SlideShare ist ein Scribd-Unternehmen logo
1 von 21
Every construction project has its
own set of circumstances that can
involve timing, legal obligations,
ownership configuration, cost
limitations, financing objectives,
owner in-house resources, and
more.
A contract is a voluntary
arrangement between
two or more parties that
is enforceable at law as a
binding legal agreement.
• The construction of
engineering works by direct
employment of an
organization independent of
any contractor eliminates
certain difficulties often no
less serious.
Direct Employment
• The responsibility for the
construction and for the cost of
the work is placed on an
organization which the owner or
governmental body must create
for this purpose, and the results
will depend largely on the
efficiency of the organization.
• The oldest and most
common method of
letting work under
contract is by receiving
bids with fixed prices.
These may be either Lump
Sums or Unit Prices.
Fixed Price
• Contracting on a basis of
either a Lump Sum or of Unit
Prices is subject to the
objection that the interests
of the contractor and of the
owner become at once
antagonistic.
• The contractor agrees to build a
project with a specific scope for
a fixed price. A lump-sum
contract is suitable if the scope
and schedule of the project are
sufficiently defined to allow the
contractor to fully estimate
project costs.
Lump Sum
• This kind of contract is based
on estimated quantities of
items included in the project
and their unit prices. The final
price of the project is
dependent on the quantities
needed to carry out the work.
Unit Price
• In general, this contract is only
suitable for projects in which the
scope is reasonably well
established, and the different
types of items (but not their
numbers) can be accurately
identified in the contract
documents.
• For certain types of construction
involving new technology or
extremely pressing needs, the
owner is sometimes forced to
assume all risks of cost overruns.
The contractor will receive the
actual direct job cost plus a fixed
percentage, and have little incentive
to reduce job cost..
Cost Plus Fixed Percentage Contract
• Furthermore, if there are pressing
needs to complete the project,
overtime payments to workers are
common and will further increase the
job cost. Unless there are compelling
reasons, such as the urgency in the
construction of military installations,
the owner should not use this type of
contract
• For this type of contract, the
contractor agrees to a penalty if the
actual cost exceeds the estimated
job cost, or a reward if the actual
cost is below the estimated job cost.
In return for taking the risk on its
own estimate, the contractor is
allowed a variable percentage of the
direct job-cost for its fee.
Cost PlusVariable Percentage
Contract
• Furthermore, the project duration is
usually specified and the contractor
must abide by the deadline for
completion. This type of contract
allocates considerable risk for cost
overruns to the owner, but also
provides incentives to contractors to
reduce costs as much as possible.
• This is another form of contract
which specifies a penalty or reward
to a contractor, depending on
whether the actual cost is greater
than or less than the contractor’s
estimated direct job cost.
Target Estimate Contract
• Usually, the percentages of savings
or overrun to be shared by the
owner and the contractor are
predetermined and the project
duration is specified in the contract.
Bonuses or penalties may be
stipulated for different project
completion dates.
• When the project scope is well
defined, an owner may choose to ask
the contractor to take all the risks,
both in terms of actual project cost
and project time. Any work change
orders from the owner must be
extremely minor if at all, since
performance specifications are
provided to the owner at the outset
of construction.
Guaranteed Maximum Cost Contract
• The owner and the contractor
agree to a project cost
guaranteed by the contractor as
maximum. There may be or may
not be additional provisions to
share any savings if any in the
contract.
-END-

Weitere ähnliche Inhalte

Was ist angesagt?

Conditions Of Contract
Conditions Of ContractConditions Of Contract
Conditions Of Contract
guestdb5e498
 
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
Praveen Premkumar
 
CONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPESCONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPES
Pundlik Rathod
 

Was ist angesagt? (20)

Types of contract
Types of contractTypes of contract
Types of contract
 
Contracts
ContractsContracts
Contracts
 
Conditions Of Contract
Conditions Of ContractConditions Of Contract
Conditions Of Contract
 
Contracts
ContractsContracts
Contracts
 
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
 
Construction Law Presentation
Construction Law PresentationConstruction Law Presentation
Construction Law Presentation
 
CONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPESCONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPES
 
Construction contracts
Construction contractsConstruction contracts
Construction contracts
 
Procurement system
Procurement systemProcurement system
Procurement system
 
Types of Contract in Construction Management
Types of Contract in Construction ManagementTypes of Contract in Construction Management
Types of Contract in Construction Management
 
types of contracts
 types of contracts types of contracts
types of contracts
 
Measure And Pay Contract
Measure And Pay Contract Measure And Pay Contract
Measure And Pay Contract
 
Contract & Tender Management
Contract & Tender ManagementContract & Tender Management
Contract & Tender Management
 
Contracts & tenders
Contracts & tendersContracts & tenders
Contracts & tenders
 
civil engineering-Contracts
civil engineering-Contractscivil engineering-Contracts
civil engineering-Contracts
 
Types of contracts
Types of contracts   Types of contracts
Types of contracts
 
What is construction management & its Benefits?
What is construction management & its Benefits?What is construction management & its Benefits?
What is construction management & its Benefits?
 
Pre qualification stages and tender selection
Pre qualification stages and tender selectionPre qualification stages and tender selection
Pre qualification stages and tender selection
 
Variations in works contracts
Variations in works contractsVariations in works contracts
Variations in works contracts
 
Bim arabia red fidic
Bim arabia red fidicBim arabia red fidic
Bim arabia red fidic
 

Andere mochten auch

Building contracts and the JCT
Building contracts and the JCTBuilding contracts and the JCT
Building contracts and the JCT
Julian Swindell
 
Certificate-FIDIC-Yellow book A.Todorov
Certificate-FIDIC-Yellow book A.TodorovCertificate-FIDIC-Yellow book A.Todorov
Certificate-FIDIC-Yellow book A.Todorov
Apostol Todorov
 
Contracts PowerPoint Presentation
Contracts PowerPoint PresentationContracts PowerPoint Presentation
Contracts PowerPoint Presentation
mbachnak
 
Introduction to Contract Law
Introduction to Contract LawIntroduction to Contract Law
Introduction to Contract Law
theacademist
 

Andere mochten auch (20)

fidic , jct and nec contracts
fidic , jct and nec contractsfidic , jct and nec contracts
fidic , jct and nec contracts
 
Building contracts and the JCT
Building contracts and the JCTBuilding contracts and the JCT
Building contracts and the JCT
 
Certificate-FIDIC-Yellow book A.Todorov
Certificate-FIDIC-Yellow book A.TodorovCertificate-FIDIC-Yellow book A.Todorov
Certificate-FIDIC-Yellow book A.Todorov
 
Types of contract
Types of contractTypes of contract
Types of contract
 
Sources of Long term finance
Sources of Long term financeSources of Long term finance
Sources of Long term finance
 
Fidic
FidicFidic
Fidic
 
Construction claims, disputes and project closure
Construction claims, disputes and project closureConstruction claims, disputes and project closure
Construction claims, disputes and project closure
 
Sources of finance
Sources of financeSources of finance
Sources of finance
 
Sources Of Long Term Finance
Sources Of Long Term FinanceSources Of Long Term Finance
Sources Of Long Term Finance
 
Fidic yellow vs silver
Fidic yellow vs silverFidic yellow vs silver
Fidic yellow vs silver
 
Essential elements of a valid contract
Essential elements of a valid contractEssential elements of a valid contract
Essential elements of a valid contract
 
ACH 216 Lecture 04c (Project Award)
ACH 216 Lecture 04c (Project Award)ACH 216 Lecture 04c (Project Award)
ACH 216 Lecture 04c (Project Award)
 
Contracts PowerPoint Presentation
Contracts PowerPoint PresentationContracts PowerPoint Presentation
Contracts PowerPoint Presentation
 
Types of conract
Types of conractTypes of conract
Types of conract
 
Introduction to Contract Law
Introduction to Contract LawIntroduction to Contract Law
Introduction to Contract Law
 
