SlideShare ist ein Scribd-Unternehmen logo
1 von 252
Downloaden Sie, um offline zu lesen
Approccio sistemico per la sicurezza
delle gallerie in caso di incendio
e problemi strutturali specifici
Prof. Dr. Ing. Franco Bontempi
Ordinario di Tecnica delle Costruzioni
Facolta’ di Ingegneria Civile e Industriale
Universita’ degli Studi di Roma La Sapienza

www.francobontempi.org

Str
o N
GER

1
www.francobontempi.org

Str
o N
GER

2
Scopo della presentazione
•

Far vedere gli aspetti piu’ generali della
progettazione strutturale antincendio:
Complessita’ del problema;
Approccio sistemico;
Natura accidentale dell’azione incendio;
Progettazione prestazionale/prescrittiva;
Aspetti specifici delle gallerie stradali.

www.francobontempi.org

Str
o N
GER

3
www.francobontempi.org

Str
o N
GER

1
OGGETTO
Caratteristiche delle gallerie
Geometrie
Impianti
4
www.francobontempi.org

Str
o N
GER

GEOMETRIE

5
www.francobontempi.org

Str
o N
GER

Tipo A - autostrade

6
www.francobontempi.org

Str
o N
GER

7
www.francobontempi.org

Str
o N
GER

Tipo B – extraurbane principali

8
Str
o N
GER
www.francobontempi.org

Tipo C – extraurbane secondarie

9
www.francobontempi.org

Str
o N
GER

10
www.francobontempi.org

Str
o N
GER

11
www.francobontempi.org

Str
o N
GER

12
www.francobontempi.org

Str
o N
GER

13
www.francobontempi.org

Str
o N
GER

14
www.francobontempi.org

Str
o N
GER

15
www.francobontempi.org

Str
o N
GER

16
www.francobontempi.org

Str
o N
GER

17
www.francobontempi.org

Str
o N
GER

Sistema vs Struttura

Opera
Viva

Opera
Morta
18
www.francobontempi.org

Str
o N
GER

IMPIANTI VENTILAZIONE

19
www.francobontempi.org

Str
o N
GER

20
www.francobontempi.org

Str
o N
GER

Piston effect

• Is the result of natural induced draft caused by
free-flowing traffic (> 50 km/h) in uni-directional
tunnel thus providing natural ventilation.

21
www.francobontempi.org

Str
o N
GER

Mechanical ventilation

• “forced” ventilation is required where piston
effect is not sufficient such as in
– congested traffic situations;
– bi-directional tunnels (piston effect is neutralized by
flow of traffic in two opposite directions);
– long tunnels with high traffic volumes.

22
Str
o N
GER
www.francobontempi.org

TUNNEL VENTILATION SYSTEMS

• Road Tunnel Ventilation Systems have two modes of
operation:
• Normal ventilation, for control of air quality inside tunnels
due to vehicle exhaust emissions:
– in any possible traffic situation, tunnel users and staff must not suffer
any damage to their health regardless the duration of their stay in the
tunnel;
– the necessary visual range must be maintained to allow for safe
stopping.

• Emergency ventilation in case of fire, for smoke control:
– the escape routes must be kept free from smoke to allow for selfrescue;
– the activities of emergency services must be supported by providing
the best possible conditions over a sufficient time period ;
– the extent of damage and injuries (to people, vehicles and the tunnel
structure itself) must be kept to a minimum.
23
www.francobontempi.org

Str
o N
GER

Longitudinal ventilation system

• employs jet fans suspended under tunnel roof; in
normal operation fresh air is introduced via
tunnel entering portal and polluted air is
discharged from tunnel leaving portal.

24
www.francobontempi.org

Str
o N
GER

25
www.francobontempi.org

Str
o N
GER

26
Str
o N
GER
www.francobontempi.org

Semi-transverse ventilation system

• employs ceiling plenum connected to central fan
room equipped with axial fans; in normal
operation fresh air is introduced along the tunnel
trough openings in the ventilation plenum while
polluted air is discharged via tunnel portals.

27
www.francobontempi.org

Str
o N
GER

Transverse ventilation system

• employs double supply and exhaust plenums
connected to central fan rooms equipped with
axial fans; in normal operation fresh air is
introduced and exhausted via openings in
double ventilation plenums.

28
www.francobontempi.org

Str
o N
GER

29
www.francobontempi.org

Str
o N
GER

30
www.francobontempi.org

Str
o N
GER

31
www.francobontempi.org

Str
o N
GER

Attachments

• Dispersion stack and fan room combined with
longitudinal ventilation: may be required in order
to reduce adverse effect on environment of
discharge of polluted air from tunnel, where
buildings are located in proximity (< 100m) to
tunnel leaving portal.

32
www.francobontempi.org

Str
o N
GER

33
www.francobontempi.org

Str
o N
GER

Ventilation unit
Air extraction

Ventilation unit
Supply of fresh air

34
www.francobontempi.org

Str
o N
GER

35
www.francobontempi.org

Str
o N
GER

2
COMPLESSITA’
Approccio prestazionale
Modellazione
Sicurezza
36
System Complexity (Perrow)

couplings

TIGHT

LINEAR interactions NONLINEAR

LOOSE

www.francobontempi.org

Str
o N
GER

37
www.francobontempi.org

Str
o N
GER

APPROCCIO PRESTAZIONALE

38
www.francobontempi.org

Str
o N
GER

39
www.francobontempi.org

Str
o N
GER

Prescrittivo (1)
APPROCCIO
PRESCRITTIVO

APPROCCIO
PRESTAZIONALE

1) BASI DEL PROGETTO,
2) LIVELLI DI SCUREZZA,
3) PRESTAZIONI ATTESE
NON ESPLICITATI

OBIETTIVI
PRESTAZIONALI E
LIVELLI DI
SICUREZZA
ESPLICITATI

1) REGOLE DI
CALCOLO E
2) COMPONENTI
MATERIALI
SPECIFICATI E
DETTAGLIATI

QUALITA' ED AFFIDABILITA'
STRUTTURALI
ASSICURATI IN MODO
INDIRETTO

INSIEME DI
STRUMENTI
LOGICI E
MATERIALI #1

INSIEME DI
STRUMENTI
LOGICI E
MATERIALI #2

INSIEME DI
STRUMENTI
LOGICI E
MATERIALI #3

GARANZIA DIRETTA DELLE PRESTAZIONI
E DELLA SICUREZZA STRUTURALI

40
Str
o N
GER
www.francobontempi.org

Prescrittivo (2)
prescrittivo
Elementi Costituenti
Elementi Costituenti
Elementi Costituenti
Elementi Costituenti
Elementi Costituenti
Elementi Costituenti
Elementi Costituenti
Elementi Costituenti

Requisiti
Requisiti

prestazionale

Requisiti
Requisiti

Elementi Costituenti
Elementi Costituenti

41
www.francobontempi.org

Str
o N
GER

Prestazionale (1)
APPROCCIO
PRESCRITTIVO

APPROCCIO
PRESTAZIONALE

1) BASI DEL PROGETTO,
2) LIVELLI DI SCUREZZA,
3) PRESTAZIONI ATTESE
NON ESPLICITATI

OBIETTIVI
PRESTAZIONALI E
LIVELLI DI
SICUREZZA
ESPLICITATI

1) REGOLE DI
CALCOLO E
2) COMPONENTI
MATERIALI
SPECIFICATI E
DETTAGLIATI

QUALITA' ED AFFIDABILITA'
STRUTTURALI
ASSICURATI IN MODO
INDIRETTO

INSIEME DI
STRUMENTI
LOGICI E
MATERIALI #1

INSIEME DI
STRUMENTI
LOGICI E
MATERIALI #2

INSIEME DI
STRUMENTI
LOGICI E
MATERIALI #3

GARANZIA DIRETTA DELLE PRESTAZIONI
E DELLA SICUREZZA STRUTURALI

42
Str
o N
GER
www.francobontempi.org

Prestazionale (2)
prescrittivo
Elementi Costituenti
Elementi Costituenti
Elementi Costituenti
Elementi Costituenti
Elementi Costituenti
Elementi Costituenti
Elementi Costituenti
Elementi Costituenti

Requisiti
Requisiti

prestazionale

Requisiti
Requisiti

Elementi Costituenti
Elementi Costituenti

43
www.francobontempi.org

Str
o N
GER

START

DEFINIZIONE E DISANIMA
DEGLI OBIETTIVI

INDIVIDUAZIONE DELLE
SOLUZIONI ATTE A
RAGGIUNGERE GLI
OBIETTIVI

ATTIVITA' DI
MODELLAZIONE E MISURA

GIUDIZIO DELLE
PRESTAZIONI
RISULTANTI

No

Yes
END

44
www.francobontempi.org

Str
o N
GER

45
www.francobontempi.org

Str
o N
GER

46
www.francobontempi.org

Str
o N
GER
livello
1

OBIETTIVI

livello
2

ESPLICITAZIONE DEGLI
OBIETTIVI ATTRAVERSO
L'INDIVIDUAZIONE DI n
PRESTAZIONI;
ordinatamente, per ciascuna di
esse, i =1,..n:

C

DEFINIZIONE DELLA
PERFORMANCE i-esima

CRITERIO (QUANTITA')
CHE MISURA
LA PERFORMANCE i-esima

LIMITI DELLA
PERFORMANCE i-esima

B

livello
3

DEFINIZIONE
DELLA
SOLUZIONE
STRUTTURALE

livello
4

VERIFICA
DELLE
CAPACITA'
PRESTAZIONALI

RISPETTO DI
PRESCRIZIONI

MODELLI
NUMERICI

A

NO

ESITO

MODELLI
FISICI

47
SI'
livello
1

OBIETTIVI

livello
2

ESPLICITAZIONE DEGLI
OBIETTIVI ATTRAVERSO
L'INDIVIDUAZIONE DI n
PRESTAZIONI;
ordinatamente, per ciascuna di
esse, i =1,..n:

