Electrical power engineering, EEP course




          Lightning protection of an office building




Esta obra está bajo una licencia de Creative Commons.




                                                        Participants:




                                                        Instructor name:




Date:        Lightning protection of an office building                    page:1
Index    Name                                                                  Page

1.       Specification                                                         3

1.1.     A risk assessment for the outer lightning of the office building
         is to be done to verify the protection level                          3

1.2      Work out a description of how the outer lightning protection
         should be created. Include a system for ”catching”,
         conducting and earthing. Additional information is found in
         appendix 1.                                                           4

1.2.1.   The Air-termination system                                            6

1.2.2.   Down-conducting system                                                11

1.2.3.   The earth-termination system                                          14

1.3      For the inner lightning protection there should be selected
         equipment for protection of the high voltage side of the supply
         transformer.                                                          17


1.4      Over-voltage protection for the electrical installations
         in the building.                                                      18


2.       Conclusion / Evaluation                                               23

3.       Literature                                                            23

4.       Appendix                                                              23




Date:    Lightning protection of an office building                   page:2
Specifications
      Our group had read and understand the normes before look for the specifique case.
After, with new knowledge to prepare a proposal for lightning protection of an office building.



1. 1 A risk assessment for the outer lightning of the office building
is to be done to verify the protection level

N g is the average annual ground flash density, in lightning flashes per square kilometer,
during the year, in the region where the building is located.
               1, 25
N g  0,04  Td  0,04  55,9  2,236 ;
 N d - average of annual frequency of direct lightning flashes to a structure can be accessed
from.
 AE - is the equivalent collection area of structure ( m 2 )
 N g  N g  AE  10 6  2,236  11700  10 6  0,0261612 ;

Risk management contains:
NC  A  B  C ;
A  A1  A2  A3  A4 ;
B  B1  B2  B3  B4 ;
C  C1  C 2  C 3 .
 A1  0,5 The construction of a building is made from concrete units, where the armament iron
is not connected between the units;
 A2  0,5 roof construction is made from ferro concrete with segment parts;
 A3  0,5 because the roof is covered with roofing felt;
 A4  0,5 on the roof there is only cooling and ventilation system which do not have
electronical material;
 B1  0,5 Building usage comparing by persons inside is between low and medium, because it
is an office building;
 B2  0,2 flammable material inside;
 B3  0,2 valuable materials inside;
 B4  10 automatical fire protection;
C1  1 no hazard to the nature – no trees or forest near, there is no material to poison the water
also;
C 2  0,1 serious breakdown if the power is off. It is an office building, so probably a lot of
people will be using computers there, and in case of power loss all the work will be stopped;
C3  1 there is no other consequences to evaluate;

N C  A  B  C  0,5  0,5  0,5  0,5  0,5  0,2  0,2  10  1  0,1  1  0,0125 ;


Date:           Lightning protection of an office building                                page:3
N d  N C so we need protection:

        NC
E 1        0,952219 ;
        Nd
while E is equal between 0,98 and 0,95 we need at least second level protection.

1.2 Work out a description of how the outer lightning protection
should be created. Include a system for ”catching”, conducting
and earthing. Additional information is found in appendix 1.
In the following exercise we will create a outer lightning protection system, based on the
given data from the appendix 1 and with the protection level 2.

The Outer protection system consists of 3 parts.
    The first part is the Air-termination system, which is intended to intercept the lightning
      flashes.(catching)
    The second part is the Down-conductor which is intended to conduct lightning current
      from the Air-termination system to the Earth-termination system. ( conducting)
    The third part is the Earth-termination system which is intended to conduct and
      disperse lightning current to the earth. (earthing)

For the construction and planning of an effective and secured outer lightning protection
system, we need information about the size and buildup of our building. So at first we made a
construction plan of the building. This is necessary to see how we can get a high security (
according to protection level 2) without using to much protection devices and money as
required.




Date:        Lightning protection of an office building                  page:4
Fig.1: top view of the building with size information ( the plan based on the picture in the appendix, it is not
                                          exact but for our use adequate)

The height of the building is 20m.




Date:           Lightning protection of an office building                                page:5
1.2.1. the Air-termination system
For planning an Air-termination system, different methods are possible. The method we will
mainly use for our system is the meshed size method, because we have a plan surface on our
roof. We will also use the protective angle method, for example to protect the air conditioning
system on the roof with small rods. The rolling sphere method we will also use.

     Table.1: positioning of air termination system for the protection level 2 (taken from IEC 1024-1)
     Protection      radius [m]       h=20m         h=30m           h=45m          h=60m          Mesh
       level          Sphere            a°             a°              a°             a°        width [m]
         2               30             35             25               *              *           10

For our building it is enough, if we put the air-termination system on the roof, because the
radius of the sphere is bigger than the height of our building (r=30m>h=20m).




                                         Fig.2: rolling sphere model

Figure 2 demonstrate very good the mode of operation of the sphere method, the header of the
lightning is in the center of the sphere, and the lightning will strike into points which have a
contact with the sphere. Now we move the sphere over the building and look for all the
contact points at the building, these points should be protected very well. Also we see
wherever we put the sphere, the side of our building is always protected by the roof. By
complex buildings it is sometimes usual to build a small model, and move the sphere over the
model, but our building has a flat roof so this is not necessary.

For the Air-termination system we can use these elements.
- rods;
- stretched wires;
- meshed conductors.

Also it is possible to use metal pipes, metal plates or other conducting material which is
normally installed on the roof. Our building has a flat roof and on the most flat roofs it is
common that metal plates are installed on the corners of the roof. So we will use these metal
plates for the Air-termination system, because this is a cheap and effective way. If metal plates
Date:         Lightning protection of an office building                              page:6
are not installed or if they are not confirm to the requirements, it is possible to replace them
with conducive lines in the corners of the building. According to the material and thickness of
the metal plates we can use them for the air-termination system (table 2). The thickness of the
metal plates is important to prevent a melt threw in case of a lightning strike. Also it is
important that these metal plates have no conductive connection into the building, because
then it is possible that they conduct the lightning power into the building. And that can cause a
lot of damage (see Fig.5.). The metal plates on the roof should have a conductive connection
between each other, so you have to take care of the expansion and shrinking of the metal
plates according to the temperature. The best way is to connect them with flexible conductors.

Table 2: minimum thickness of metal plates or pipes (taken from IEC 1024-1)

                         Protection level            Material       Thickness [mm]
                                                       Fe                  4
                                1,2,3&4                Cu                  5
                                                       Al                  7



Table 3: minimum dimension of LPS materials (taken from IEC 1024-1)

                    Protection            Material    Airtermin-   Downcond-    Earthermin-
                       level                         ation [mm²]   uctor[mm²]   ation[mm²]
                                            Cu           35           16             50
                      1,2,3,4               Al           70           25              -
                                            Fe           50           50             80

We will protect the flat roof with a system of meshed conductors and the constructional
systems on the roof we will protect with small rods. This is the most effective way for our
building. The mesh width is according to protection level 2, 10 meters (table 1). It is important
to say that this is just a protection for the building, so it is not allowed for people to enter the
roof in case of a thunderstorm. If we want to protect people on the roof, we need to install big
rods. But for our building this is not necessary.




Date:          Lightning protection of an office building                            page:7
Fig.3: meshed conductor system for a flat roof (taken from www.dehn.de)



In Fig.3 is shown a meshed conductor system, similar to the system we want to install. The
meshed conductors are connected with the metal plates by a flexible connector (conductive),
this is because of mechanical moving, shrinking and expansion of the conductors and the
plates. There are also conductor holders installed (in distance of about 1m), to fix the
conductors and to prevent damage from the roof (melt threw the roofing felt). So we install a
meshed conductor system with the maximum mesh width of 10m and with a thickness of the
conductors according to table 3. The Air-termination system has to be connected with the
down-conducting system.
In the next step we want to protect constructional systems on our roof (e.g. cooling and
ventilation system).




                          Fig.5: example of connecting the ventilation system




Date:        Lightning protection of an office building                          page:8
In Fig.5 we have a very bad example of connecting a ventilation system. The ventilation
system is connected with the Air-termination circuit through a contact with the meshed
conductors. So if a lightning strikes into our protection system on the roof, current will run
through the conductive parts of the ventilation system into the building (The yellow arrows
symbolize the current flow in case of a lightning strike). Inside the building it is possible that
electronic components are placed close to the ventilation system, which can be destroyed by
an induced voltage. Also the ventilation system is not protected to a direct lightning strike.




