicky Blo...
Portfolio management in the government sector....the ONS journey by Nicky Blo...Portfolio management in the government sector....the ONS journey by Nicky Blo...
Portfolio management in the government sector....the ONS journey by Nicky Blo...
 

Mehr von Glen Alleman

Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planningGlen Alleman
 
A Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSA Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSGlen Alleman
 
Increasing the Probability of Project Success
Increasing the Probability of Project SuccessIncreasing the Probability of Project Success
Increasing the Probability of Project SuccessGlen Alleman
 
Process Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMProcess Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMGlen Alleman
 
Practices of risk management
Practices of risk managementPractices of risk management
Practices of risk managementGlen Alleman
 
Principles of Risk Management
Principles of Risk ManagementPrinciples of Risk Management
Principles of Risk ManagementGlen Alleman
 
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Glen Alleman
 
From Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringFrom Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringGlen Alleman
 
NAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideNAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideGlen Alleman
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineGlen Alleman
 
Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Glen Alleman
 
IMP / IMS Step by Step
IMP / IMS Step by StepIMP / IMS Step by Step
IMP / IMS Step by StepGlen Alleman
 
DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)Glen Alleman
 
Making the impossible possible
Making the impossible possibleMaking the impossible possible
Making the impossible possibleGlen Alleman
 
Heliotropic Abundance
Heliotropic AbundanceHeliotropic Abundance
Heliotropic AbundanceGlen Alleman
 
Capabilities based planning
Capabilities based planningCapabilities based planning
Capabilities based planningGlen Alleman
 
Process Flow and Narrative for Agile
Process Flow and Narrative for AgileProcess Flow and Narrative for Agile
Process Flow and Narrative for AgileGlen Alleman
 
Building the Performance Measurement Baseline
Building the Performance Measurement BaselineBuilding the Performance Measurement Baseline
Building the Performance Measurement BaselineGlen Alleman
 
Program Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaProgram Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaGlen Alleman
 
Policy and Procedure Rollout
Policy and Procedure RolloutPolicy and Procedure Rollout
Policy and Procedure RolloutGlen Alleman
 

Mehr von Glen Alleman (20)

Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planning
 
A Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSA Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMS
 
Increasing the Probability of Project Success
Increasing the Probability of Project SuccessIncreasing the Probability of Project Success
Increasing the Probability of Project Success
 
Process Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMProcess Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPM
 
Practices of risk management
Practices of risk managementPractices of risk management
Practices of risk management
 
Principles of Risk Management
Principles of Risk ManagementPrinciples of Risk Management
Principles of Risk Management
 
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
 
From Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringFrom Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems Engineering
 
NAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideNAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guide
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement Baseline
 
Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Integrated master plan methodology (v2)
Integrated master plan methodology (v2)
 
IMP / IMS Step by Step
IMP / IMS Step by StepIMP / IMS Step by Step
IMP / IMS Step by Step
 
DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)
 
Making the impossible possible
Making the impossible possibleMaking the impossible possible
Making the impossible possible
 
Heliotropic Abundance
Heliotropic AbundanceHeliotropic Abundance
Heliotropic Abundance
 
Capabilities based planning
Capabilities based planningCapabilities based planning
Capabilities based planning
 
Process Flow and Narrative for Agile
Process Flow and Narrative for AgileProcess Flow and Narrative for Agile
Process Flow and Narrative for Agile
 
Building the Performance Measurement Baseline
Building the Performance Measurement BaselineBuilding the Performance Measurement Baseline
Building the Performance Measurement Baseline
 
Program Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaProgram Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six Sigma
 
Policy and Procedure Rollout
Policy and Procedure RolloutPolicy and Procedure Rollout
Policy and Procedure Rollout
 

Kürzlich hochgeladen

Breaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountBreaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountPuma Security, LLC
 
[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdfhans926745
 
Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Allon Mureinik
 
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure serviceWhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure servicePooja Nehwal
 