C

DEFINIZIONE DELLA
PERFORMANCE i-esima

CRITERIO (QUANTITA')
CHE MISURA
LA PERFORMANCE i-esima

LIMITI DELLA
PERFORMANCE i-esima

B

livello
3

DEFINIZIONE
DELLA
SOLUZIONE
STRUTTURALE

livello
4

VERIFICA
DELLE
CAPACITA'
PRESTAZIONALI

RISPETTO DI
PRESCRIZIONI

MODELLI
NUMERICI

A

NO

ESITO

MODELLI
FISICI

SI'

www.francobontempi.org

Str
o N
GER

48
www.francobontempi.org

Str
o N
GER

MODELLAZIONE

49
www.francobontempi.org

Str
o N
GER

50
www.francobontempi.org

Analysis Strategy #1:
Sensitivity governance of priorities

Str
o N
GER

51
www.francobontempi.org

Analysis Strategy #2:
Bounding behavior governance

Str
o N
GER

52
www.francobontempi.org

Analysis Strategy #3:
Redundancy Governance

Str
o N
GER

53
www.francobontempi.org

Str
o N
GER

NUMERICAL
MODELING

54
www.francobontempi.org

Factors for Coupling

Str
o N
GER

time
tK

TERMAL
STATE
(Temperature Field
and Termic Related
Properties)

MECHANICAL
STATE
(Strain and Stress
Fields and
Mechanical related
Properties)

INFORMATION
FLOW DIRECTION

55
time
tK

time
tK

time
tK

time
tK

TERMAL
STATE
(Temperature Field
and Termic Related
Properties)

TERMAL
STATE
(Temperature Field
and Termic Related
Properties)

TERMAL
STATE
(Temperature Field
and Termic Related
Properties)

TERMAL
STATE
(Temperature Field
and Termic Related
Properties)

www.francobontempi.org

Fully Coupled Scheme

Str
o N
GER

MECHANICAL
STATE
(Strain and Stress
Fields and
Mechanical related
Properties)

MECHANICAL
STATE
(Strain and Stress
Fields and
Mechanical related
Properties)

MECHANICAL
STATE
(Strain and Stress
Fields and
Mechanical related
Properties)

MECHANICAL
STATE
(Strain and Stress
Fields and
Mechanical related
Properties)

56
time
tK

time
tK

time
tK

time
tK

TERMAL
STATE
(Temperature Field
and Termic Related
Properties)

TERMAL
STATE
(Temperature Field
and Termic Related
Properties)

TERMAL
STATE
(Temperature Field
and Termic Related
Properties)

TERMAL
STATE
(Temperature Field
and Termic Related
Properties)

www.francobontempi.org

Staggered Coupled Scheme

Str
o N
GER

MECHANICAL
STATE
(Strain and Stress
Fields and
Mechanical related
Properties)

MECHANICAL
STATE
(Strain and Stress
Fields and
Mechanical related
Properties)

MECHANICAL
STATE
(Strain and Stress
Fields and
Mechanical related
Properties)

MECHANICAL
STATE
(Strain and Stress
Fields and
Mechanical related
Properties)

57
time
tK

time
tK

time
tK

time
tK

TERMAL
STATE
(Temperature Field
and Termic Related
Properties)

TERMAL
STATE
(Temperature Field
and Termic Related
Properties)

TERMAL
STATE
(Temperature Field
and Termic Related
Properties)

TERMAL
STATE
(Temperature Field
and Termic Related
Properties)

www.francobontempi.org

Temperature Driven Scheme

Str
o N
GER

MECHANICAL
STATE
(Strain and Stress
Fields and
Mechanical related
Properties)

MECHANICAL
STATE
(Strain and Stress
Fields and
Mechanical related
Properties)

MECHANICAL
STATE
(Strain and Stress
Fields and
Mechanical related
Properties)

MECHANICAL
STATE
(Strain and Stress
Fields and
Mechanical related
Properties)

58
time
tK

time
tK

time
tK

time
tK

TERMAL
STATE
(Temperature Field
and Termic Related
Properties)

TERMAL
STATE
(Temperature Field
and Termic Related
Properties)

TERMAL
STATE
(Temperature Field
and Termic Related
Properties)

TERMAL
STATE
(Temperature Field
and Termic Related
Properties)

www.francobontempi.org

Scheme With No Memory

Str
o N
GER

MECHANICAL
STATE
(Strain and Stress
Fields and
Mechanical related
Properties)

MECHANICAL
STATE
(Strain and Stress
Fields and
Mechanical related
Properties)

MECHANICAL
STATE
(Strain and Stress
Fields and
Mechanical related
Properties)

MECHANICAL
STATE
(Strain and Stress
Fields and
Mechanical related
Properties)

59
www.francobontempi.org

Str
o N
GER

60
www.francobontempi.org

Str
o N
GER

61
www.francobontempi.org

Str
o N
GER

62
www.francobontempi.org

Str
o N
GER

63
www.francobontempi.org

Str
o N
GER

SICUREZZA

64
RELIABILITY
A way to assess
the dependability of a system

ATTRIBUTES

AVAILABILITY
MAINTAINABILITY
SAFETY

the trustworthiness
of a system which allows
reliance to be justifiably placed
on the service it delivers

SECURITY
INTEGRITY

DEPENDABILITY
of
STRUCTURAL
SYSTEMS

www.francobontempi.org

Str
o N
GER

High level / active
performance

FAULT
THREATS

An understanding of the things
that can affect the dependability
of a system

ERROR
FAILURE

Low level / passive
performance
it is a defect and represents a
potential cause of error, active or dormant
the system is in an incorrect state:
it may or may not cause failure
permanent interruption of a system ability
to perform a required function
under specified operating conditions

FAULT TOLERANT
DESIGN
FAULT DETECTION
MEANS
FAULT DIAGNOSIS
ways to increase
the dependability of a system

Visions, I., Laprie, J.C., Randell,
B.,
Dependability and its threats:
a taxonomy,
18th IFIP
World Computer Congress,

65

FAULT MANAGING

Toulouse (France) 2004.
RELIABILITY

www.francobontempi.org

Structural Robustness (1)

Str
o N
GER

AVAILABILITY

ATTRIBUTE
S

MAINTAINABILITY
SAFETY
SECURITY
INTEGRITY

FAULT
THREATS

ERROR
FAILURE

it is a defect and represents a
potential cause of error, active or dormant
the system is in an incorrect state:
it may or may not cause failure
permanent interruption of a system ability
66
66
to perform a required function
under specified operating conditions
• Capacity of a construction to show a
regular decrease of its structural quality
due to negative causes. It implies:
a) some smoothness of the decrease of
structural performance due to
negative events (intensive feature);
b) some limited spatial spread of the
rupture (extensive feature).
67

www.francobontempi.org

Structural Robustness (2)

Str
o N
GER
1st level:
Material
Point

3rd level:
Structural
Element

4th level:
Structural
System

2nd level:
Element
Section

Structural Robustness
Assessment

Usual ULS & SLS
Verification Format
www.francobontempi.org

Levels of Structural Crisis

Str
o N
GER

68
STRUCTURE
& LOADS

Collapse
Mechanism

NO SWAY

SWAY

“IMPLOSION”
OF THE
STRUCTURE

www.francobontempi.org

Bad vs Good Collapses

Str
o N
GER

is a process in which
objects are destroyed by
collapsing on themselves

“EXPLOSION”
OF THE
STRUCTURE
is a process
69
NOT CONFINED
www.francobontempi.org

Str
o N
GER

Design Strategy #1: Continuity

70
www.francobontempi.org

Str
o N
GER

Design Strategy #2: Segmentation

71
www.francobontempi.org

Str
o N
GER

Esempio di valutazione
di roubustezza strutturale

72
www.francobontempi.org

Str
o N
GER

Esempio: edificio alto

73
73
www.francobontempi.org

Str
o N
GER

Analisi di un componente tipico

D0

74
Str
o N
GER
www.francobontempi.org

Scenari (1-2)

D1

D2

75
Str
o N
GER
www.francobontempi.org

Scenari (3-4)

D3

D4

76
www.francobontempi.org

Str
o N
GER

Modalità di collasso (1-2)

D1

D2

77
www.francobontempi.org

Str
o N
GER

Modalità di collasso (3-4)

D3

D4

78
Str
o N
GER
www.francobontempi.org

Sintesi dei risultati: elemento critico

0

4

Lo scenario D4
è quello più cattivo:
l’elemento strutturale
critico individuato è la
colonna più esterna!
79
www.francobontempi.org

Modellazione edificio alto

Str
o N
GER

80
www.francobontempi.org

Str
o N
GER

81
www.francobontempi.org

Str
o N
GER

Scenari di danneggiamento

Scenario 1

Scenario 2

Scenario 3

Scenario 4

(1 asta
eliminata)

(3 aste
eliminate)

(5 aste
eliminate)

(7 aste
eliminate)
82
www.francobontempi.org

Str
o N
GER

Collasso secondo scenario 1

83
www.francobontempi.org

Str
o N
GER

Collasso secondo scenario 2

84
www.francobontempi.org

Str
o N
GER

Collasso secondo scenario 3

85
www.francobontempi.org

Str
o N
GER

Collasso secondo scenario 4

86
www.francobontempi.org

Str
o N
GER

Sintesi dei risultati
Moltiplicatore Ultimo e sua variazione

u
4,50
4,00
3,50
3,00
2,50
2,00
1,50
1,00
0,50
0,00

Delta u
Δ F
Fu

0,48

4,05

D0

3,57

D1

0,86

3,19

1,41

1,65

2,64

2,40

D3

D4

D2

Scenario di danneggiamento
87
www.francobontempi.org

Str
o N
GER

3
AZIONE
Natura dell’azione incendio
Carattere accidentale
Carattere estensivo
Carattere intensivo
88
www.francobontempi.org

Str
o N
GER

Aspetti caratteristici dell’incendio

• Carattere estensivo
(diffusione nello spazio):
1.wildfire
2.urbanfire
3.all’esterno di una costruzione
4.all’interno di una costruzione

• Carattere intensivo
(andamento nel tempo).
• Natura accidentale.
89
www.francobontempi.org