Sources of finance
Sources of financeSources of finance
Sources of finance
 
Types of contract
Types of contractTypes of contract
Types of contract
 
ESSENTIAL ELEMENTS OF A VALID CONTRACT
ESSENTIAL ELEMENTS OF A VALID CONTRACTESSENTIAL ELEMENTS OF A VALID CONTRACT
ESSENTIAL ELEMENTS OF A VALID CONTRACT
 
Sources of finance
Sources of financeSources of finance
Sources of finance
 
Study notes contract law
Study notes   contract lawStudy notes   contract law
Study notes contract law
 

Ähnlich wie Types and forms of contracts

Chapter-2 Construction Contract. Subject code:3160614ptx
Chapter-2 Construction Contract. Subject code:3160614ptxChapter-2 Construction Contract. Subject code:3160614ptx
Chapter-2 Construction Contract. Subject code:3160614ptx
sulevrunda
 
Unit V - Contracts.pptx
Unit V - Contracts.pptxUnit V - Contracts.pptx
Unit V - Contracts.pptx
jairam131
 
Types of contract in Project management
Types of contract in Project managementTypes of contract in Project management
Types of contract in Project management
Ali Heydari
 

Ähnlich wie Types and forms of contracts (20)

Negotiated contracts
Negotiated contractsNegotiated contracts
Negotiated contracts
 
5 Popular Types of Construction Contracts
5 Popular Types of Construction Contracts5 Popular Types of Construction Contracts
5 Popular Types of Construction Contracts
 
Chapter-2 Construction Contract. Subject code:3160614ptx
Chapter-2 Construction Contract. Subject code:3160614ptxChapter-2 Construction Contract. Subject code:3160614ptx
Chapter-2 Construction Contract. Subject code:3160614ptx
 
Contracts and their types
Contracts and their typesContracts and their types
Contracts and their types
 
Final types of contracts- different types of contracts
Final types of contracts- different types of contractsFinal types of contracts- different types of contracts
Final types of contracts- different types of contracts
 
Construction Contract in Malaysia
Construction Contract in MalaysiaConstruction Contract in Malaysia
Construction Contract in Malaysia
 
types-170309142854.pptx
types-170309142854.pptxtypes-170309142854.pptx
types-170309142854.pptx
 
Unit V - Contracts.pptx
Unit V - Contracts.pptxUnit V - Contracts.pptx
Unit V - Contracts.pptx
 
Unit-1_Contracts
Unit-1_ContractsUnit-1_Contracts
Unit-1_Contracts
 
TOPIC2.pdf
TOPIC2.pdfTOPIC2.pdf
TOPIC2.pdf
 
Contract Management - Contracts Types and Payment Structure
Contract Management - Contracts Types and Payment StructureContract Management - Contracts Types and Payment Structure
Contract Management - Contracts Types and Payment Structure
 
Contract- Vijay Suryawanshi
Contract- Vijay SuryawanshiContract- Vijay Suryawanshi
Contract- Vijay Suryawanshi
 
Project procuremenet contract in ethiopia
Project procuremenet contract in ethiopiaProject procuremenet contract in ethiopia
Project procuremenet contract in ethiopia
 
Contracts and-tenders
Contracts and-tendersContracts and-tenders
Contracts and-tenders
 
Ias 11
Ias 11Ias 11
Ias 11
 
contracts-unit 3.ppt
contracts-unit 3.pptcontracts-unit 3.ppt
contracts-unit 3.ppt
 
Construction Contract Issues for Owners of Residences
Construction Contract Issues for Owners of ResidencesConstruction Contract Issues for Owners of Residences
Construction Contract Issues for Owners of Residences
 
Types of contract in Project management
Types of contract in Project managementTypes of contract in Project management
Types of contract in Project management
 
Lecture 3.pptx
Lecture 3.pptxLecture 3.pptx
Lecture 3.pptx
 
CE-CONTRACTS-REPORT.pdf
CE-CONTRACTS-REPORT.pdfCE-CONTRACTS-REPORT.pdf
CE-CONTRACTS-REPORT.pdf
 

Kürzlich hochgeladen

Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills KuwaitKuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
jaanualu31
 

Kürzlich hochgeladen (20)

Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdf
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS Lambda
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equation
 