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking MenDelhi Call girls
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking MenDelhi Call girls
 
Slack Application Development 101 Slides
Slack Application Development 101 SlidesSlack Application Development 101 Slides
Slack Application Development 101 Slidespraypatel2
 
08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking MenDelhi Call girls
 
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...Neo4j
 
Salesforce Community Group Quito, Salesforce 101
Salesforce Community Group Quito, Salesforce 101Salesforce Community Group Quito, Salesforce 101
Salesforce Community Group Quito, Salesforce 101Paola De la Torre
 
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024BookNet Canada
 
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Miguel Araújo
 
Handwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsHandwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsMaria Levchenko
 
Data Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonData Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonAnna Loughnan Colquhoun
 
Unblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen FramesUnblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen FramesSinan KOZAK
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)Gabriella Davis
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerThousandEyes
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsEnterprise Knowledge
 
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | DelhiFULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhisoniya singh
 
A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024Results
 

Kürzlich hochgeladen (20)

Breaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountBreaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path Mount
 
[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf
 
Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)
 
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure serviceWhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
 
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men
 
Slack Application Development 101 Slides
Slack Application Development 101 SlidesSlack Application Development 101 Slides
Slack Application Development 101 Slides
 
08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men
 
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
 
Salesforce Community Group Quito, Salesforce 101
Salesforce Community Group Quito, Salesforce 101Salesforce Community Group Quito, Salesforce 101
Salesforce Community Group Quito, Salesforce 101
 
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
 
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
 
Handwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsHandwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed texts
 
Data Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonData Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt Robison
 
Unblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen FramesUnblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen Frames
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected Worker
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI Solutions
 
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | DelhiFULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
 