                                Fig.6.example of protecting the ventilation system

Fig.6. is a much better example how to protect a constructional system. The size of the rods
can be calculated with the protective angle method. The Air-termination system is not
connected to the ventilation system (pipe), no lightning power will run into the building. It is
not necessary to protect these small pipe with two rods, one rod is enough if it is high enough
to protect the hole pipe.

Table 4: shows the relationship between size of the rod and the angle alpha for the protection level 2
         (This cutout of a table is taken from www.dehn.de)




It is important that no component of the air termination system is close to electronic or other
sensitive installations (automatic fire detection, alarm system and sprinkler system), because
threw the components of the lightning protection system runs a very high current in case of a
lightning strike. So these sensitive installations can be damaged because of sparks, heat or
induced voltage. The protective rods have to be placed in a distance to the installations we
have to protect, by strong wind influences the rods can move with the wind, and therefore it is
important to stabilize the rods with isolated distance pieces.
Date:           Lightning protection of an office building                               page:9
Final plan of the Air-termination system:




                            Fig. 7: Air-termination system for the bulding




Date:        Lightning protection of an office building                      page:10
1.2.2. Down-conducting system
The Down-conducting system conducts the lightning power from the Air-terminations system
to the Earth-termination system. To prevent damage it is important that the Down-conducting
system consists of:

    -   A satisfactory number of parallel down-conducting current paths (as larger the number
        of the current paths as smaller is the current threw each path)
    -   The length of the current-paths should be as short as possible (vertical and no ties,
        loops)

In the Appendix it is written that an electrical continuity of the armament iron should be
established. If this is possible we can use the armament iron construction for our Down-
conducting system. If we use the armament iron, we have to take care about different points:

    -   the thickness of the metal-constructions should be not smaller then 0,5mm
    -   the different parts of the metal constructions have to be connected in the vertical
        direction
    -   a ring conducting system around the building is not necessary
    -   in case of a lightning strike current is running threw the armament iron

If we connect the different parts of the armament iron, we have to take care of a secured
connection. The distance between the connectors should be not bigger then 15m, table 5 (if an
electrical continuity of the iron is not possible). If we are not aware about this we get a high
current in some current paths, electrical installation can be damaged. But in our case we have
continuity connection, so that the current in each path should not become to high.

 Table 5: Average distance between down-conductors according to the protection level (taken from IEC 1024-1)

                                       Protection        Average
                                         level         distance [m]
                                           1                10
                                           2                15
                                           3                20
                                           4                25

Calculation of the safety distance d:

d=ki*(kc / km)*l

ki= depends on the selected protection level of LPS
kc= depends on dimensional configuration
km= depends on separation material
l= length along the down-conductor from the point where the proximity is to be considered to
the nearest equipotential bonding point

Table 6: Values of coefficient km & ki (taken from IEC 1024-1)

                                Protection level       ki           km
                                       2             0,075         Air 1
                                                                  Solid 0,5

Date:          Lightning protection of an office building                           page:11
In case of a lightning strike, current will run threw the armament iron. Inside the building are
also electrical devices and other conductive parts installed, which can be damaged by sparks
and induced voltage. Therefore it is important to take care about the safety distance; the
installations should not get closer then the distance d to the Down-conducting parts. If this is
not possible we have to make a special isolation for these components.




                 Fig.8: connection between down-conducting and air-termination system


Fig.8 shows a schematic picture of our roof construction, several down conductors are
connected between the metal plates on the roof and the armament iron. By this connection we
have to take care about loops, loops should be avoided. If this is not possible the proximity
distance should be larger then the safety distance d, else we can get unintentional sparks. Roof
break-threw are not necessary for our building, because this is just necessary for areas bigger
then 40x40m. Block B is longer then 40m but it is also smaller then 40m, so the current will
not have a to long way to earth. The down-conductors from the roof to the armament iron
should be placed in a distance not bigger then 15m and close to corners of the building. If the
down conducting system threw the armament iron is not confirm to the requirements, we have
to install down conductors on the surface of the building.




Date:        Lightning protection of an office building                         page:12
Fig.8c: Down-conducting system threw armament iron (taken from 61024-2)

1=horizontal air-termination conductors
2=test joint
3=equipotential bar of the internal LPS




                                Fig.9: places of down-conductor connections

 The connection of the Down-conducting system to the earth-termination system is already
installed (“the foundation electrode placed in the border foundation of the building and
connected to the armament iron” Appendix). We should install test joints on the connections
Date:          Lightning protection of an office building                        page:13
between the down-conducting to the earth-termination system. These joints facilitate the
determination by measurement that an adequate number of connections to the earth-
termination system still exist, it is possible to check the continuous connection between air-
termination system and earth. Also it is possible to measure the earth resistance.

If the down conducting system threw the armament iron is not confirm to the requirements or
is not possible, we have to install down conductors on the surface of the building. The biggest
distance between the down-conductors we can take from table 5, is 15m. So we will place the
down-conductors on the same position like we place the down-conductors to connect with
armament iron (Fig 9., red spots). The minimum thickness of the down-conductors is shown in
table 3.




                     Fig.10: down-conducting system on the surface of the building

In Fig.10 is shown a down-conducting system on the surface of the building. The lightning
current is running outside the building to the earth-termination system, but you also have to
take care of the safety distance d. We will place distance holders each meter. Also you have to
prevent that the down-conductors get to close to windows and doors. By down-conductors on
the surface it is sometimes necessary to install ring-conductors around the building, and
connect them to the down-conductors. This installation helps to distribute the lightning current
on each path, also it realize a better equipotential between the down-conductors. On buildings
of the height of 20m and less this is not necessary; the foundation electrode is enough to put
the down-conductors on the same potential. The down-conductors have to be connected with
the earth-termination system threw test joints.

1.2.3. The earth-termination system
The task of an earth-termination system is:

           Conducting of the lightning current into the earth without causing dangerous over
            voltages
           Equipotential bonding between the down-conductors
           Potential control in the vicinity of conductive building walls
           Interception of the lightning current when propagation on earth’s surface


Date:         Lightning protection of an office building                         page:14
The installed foundation electrode meets all these requirements.
Earthing and equalization connections:
The earth electrode for installations (lightning protection, protection against indirect contact, EMC,etc.) is
established as a foundation electrode placed in the border foundation of the building and connected to the
armament iron. The electrodes are “connected” to the room with the main electrical panel. To assure and to
make the protection systems effective, electrical continuity of the armament iron should be established.
Taken from Appendix1

The earth-termination system already exists and it is already connected to the down-conductor
(armament iron). So our work is to check, if everything is confirm to the requirements. The
necessary length of the earth-electrode is shown in Fig.11, p is the specific resistance for a
cubic meter of earth.




          Fig.11: minimum length l1 of earth electrodes according to the protection level (IEC 1024-1)



In the building a foundation electrode is installed, the foundation electrode is a type B
arrangement of an earth electrode. For this type the radius of the area enclosed by earth
electrode shall be not less than the length l1.

                                                     r ≥ l1;

For the protection level 2 the length l1 is a constant of 5 meters, which is not depending on the
specific resistance. So it is not necessary to measure the specific resistance of the earth. To
calculate the radius we can use the formula:

                                                  r= √(A/π);

A= area enclosed by earth electrode.
The electrode is close to the border of the building, so we will calculate approximately the
area for the bloc A.

Date:           Lightning protection of an office building                              page:15
A= 13,44m*25,2m*2+13,44m*(25,2m-12,8m)= 844m²  r=16,39m ;

The length / radius of the earth electrode is long enough in our building. The minimum
thickness of the earth-electrode is shown in table 3. Especially in the earth termination system
we have to take care about the corrosion of the material, because the material is exposed to
water, soil drying and freezing.

Table7: LPS materials and condition of use (taken from IEC 1024-1)




Table 7 shows the condition of use of the material, e.g. for our earth-termination system
stainless steel is a good solution. The electrode is surrounded by concrete so it is protected
very well against water and corrosion. Also copper we can use because in the appendix is
written, “There may not be any material combinations that can cause galvanic corrosion in the
construction.” If it is possible a galvanized steel strip, should be installed in the foundation
and be taken upwards with a connection to the down-conducting test joints, else it is possible
to perform the connection to the down conducting system on the brick wall. A foundation
electrode is normally a good solution for an earth-termination system, because the concrete
has a low specific resistance (150-500Ωm) and protects the metal from corrosion.