Learn the concepts of Thermodynamics on Magic Marks
Learn the concepts of Thermodynamics on Magic MarksLearn the concepts of Thermodynamics on Magic Marks
Learn the concepts of Thermodynamics on Magic Marks
 
kiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal loadkiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal load
 
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
 
Air Compressor reciprocating single stage
Air Compressor reciprocating single stageAir Compressor reciprocating single stage
Air Compressor reciprocating single stage
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna Municipality
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills KuwaitKuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.ppt
 
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptxA CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptx
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 
Rums floating Omkareshwar FSPV IM_16112021.pdf
Rums floating Omkareshwar FSPV IM_16112021.pdfRums floating Omkareshwar FSPV IM_16112021.pdf
Rums floating Omkareshwar FSPV IM_16112021.pdf
 
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
 

Types and forms of contracts

  • 1.
  • 2. Every construction project has its own set of circumstances that can involve timing, legal obligations, ownership configuration, cost limitations, financing objectives, owner in-house resources, and more.
  • 3.
  • 4. A contract is a voluntary arrangement between two or more parties that is enforceable at law as a binding legal agreement.
  • 5. • The construction of engineering works by direct employment of an organization independent of any contractor eliminates certain difficulties often no less serious. Direct Employment
  • 6. • The responsibility for the construction and for the cost of the work is placed on an organization which the owner or governmental body must create for this purpose, and the results will depend largely on the efficiency of the organization.
  • 7. • The oldest and most common method of letting work under contract is by receiving bids with fixed prices. These may be either Lump Sums or Unit Prices. Fixed Price
  • 8. • Contracting on a basis of either a Lump Sum or of Unit Prices is subject to the objection that the interests of the contractor and of the owner become at once antagonistic.
  • 9. • The contractor agrees to build a project with a specific scope for a fixed price. A lump-sum contract is suitable if the scope and schedule of the project are sufficiently defined to allow the contractor to fully estimate project costs. Lump Sum
  • 10. • This kind of contract is based on estimated quantities of items included in the project and their unit prices. The final price of the project is dependent on the quantities needed to carry out the work. Unit Price
  • 11. • In general, this contract is only suitable for projects in which the scope is reasonably well established, and the different types of items (but not their numbers) can be accurately identified in the contract documents.
  • 12. • For certain types of construction involving new technology or extremely pressing needs, the owner is sometimes forced to assume all risks of cost overruns. The contractor will receive the actual direct job cost plus a fixed percentage, and have little incentive to reduce job cost.. Cost Plus Fixed Percentage Contract
  • 13. • Furthermore, if there are pressing needs to complete the project, overtime payments to workers are common and will further increase the job cost. Unless there are compelling reasons, such as the urgency in the construction of military installations, the owner should not use this type of contract
  • 14. • For this type of contract, the contractor agrees to a penalty if the actual cost exceeds the estimated job cost, or a reward if the actual cost is below the estimated job cost. In return for taking the risk on its own estimate, the contractor is allowed a variable percentage of the direct job-cost for its fee. Cost PlusVariable Percentage Contract
  • 15. • Furthermore, the project duration is usually specified and the contractor must abide by the deadline for completion. This type of contract allocates considerable risk for cost overruns to the owner, but also provides incentives to contractors to reduce costs as much as possible.
  • 16. • This is another form of contract which specifies a penalty or reward to a contractor, depending on whether the actual cost is greater than or less than the contractor’s estimated direct job cost. Target Estimate Contract
  • 17. • Usually, the percentages of savings or overrun to be shared by the owner and the contractor are predetermined and the project duration is specified in the contract. Bonuses or penalties may be stipulated for different project completion dates.
  • 18. • When the project scope is well defined, an owner may choose to ask the contractor to take all the risks, both in terms of actual project cost and project time. Any work change orders from the owner must be extremely minor if at all, since performance specifications are provided to the owner at the outset of construction. Guaranteed Maximum Cost Contract
  • 19. • The owner and the contractor agree to a project cost guaranteed by the contractor as maximum. There may be or may not be additional provisions to share any savings if any in the contract.
  • 20.
  • 21. -END-