Str
o N
GER

Carattere intensivo

90
ISO 13387: Example of Design Fire

www.francobontempi.org

Str
o N
GER

91
Str
o N
GER
www.francobontempi.org

Andamento nel tempo potenza termica

92
www.francobontempi.org

Str
o N
GER

93
Strategie
flashover

Temperatura T(t)

www.francobontempi.org

Str
o N
GER

STRATEGIE
ATTIVE
(approccio
sistemico)

STRATEGIE
PASSIVE
(approccio
strutturale)
andamento di T(t) a
seguito del successo
delle strategie attive

94

Tempo t
www.francobontempi.org

Str
o N
GER

Fire Safety Strategies
prevention

protection
active






Limit ignition
sources
Limit hazardous
human behavior
Emergency
procedure and
evacuation





Detection measures
(smoke, heat, flame
detectors)
Suppression
measures (sprinklers,
fire extinguisher,
standpipes, firemen)
Smoke and heat
evacuation system

systemic

F
L
A
S
H
O
V
E
R

robustness

passive




Create fire
compartments
Prevent damage
in the elements
Prevent loss of
functionality in
the building



Prevent the
propagation of
collapse, once
local damages
occurred (e.g.
redundancy)

structural

95
Str
o N
GER

1

prevention
N

2

3

www.francobontempi.org

Fire Safety Strategies
4

doesn’t
trigger

Y

Y

extinguishes
active
protection

triggers

Y

N

no
failures
passive
protection

spreads
N

Y

damages

no
collapse
robustness

N

collapse
96
www.francobontempi.org

Str
o N
GER

97
www.francobontempi.org

Str
o N
GER

98
www.francobontempi.org

Str
o N
GER

SnakeFighter

99
www.francobontempi.org

Str
o N
GER

Carattere estensivo

100
www.francobontempi.org

Str
o N
GER

The Great Fire of Chicago, Oct. 7-10, 1871

101
www.francobontempi.org

Str
o N
GER

102
www.francobontempi.org

Str
o N
GER

103
www.francobontempi.org

Str
o N
GER

104
www.francobontempi.org

Str
o N
GER

105
www.francobontempi.org

Str
o N
GER

Windsor Hotel Madrid

106
www.francobontempi.org

Str
o N
GER

Natura accidentale

107
www.francobontempi.org

Situazioni HPLC

Str
o N
GER

High Probability Low Consequences
108
www.francobontempi.org

Str
o N
GER

LPHC events

Low Probability High Consequences
109
HPLC vs LPHC events
HPLC
LPHC
High Probability Low Probability
Low
High
Consequences Consequences
release of energy
numbers of breakdown
people involved
nonlinearity
interactions
uncertainty
decomposability
course predictability

SMALL
SMALL
FEW
WEAK
WEAK
WEAK

LARGE
LARGE
MANY
STRONG
STRONG
STRONG

HIGH
HIGH

LOW
LOW

110
www.francobontempi.org

Str
o N
GER

Impostazione
del problema:
DETERMINISTICA

STOCASTICA

Approcci di analisi
HPLC

LPHC

Eventi Frequenti con
Conseguenze Limitate

Eventi Rari con
Conseguenze Elevate
ANALISI
PRAGMATICA
CON SCENARI

ANALISI
QUALITATIVA
DETERMINISTICA

ANALISI
QUANTITATIVA
PROBABILISTICA

Complessità:
Aspetti non lineari e
Meccanismi di interazioni

111
www.francobontempi.org

Str
o N
GER

Italian Code for Constructions
D.M. 14 settembre 2005
CAPITOLO 2:
SICUREZZA
E
PRESTAZONI
ATTESE

DOMANDA

PRODOTTO

CAPITOLO 5:
NORME
SULLE
COSTRUZIONI
CAPITOLO 3:
AZIONI
AMBIENTALI

QUALITA’

CAPITOLO 4:
AZIONI
ACCIDENTALI

CAPITOLO 6:
AZIONI
ANTROPICHE

CAPITOLO 7:
NORME PER LE
OPERE
INTERAGENTI
CON I TERRENI E
CON LE ROCCE,
PER GLI
INTERVENTI NEI
TERRENI E PER
LA SICUREZZA
DEI PENDII
CAPITOLO 9:
NORME
SULLE
COSTRUZIONI
ESISTENTI

CONTROLLO

CAPITOLO 11:
MATERIALI
E
PRODOTTI
PER USO
STRUTTURALE
CAPITOLO 8:
COLLAUDO
STATICO
CAPITOLO 10:
NORME PER LA
REDAZIONI DEI
PROGETTI
ESECUTIVI

112
www.francobontempi.org

Str
o N
GER

Scenari (D.M. 14 settembre 2005)
Il Progettista, a seguito della classificazione e della caratterizzazione delle azioni,
deve individuare le possibili situazioni contingenti in cui le azioni possono
cimentare l’opera stessa. A tal fine, è definito:


lo scenario: un insieme organizzato e realistico di situazioni in cui l’opera
potrà trovarsi durante la vita utile di progetto;



lo scenario di carico: un insieme organizzato e realistico di azioni che
cimentano la struttura;



lo scenario di contingenza: l’identificazione di uno stato plausibile e
coerente per l’opera, in cui un insieme di azioni (scenario di carico) è
applicato su una configurazione strutturale.

Per ciascuno stato limite considerato devono essere individuati scenari di carico
(ovvero insiemi organizzati e coerenti nello spazio e nel tempo di azioni) che
rappresentino le combinazioni delle azioni realisticamente possibili e
verosimilmente più restrittive.
113
Str
o N
GER

Establish
performance
requirements

www.francobontempi.org

Determine geometry,
construction and
use of the building

Establish maximum likely
fuel loads

Buchanan, 2002

Estimate maximum likely
number of occupants
and their locations

Assume certain fire protection
features

Carry out fire engineering
analysis

Modify fire
protection
features

No

Acceptable
performance

Yes

Accept
design

114
www.francobontempi.org

Str
o N
GER

115
www.francobontempi.org

Str
o N
GER

4
SVILUPPO
Dinamica degli incendi in galleria
Effetti della ventilazione

116
www.francobontempi.org

Str
o N
GER

FIRE DYNAMICS IN TUNNELS

117
Tunnel Fires vs Compartment Fires (0)

118
www.francobontempi.org

Str
o N
GER

Tunnel Fires Progression (1)

119
www.francobontempi.org

Str
o N
GER

120
www.francobontempi.org

Str
o N
GER

121
www.francobontempi.org

Str
o N
GER

Tunnel Fires Progression (2)

122
www.francobontempi.org

Str
o N
GER

Effects of ventilation

123
www.francobontempi.org

Str
o N
GER

Temperature development

124
www.francobontempi.org

Str
o N
GER

Smoke development

• A smoke layer may be created in tunnels at the early stages
of a fire with essentially no longitudinal ventilation. However,
the smoke layer will gradually descend further from the fire.
• If the tunnel is very long, the smoke layer may descend to the
tunnel surface at a specific distance from the fire depending
on the fire size, tunnel type, and the perimeter and height of
the tunnel cross section.
• When the longitudinal ventilation is gradually increased, the
stratified layer will gradually dissolve.
• A backlayering of smoke is created on the upstream side of
the fire.
• Downstream from the fire there is a degree of stratification of
the smoke that is governed by the heat losses to the
surrounding walls and by the turbulent mixing between the
buoyant smoke layers and the normally opposite moving cold
layer.
125
www.francobontempi.org

Str
o N
GER

Backlayering

126
www.francobontempi.org

Str
o N
GER

127
www.francobontempi.org

Str
o N
GER

Maximum gas temperatures in the ceiling area of
the tunnel during tests with road vehicles

128
www.francobontempi.org

Str
o N
GER

Maximum gas temperatures in the ceiling area of
the tunnel during tests with road vehicles

129
www.francobontempi.org

Str
o N
GER

Maximum gas temperatures in the cross section
of the tunnel during tests with road vehicles

130
www.francobontempi.org

Str
o N
GER

EMERGENCY VENTILATION

131
www.francobontempi.org

Str
o N
GER

Smoke stratification

132
www.francobontempi.org

Str
o N
GER

Natural smoke venting

• It can be sufficient in short, level tunnels
where smoke stratification allows for
escape in clear/tenable conditions.

133
www.francobontempi.org

Str
o N
GER

Smoke filling long tunnel

134
www.francobontempi.org

Str
o N
GER

Emergency ventilation with
longitudinal system

• It can be employed in unidirectional, medium length
tunnels, with free flowing traffic conditions. Smoke is
mechanically exhausted in direction of traffic circulation,
clear tenable conditions for escape are obtained on
upstream side of fire.

135
www.francobontempi.org

Str
o N
GER

136
www.francobontempi.org

Str
o N
GER

137
www.francobontempi.org

Str
o N
GER

k size factor for HGV fire

138
www.francobontempi.org

Str
o N
GER

k size factor for small pool fire

139
www.francobontempi.org

Str
o N
GER

Emergency ventilation with semitransverse “point extraction” system

• Smoke is mechanically exhausted from single ceiling
opening (reverse mode) leaving clear tenable escape
conditions on both sides of fire.

140
www.francobontempi.org

Str
o N
GER

141
www.francobontempi.org

Str
o N
GER

Observation: goal

• The purpose of controlling the spread of smoke
is to keep people as long as possible in a
smoke-free environment.
• This means that the smoke stratification must be
kept intact, leaving a more or less clear and
breathable air underneath the smoke layer.
• The stratified smoke is taken out of the tunnel
through exhaust openings located in the ceiling
or at the top of the sidewalls.