Date:          Lightning protection of an office building                 page:16
1.3 For the inner lightning protection there should be selected
equipment for protection of the high voltage side of the supply
transformer.
Electrical installation:
The building is connected to the public grid at voltage level 10.5 kV. The grid voltage is
transformed down by a 10.5/0.42 kV Dyn 5 transformer. Rated power is 800 kVA. The distance
from the transformer to the main electrical panel located in the basement of the building is 12 m.
Taken from appendix




                                 Fig.1.3.1: electrical connection of the building

Used Cable information:

Cable type Nkt-cable 3x95mm² PEX-Cu 12kV

Length          =10000m
Vcable          =200*106 m/s
C´              =0,34µF/km
X´              =0,097Ω/km

Calculation of wave impedance and wave time constant:

F               =50Hz
L               =X / (2*π*f)= 3,08*10-4 Vs / A*km
Z               =√ (L / C)= √ ((3,08*10-4 Vs / A*km) / (0,34μF/km)) = 30,13Ω
Ψ               = length / Vcable = 10000m / (200*106 m/s) = 50µs

Surge arrester information: more information on appendix 2

Type            = Esra 12
Ur              = 12 kV
                   guaranteed protective

                                          characteristics
Uc              =Max. conti. operating voltage= (UmaxL*1,05) / √3 =7,27kV                            <9,6kV
UmaxL           =max. system voltage= 12kV
Ur0             =voltage marking at component= Uc / 0,8= 9,09kV
Ue              =temporary over voltage= ke*Uc= √3 * 7,27kV=12,6kV                                   <14,2kV
Date:           Lightning protection of an office building                              page:17
ke            =earth fault factor;
kt            = 3;

UL=(kt*Ur*ke*√2) / √3 = 44,55kV;


Calculation of the consuming energy:

Urest = switching surge voltage taken from the surge arrester information = 28,6kV;

W=( (UL- Urest) / Z) * Urest*2* Ψ= 1509,25 VAs= 0,419Wh= 4,19*10-4kWh;

Transforming kWhJ: 4,19*10-4kWh * 3,6 · 106 = 1509,25J;

W / UmaxL= 0,125 kJ / kV;

The surge arrester ESRA 12 can withstand a Energy of 2,1 kJ / kV Line discharge, our
calculated value is much lower. So we can use the ESRA 12 for the protection of the
transformer on the high voltage side.



1.4 Work out over-voltage protection for the electrical
installations in the building.

In the following exercise:
     Describe the necessary initiative to achieve potential equalization (same voltage).
     The proposal should include the main and group electrical panels (switch boards) and
        possible instrument/device protection.
     The proposal should be based on appendix , which only contains information about
        block B of the building.
     Hence the proposal for the inner lightning protection should be limited to block B.

equipotential bonding:

We need equipotential bonding to set all the metal installations to one voltage level. So the
metal installation inside the building should be connected to an equipotential bonding. If there
is no equipotential, dangerous touch voltage can occur for example between PE-conductor of
the electrical equipment and metal pipes of the radiator. Threw the PE-conductor can run
voltage which can damage electrical devices.
In the building two types of equipotential bonding can be installed, the main equipotential
bonding (EB) and additional equipotential bondings. To the main equipotential bonding
should be connected:

           foundation earthing electrodes;
           central heating system;
           metal drain pipe;
           internal gas pipe;
           earthing conuctor for antennas;

Date:         Lightning protection of an office building                  page:18
   PEN-conductor (main electrical panel) / electrical equipment;
           Conductive parts of the construction of the building.

The main equipotential bonding should be placed in the basement, near to the earth-level and
not to far from the main electrical panel (service entrance box).




    Fig.12:Internal lightning protection with a common entry of all supply lines (taken from www.dehn.de)

Fig.12 shows how we can connect the different metal installations in our building, the
connection to the power supply is protected with a surge arrester. The equipotential cables can
be marked like the PE-conductor, yellow and green. The thickness of these cables should be
not smaller then the half of the main equipotential cable ( normally the PE-conductor of the
power supply), but at least not smaller then 6mm². The equipotential bounding is connected to
the foundation electrode.




Date:         Lightning protection of an office building                            page:19
Fig.13: equipotential bonding




   Protection of electrical devices:




Date:       Lightning protection of an office building            page:20
Fig.14:single-line diagram for the power supply system of the building (taken from appendix)

There are three different classes of over voltage protection. We will use all three classes of
protection.

-              Class B Lightning Current Arrester
        Single-pole arrester in the specification class B for the protection
        of electrical consumer installations and equipment in case of
        over voltage or direct lightning strikes.  will protect the input side of the main
        electrical panel (F1)

-             Class C Surge Arrester
        Single-pole arrester in the specification class C for the protection
        of electrical consumer installations and equipment against
        over voltage caused by distant lightning strikes or switching
        operations.  will protect the input side of the group electrical panel (F2)

-             Class D Surge Arrester for Device Protection
        Double-pole arrester in the specification class D for the protection
        of electrical installations against over voltage caused by distant
        lightning strikes or switching operations.  will protect the electrical equipment
        (F3-F28)

The voltage and the current of the lightning will be reduced from the class B arrester to the
class C arrester, from the class C arrester to the class D arrester and at the output side of the
class D arrester the voltage and the current surge should cause no damage in the electronic
devices.

Protection plan of electric devices:




                            Fig.15: protection of the electric devices in the building

Cable length 2 should be not longer then 5 meters, so we can put it also inside the group
panels on each floor. Cable length 1 should be not longer then 15m, but in our building the
Date:         Lightning protection of an office building                                 page:21
cable length is between 30 and 50m. So it will be a good idea to install also a limiter link
between the main electrical panel and the group panel.

-              Limitor Link Decoupling Inductor
        Supplies the inductance for energy-control coordination between
        the lightning current arrester and the surge arrester when the
        impedance of the lines connecting these components does not
        provide sufficient damping.

Principle of a surge arrester :




                              Fig.16: principle of a surge arrester (switch)
A – Isolator
B – Metal
C – Transfer connectors
D – Break down plates
E – Choke absorber

A ignition tension appears in point number 1 and the spark rise until the 4th point were it’s
break and spread out in two different ways. At the 6th point the small plates transform the half
of spark into less powerful sparks. The small sparks that goes back, to the side of the stroke,
the remove power to the stroke, and the another sparks go to the earth using PE connection.




Date:          Lightning protection of an office building                      page:22
Example for used equipment:




                         Fig.17: example of equipment (taken from www.abb.de)




2. Conclusion / Evaluation

While we were doing this work, we got a lot of knowledge about Lightning protection.
However this kind installation and the tools is very specific and so this kind of installations
only can be done by a specialize company. After this work we are able to understand the
principles of lightning protection and work in the area.


3. Literature:


   1.   IEC 61024-1 (-1), (-2) Protection of structures against lightning.
   2.   www.abb.de.
   3.   IEC 611312-1 Protection against lightning electromagnetic impulse.
   4.   Dehn+Sohne „Lighting Protection Guide“ www.dehn.de


4. Appendix:

1. PROB-P, appendix for report no.2.
2. Surge arrester.



Date:         Lightning protection of an office building                        page:23

Weitere ähnliche Inhalte

Was ist angesagt?