A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024
 

A possible cure 2014 may9

  • 1. + We have lots data. Let’s use it create more credible estimates to help tame the growth beast A Cure for Unanticipated Cost and Schedule Growth Thomas J. Coonce Glen B. Alleman
  • 2. +Why Are We Here? n In spite the estimating community’s efforts to provide credible estimates, government programs still seem to deliver less than promised, cost more than planned, and take longer than needed. n Lots of reasons. Some well established; some hypothesized n When estimates are consistently biased low n Decisions of choice are distorted n Cost growth causes more growth as programs are stretched out to fund portfolios with fixed budgets n Taxpayers become more cynical and negative about government n The estimating community’s credibility is seriously questioned 2
  • 3. +Why are We Here? (Concluded) n This presentation will n Summarize many of the reasons documented and hypothesized why programs deliver less, cost more and are late; n Provide a broad brush of what the community has done to improve the imbalance; n Assert that we can not solve all the root causes, but we can effectively use historical experience (reference class forecasting) to provide more credible estimates for future systems; and n Propose and discuss a number of changes needed in estimating, acquisition, and the contracting communities to restore balance and credibility and go a long way to tame the growth beast 3
  • 4. +Cost and Schedule Growth 4 Average Median NASA in the 90s 36% 26% 78% NASA in the 70s 43% 26% 75% NASA in the 80s (GAO) 83% 60% 89% DoD RDT&E 45% 27% 76% Cost/Budget Growth2 Study Percent of Projects Which Experienced Growth “In 1982, an unnamed witness at a House Armed Service Committee stated, ‘Enough material has been written on the subject of cost growth during the last ten years to fill a Minuteman silo’. Unfortunately, cost growth is still with us. In a decade since that testimony enough additional information on cost growth has been written to fill a second minuteman silo”1 1. Cost Growth in DoD Major Programs:A Historical Perspective,Col.Harry Calcutt, April 1993, http://www.dtic.mil/dtic/tr/fulltext/u2/a276950.pdf 2. Hamaker and Schaffer, NASA, 2004
  • 5. +Cost & Schedule Growth Summary at NASA - Combined 30 Mission Growth Average Over & Above Reserves3 42% 29% 21% 0% 10% 20% 30% 40% 50% 60% From Phase B Start From PDR From CDR DevelopmentCostGrowth 29% 23% 19% 0% 10% 20% 30% 40% 50% 60% From Phase B Start From PDR From CDR PhaseB/C/DScheduleGrowth 5 3 Internal NASA Study,2009 Development Cost Growth* Schedule Growth
  • 6. +Cost and Schedule Growth (Continued) n Many researcherhave tried to understandthe root causes for growth.Here is a list from one study4 n Requirements related n Poor initial requirement definition n Poor performance/cost trade-off during development n Changes in quantity requirements n Estimating related n Errors due to limitation is estimating procedures n Failure to understand and account for technical risks n Poor inflation estimates n Top down pressure to reduce estimates n Lack of valid independent cost estimates 6 4 Calcutt, April 1993
  • 7. +Cost and Schedule Growth (Continued) n Program Management related n Lack of program management expertise n Mismanagement/human error n Over optimism n Schedule concurrency n Program stretch outs to keep production lines open n Contracting related n Lack of competition n Contractor buy-in n Use of wrong type of contract n Inconsistent contract management/admin procedures n Too much contractor oversight n Waste n Excess profits n Contractors overstaffed n Contractor indirect costs unreasonable n Taking too long to resolve undefinitized contracts 7 Root causes from Col. Calcutt’s study (continued)
  • 8. +Cost and Schedule Growth (Continued) n Budget related n Funding instabilities caused by trying to fund too many programs n Funding instabilities caused by congressional decisions n Inefficient production rates due to stretching out programs n Failure to fund for management reserves n Failure to fund programs at most likely cost 8 Root causes from Col. Calcutt’s study (Concluded)
  • 9. +Cost and Schedule Growth (Concluded) n Inception related n Unrealistic performance expectations n Unrealistic baseline estimates for cost or schedule n Immature technologies or excessive manufacturing or integration risk n Execution related n Unanticipated design, engineering mfg or technology integration issues n Changes in procurement quantities n Inadequate program funding or funding instability n Poor performance by government or contractor personnel 9 5 Report to Congress on Performance Assessment and Root Cause Analyses,Office of the Under Secretary of Defense for Acquisition,Technology and Logistics,March 2014, p. 7, http://www.acq.osd.mil/parca/docs/2014- parca-report-to-congress.pdf Root causes cited by the Office of Program Assessment and Root Cause Analysis (PARCA)5