142
www.francobontempi.org

Str
o N
GER

Observation: longitudinal velocity

• With practically zero longitudinal air velocity, the
smoke layer expands to both sides of the fire.
The smoke spreads in a stratified way for up to
10 min.
• After this initial phase, smoke begins to mix over
the entire cross section, unless by this time the
extraction is in full operation.
• The longitudinal velocity of the tunnel air must
be below 2 m/s in the vicinity of the fire
incidence zone. With higher velocities, the
vertical turbulence in the shear layer between
smoke and fresh air quickly cools the upper
layer and the smoke then mixes over the entire
143
cross section.
www.francobontempi.org

Str
o N
GER

Observations: turbulence

• With an air velocity of around 2 m/s, most of the
smoke of a medium-size fire spreads to one side
of the fire (limited backlayering) and starts
mixing over the whole cross section at a
distance of 400 to 600 m downstream of the fire
site. This mixing over the cross section can also
be prevented if the smoke extraction is activated
early enough.
• Vehicles standing in the longitudinal air flow
increase strongly the vertical turbulence and
encourage the vertical mixing of the smoke.
144
www.francobontempi.org

Str
o N
GER

Observation: fresh air

• In a transverse ventilation system, the fresh air
jets entering the tunnel at the floor level induce a
rotation of the longitudinal airflow, which tends to
bring the smoke layer down to the road.
• No fresh air is to be injected from the ceiling in a
zone with smoke because this increases the
amount of smoke and tends to suppress the
stratification.

145
www.francobontempi.org

Str
o N
GER

Observation: smoke extraction

• In reversible semi-transverse ventilation with the
duct at the ceiling, the fresh air is added through
ceiling openings in normal ventilation operation.
• If a fire occurs, as long as fresh air is supplied
through ceiling openings, the smoke quantity
increases by this amount and strong jets tend to
bring the smoke down to the road surface. The
conversion of the duct from supply to extraction
must be done as quickly as possible.
146
www.francobontempi.org

Str
o N
GER

Observation: traffic conditions

• For a tunnel with one-way traffic, designed for
queues (an urban area), the ventilation design
must take into consideration that cars can likely
stand to both sides of the fire because of the
traffic. In urban areas it is usual to find stop-andgo traffic situations.
• For a tunnel with two-way traffic, where the
vehicles run in both directions, it must be taken
into consideration that in the event of a fire
vehicles will generally be trapped on both sides
of the fire.
147
www.francobontempi.org

Strategies

Str
o N
GER

148
www.francobontempi.org

Str
o N
GER

Smoke extraction

• Continuous extraction into a return air duct is
needed to remove a stratified smoke layer out of
the tunnel without disturbing the stratification.
• The traditional way to extract smoke is to use
small ceiling openings distributed at short
intervals throughout the tunnel.
• Another efficient way to remove smoke quickly
out of the traffic space is to install large openings
with remotely controlled dampers. They are
normally in an open position where equal
extraction is taking place over the whole tunnel
length.
149
Tunnel with a single-point
extraction system

The usual way to control the longitudinal velocity is to provide several
independent ventilation sections.
When a tunnel has several ventilation sections, a certain longitudinal
velocity in the fire section can be maintained by a suitable operation of the
individual air ducts.
By reversing the fan operation in the exhaust air duct, this duct can be
150
used to supply air and vice versa.

www.francobontempi.org

Str
o N
GER
www.francobontempi.org

Str
o N
GER

FIRE MODELING

151
www.francobontempi.org

Str
o N
GER

152
www.francobontempi.org

Str
o N
GER

Levels

153
www.francobontempi.org

Str
o N
GER

1D

154
www.francobontempi.org

Str
o N
GER

1D

155
www.francobontempi.org

Str
o N
GER

2D (zone model)

156
www.francobontempi.org

Str
o N
GER

2D (zone model)

157
www.francobontempi.org

Str
o N
GER

158
3D (ventilation)

www.francobontempi.org

FDS Simulation

Str
o N
GER

159
3D (fire)

www.francobontempi.org

FDS Simulation

Str
o N
GER

160
www.francobontempi.org

Str
o N
GER

3D (traffic)

161
www.francobontempi.org

Str
o N
GER

162
www.francobontempi.org

Str
o N
GER

Multiscale

163
www.francobontempi.org

Str
o N
GER

Multiscale (ventilation)

164
www.francobontempi.org

Str
o N
GER

Multiscale (fire)

165
www.francobontempi.org

Str
o N
GER

Multiscale (structural)

166
www.francobontempi.org

Str
o N
GER

Multiscale (structural)

167
www.francobontempi.org

Str
o N
GER

5
PROGETTO
Basis
Failure path
Risk
168
www.francobontempi.org

Str
o N
GER

BASIS

169
www.francobontempi.org

Str
o N
GER

3/22/2011

Design Process - ISO 13387
A. Design constraints and possibilities
(blue),
B. Action definition and development
(red),
C. Passive system and active response
(yellow),
D. Safety and performance
(purple).
170
DESIGN

ACTION

RESPONSE

FSE

SS0a
PRESCRIBED
DESIGN
PARAMETERS

SS0b
ESTIMATED
DESIGN
PARAMETERS

(1+2)
ACTION
DEFINITION
AND
DEVELOPMENT

(3+4)
SYSTEM
PASSIVE
AND ACTIVE
RESPONSE

SS5
life safety:
occupant behavior,
location and
condition

SS1
initiation and
development
of fire and
fire efluent

SS6
property
loss

SS2
movement of
fire effluent

SS7
business
interruption

SS3
structural response
and fire spread
beyond enclosure
of origin

SS8
contamination
of
environment

SS4
detection,
activitation and
suppression

SS9
destruction
of
heritage

SAFETY & PERFORMANCE

(0)
DESIGN
CONSTRAINTS
AND
POSSIBILITIES

BUS OF INFORMATION

www.francobontempi.org

Str
o N
GER

RESULTS

171
www.francobontempi.org

Str
o N
GER

STRUCTURAL
CONCEPTION

Yes
threats
No
STRUCTURAL
TOPOLOGY
&
GEOMETRY
passive
structural
characteristics

Yes
threats
No
STRUCTURAL
MATERIAL
& PARTS

Yes

STRUCTURAL
SYSTEM
CHARACTERISTICS

threats
No
FIRE DETECTION
& SUPPRESSION

active
structural
characteristics

Yes
threats

STRUCTURAL
SYSTEM
WEAKNESS

No
ORGANIZATION &
FIREFIGHTERS

Yes
threats
No
alive
structural
characteristics

MAINTENANCE
& USE

Yes
threats
No

172
STRUCTURAL
CONCEPTION

STRUCTURAL
CONCEPTION

Yes
threats
No
STRUCTURAL
TOPOLOGY
&
GEOMETRY
passive
structural
char acteristics

www.francobontempi.org

Str
o N
GER

Yes
threats
No
STRUCTURAL
MATERIAL
& PARTS

Yes
threats
No

Yes

FIRE DETECTION
& SUPPRESSION

active
structural
char acteristics

threats

Yes
threats
No

ORGANIZATION &
FIREFIGHTERS

Yes

No

threats
No
alive
structural
char acteristics

MAINTENANCE
& USE

Yes

STRUCTURAL
TOPOLOGY
&
GEOMETRY

threats
No

passive
structural
characteristics

Yes
threats
No
STRUCTURAL
MATERIAL
& PARTS

Yes
threats
No

173
No

www.francobontempi.org

FIRE DETECTION
& SUPPRESSION

Str
o N
GER

STRUCTURAL
CONCEPTION

Yes
threats
No
STRUCTURAL
TOPOLOGY
&
GEOMETRY
passive
structural
char acteristics

Yes
threats
No
STRUCTURAL
MATERIAL
& PARTS

active
structural
characteristics

Yes
threats
No

Yes
threats
No
FIRE DETECTION
& SUPPRESSION

active
structural
char acteristics

Yes
threats
No

ORGANIZATION &
FIREFIGHTERS

ORGANIZATION &
FIREFIGHTERS

Yes
threats
No
alive
structural
char acteristics

MAINTENANCE
& USE

Yes
threats
No

Yes
threats
No
alive
structural
characteristics

MAINTENANCE
& USE

Yes
threats
No

3/22/2011

PROGETTAZIONE STRUTTURALE
ANTINCENDIO

174
174
www.francobontempi.org

Str
o N
GER

Fire fighting timeline

175
www.francobontempi.org

Str
o N
GER

STRUCTURAL
CONCEPTION

STRUCTURAL
TOPOLOGY
&
GEOMETRY
STRUCTURAL
MATERIAL
& PARTS

FIRE DETECTION
& SUPPRESSION

ORGANIZATION &
FIREFIGHTERS

MAINTENANCE
& USE

CRISIS

176
IN
-D
EP
TH

DE
FE

NC
E

www.francobontempi.org

Str
o N
GER

FAILURE PATH

177
www.francobontempi.org

Str
o N
GER

Controlled vs. Uncontrolled Events

178
www.francobontempi.org

Str
o N
GER

Controlled vs. Uncontrolled Events

179
Fire safety concepts tree (NFPA)
1

1
Strategie per
la gestione
dell'incendio

2

2

3
Gestione
dell'evento

Prevenzione

4
Gestione
dell'incendio

3

15
Gestione delle
persone e
dei beni

16
Difesa sul posto

4

18
Disposibilità
delle vie
di fuga

5
6
7
8
9

17
Spostamento

5
Controllo
della quantità
di
combustibile

10
Soppressione
dell'incendio

11
Automatica

6
Controllo dei
materiali
presenti

13
Controllo
dell'incendio
attraverso il
progetto

19
Far avvenire
il deflusso

Buchanan, 2002

www.francobontempi.org

Str
o N
GER

12
Manuale

7
Controllo
del movimento
dell'incendio

8
Ventilazione

14
Resistenza e
stabilità
strutturale

9
Contenimento

180
Fire safety concepts tree (NFPA)
1

1
Strategie per
la gestione
dell'incendio

2

2

3
Gestione
dell'evento

Prevenzione

4
Gestione
dell'incendio

3

15
Gestione delle
persone e
dei beni

16
Difesa sul posto

4

18
Disposibilità
delle vie
di fuga

5
6
7
8
9

17
Spostamento

5
Controllo
della quantità
di
combustibile

10
Soppressione
dell'incendio

11
Automatica

6
Controllo dei
materiali
presenti

13
Controllo
dell'incendio
attraverso il
progetto

19
Far avvenire
il deflusso

Buchanan, 2002

www.francobontempi.org

Str
o N
GER

12
Manuale

7
Controllo
del movimento
dell'incendio

8
Ventilazione

14
Resistenza e
stabilità
strutturale

9
Contenimento

181
www.francobontempi.org

Str
o N
GER

Basis of tunnel fire safety design

• The first priority identified in the literature for fire
design of all tunnels is to ensure:
1. Prevention of critical events that may endanger
human life, the environment, and the tunnel structure
and installations.
2. Self-rescue of people present in the tunnel at time of
the fire.
3. Effective action by the rescue forces.
4. Protection of the environment.
5. Limitation of the material and structural damage.