Lightning protection to structures and power systems
Lightning protection to structures and power systemsLightning protection to structures and power systems
Lightning protection to structures and power systemsSuryanarayana Danturti
 
Lightning Protection
Lightning ProtectionLightning Protection
Lightning Protectionsuresh5
 
Lightning, Surge Protection & Earthing of Electrical & Electronic Systems in ...
Lightning, Surge Protection & Earthing of Electrical & Electronic Systems in ...Lightning, Surge Protection & Earthing of Electrical & Electronic Systems in ...
Lightning, Surge Protection & Earthing of Electrical & Electronic Systems in ...Living Online
 
Lightning and surge protection devices
Lightning and surge protection devicesLightning and surge protection devices
Lightning and surge protection devicesArturoOsborn
 
Zibens aizsardzība ar CVM metodi, labā prakse un risinājumi. Risinājumi sarež...
Zibens aizsardzība ar CVM metodi, labā prakse un risinājumi. Risinājumi sarež...Zibens aizsardzība ar CVM metodi, labā prakse un risinājumi. Risinājumi sarež...
Zibens aizsardzība ar CVM metodi, labā prakse un risinājumi. Risinājumi sarež...Elektrumlv
 
SurgeSafe Lightning Protection system -Presentation
SurgeSafe Lightning Protection system -PresentationSurgeSafe Lightning Protection system -Presentation
SurgeSafe Lightning Protection system -PresentationBadami Shantha Kumar
 
Lightning protection and ground solutions for wireless networks
Lightning protection and ground solutions for wireless networksLightning protection and ground solutions for wireless networks
Lightning protection and ground solutions for wireless networksComms Connect
 
Erico Eritech Lightning Protection - IEC62305 Earthing Design Guide
Erico Eritech Lightning Protection - IEC62305 Earthing Design GuideErico Eritech Lightning Protection - IEC62305 Earthing Design Guide
Erico Eritech Lightning Protection - IEC62305 Earthing Design GuideThorne & Derrick International
 
Wind Farm Earthing, Lightning & Overvoltage Protection - Wind Turbines Earthi...
Wind Farm Earthing, Lightning & Overvoltage Protection - Wind Turbines Earthi...Wind Farm Earthing, Lightning & Overvoltage Protection - Wind Turbines Earthi...
Wind Farm Earthing, Lightning & Overvoltage Protection - Wind Turbines Earthi...Thorne & Derrick International
 
Lightning protection of windmill
Lightning protection of windmill Lightning protection of windmill
Lightning protection of windmill AKHIL G
 
Earthing System in Building services
Earthing System in Building servicesEarthing System in Building services
Earthing System in Building servicesJeelkumar Patel
 
LightningMat by Lightningman
LightningMat by LightningmanLightningMat by Lightningman
LightningMat by LightningmanGrant Kirkby
 
One nation pride defence presentation jmv lps
One nation pride defence presentation jmv lpsOne nation pride defence presentation jmv lps
One nation pride defence presentation jmv lpsMahesh Chandra Manav
 
Ham radio lightning protection August 2009
Ham radio lightning protection August 2009Ham radio lightning protection August 2009
Ham radio lightning protection August 2009Martin Schweiger
 

Was ist angesagt? (18)

Lightning protection to structures and power systems
Lightning protection to structures and power systemsLightning protection to structures and power systems
Lightning protection to structures and power systems
 
Lighting
LightingLighting
Lighting
 
Lightning Protection
Lightning ProtectionLightning Protection
Lightning Protection
 
Seminar on Lightning of building
Seminar on Lightning of buildingSeminar on Lightning of building
Seminar on Lightning of building
 
Lightning Protection
Lightning ProtectionLightning Protection
Lightning Protection
 
Lightning, Surge Protection & Earthing of Electrical & Electronic Systems in ...
Lightning, Surge Protection & Earthing of Electrical & Electronic Systems in ...Lightning, Surge Protection & Earthing of Electrical & Electronic Systems in ...
Lightning, Surge Protection & Earthing of Electrical & Electronic Systems in ...
 
Lightning and surge protection devices
Lightning and surge protection devicesLightning and surge protection devices
Lightning and surge protection devices
 
Zibens aizsardzība ar CVM metodi, labā prakse un risinājumi. Risinājumi sarež...
Zibens aizsardzība ar CVM metodi, labā prakse un risinājumi. Risinājumi sarež...Zibens aizsardzība ar CVM metodi, labā prakse un risinājumi. Risinājumi sarež...
Zibens aizsardzība ar CVM metodi, labā prakse un risinājumi. Risinājumi sarež...
 
SurgeSafe Lightning Protection system -Presentation
SurgeSafe Lightning Protection system -PresentationSurgeSafe Lightning Protection system -Presentation
SurgeSafe Lightning Protection system -Presentation
 
Lightning protection and ground solutions for wireless networks
Lightning protection and ground solutions for wireless networksLightning protection and ground solutions for wireless networks
Lightning protection and ground solutions for wireless networks
 
Erico Eritech Lightning Protection - IEC62305 Earthing Design Guide
Erico Eritech Lightning Protection - IEC62305 Earthing Design GuideErico Eritech Lightning Protection - IEC62305 Earthing Design Guide
Erico Eritech Lightning Protection - IEC62305 Earthing Design Guide
 
Wind Farm Earthing, Lightning & Overvoltage Protection - Wind Turbines Earthi...
Wind Farm Earthing, Lightning & Overvoltage Protection - Wind Turbines Earthi...Wind Farm Earthing, Lightning & Overvoltage Protection - Wind Turbines Earthi...
Wind Farm Earthing, Lightning & Overvoltage Protection - Wind Turbines Earthi...
 
Lightning protection of windmill
Lightning protection of windmill Lightning protection of windmill
Lightning protection of windmill
 
Earthing System in Building services
Earthing System in Building servicesEarthing System in Building services
Earthing System in Building services
 
LightningMat by Lightningman
LightningMat by LightningmanLightningMat by Lightningman
LightningMat by Lightningman
 
Shruthi
ShruthiShruthi
Shruthi
 
One nation pride defence presentation jmv lps
One nation pride defence presentation jmv lpsOne nation pride defence presentation jmv lps
One nation pride defence presentation jmv lps
 
Ham radio lightning protection August 2009
Ham radio lightning protection August 2009Ham radio lightning protection August 2009
Ham radio lightning protection August 2009
 

Ähnlich wie Lighting protection of an office building

Smart india inteligence india presentation by jmv lps
Smart india inteligence india presentation by jmv lpsSmart india inteligence india presentation by jmv lps
Smart india inteligence india presentation by jmv lpsMahesh Chandra Manav
 
ANALISIS PERANCANGAN SISTEM PROTEKSI BANGUNAN THE BELLAGIO RESIDENCE TERHADAP...
ANALISIS PERANCANGAN SISTEM PROTEKSI BANGUNAN THE BELLAGIO RESIDENCE TERHADAP...ANALISIS PERANCANGAN SISTEM PROTEKSI BANGUNAN THE BELLAGIO RESIDENCE TERHADAP...
ANALISIS PERANCANGAN SISTEM PROTEKSI BANGUNAN THE BELLAGIO RESIDENCE TERHADAP...SyamsirAbduh2
 
Development Design of Lightning Protection System in Rig PDSI #38.2/D1000-E
Development Design of Lightning Protection System in Rig PDSI #38.2/D1000-EDevelopment Design of Lightning Protection System in Rig PDSI #38.2/D1000-E
Development Design of Lightning Protection System in Rig PDSI #38.2/D1000-ESyamsirAbduh2
 
Development Design of Lightning Protection System in Rig PDSI #38.2/D1000-E
Development Design of Lightning Protection System in Rig PDSI #38.2/D1000-EDevelopment Design of Lightning Protection System in Rig PDSI #38.2/D1000-E
Development Design of Lightning Protection System in Rig PDSI #38.2/D1000-ESyamsirAbduh2
 
Hybrid battery +solar pv grid tie power project presentation by jmv lps
Hybrid battery +solar pv grid tie power project presentation by jmv lpsHybrid battery +solar pv grid tie power project presentation by jmv lps
Hybrid battery +solar pv grid tie power project presentation by jmv lpsMahesh Chandra Manav
 
Lightnng protection as Per IEC 62305 Presentaton by JMV LPS LTD
Lightnng protection  as Per IEC 62305 Presentaton by JMV LPS LTDLightnng protection  as Per IEC 62305 Presentaton by JMV LPS LTD
Lightnng protection as Per IEC 62305 Presentaton by JMV LPS LTDMahesh Chandra Manav
 
Presentation file For Lightning ( 24 Jan 2020).pptx
Presentation file For Lightning ( 24 Jan 2020).pptxPresentation file For Lightning ( 24 Jan 2020).pptx
Presentation file For Lightning ( 24 Jan 2020).pptxssuser76e138
 
Indian smart airports presentation by jmv lps
Indian smart airports presentation by jmv lpsIndian smart airports presentation by jmv lps
Indian smart airports presentation by jmv lpsMahesh Chandra Manav
 
Lightning and Surge Protection for Potentially Explosive Atmospheres
Lightning and Surge Protection for Potentially Explosive AtmospheresLightning and Surge Protection for Potentially Explosive Atmospheres
Lightning and Surge Protection for Potentially Explosive AtmospheresInstrument Specialties, Inc.
 