  • 10. +A Broad Brush Of What The Estimating Community Has Done to Tame the Growth Beast n Instituted independent estimating organizations at various levels with DoD and civilian agencies n Developed cost estimates using analogous historical data (reference class forecasting) n Required a Cost Analysis Requirements Description (CARD) to ensure cost estimates are based on the agreed requirements n Developed a variety of professional training and certification programs, e.g., Certified Cost Estimator/Analyst (CCEA), Certified Parametric Practitioner (CPP), AACE certifications, and PMI n Augmented independent estimating teams with program management and scheduling personnel e.g., NASA and DoE n Continued to collect historical cost and technical data to improve parametric cost estimates n Began to develop estimates using planned top-level schedules and historical head counts (recognition that time and people are big cost drivers) n Another form of reference class forecasting 10
  • 11. +A Broad Brush Of What The Estimating Community Has Done (Concluded) n Begun to set cost and schedule targets based on the historical variability of cost and schedules n The Weapon System Acquisition Reform Act (WSARA) of 2009 required DoD programs to be budgeted at the 80% cost confidence level 6 n NASA requires programs to budgeted with a 70% probability of meeting both cost and schedule targets 11 6 According to the FY 2011 Annual Report on Cost Assessment Activities by the Director,Cost Assessment and Program Evaluation (CAPE),the WSARA requirement for confidence levels was eliminated in the National Defense Authorization Act for Fiscal Year 2011, Public Law 111-383. “Today,the requirement is to select a confidence level such that it provides a high degree of confidence that the program can be completed without the need for significant adjustment to program budgets”. http://www.pae.osd.mil/files/Reports/CA_AR_20120508.pdf
  • 12. +So What? n The estimatingcommunity is the best position to understand,document and communicate the myriad reasons for cost and schedule growth. n We are the masters at collecting the data and evidence! n But it is not our role to make the changes.We can only advise n We can,however,improve our estimates by usingour historical data more effectively n We can persuade government leadershipto require contractors to do the same 12
  • 13. +A Few Observations n Our estimates are typically formed around a product-oriented structure.We have great historical databases upon which to develop credible estimates. n We typically estimate individual WBS elements by developing Cost Estimating Relationships (CERs) like this: 13 $ Cost Driver (Weight) Cost = a + bXc Input variable WBS Cost Estimate Historical data point Cost estimating relationship Standard percent error boundsTECHNICAL RISK COMBINED COST MODELING AND TECHNICAL RISK COST MODELING UNCERTAINTY CER
  • 14. +A Few Observations (Continued) n But we have difficulty persuading government leadership to increase their estimates that reflect the historical variances because they can’t relate it to their implementation plans that look like this: 14
  • 15. + Uncertainty in the PM’s Plan Must be Driven by Historical Data 15 U/C Project End U/C U/C U/C U/C U/C TD $ TD $ = Segment Duration X Burn Rate U/C U/C U/C TI $U/C TI $U/C TI $U/C TI $U/C TI $U/C Task Duration Burn Rate Burn Rate Uncertainty Duration Uncertainty Risk Probability of Occurrence TI$ Uncertainty TI = Time-Independent Cost: Does not change as schedule slips. Example: Materials TD = Time-Dependent Cost: Increases as schedule slips. Example: LOE; ‘marching Army
  • 16. +A Few Observations (Concluded) 16 PDF & CDF Integrated Master Schedule-Based 71.23% 0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1 1.1 0 0.05 0.1 0.15 0.2 0.25 0 5 10 15 20 CumulativeProbability ProbabilityDensity PDF & CDF CER-Based = 71.23% 0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1 1.1 0 0.05 0.1 0.15 0.2 0.25 0 5 10 15 20 CumulativeProbability ProbabilityDensity Historical Cost Data by WBS Historical Activity Durations and Associated Costs
  • 17. +Rationale for Budgeting at the 70 percent Joint Confidence Level n Schedule drives a large component of cost n We want programs to deliver on or before promised and at or below the budgeted cost. This is the problem we are trying to solve. n We should have a better than 50/50 change of meeting planned targets. (Don’t we owe this to the taxpayers?) n There is no general consensus within the estimating community about the right joint confidence level upon which to set budgets n Little empirical data (Too soon to tell if NASA’s experiment is working) n More research needed n Until then, pick a “reasonably” high number and see if it works. 17
  • 18. +A Proposed Solution - Step 1: Program Office Creates a Request for Information (RFI) 18 1.0 Develop Draft Integrated Master Plan (IMP) Program Capabilities (Requirements) 2.0 Develop Summary Level Integrated Master Schedule (IMS) 3.0 Develop Summary- Level Baseline Cost-Loaded IMS Historical Activity Durations and Associated Costs 5.0 Create Joint Probability Distribution 4.0 Create Risk Register (RR) Risk Register 6.0 Decide on Target Cost and Completion Date 7.0 Prepare RFI Package with IMS and RR RFI to Industry