• Furthermore, part of the objective is to reduce
the consequences and minimize the economic
loss caused by fires.
182
www.francobontempi.org

Str
o N
GER

183
www.francobontempi.org

Str
o N
GER

RISK CONCERN

184
www.francobontempi.org

Str
o N
GER

Risk treatment
START

100 %

Option 1 :
RISK
AVOIDANCE

50 %

No
50 %

Yes

Option 2 :
RISK
REDUCTION

20 %

No
30 %

Yes

Option 3 :
RISK
TRANSFER

No
25 %

Yes
5%
Option 4 :
RISK
ACCEPTANCE

No
STOP

185
Str
o N
GER
www.francobontempi.org

Option 1 Risk avoidance, which usually means not
proceeding to continue with the system; this is not
always a feasible option, but may be the only
course of action if the hazard or their probability of
occurrence or both are particularly serious;
Option 2 Risk reduction, either through (a) reducing the
probability of occurrence of some events, or (b)
through reduction in the severity of the
consequences, such as downsizing the system, or
(c) putting in place control measures;
Option 3 Risk transfer, where insurance or other financial
mechanisms can be put in place to share or
completely transfer the financial risk to other
parties; this is not a feasible option where the
primary consequences are not financial;
Option 4 Risk acceptance, even when it exceeds the criteria,
but perhaps only for a limited time until other
186
measures can be taken.
Quantitative Risk Analysis

Luur, 2002

www.francobontempi.org

Str
o N
GER

187
www.francobontempi.org

Str
o N
GER

Risk Analysis, Assessment, Management
(IEC 1995)

188
www.francobontempi.org

RISK CONCERNS

Str
o N
GER

DEFINE CONTEXT
(social, individual,
political, organizational,
technological)

RSK ANALYSIS
(for the system are defined organization,
scenarios, and consequences of
occurences)

RISK
ANALYSIS
RISK
ASSESSMENT

RISK
MANAGEMENT

RISK ASSESSMENT
(compare risks
against criteria)

MONITOR
AND
REVIEW

RISK TREATMENT
option 1 - avoidance
option 2 - reduction
option 3 - transfer
option 4 - acceptance

189
www.francobontempi.org

Str
o N
GER

190
www.francobontempi.org

Str
o N
GER

RISK
ANALYSIS

SCENARIOS

DEFINE SYSTEM
(the system is usually decomposed into
a number of smaller subsystems and/or
components)

HAZARD SCENARIO ANALYSIS
(what can go wrong?
how can it happen?
waht controls exist?)

ESTIMATE
CONSEQUENCES
(magnitude)

ESTIMATE
PROBABILITIES
(of occurrences)

DEFINE
RISK SCENARIOS

SENSITIVITY
ANALYSIS

FIRE
EVENT

191
ISHIKAWA DIAGRAM

www.francobontempi.org

Str
o N
GER

192
www.francobontempi.org

Str
o N
GER

193
www.francobontempi.org

Str
o N
GER

EVENT TREE
Triggering
event

Fire
ignition

Fire
location

1. Fire
extinguished
by personnel

2. Intrusion of
fire fighters

3. Fire
suppression

Scenario

A1
YES (P1)
AREA A
(PA)

NO (1-P1)

Arson

YES (P2)

A2

YES (P3)
NO (1-P3)

A3

NO (1-P2)

A4

YES (P3)
NO (1-P3)

A5

Short
circuit

B1
YES (P1)

Explosion
AREA B
(PB)

NO (1-P1)

Cigarette
fire

YES (P2)

B2

YES (P3)
NO (1-P3)

B3

NO (1-P2)

B4

YES (P3)
NO (1-P3)

B5

Other
C1
YES (P1)
AREA C
(PC)

PREPARAZIONE

NO (1-P1)

YES (P2)

C2

YES (P3)
NO (1-P3)

C3

EVOLUZIONE
NO (1-P2)

YES (P3)
NO (1-P3)

C4

194

C5
www.francobontempi.org

Str
o N
GER

NUMERICAL
MODELING

SIMULATIONS

DEFINE SYSTEM
(the system is usually decomposed into
a number of smaller subsystems and/or
components)

HAZARD SCENARIO ANALYSIS
(what can go wrong?
how can it happen?
waht controls exist?)

ESTIMATE
CONSEQUENCES
(magnitude)

RISK
ANALYSIS

ESTIMATE
PROBABILITIES
(of occurrences)

DEFINE
RISK SCENARIOS

SENSITIVITY
ANALYSIS

195
www.francobontempi.org

Str
o N
GER

196
www.francobontempi.org

Str
o N
GER

197
www.francobontempi.org

Str
o N
GER

198
Str
o N
GER
www.francobontempi.org

F (frequency) – N (number of fatalities) curve

• An F–N curve is an alternative way of describing
the risk associated with loss of lives.
• An F–N curve shows the frequency (i.e. the
expected number) of accident events with at
least N fatalities, where the axes normally are
logarithmic.
• The F–N curve describes risk related to largescale accidents, and is thus especially suited for
characterizing societal risk.
199
www.francobontempi.org

Str
o N
GER

FN-curves UK Road Rail Aviation Transport, 67-01

200
www.francobontempi.org

Str
o N
GER

Persson, M. Quantitative Risk Analysis Procedure for
the Fire Evacuation of a Road Tunnel - An Illustrative
Example. Lund, 2002

201
www.francobontempi.org

Str
o N
GER

Risk acceptance – ALARP (1)
RISK MAGNITUDE
INTOLERABLE
REGION

As
Low
As
Reasonably
Practicable

BROADLY ACCEPTABLE
REGION

Risk cannot be justified
in any circumstances
Tolerable only if risk
reduction is impracticable
or if its cost is greatly
disproportionate to the
improvement gained
Tolerable if cost of
reduction would exceed
the improvements gained

As
Low
As
Reasonably
Achievable

Necessary to maintain
assurance that the risk
remains at this level

202
www.francobontempi.org

Str
o N
GER

Risk acceptance – ALARP (2)

203
www.francobontempi.org

Str
o N
GER

204
www.francobontempi.org

Str
o N
GER

Risk reduction by design

205
Str
o N
GER
www.francobontempi.org

Monetary values – cost of human life (!)
What is the maximum amount the society (or the
decisionmaker) is willing to pay to reduce
the expected number of fatalities by 1?
Typical numbers for the value of a statistical life used in
cost-benefit analysis are 1–10 million euros.

206
www.francobontempi.org

Str
o N
GER

6
RESISTENZA

207
www.francobontempi.org

Str
o N
GER

The burnt out interior
of the Mont Blanc Tunnel

208
www.francobontempi.org

Str
o N
GER

Curve temperatura - tempo

209
Str
o N
GER
www.francobontempi.org

Types of fire exposure
for tunnel analysis
Cellulosic
RABT-ZTV train

Hydrocarbon
RABT-ZTV car

Hydrocarbon modified
RWS

1400
1200

Temperature (°C)

1000
800
600
400
200
0
0

30

60

90
Time (min.)

120

150

180

210
www.francobontempi.org

Str
o N
GER

Cellulosic curve

• Defined in various national standards, e.g. ISO 834, BS 476: part 20, DIN
4102, AS 1530 etc.
• This curve is the lowest used in normal practice.
• It is based on the burning rate of the materials found in general building
211
materials.
www.francobontempi.org

Str
o N
GER

Hydrocarbon (HC) curve

• Although the cellulosic curve has been in use for many years, it soon became
apparent that the burning rates for certain materials e.g. petrol gas, chemicals
etc, were well in excess of the rate at which for instance, timber would burn.
• The hydrocarbon curve is applicable where small petroleum fires might occur,
i.e. car fuel tanks, petrol or oil tankers, certain chemical tankers etc.
212
www.francobontempi.org

Str
o N
GER

Hydrocarbon mod. (HCM) curve

• Increased version of the hydrocarbon curve, prescribed by the French
regulations.
• The maximum temperature of the HCM curve is 1300ºC instead of the
1100ºC, standard HC curve.
• However, the temperature gradient in the first few minutes of the HCM fire is
as severe as all hydrocarbon based fires possibly causing a temperature
shock to the surrounding concrete structure and concrete spalling as a result
213
of it.
www.francobontempi.org

Str
o N
GER

RABT ZTV curves
RABT-ZTV (train)
Time (minutes) T (°C)
0
15
5
1200
60
1200
170
15
RABT-ZTV (car)
Time (minutes) T (°C)
0
15
5
1200
30
1200
140
15

• The RABT curve was developed in Germany as a result of a series of test
programs such as the EUREKA project. In the RABT curve, the temperature
rise is very rapid up to 1200°C within 5 minutes.
• The failure criteria for specimens exposed to the RABT-ZTV time-temperature
curve is that the temperature of the reinforcement should not exceed 300°C.
There is no requirement for a maximum interface temperature.
214
www.francobontempi.org

Str
o N
GER

RWS (Rijkswaterstaat) curve
RWS,
RijksWaterStaat
Time
T
(minutes)
(°C)
0
20
3
890
5
1140
10
1200
30
1300
60
1350
90
1300
120
1200
180
1200

• The RWS curve was developed by the Ministry of Transport in the
Netherlands. This curve is based on the assumption that in a worst case
scenario, a 50 m³ fuel, oil or petrol, tanker fire with a fire load of 300MW could
occur, lasting up to 120 minutes.
• The failure criteria for specimens is that the temperature of the interface
between the concrete and the fire protective lining should not exceed 380°C
215
and the temperature on the reinforcement should not exceed 250°C.
www.francobontempi.org

Str
o N
GER

216
www.francobontempi.org

Str
o N
GER

217
www.francobontempi.org

Str
o N
GER

Lönnermark, A. and Ingason, H., “Large Scale Fire Tests in the Runehamar
tunnel – gas temperature and Radiation”,
Proceedings of the International Seminar on Catastrophic Tunnel Fires,
Borås, Sweden, 20-21 November 2003.