Jmv presentation smart process plant (fertilizer)
Jmv  presentation  smart process  plant (fertilizer)Jmv  presentation  smart process  plant (fertilizer)
Jmv presentation smart process plant (fertilizer)Mahesh Chandra Manav
 
Solar power pv presentation by jmv lps ltd (2)
Solar power pv presentation by jmv lps ltd (2)Solar power pv presentation by jmv lps ltd (2)
Solar power pv presentation by jmv lps ltd (2)Mahesh Chandra Manav
 
Jmv presentation smart power transmission projects cea
Jmv  presentation  smart power transmission projects  ceaJmv  presentation  smart power transmission projects  cea
Jmv presentation smart power transmission projects ceaMahesh Chandra Manav
 
A LITERATURE SURVEY ON ELECTROMAGNETIC SHIELDING
A LITERATURE SURVEY ON ELECTROMAGNETIC SHIELDINGA LITERATURE SURVEY ON ELECTROMAGNETIC SHIELDING
A LITERATURE SURVEY ON ELECTROMAGNETIC SHIELDINGIJEEE
 
Road train-tunnel project presentation by jmv lps (1)
Road  train-tunnel project presentation by jmv lps (1)Road  train-tunnel project presentation by jmv lps (1)
Road train-tunnel project presentation by jmv lps (1)Mahesh Chandra Manav
 
Presentation department of space by jmv lps
Presentation department of space by jmv lpsPresentation department of space by jmv lps
Presentation department of space by jmv lpsMahesh Chandra Manav
 
Presentation department of space by jmv lps
Presentation department of space by jmv lpsPresentation department of space by jmv lps
Presentation department of space by jmv lpsMahesh Chandra Manav
 
Presentation fire and safety protection by jmv lps
Presentation  fire and safety protection by jmv lpsPresentation  fire and safety protection by jmv lps
Presentation fire and safety protection by jmv lpsMahesh Chandra Manav
 
Presentation fire and safety protection by jmv lps
Presentation  fire and safety protection by jmv lpsPresentation  fire and safety protection by jmv lps
Presentation fire and safety protection by jmv lpsMahesh Chandra Manav
 
Presentation fire and safety protection by jmv lps
Presentation  fire and safety protection by jmv lpsPresentation  fire and safety protection by jmv lps
Presentation fire and safety protection by jmv lpsMahesh Chandra Manav
 

Ähnlich wie Lighting protection of an office building (20)

Smart india inteligence india presentation by jmv lps
Smart india inteligence india presentation by jmv lpsSmart india inteligence india presentation by jmv lps
Smart india inteligence india presentation by jmv lps
 
ANALISIS PERANCANGAN SISTEM PROTEKSI BANGUNAN THE BELLAGIO RESIDENCE TERHADAP...
ANALISIS PERANCANGAN SISTEM PROTEKSI BANGUNAN THE BELLAGIO RESIDENCE TERHADAP...ANALISIS PERANCANGAN SISTEM PROTEKSI BANGUNAN THE BELLAGIO RESIDENCE TERHADAP...
ANALISIS PERANCANGAN SISTEM PROTEKSI BANGUNAN THE BELLAGIO RESIDENCE TERHADAP...
 
Development Design of Lightning Protection System in Rig PDSI #38.2/D1000-E
Development Design of Lightning Protection System in Rig PDSI #38.2/D1000-EDevelopment Design of Lightning Protection System in Rig PDSI #38.2/D1000-E
Development Design of Lightning Protection System in Rig PDSI #38.2/D1000-E
 
Development Design of Lightning Protection System in Rig PDSI #38.2/D1000-E
Development Design of Lightning Protection System in Rig PDSI #38.2/D1000-EDevelopment Design of Lightning Protection System in Rig PDSI #38.2/D1000-E
Development Design of Lightning Protection System in Rig PDSI #38.2/D1000-E
 
Jmv presentation solar 2017
Jmv  presentation solar 2017Jmv  presentation solar 2017
Jmv presentation solar 2017
 
Hybrid battery +solar pv grid tie power project presentation by jmv lps
Hybrid battery +solar pv grid tie power project presentation by jmv lpsHybrid battery +solar pv grid tie power project presentation by jmv lps
Hybrid battery +solar pv grid tie power project presentation by jmv lps
 
Lightnng protection as Per IEC 62305 Presentaton by JMV LPS LTD
Lightnng protection  as Per IEC 62305 Presentaton by JMV LPS LTDLightnng protection  as Per IEC 62305 Presentaton by JMV LPS LTD
Lightnng protection as Per IEC 62305 Presentaton by JMV LPS LTD
 
Presentation file For Lightning ( 24 Jan 2020).pptx
Presentation file For Lightning ( 24 Jan 2020).pptxPresentation file For Lightning ( 24 Jan 2020).pptx
Presentation file For Lightning ( 24 Jan 2020).pptx
 
Indian smart airports presentation by jmv lps
Indian smart airports presentation by jmv lpsIndian smart airports presentation by jmv lps
Indian smart airports presentation by jmv lps
 
Lightning and Surge Protection for Potentially Explosive Atmospheres
Lightning and Surge Protection for Potentially Explosive AtmospheresLightning and Surge Protection for Potentially Explosive Atmospheres
Lightning and Surge Protection for Potentially Explosive Atmospheres
 
Jmv presentation smart process plant (fertilizer)
Jmv  presentation  smart process  plant (fertilizer)Jmv  presentation  smart process  plant (fertilizer)
Jmv presentation smart process plant (fertilizer)
 
Solar power pv presentation by jmv lps ltd (2)
Solar power pv presentation by jmv lps ltd (2)Solar power pv presentation by jmv lps ltd (2)
Solar power pv presentation by jmv lps ltd (2)
 
Jmv presentation smart power transmission projects cea
Jmv  presentation  smart power transmission projects  ceaJmv  presentation  smart power transmission projects  cea
Jmv presentation smart power transmission projects cea
 
A LITERATURE SURVEY ON ELECTROMAGNETIC SHIELDING
A LITERATURE SURVEY ON ELECTROMAGNETIC SHIELDINGA LITERATURE SURVEY ON ELECTROMAGNETIC SHIELDING
A LITERATURE SURVEY ON ELECTROMAGNETIC SHIELDING
 
Road train-tunnel project presentation by jmv lps (1)
Road  train-tunnel project presentation by jmv lps (1)Road  train-tunnel project presentation by jmv lps (1)
Road train-tunnel project presentation by jmv lps (1)
 
Presentation department of space by jmv lps
Presentation department of space by jmv lpsPresentation department of space by jmv lps
Presentation department of space by jmv lps
 
Presentation department of space by jmv lps
Presentation department of space by jmv lpsPresentation department of space by jmv lps
Presentation department of space by jmv lps
 
Presentation fire and safety protection by jmv lps
Presentation  fire and safety protection by jmv lpsPresentation  fire and safety protection by jmv lps
Presentation fire and safety protection by jmv lps
 
Presentation fire and safety protection by jmv lps
Presentation  fire and safety protection by jmv lpsPresentation  fire and safety protection by jmv lps
Presentation fire and safety protection by jmv lps
 
Presentation fire and safety protection by jmv lps
Presentation  fire and safety protection by jmv lpsPresentation  fire and safety protection by jmv lps
Presentation fire and safety protection by jmv lps
 

Mehr von freelay

Control And Programingof Synchronous Generator
Control And Programingof Synchronous GeneratorControl And Programingof Synchronous Generator
Control And Programingof Synchronous Generatorfreelay
 
Ruido y vibraciones de instalaciones electricas en edificios
Ruido y vibraciones de instalaciones electricas en edificiosRuido y vibraciones de instalaciones electricas en edificios
Ruido y vibraciones de instalaciones electricas en edificiosfreelay
 
Proyecto centros de transformacion
Proyecto centros de transformacionProyecto centros de transformacion
Proyecto centros de transformacionfreelay
 
Low voltage systems
Low voltage systemsLow voltage systems
Low voltage systemsfreelay
 
La transicion energetica y el cambio climatico
La transicion energetica y el cambio climaticoLa transicion energetica y el cambio climatico
La transicion energetica y el cambio climaticofreelay
 
Ensayos en un transformacion trifasico
Ensayos en un transformacion trifasicoEnsayos en un transformacion trifasico
Ensayos en un transformacion trifasicofreelay
 
Diseño de una subestacion de intermperie 132 45 kv
Diseño de una subestacion de intermperie 132 45 kvDiseño de una subestacion de intermperie 132 45 kv
Diseño de una subestacion de intermperie 132 45 kvfreelay
 

Mehr von freelay (7)