  • 19. +A Proposed Solution - Step 2: Contractors Review and Submit Revised Plan n Is the top-level plan logical given the technical challenges and capabilities required? If no, n What other activities should be included or dropped? n What changes in logic are required? n Are activities durations “consistent” (within family) of your experience? n Are the costs “consistent” (within family) of your experience? n Is the PMO’s perspective on risks realistic? If not, n Which risks are overstated? n Which risks are understated? n Which risks were missed? And what is your assessment of probabilities and consequences for those risks? n Revise and submit contractor-modified high level cost-level plan, updated Risk Register, and Probability Assessment 19
  • 20. +A Proposed Solution - Step 3: Program Office Uses the Responses to RFIs to Improve an RFP 20 8.0 Assess Responsesto RFI Updated Risk Register(RR) Updated Program Capabilities (Requirements) 10.0 Re-create Joint Probability Distribution Updated Cost-LoadedIMS 11.0 Decide on Targeted Cost and Completion Date Multiple responses 12.0 Create Request for Proposal (RFP) 9.0 Update IMP/ IMS, Risk Register, and/or Modify Rqmts
  • 21. +A Proposed Solution - Step 4: Bidders Prepare Responses to Proposals 21 13.0 Create Contractor Version of IMP 14.0 Develop Summary Level IMS 15.0 Develop Detailed Cost or Resource- Loaded IMS ContractorHistorical Activity Durationsand Associated Costs 17.0 Create Joint Probability Distribution 16.0 Create Updated Risk Register (RR) ContractorRisk Register(RR) 18.0 Specify Joint Confidence Level of Targeted Cost and Completion Date 19.0 Complete Preparation of Proposal Response to RFP Updated Program Capabilities (Requirements)
  • 22. +A Proposed Solution - Step 5: Program Office Evaluates and Oversees the Contractors n Government program offices should: n Award contracts based on the “credibility” of the historical uncertainty data used and discrete risks for the joint cost and schedules proposed n Hold requirements stable after contract awards n Require contractors to submit updated Risk Registers, and probability statements associated with Best Case,Worse Case and Mostly Likely Estimates at Complete in Format 5 of the Integrated Program Management Reports (IPMRs) every six months (What gets measured, gets managed) 22
  • 23. +A Proposed Solution - Step 6: Contractors Execute to the Plan n Winningcontractors should: n Set Program Management Baselines (PMBs) n Using more detailed cost or resource-loaded Integrated Master Schedules (IMSes) n With at least a 50% joint probability of meeting cost and schedule targets n Set up objective measures of progress at IBRs that are directly connected back to user-desired capabilities through appropriate Technical Performance Measures (TPMs) n Record progress (Budgeted Cost of Work Performed) using the pre-defined set of progress criteria n Maintain risk registers and use them to provide probability statements of cost and completion dates every six months 23
  • 24. +More on Why n We don’t really need to understand why we have cost and schedule growth; we just need to estimate future programs using all the historical experience n We need to speak the same language that the government PM speaks. Independent product-oriented estimates based on historical data are “right” if the probabilities are set right, but government program managers have difficulty relating these estimates to their plans or potential bidders’ plans n Activity-based estimates that are grounded with historical data help government PMs to revise their plans based on well communicated reasons for the cost and schedule variations, i.e., what happened to similar programs in the past n Initial government probabilistic estimates that are based on a program’s activity-based plan that recognize the “natural variation” of cost and schedule performance of historical projects, should tame the growth beast if the joint probabilities are greater than 70 percent n Estimates that are activity-based aid government PMs and contractors to manage the contracts during execution. The language is the same and the focus is on their plan (the PMB) and the risks! 24
  • 25. +Some How Challenges n Estimating community needs to start collecting common development activity duration data and associated costs n Some of this may already be available from the schedule data contained in the Earned Value Management Central Repository (EVM-CR) n Government program office have to step up their game n Need to think through the development of the system capabilities and document those in an IMP n Need to create a notional summary-level cost-loaded activity-based plan n Need to get help on the historical variation of activity durations and associated costs n Need to coordinate with the acquisition community on the RFI and follow-on RFP process n Integrate Program Management Report (IPMR) Data Item Description (DID) would need to be updated n Require the Integrated Master Plan (IMP) as part of the RFP submission n Add submission of the contractor’s Risk Register and instrumented native probability models every six months n Others? 25