218
www.francobontempi.org

Str
o N
GER

219
www.francobontempi.org

Str
o N
GER

220
www.francobontempi.org

Str
o N
GER

Fire Scenario Recommendation

221
www.francobontempi.org

Str
o N
GER

Verifiche

222
www.francobontempi.org

Str
o N
GER

Mechanical Analysis
• The mechanical analysis shall be performed for the
same duration as used in the temperature analysis.
• Verification of fire resistance should be in:
– in the strength domain:
Rfi,d,t ≥ Efi,requ,t
(resistance at time t ≥ load effects at time t);
– in the time domain:
tfi,d ≥ tfi,requ
(design value of time fire resistance ≥
time required)
– In the temperature domain:
Td ≤ Tcr
(design value of the material temperature ≤
critical material temperature);
223
www.francobontempi.org

Str
o N
GER

Verification of fire resistance (3D)
R = structural resistance

R=R(t,T)=R(t,T(t))=R(t)

t = time

T=T(t)
T = temperature

224
www.francobontempi.org

Str
o N
GER

Verification of fire resistance (R-safe)
R = structural resistance

Rfi,d,t

Efi,requ,t

t = time

T = temperature

225
www.francobontempi.org

Str
o N
GER

Verification of fire resistance (R-fail)
R = structural resistance

Failure !
Rfi,d,t

Efi,requ,t

t = time

T = temperature

226
www.francobontempi.org

Str
o N
GER

Verification of fire resistance (t)
R = structural resistance

Failure !

Efi,requ,t

Rfi,d,t
t = time

T = temperature

tfi,d ≥ tfi,requ
227
www.francobontempi.org

Str
o N
GER

Verification of fire resistance (T)
R = structural resistance

Failure !

Efi,requ,t
Rfi,d,t
t = time

Td ≤ Tcr

T = temperature

228
www.francobontempi.org

Str
o N
GER

Verification of fire resistance (T)
R = structural resistance

Failure !

Efi,requ,t
Rfi,d,t
t = time

Td ≤ Tcr

T = temperature

229
www.francobontempi.org

Str
o N
GER

Comportamenti termo-meccanici

230
www.francobontempi.org

Str
o N
GER

Trasformazione del calcestruzzo
alle alte temperature

231
www.francobontempi.org

Str
o N
GER

Parametri per la relazione tensioni-deformazioni
per il calcestruzzo ad elevate temperature.

232
www.francobontempi.org

Str
o N
GER

Calcestruzzo ad aggregato siliceo in condizioni di
compressione uniassiale ad elevate temperature

233
www.francobontempi.org

Str
o N
GER

Variazione del coefficiente di riduzione della
resistenza a compressione del calcestruzzo ad
aggregato siliceo con la temperatura

234
www.francobontempi.org

Str
o N
GER

Relazioni tensioni-deformazioni per acciai da
calcestruzzo armato ordinario
laminati a caldo ad elevate temperature

235
www.francobontempi.org

Str
o N
GER

Parametri per la relazione tensioni-deformazioni
per acciai da calcestruzzo armato ordinario
laminati a caldo, a temperature elevate

236
Spalling
Spalling is an umbrella term, covering different damage phenomena
that may occur to a concrete structure during fire. These phenomena
are caused by different mechanisms:
•Pore pressure rises due to evaporating water when the temperature rises;
•Compression of the heated surface due to a thermal gradient in the cross
section;
•Internal cracking due to difference in thermal expansion between
aggregate and cement paste;
•Cracking due to difference in thermal expansion/deformation between
concrete and reinforcement bars;
•Strength loss due to chemical transitions during heating.

www.francobontempi.org

Str
o N
GER

237
Spalling criteria (literature review)
• Explosive spalling occurs during the first 20-30 minutes of the
standard cellulosic and hydrocarbon fire curves.
• After the 2nd minute of a typical hydrocarbon exposure, spalling can
occur in high strength concretes with polypropylene fibres and in
concretes with high moisture content independent of the type of
standard curve. Also, concretes with high moisture content can
suffer spalling after the 3rd minute of exposure.
• External temperature increments between 20-30ºC/min are typical
in the occurrence of explosive spalling.
• Temperature increments of more than 3ºC/min are enough for the
occurrence of explosive spalling.
• Concrete external layers can be released from concrete members
when these reach temperatures between 250 - 420ºC; 375 - 425ºC.
www.francobontempi.org

Str
o N
GER

238
www.francobontempi.org

Str
o N
GER

239
www.francobontempi.org

Str
o N
GER

240
www.francobontempi.org

Str
o N
GER

7
CONCLUSIONI
Conceptual design
Resilience

241
www.francobontempi.org

Str
o N
GER

242
www.francobontempi.org

Str
o N
GER

Conceptual Design

243
www.francobontempi.org

Str
o N
GER

Conceptual Design

DISASTER CHAIN
MULTI-HAZARD
BLACK-SWAN
244
www.francobontempi.org

Str
o N
GER

Forensic Engineering
Flow chart

Tabella dotazioni Frejùs

245
www.francobontempi.org

Str
o N
GER

Resilience

246
www.francobontempi.org

Str
o N
GER

Resilience

• Resilience is defined as
“the positive ability of a system or
company to adapt itself to the
consequences of a catastrophic failure
caused by power outage, a fire, a bomb
or similar event”
or as
"the ability of a system to cope with
change".
247
www.francobontempi.org

Str
o N
GER

RESILIENCE
248
www.francobontempi.org

Str
o N
GER

249
www.francobontempi.org

Str
o N
GER

•
•
•
•
•

ACKNOWLEDGEMENTS
Dr. Konstantinos GKOUMAS – Uniroma1
Dr. Francesco PETRINI – Uniroma1
Ing. Alessandra LO CANE – MIT
Dr. Filippo GENTILI – Coimbra (PT)
Mr. Tiziano BARONCELLI – Uniroma1
250
Str
o N
GER
www.stronger2012.com

251
251
StroNGER S.r.l.
Research Spin-off for Structures of the Next Generation:
Energy Harvesting and Resilience
Roma – Milano – Terni – Atene - Nice Cote Azur

Str
o N
GER
www.stronger2012.com
Sede operativa: Via Giacomo Peroni 442-444, Tecnopolo Tiburtino,
00131 Roma (ITALY) - info@stronger2012.com
252

Weitere ähnliche Inhalte

Andere mochten auch

OTTIMIZZAZIONE TOPOLOGICA EVOLUTIVA: MODELLI STRUT-AND-TIE
OTTIMIZZAZIONE TOPOLOGICA EVOLUTIVA: MODELLI STRUT-AND-TIEOTTIMIZZAZIONE TOPOLOGICA EVOLUTIVA: MODELLI STRUT-AND-TIE
OTTIMIZZAZIONE TOPOLOGICA EVOLUTIVA: MODELLI STRUT-AND-TIEFranco Bontempi Org Didattica
 
Il metodo amoeba per il dimensionamento delle sezioni in acciaio
Il metodo amoeba per il dimensionamento delle sezioni in acciaioIl metodo amoeba per il dimensionamento delle sezioni in acciaio
Il metodo amoeba per il dimensionamento delle sezioni in acciaioFranco Bontempi Org Didattica
 
Applicazione dal Corso di dottorato: Ottimizzazione Strutturale - Bontempi
Applicazione dal Corso di dottorato: Ottimizzazione Strutturale - BontempiApplicazione dal Corso di dottorato: Ottimizzazione Strutturale - Bontempi
Applicazione dal Corso di dottorato: Ottimizzazione Strutturale - BontempiFranco Bontempi Org Didattica
 
ANALISI STRUTTURALE DI PONTI E DI OPERE COMPLESSE DI INGEGNERIA CIVILE
ANALISI STRUTTURALE DI PONTI E DI OPERE COMPLESSE DI INGEGNERIA CIVILEANALISI STRUTTURALE DI PONTI E DI OPERE COMPLESSE DI INGEGNERIA CIVILE
ANALISI STRUTTURALE DI PONTI E DI OPERE COMPLESSE DI INGEGNERIA CIVILEFranco Bontempi Org Didattica
 
Appunti del corso di dottorato: Ottimizzazione Strutturale / Structural Optim...
Appunti del corso di dottorato: Ottimizzazione Strutturale / Structural Optim...Appunti del corso di dottorato: Ottimizzazione Strutturale / Structural Optim...
Appunti del corso di dottorato: Ottimizzazione Strutturale / Structural Optim...Franco Bontempi Org Didattica
 
CM - Petrini - Fatica nelle strutture metalliche - 21/11/2013
CM - Petrini - Fatica nelle strutture metalliche - 21/11/2013CM - Petrini - Fatica nelle strutture metalliche - 21/11/2013
CM - Petrini - Fatica nelle strutture metalliche - 21/11/2013Franco Bontempi Org Didattica
 
Lezione Sicurezza Strutturale Antincendio Costruzioni Metalliche 17 oct 2013
Lezione Sicurezza Strutturale Antincendio Costruzioni Metalliche 17 oct 2013Lezione Sicurezza Strutturale Antincendio Costruzioni Metalliche 17 oct 2013
Lezione Sicurezza Strutturale Antincendio Costruzioni Metalliche 17 oct 2013Franco Bontempi Org Didattica
 
PSA - Caratteristiche del Fenomeno Incendio - Bontempi
PSA - Caratteristiche del Fenomeno Incendio - BontempiPSA - Caratteristiche del Fenomeno Incendio - Bontempi
PSA - Caratteristiche del Fenomeno Incendio - BontempiFranco Bontempi Org Didattica
 
PSA - Natura accidentale dell'Azione Incendio e Procedimenti di Verifica - Bo...
PSA - Natura accidentale dell'Azione Incendio e Procedimenti di Verifica - Bo...PSA - Natura accidentale dell'Azione Incendio e Procedimenti di Verifica - Bo...
PSA - Natura accidentale dell'Azione Incendio e Procedimenti di Verifica - Bo...Franco Bontempi Org Didattica
 