Control And Programingof Synchronous Generator
Control And Programingof Synchronous GeneratorControl And Programingof Synchronous Generator
Control And Programingof Synchronous Generator
 
Ruido y vibraciones de instalaciones electricas en edificios
Ruido y vibraciones de instalaciones electricas en edificiosRuido y vibraciones de instalaciones electricas en edificios
Ruido y vibraciones de instalaciones electricas en edificios
 
Proyecto centros de transformacion
Proyecto centros de transformacionProyecto centros de transformacion
Proyecto centros de transformacion
 
Low voltage systems
Low voltage systemsLow voltage systems
Low voltage systems
 
La transicion energetica y el cambio climatico
La transicion energetica y el cambio climaticoLa transicion energetica y el cambio climatico
La transicion energetica y el cambio climatico
 
Ensayos en un transformacion trifasico
Ensayos en un transformacion trifasicoEnsayos en un transformacion trifasico
Ensayos en un transformacion trifasico
 
Diseño de una subestacion de intermperie 132 45 kv
Diseño de una subestacion de intermperie 132 45 kvDiseño de una subestacion de intermperie 132 45 kv
Diseño de una subestacion de intermperie 132 45 kv
 

Kürzlich hochgeladen

Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...christianmathematics
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfJayanti Pande
 
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxBasic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxDenish Jangid
 
Application orientated numerical on hev.ppt
Application orientated numerical on hev.pptApplication orientated numerical on hev.ppt
Application orientated numerical on hev.pptRamjanShidvankar
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdfQucHHunhnh
 
PROCESS RECORDING FORMAT.docx
PROCESS      RECORDING        FORMAT.docxPROCESS      RECORDING        FORMAT.docx
PROCESS RECORDING FORMAT.docxPoojaSen20
 
Making and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdfMaking and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdfChris Hunter
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Celine George
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104misteraugie
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfagholdier
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introductionMaksud Ahmed
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxheathfieldcps1
 
Unit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptxUnit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptxVishalSingh1417
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdfQucHHunhnh
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxVishalSingh1417
 
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhikauryashika82
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAssociation for Project Management
 

Kürzlich hochgeladen (20)

Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdf
 
Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024
 
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxBasic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
 
Application orientated numerical on hev.ppt
Application orientated numerical on hev.pptApplication orientated numerical on hev.ppt
Application orientated numerical on hev.ppt
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdf
 
PROCESS RECORDING FORMAT.docx
PROCESS      RECORDING        FORMAT.docxPROCESS      RECORDING        FORMAT.docx
PROCESS RECORDING FORMAT.docx
 
Making and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdfMaking and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdf
 
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdf
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introduction
 
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
 
Unit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptxUnit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptx
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdf
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptx
 