Vulnerabilità delle costruzioni ai fenomeni geologici e idrogeologici - Stefa...
Vulnerabilità delle costruzioni ai fenomeni geologici e idrogeologici - Stefa...Vulnerabilità delle costruzioni ai fenomeni geologici e idrogeologici - Stefa...
Vulnerabilità delle costruzioni ai fenomeni geologici e idrogeologici - Stefa...Franco Bontempi Org Didattica
 
Analisi strutturale in caso di incendio: impostazione e applicazioni
Analisi strutturale in caso di incendio:  impostazione e applicazioniAnalisi strutturale in caso di incendio:  impostazione e applicazioni
Analisi strutturale in caso di incendio: impostazione e applicazioniFranco Bontempi Org Didattica
 
Presentazione della Relazione sulle Opinioni degli Studenti - Facolta' di Ing...
Presentazione della Relazione sulle Opinioni degli Studenti - Facolta' di Ing...Presentazione della Relazione sulle Opinioni degli Studenti - Facolta' di Ing...
Presentazione della Relazione sulle Opinioni degli Studenti - Facolta' di Ing...Franco Bontempi Org Didattica
 
FIRE RISK in STAGED CONSTRUCTION: Safety & Security.
FIRE RISK in STAGED CONSTRUCTION: Safety & Security.FIRE RISK in STAGED CONSTRUCTION: Safety & Security.
FIRE RISK in STAGED CONSTRUCTION: Safety & Security.Franco Bontempi Org Didattica
 
TdC - Esempi di analisi non lineare di strutture in c.a./c.a.p.
TdC - Esempi di analisi non lineare di strutture in c.a./c.a.p.TdC - Esempi di analisi non lineare di strutture in c.a./c.a.p.
TdC - Esempi di analisi non lineare di strutture in c.a./c.a.p.Franco Bontempi Org Didattica
 
PSA - Impostazione del problema della sicurezza strutturale in presenza di in...
PSA - Impostazione del problema della sicurezza strutturale in presenza di in...PSA - Impostazione del problema della sicurezza strutturale in presenza di in...
PSA - Impostazione del problema della sicurezza strutturale in presenza di in...Franco Bontempi Org Didattica
 

Andere mochten auch (20)

Lezione metalliche sismica parte_i
Lezione metalliche sismica parte_iLezione metalliche sismica parte_i
Lezione metalliche sismica parte_i
 
OTTIMIZZAZIONE TOPOLOGICA EVOLUTIVA: MODELLI STRUT-AND-TIE
OTTIMIZZAZIONE TOPOLOGICA EVOLUTIVA: MODELLI STRUT-AND-TIEOTTIMIZZAZIONE TOPOLOGICA EVOLUTIVA: MODELLI STRUT-AND-TIE
OTTIMIZZAZIONE TOPOLOGICA EVOLUTIVA: MODELLI STRUT-AND-TIE
 
Il metodo amoeba per il dimensionamento delle sezioni in acciaio
Il metodo amoeba per il dimensionamento delle sezioni in acciaioIl metodo amoeba per il dimensionamento delle sezioni in acciaio
Il metodo amoeba per il dimensionamento delle sezioni in acciaio
 
CM - robustezza resilienza CTA 2013
CM - robustezza resilienza CTA 2013CM - robustezza resilienza CTA 2013
CM - robustezza resilienza CTA 2013
 
Applicazione dal Corso di dottorato: Ottimizzazione Strutturale - Bontempi
Applicazione dal Corso di dottorato: Ottimizzazione Strutturale - BontempiApplicazione dal Corso di dottorato: Ottimizzazione Strutturale - Bontempi
Applicazione dal Corso di dottorato: Ottimizzazione Strutturale - Bontempi
 
ANALISI STRUTTURALE DI PONTI E DI OPERE COMPLESSE DI INGEGNERIA CIVILE
ANALISI STRUTTURALE DI PONTI E DI OPERE COMPLESSE DI INGEGNERIA CIVILEANALISI STRUTTURALE DI PONTI E DI OPERE COMPLESSE DI INGEGNERIA CIVILE
ANALISI STRUTTURALE DI PONTI E DI OPERE COMPLESSE DI INGEGNERIA CIVILE
 
Appunti del corso di dottorato: Ottimizzazione Strutturale / Structural Optim...
Appunti del corso di dottorato: Ottimizzazione Strutturale / Structural Optim...Appunti del corso di dottorato: Ottimizzazione Strutturale / Structural Optim...
Appunti del corso di dottorato: Ottimizzazione Strutturale / Structural Optim...
 
CM - Petrini - Fatica nelle strutture metalliche - 21/11/2013
CM - Petrini - Fatica nelle strutture metalliche - 21/11/2013CM - Petrini - Fatica nelle strutture metalliche - 21/11/2013
CM - Petrini - Fatica nelle strutture metalliche - 21/11/2013
 
Lezione Sicurezza Strutturale Antincendio Costruzioni Metalliche 17 oct 2013
Lezione Sicurezza Strutturale Antincendio Costruzioni Metalliche 17 oct 2013Lezione Sicurezza Strutturale Antincendio Costruzioni Metalliche 17 oct 2013
Lezione Sicurezza Strutturale Antincendio Costruzioni Metalliche 17 oct 2013
 
PSA - Caratteristiche del Fenomeno Incendio - Bontempi
PSA - Caratteristiche del Fenomeno Incendio - BontempiPSA - Caratteristiche del Fenomeno Incendio - Bontempi
PSA - Caratteristiche del Fenomeno Incendio - Bontempi
 
PSA - Natura accidentale dell'Azione Incendio e Procedimenti di Verifica - Bo...
PSA - Natura accidentale dell'Azione Incendio e Procedimenti di Verifica - Bo...PSA - Natura accidentale dell'Azione Incendio e Procedimenti di Verifica - Bo...
PSA - Natura accidentale dell'Azione Incendio e Procedimenti di Verifica - Bo...
 
Optimization course rome 05_05_2015_fp
Optimization course rome 05_05_2015_fpOptimization course rome 05_05_2015_fp
Optimization course rome 05_05_2015_fp
 
Vulnerabilità delle costruzioni ai fenomeni geologici e idrogeologici - Stefa...
Vulnerabilità delle costruzioni ai fenomeni geologici e idrogeologici - Stefa...Vulnerabilità delle costruzioni ai fenomeni geologici e idrogeologici - Stefa...
Vulnerabilità delle costruzioni ai fenomeni geologici e idrogeologici - Stefa...
 
Analisi strutturale in caso di incendio: impostazione e applicazioni
Analisi strutturale in caso di incendio:  impostazione e applicazioniAnalisi strutturale in caso di incendio:  impostazione e applicazioni
Analisi strutturale in caso di incendio: impostazione e applicazioni
 
Presentazione della Relazione sulle Opinioni degli Studenti - Facolta' di Ing...
Presentazione della Relazione sulle Opinioni degli Studenti - Facolta' di Ing...Presentazione della Relazione sulle Opinioni degli Studenti - Facolta' di Ing...
Presentazione della Relazione sulle Opinioni degli Studenti - Facolta' di Ing...
 
PSA - Azione Incendio: modellazione - Gentili
PSA - Azione Incendio: modellazione - GentiliPSA - Azione Incendio: modellazione - Gentili
PSA - Azione Incendio: modellazione - Gentili
 
FIRE RISK in STAGED CONSTRUCTION: Safety & Security.
FIRE RISK in STAGED CONSTRUCTION: Safety & Security.FIRE RISK in STAGED CONSTRUCTION: Safety & Security.
FIRE RISK in STAGED CONSTRUCTION: Safety & Security.
 
CM 2014_GG_Plates and shells
CM 2014_GG_Plates and shellsCM 2014_GG_Plates and shells
CM 2014_GG_Plates and shells
 
TdC - Esempi di analisi non lineare di strutture in c.a./c.a.p.
TdC - Esempi di analisi non lineare di strutture in c.a./c.a.p.TdC - Esempi di analisi non lineare di strutture in c.a./c.a.p.
TdC - Esempi di analisi non lineare di strutture in c.a./c.a.p.
 
PSA - Impostazione del problema della sicurezza strutturale in presenza di in...
PSA - Impostazione del problema della sicurezza strutturale in presenza di in...PSA - Impostazione del problema della sicurezza strutturale in presenza di in...
PSA - Impostazione del problema della sicurezza strutturale in presenza di in...
 

Ähnlich wie Approccio sistemico per la sicurezza delle gallerie in caso di incendio

Convegno sulla Resistenza al Fuoco, Cosenza 6 Febbraio 2014, Bontempi
Convegno sulla Resistenza al Fuoco, Cosenza 6 Febbraio 2014, BontempiConvegno sulla Resistenza al Fuoco, Cosenza 6 Febbraio 2014, Bontempi
Convegno sulla Resistenza al Fuoco, Cosenza 6 Febbraio 2014, BontempiStroNGER2012
 
Sicurezza Strutturale di Gallerie in Caso di Incendio
Sicurezza Strutturale di Gallerie in Caso di IncendioSicurezza Strutturale di Gallerie in Caso di Incendio
Sicurezza Strutturale di Gallerie in Caso di IncendioFranco Bontempi
 
Fire regulation service sector Mauritius
Fire regulation service sector MauritiusFire regulation service sector Mauritius
Fire regulation service sector MauritiusKamlesh Etwaro
 
Ensuring Safety for the Construction Workers involved in Metro Tunnelling Pro...
Ensuring Safety for the Construction Workers involved in Metro Tunnelling Pro...Ensuring Safety for the Construction Workers involved in Metro Tunnelling Pro...
Ensuring Safety for the Construction Workers involved in Metro Tunnelling Pro...IRJET Journal
 
Approccio sistemico per la sicurezza delle gallerie in caso di incendio e pro...
Approccio sistemico per la sicurezza delle gallerie in caso di incendio e pro...Approccio sistemico per la sicurezza delle gallerie in caso di incendio e pro...
Approccio sistemico per la sicurezza delle gallerie in caso di incendio e pro...Franco Bontempi Org Didattica
 