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across Sectors
 

Lighting protection of an office building

  • 1. Electrical power engineering, EEP course Lightning protection of an office building Esta obra está bajo una licencia de Creative Commons. Participants: Instructor name: Date: Lightning protection of an office building page:1
  • 2. Index Name Page 1. Specification 3 1.1. A risk assessment for the outer lightning of the office building is to be done to verify the protection level 3 1.2 Work out a description of how the outer lightning protection should be created. Include a system for ”catching”, conducting and earthing. Additional information is found in appendix 1. 4 1.2.1. The Air-termination system 6 1.2.2. Down-conducting system 11 1.2.3. The earth-termination system 14 1.3 For the inner lightning protection there should be selected equipment for protection of the high voltage side of the supply transformer. 17 1.4 Over-voltage protection for the electrical installations in the building. 18 2. Conclusion / Evaluation 23 3. Literature 23 4. Appendix 23 Date: Lightning protection of an office building page:2
  • 3. Specifications Our group had read and understand the normes before look for the specifique case. After, with new knowledge to prepare a proposal for lightning protection of an office building. 1. 1 A risk assessment for the outer lightning of the office building is to be done to verify the protection level N g is the average annual ground flash density, in lightning flashes per square kilometer, during the year, in the region where the building is located. 1, 25 N g  0,04  Td  0,04  55,9  2,236 ; N d - average of annual frequency of direct lightning flashes to a structure can be accessed from. AE - is the equivalent collection area of structure ( m 2 ) N g  N g  AE  10 6  2,236  11700  10 6  0,0261612 ; Risk management contains: NC  A  B  C ; A  A1  A2  A3  A4 ; B  B1  B2  B3  B4 ; C  C1  C 2  C 3 . A1  0,5 The construction of a building is made from concrete units, where the armament iron is not connected between the units; A2  0,5 roof construction is made from ferro concrete with segment parts; A3  0,5 because the roof is covered with roofing felt; A4  0,5 on the roof there is only cooling and ventilation system which do not have electronical material; B1  0,5 Building usage comparing by persons inside is between low and medium, because it is an office building; B2  0,2 flammable material inside; B3  0,2 valuable materials inside; B4  10 automatical fire protection; C1  1 no hazard to the nature – no trees or forest near, there is no material to poison the water also; C 2  0,1 serious breakdown if the power is off. It is an office building, so probably a lot of people will be using computers there, and in case of power loss all the work will be stopped; C3  1 there is no other consequences to evaluate; N C  A  B  C  0,5  0,5  0,5  0,5  0,5  0,2  0,2  10  1  0,1  1  0,0125 ; Date: Lightning protection of an office building page:3
  • 4. N d  N C so we need protection: NC E 1  0,952219 ; Nd while E is equal between 0,98 and 0,95 we need at least second level protection. 1.2 Work out a description of how the outer lightning protection should be created. Include a system for ”catching”, conducting and earthing. Additional information is found in appendix 1. In the following exercise we will create a outer lightning protection system, based on the given data from the appendix 1 and with the protection level 2. The Outer protection system consists of 3 parts.  The first part is the Air-termination system, which is intended to intercept the lightning flashes.(catching)  The second part is the Down-conductor which is intended to conduct lightning current from the Air-termination system to the Earth-termination system. ( conducting)  The third part is the Earth-termination system which is intended to conduct and disperse lightning current to the earth. (earthing) For the construction and planning of an effective and secured outer lightning protection system, we need information about the size and buildup of our building. So at first we made a construction plan of the building. This is necessary to see how we can get a high security ( according to protection level 2) without using to much protection devices and money as required. Date: Lightning protection of an office building page:4
  • 5. Fig.1: top view of the building with size information ( the plan based on the picture in the appendix, it is not exact but for our use adequate) The height of the building is 20m. Date: Lightning protection of an office building page:5
  • 6. 1.2.1. the Air-termination system For planning an Air-termination system, different methods are possible. The method we will mainly use for our system is the meshed size method, because we have a plan surface on our roof. We will also use the protective angle method, for example to protect the air conditioning system on the roof with small rods. The rolling sphere method we will also use. Table.1: positioning of air termination system for the protection level 2 (taken from IEC 1024-1) Protection radius [m] h=20m h=30m h=45m h=60m Mesh level Sphere a° a° a° a° width [m] 2 30 35 25 * * 10 For our building it is enough, if we put the air-termination system on the roof, because the radius of the sphere is bigger than the height of our building (r=30m>h=20m). Fig.2: rolling sphere model Figure 2 demonstrate very good the mode of operation of the sphere method, the header of the lightning is in the center of the sphere, and the lightning will strike into points which have a contact with the sphere. Now we move the sphere over the building and look for all the contact points at the building, these points should be protected very well. Also we see wherever we put the sphere, the side of our building is always protected by the roof. By complex buildings it is sometimes usual to build a small model, and move the sphere over the model, but our building has a flat roof so this is not necessary. For the Air-termination system we can use these elements. - rods; - stretched wires; - meshed conductors. Also it is possible to use metal pipes, metal plates or other conducting material which is normally installed on the roof. Our building has a flat roof and on the most flat roofs it is common that metal plates are installed on the corners of the roof. So we will use these metal plates for the Air-termination system, because this is a cheap and effective way. If metal plates Date: Lightning protection of an office building page:6
  • 7. are not installed or if they are not confirm to the requirements, it is possible to replace them with conducive lines in the corners of the building. According to the material and thickness of the metal plates we can use them for the air-termination system (table 2). The thickness of the metal plates is important to prevent a melt threw in case of a lightning strike. Also it is important that these metal plates have no conductive connection into the building, because then it is possible that they conduct the lightning power into the building. And that can cause a lot of damage (see Fig.5.). The metal plates on the roof should have a conductive connection between each other, so you have to take care of the expansion and shrinking of the metal plates according to the temperature. The best way is to connect them with flexible conductors. Table 2: minimum thickness of metal plates or pipes (taken from IEC 1024-1) Protection level Material Thickness [mm] Fe 4 1,2,3&4 Cu 5 Al 7 Table 3: minimum dimension of LPS materials (taken from IEC 1024-1) Protection Material Airtermin- Downcond- Earthermin- level ation [mm²] uctor[mm²] ation[mm²] Cu 35 16 50 1,2,3,4 Al 70 25 - Fe 50 50 80 We will protect the flat roof with a system of meshed conductors and the constructional systems on the roof we will protect with small rods. This is the most effective way for our building. The mesh width is according to protection level 2, 10 meters (table 1). It is important to say that this is just a protection for the building, so it is not allowed for people to enter the roof in case of a thunderstorm. If we want to protect people on the roof, we need to install big rods. But for our building this is not necessary. Date: Lightning protection of an office building page:7
  • 8. Fig.3: meshed conductor system for a flat roof (taken from www.dehn.de) In Fig.3 is shown a meshed conductor system, similar to the system we want to install. The meshed conductors are connected with the metal plates by a flexible connector (conductive), this is because of mechanical moving, shrinking and expansion of the conductors and the plates. There are also conductor holders installed (in distance of about 1m), to fix the conductors and to prevent damage from the roof (melt threw the roofing felt). So we install a meshed conductor system with the maximum mesh width of 10m and with a thickness of the conductors according to table 3. The Air-termination system has to be connected with the down-conducting system. In the next step we want to protect constructional systems on our roof (e.g. cooling and ventilation system). Fig.5: example of connecting the ventilation system Date: Lightning protection of an office building page:8
  • 9. In Fig.5 we have a very bad example of connecting a ventilation system. The ventilation system is connected with the Air-termination circuit through a contact with the meshed conductors. So if a lightning strikes into our protection system on the roof, current will run through the conductive parts of the ventilation system into the building (The yellow arrows symbolize the current flow in case of a lightning strike). Inside the building it is possible that electronic components are placed close to the ventilation system, which can be destroyed by an induced voltage. Also the ventilation system is not protected to a direct lightning strike. Fig.6.example of protecting the ventilation system Fig.6. is a much better example how to protect a constructional system. The size of the rods can be calculated with the protective angle method. The Air-termination system is not connected to the ventilation system (pipe), no lightning power will run into the building. It is not necessary to protect these small pipe with two rods, one rod is enough if it is high enough to protect the hole pipe. Table 4: shows the relationship between size of the rod and the angle alpha for the protection level 2 (This cutout of a table is taken from www.dehn.de) It is important that no component of the air termination system is close to electronic or other sensitive installations (automatic fire detection, alarm system and sprinkler system), because threw the components of the lightning protection system runs a very high current in case of a lightning strike. So these sensitive installations can be damaged because of sparks, heat or induced voltage. The protective rods have to be placed in a distance to the installations we have to protect, by strong wind influences the rods can move with the wind, and therefore it is important to stabilize the rods with isolated distance pieces. Date: Lightning protection of an office building page:9
  • 10. Final plan of the Air-termination system: Fig. 7: Air-termination system for the bulding Date: Lightning protection of an office building page:10
  • 11. 1.2.2. Down-conducting system The Down-conducting system conducts the lightning power from the Air-terminations system to the Earth-termination system. To prevent damage it is important that the Down-conducting system consists of: - A satisfactory number of parallel down-conducting current paths (as larger the number of the current paths as smaller is the current threw each path) - The length of the current-paths should be as short as possible (vertical and no ties, loops) In the Appendix it is written that an electrical continuity of the armament iron should be established. If this is possible we can use the armament iron construction for our Down- conducting system. If we use the armament iron, we have to take care about different points: - the thickness of the metal-constructions should be not smaller then 0,5mm - the different parts of the metal constructions have to be connected in the vertical direction - a ring conducting system around the building is not necessary - in case of a lightning strike current is running threw the armament iron If we connect the different parts of the armament iron, we have to take care of a secured connection. The distance between the connectors should be not bigger then 15m, table 5 (if an electrical continuity of the iron is not possible). If we are not aware about this we get a high current in some current paths, electrical installation can be damaged. But in our case we have continuity connection, so that the current in each path should not become to high. Table 5: Average distance between down-conductors according to the protection level (taken from IEC 1024-1) Protection Average level distance [m] 1 10 2 15 3 20 4 25 Calculation of the safety distance d: d=ki*(kc / km)*l ki= depends on the selected protection level of LPS kc= depends on dimensional configuration km= depends on separation material l= length along the down-conductor from the point where the proximity is to be considered to the nearest equipotential bonding point Table 6: Values of coefficient km & ki (taken from IEC 1024-1) Protection level ki km 2 0,075 Air 1 Solid 0,5 Date: Lightning protection of an office building page:11
  • 12. In case of a lightning strike, current will run threw the armament iron. Inside the building are also electrical devices and other conductive parts installed, which can be damaged by sparks and induced voltage. Therefore it is important to take care about the safety distance; the installations should not get closer then the distance d to the Down-conducting parts. If this is not possible we have to make a special isolation for these components. Fig.8: connection between down-conducting and air-termination system Fig.8 shows a schematic picture of our roof construction, several down conductors are connected between the metal plates on the roof and the armament iron. By this connection we have to take care about loops, loops should be avoided. If this is not possible the proximity distance should be larger then the safety distance d, else we can get unintentional sparks. Roof break-threw are not necessary for our building, because this is just necessary for areas bigger then 40x40m. Block B is longer then 40m but it is also smaller then 40m, so the current will not have a to long way to earth. The down-conductors from the roof to the armament iron should be placed in a distance not bigger then 15m and close to corners of the building. If the down conducting system threw the armament iron is not confirm to the requirements, we have to install down conductors on the surface of the building. Date: Lightning protection of an office building page:12
  • 13. Fig.8c: Down-conducting system threw armament iron (taken from 61024-2) 1=horizontal air-termination conductors 2=test joint 3=equipotential bar of the internal LPS Fig.9: places of down-conductor connections The connection of the Down-conducting system to the earth-termination system is already installed (“the foundation electrode placed in the border foundation of the building and connected to the armament iron” Appendix). We should install test joints on the connections Date: Lightning protection of an office building page:13
  • 14. between the down-conducting to the earth-termination system. These joints facilitate the determination by measurement that an adequate number of connections to the earth- termination system still exist, it is possible to check the continuous connection between air- termination system and earth. Also it is possible to measure the earth resistance. If the down conducting system threw the armament iron is not confirm to the requirements or is not possible, we have to install down conductors on the surface of the building. The biggest distance between the down-conductors we can take from table 5, is 15m. So we will place the down-conductors on the same position like we place the down-conductors to connect with armament iron (Fig 9., red spots). The minimum thickness of the down-conductors is shown in table 3. Fig.10: down-conducting system on the surface of the building In Fig.10 is shown a down-conducting system on the surface of the building. The lightning current is running outside the building to the earth-termination system, but you also have to take care of the safety distance d. We will place distance holders each meter. Also you have to prevent that the down-conductors get to close to windows and doors. By down-conductors on the surface it is sometimes necessary to install ring-conductors around the building, and connect them to the down-conductors. This installation helps to distribute the lightning current on each path, also it realize a better equipotential between the down-conductors. On buildings of the height of 20m and less this is not necessary; the foundation electrode is enough to put the down-conductors on the same potential. The down-conductors have to be connected with the earth-termination system threw test joints. 1.2.3. The earth-termination system The task of an earth-termination system is:  Conducting of the lightning current into the earth without causing dangerous over voltages  Equipotential bonding between the down-conductors  Potential control in the vicinity of conductive building walls  Interception of the lightning current when propagation on earth’s surface Date: Lightning protection of an office building page:14
  • 15. The installed foundation electrode meets all these requirements. Earthing and equalization connections: The earth electrode for installations (lightning protection, protection against indirect contact, EMC,etc.) is established as a foundation electrode placed in the border foundation of the building and connected to the armament iron. The electrodes are “connected” to the room with the main electrical panel. To assure and to make the protection systems effective, electrical continuity of the armament iron should be established. Taken from Appendix1 The earth-termination system already exists and it is already connected to the down-conductor (armament iron). So our work is to check, if everything is confirm to the requirements. The necessary length of the earth-electrode is shown in Fig.11, p is the specific resistance for a cubic meter of earth. Fig.11: minimum length l1 of earth electrodes according to the protection level (IEC 1024-1) In the building a foundation electrode is installed, the foundation electrode is a type B arrangement of an earth electrode. For this type the radius of the area enclosed by earth electrode shall be not less than the length l1. r ≥ l1; For the protection level 2 the length l1 is a constant of 5 meters, which is not depending on the specific resistance. So it is not necessary to measure the specific resistance of the earth. To calculate the radius we can use the formula: r= √(A/π); A= area enclosed by earth electrode. The electrode is close to the border of the building, so we will calculate approximately the area for the bloc A. Date: Lightning protection of an office building page:15
  • 16. A= 13,44m*25,2m*2+13,44m*(25,2m-12,8m)= 844m²  r=16,39m ; The length / radius of the earth electrode is long enough in our building. The minimum thickness of the earth-electrode is shown in table 3. Especially in the earth termination system we have to take care about the corrosion of the material, because the material is exposed to water, soil drying and freezing. Table7: LPS materials and condition of use (taken from IEC 1024-1) Table 7 shows the condition of use of the material, e.g. for our earth-termination system stainless steel is a good solution. The electrode is surrounded by concrete so it is protected very well against water and corrosion. Also copper we can use because in the appendix is written, “There may not be any material combinations that can cause galvanic corrosion in the construction.” If it is possible a galvanized steel strip, should be installed in the foundation and be taken upwards with a connection to the down-conducting test joints, else it is possible to perform the connection to the down conducting system on the brick wall. A foundation electrode is normally a good solution for an earth-termination system, because the concrete has a low specific resistance (150-500Ωm) and protects the metal from corrosion. Date: Lightning protection of an office building page:16
  • 17. 1.3 For the inner lightning protection there should be selected equipment for protection of the high voltage side of the supply transformer. Electrical installation: The building is connected to the public grid at voltage level 10.5 kV. The grid voltage is transformed down by a 10.5/0.42 kV Dyn 5 transformer. Rated power is 800 kVA. The distance from the transformer to the main electrical panel located in the basement of the building is 12 m. Taken from appendix Fig.1.3.1: electrical connection of the building Used Cable information: Cable type Nkt-cable 3x95mm² PEX-Cu 12kV Length =10000m Vcable =200*106 m/s C´ =0,34µF/km X´ =0,097Ω/km Calculation of wave impedance and wave time constant: F =50Hz L =X / (2*π*f)= 3,08*10-4 Vs / A*km Z =√ (L / C)= √ ((3,08*10-4 Vs / A*km) / (0,34μF/km)) = 30,13Ω Ψ = length / Vcable = 10000m / (200*106 m/s) = 50µs Surge arrester information: more information on appendix 2 Type = Esra 12 Ur = 12 kV guaranteed protective characteristics Uc =Max. conti. operating voltage= (UmaxL*1,05) / √3 =7,27kV <9,6kV UmaxL =max. system voltage= 12kV Ur0 =voltage marking at component= Uc / 0,8= 9,09kV Ue =temporary over voltage= ke*Uc= √3 * 7,27kV=12,6kV <14,2kV Date: Lightning protection of an office building page:17
  • 18. ke =earth fault factor; kt = 3; UL=(kt*Ur*ke*√2) / √3 = 44,55kV; Calculation of the consuming energy: Urest = switching surge voltage taken from the surge arrester information = 28,6kV; W=( (UL- Urest) / Z) * Urest*2* Ψ= 1509,25 VAs= 0,419Wh= 4,19*10-4kWh; Transforming kWhJ: 4,19*10-4kWh * 3,6 · 106 = 1509,25J; W / UmaxL= 0,125 kJ / kV; The surge arrester ESRA 12 can withstand a Energy of 2,1 kJ / kV Line discharge, our calculated value is much lower. So we can use the ESRA 12 for the protection of the transformer on the high voltage side. 1.4 Work out over-voltage protection for the electrical installations in the building. In the following exercise:  Describe the necessary initiative to achieve potential equalization (same voltage).  The proposal should include the main and group electrical panels (switch boards) and possible instrument/device protection.  The proposal should be based on appendix , which only contains information about block B of the building.  Hence the proposal for the inner lightning protection should be limited to block B. equipotential bonding: We need equipotential bonding to set all the metal installations to one voltage level. So the metal installation inside the building should be connected to an equipotential bonding. If there is no equipotential, dangerous touch voltage can occur for example between PE-conductor of the electrical equipment and metal pipes of the radiator. Threw the PE-conductor can run voltage which can damage electrical devices. In the building two types of equipotential bonding can be installed, the main equipotential bonding (EB) and additional equipotential bondings. To the main equipotential bonding should be connected:  foundation earthing electrodes;  central heating system;  metal drain pipe;  internal gas pipe;  earthing conuctor for antennas; Date: Lightning protection of an office building page:18
  • 19. PEN-conductor (main electrical panel) / electrical equipment;  Conductive parts of the construction of the building. The main equipotential bonding should be placed in the basement, near to the earth-level and not to far from the main electrical panel (service entrance box). Fig.12:Internal lightning protection with a common entry of all supply lines (taken from www.dehn.de) Fig.12 shows how we can connect the different metal installations in our building, the connection to the power supply is protected with a surge arrester. The equipotential cables can be marked like the PE-conductor, yellow and green. The thickness of these cables should be not smaller then the half of the main equipotential cable ( normally the PE-conductor of the power supply), but at least not smaller then 6mm². The equipotential bounding is connected to the foundation electrode. Date: Lightning protection of an office building page:19
  • 20. Fig.13: equipotential bonding Protection of electrical devices: Date: Lightning protection of an office building page:20
  • 21. Fig.14:single-line diagram for the power supply system of the building (taken from appendix) There are three different classes of over voltage protection. We will use all three classes of protection. - Class B Lightning Current Arrester Single-pole arrester in the specification class B for the protection of electrical consumer installations and equipment in case of over voltage or direct lightning strikes.  will protect the input side of the main electrical panel (F1) - Class C Surge Arrester Single-pole arrester in the specification class C for the protection of electrical consumer installations and equipment against over voltage caused by distant lightning strikes or switching operations.  will protect the input side of the group electrical panel (F2) - Class D Surge Arrester for Device Protection Double-pole arrester in the specification class D for the protection of electrical installations against over voltage caused by distant lightning strikes or switching operations.  will protect the electrical equipment (F3-F28) The voltage and the current of the lightning will be reduced from the class B arrester to the class C arrester, from the class C arrester to the class D arrester and at the output side of the class D arrester the voltage and the current surge should cause no damage in the electronic devices. Protection plan of electric devices: Fig.15: protection of the electric devices in the building Cable length 2 should be not longer then 5 meters, so we can put it also inside the group panels on each floor. Cable length 1 should be not longer then 15m, but in our building the Date: Lightning protection of an office building page:21
  • 22. cable length is between 30 and 50m. So it will be a good idea to install also a limiter link between the main electrical panel and the group panel. - Limitor Link Decoupling Inductor Supplies the inductance for energy-control coordination between the lightning current arrester and the surge arrester when the impedance of the lines connecting these components does not provide sufficient damping. Principle of a surge arrester : Fig.16: principle of a surge arrester (switch) A – Isolator B – Metal C – Transfer connectors D – Break down plates E – Choke absorber A ignition tension appears in point number 1 and the spark rise until the 4th point were it’s break and spread out in two different ways. At the 6th point the small plates transform the half of spark into less powerful sparks. The small sparks that goes back, to the side of the stroke, the remove power to the stroke, and the another sparks go to the earth using PE connection. Date: Lightning protection of an office building page:22
  • 23. Example for used equipment: Fig.17: example of equipment (taken from www.abb.de) 2. Conclusion / Evaluation While we were doing this work, we got a lot of knowledge about Lightning protection. However this kind installation and the tools is very specific and so this kind of installations only can be done by a specialize company. After this work we are able to understand the principles of lightning protection and work in the area. 3. Literature: 1. IEC 61024-1 (-1), (-2) Protection of structures against lightning. 2. www.abb.de. 3. IEC 611312-1 Protection against lightning electromagnetic impulse. 4. Dehn+Sohne „Lighting Protection Guide“ www.dehn.de 4. Appendix: 1. PROB-P, appendix for report no.2. 2. Surge arrester. Date: Lightning protection of an office building page:23