Navigating the Depths The Power of Sewer Camera Inspection.pptx
Navigating the Depths The Power of Sewer Camera Inspection.pptxNavigating the Depths The Power of Sewer Camera Inspection.pptx
Navigating the Depths The Power of Sewer Camera Inspection.pptxEco 1 Plumbing LLC
 
List of robotics projects in Horizon 2020
List of robotics projects in Horizon 2020List of robotics projects in Horizon 2020
List of robotics projects in Horizon 2020alain Clapaud
 
amTec Germany Presentation on European Flange Design Rules (EN 1591-1) & Gask...
amTec Germany Presentation on European Flange Design Rules (EN 1591-1) & Gask...amTec Germany Presentation on European Flange Design Rules (EN 1591-1) & Gask...
amTec Germany Presentation on European Flange Design Rules (EN 1591-1) & Gask...PGE India - PILOT Gaskets
 
Fire safety in Office building Literature, net and live case study
Fire safety in Office building Literature, net and live case studyFire safety in Office building Literature, net and live case study
Fire safety in Office building Literature, net and live case studyIrene Devakirubai
 
Building code sdlac_v1_0
Building code sdlac_v1_0Building code sdlac_v1_0
Building code sdlac_v1_0Jaime Céspedes
 
Modern fastening systems in tunnel construction
Modern fastening systems in tunnel constructionModern fastening systems in tunnel construction
Modern fastening systems in tunnel constructionStefan Lammert
 
Statutory requirments on Health Safety Environment
Statutory requirments on Health Safety  EnvironmentStatutory requirments on Health Safety  Environment
Statutory requirments on Health Safety EnvironmentVikasMore37
 
magnetic flux leakage inspection-en.pdf
magnetic flux leakage inspection-en.pdfmagnetic flux leakage inspection-en.pdf
magnetic flux leakage inspection-en.pdfAbinash Behera
 
Precommisioning and commissioning updated
Precommisioning and commissioning updatedPrecommisioning and commissioning updated
Precommisioning and commissioning updatedPersonal Secret
 
Nfpa fixed guideway transit and passenger rail systems
Nfpa fixed guideway transit and passenger rail systemsNfpa fixed guideway transit and passenger rail systems
Nfpa fixed guideway transit and passenger rail systemsR821992
 
Hotel - Specialised Services
Hotel - Specialised ServicesHotel - Specialised Services
Hotel - Specialised ServicesUtsavChaudhury
 

Ähnlich wie Approccio sistemico per la sicurezza delle gallerie in caso di incendio (20)

Convegno sulla Resistenza al Fuoco, Cosenza 6 Febbraio 2014, Bontempi
Convegno sulla Resistenza al Fuoco, Cosenza 6 Febbraio 2014, BontempiConvegno sulla Resistenza al Fuoco, Cosenza 6 Febbraio 2014, Bontempi
Convegno sulla Resistenza al Fuoco, Cosenza 6 Febbraio 2014, Bontempi
 
PSA - Sicurezza delle gallerie in caso di incendio
PSA - Sicurezza delle gallerie in caso di incendioPSA - Sicurezza delle gallerie in caso di incendio
PSA - Sicurezza delle gallerie in caso di incendio
 
Sicurezza Strutturale di Gallerie in Caso di Incendio
Sicurezza Strutturale di Gallerie in Caso di IncendioSicurezza Strutturale di Gallerie in Caso di Incendio
Sicurezza Strutturale di Gallerie in Caso di Incendio
 
Fire regulation service sector Mauritius
Fire regulation service sector MauritiusFire regulation service sector Mauritius
Fire regulation service sector Mauritius
 
Ensuring Safety for the Construction Workers involved in Metro Tunnelling Pro...
Ensuring Safety for the Construction Workers involved in Metro Tunnelling Pro...Ensuring Safety for the Construction Workers involved in Metro Tunnelling Pro...
Ensuring Safety for the Construction Workers involved in Metro Tunnelling Pro...
 
Approccio sistemico per la sicurezza delle gallerie in caso di incendio e pro...
Approccio sistemico per la sicurezza delle gallerie in caso di incendio e pro...Approccio sistemico per la sicurezza delle gallerie in caso di incendio e pro...
Approccio sistemico per la sicurezza delle gallerie in caso di incendio e pro...
 
Navigating the Depths The Power of Sewer Camera Inspection.pptx
Navigating the Depths The Power of Sewer Camera Inspection.pptxNavigating the Depths The Power of Sewer Camera Inspection.pptx
Navigating the Depths The Power of Sewer Camera Inspection.pptx
 
List of robotics projects in Horizon 2020
List of robotics projects in Horizon 2020List of robotics projects in Horizon 2020
List of robotics projects in Horizon 2020
 
amTec Germany Presentation on European Flange Design Rules (EN 1591-1) & Gask...
amTec Germany Presentation on European Flange Design Rules (EN 1591-1) & Gask...amTec Germany Presentation on European Flange Design Rules (EN 1591-1) & Gask...
amTec Germany Presentation on European Flange Design Rules (EN 1591-1) & Gask...
 
Fire safety in Office building Literature, net and live case study
Fire safety in Office building Literature, net and live case studyFire safety in Office building Literature, net and live case study
Fire safety in Office building Literature, net and live case study
 
Building code sdlac_v1_0
Building code sdlac_v1_0Building code sdlac_v1_0
Building code sdlac_v1_0
 
Modern fastening systems in tunnel construction
Modern fastening systems in tunnel constructionModern fastening systems in tunnel construction
Modern fastening systems in tunnel construction
 
Mdg 41 review - Gary Nauer
Mdg 41 review - Gary NauerMdg 41 review - Gary Nauer
Mdg 41 review - Gary Nauer
 
FG-OD PPT EN_Jan 2016
FG-OD PPT EN_Jan 2016 FG-OD PPT EN_Jan 2016
FG-OD PPT EN_Jan 2016
 
Statutory requirments on Health Safety Environment
Statutory requirments on Health Safety  EnvironmentStatutory requirments on Health Safety  Environment
Statutory requirments on Health Safety Environment
 
The ultimate solution of bolting technology
The ultimate solution of bolting technologyThe ultimate solution of bolting technology
The ultimate solution of bolting technology
 
magnetic flux leakage inspection-en.pdf
magnetic flux leakage inspection-en.pdfmagnetic flux leakage inspection-en.pdf
magnetic flux leakage inspection-en.pdf
 
Precommisioning and commissioning updated
Precommisioning and commissioning updatedPrecommisioning and commissioning updated
Precommisioning and commissioning updated
 
Nfpa fixed guideway transit and passenger rail systems
Nfpa fixed guideway transit and passenger rail systemsNfpa fixed guideway transit and passenger rail systems
Nfpa fixed guideway transit and passenger rail systems
 
Hotel - Specialised Services
Hotel - Specialised ServicesHotel - Specialised Services
Hotel - Specialised Services
 

Mehr von Franco Bontempi Org Didattica

II evento didattica 5 aprile 2022 TECNICA DELLE COSTRUZIONI.pdf
II evento didattica 5 aprile 2022 TECNICA DELLE COSTRUZIONI.pdfII evento didattica 5 aprile 2022 TECNICA DELLE COSTRUZIONI.pdf
II evento didattica 5 aprile 2022 TECNICA DELLE COSTRUZIONI.pdfFranco Bontempi Org Didattica
 
ICAR 09_incontro del 5 aprile 2022_secondo annuncio.pdf
ICAR 09_incontro del 5 aprile 2022_secondo annuncio.pdfICAR 09_incontro del 5 aprile 2022_secondo annuncio.pdf
ICAR 09_incontro del 5 aprile 2022_secondo annuncio.pdfFranco Bontempi Org Didattica
 
Structural health monitoring of a cable-stayed bridge with Bayesian neural ne...
Structural health monitoring of a cable-stayed bridge with Bayesian neural ne...Structural health monitoring of a cable-stayed bridge with Bayesian neural ne...
Structural health monitoring of a cable-stayed bridge with Bayesian neural ne...Franco Bontempi Org Didattica
 
Soft computing based multilevel strategy for bridge integrity monitoring
Soft computing based multilevel strategy for bridge integrity monitoringSoft computing based multilevel strategy for bridge integrity monitoring
Soft computing based multilevel strategy for bridge integrity monitoringFranco Bontempi Org Didattica
 
Systemic approach for the maintenance of complex structural systems
Systemic approach for the maintenance of complex structural systemsSystemic approach for the maintenance of complex structural systems
Systemic approach for the maintenance of complex structural systemsFranco Bontempi Org Didattica
 
The role of softening in the numerical analysis of R.C. framed structures
The role of softening in the numerical analysis of R.C. framed structuresThe role of softening in the numerical analysis of R.C. framed structures
The role of softening in the numerical analysis of R.C. framed structuresFranco Bontempi Org Didattica
 
Reliability of material and geometrically non-linear reinforced and prestress...
Reliability of material and geometrically non-linear reinforced and prestress...Reliability of material and geometrically non-linear reinforced and prestress...
Reliability of material and geometrically non-linear reinforced and prestress...Franco Bontempi Org Didattica
 
Probabilistic Service Life Assessment and Maintenance Planning of Concrete St...
Probabilistic Service Life Assessment and Maintenance Planning of Concrete St...Probabilistic Service Life Assessment and Maintenance Planning of Concrete St...
Probabilistic Service Life Assessment and Maintenance Planning of Concrete St...Franco Bontempi Org Didattica
 
Cellular Automata Approach to Durability Analysis of Concrete Structures in A...
Cellular Automata Approach to Durability Analysis of Concrete Structures in A...Cellular Automata Approach to Durability Analysis of Concrete Structures in A...
Cellular Automata Approach to Durability Analysis of Concrete Structures in A...Franco Bontempi Org Didattica
 
UNA FORMULAZIONE DEL DEGRADO DELLA RISPOSTA DI STRUTTURE INTELAIATE IN C.A./C...
UNA FORMULAZIONE DEL DEGRADO DELLA RISPOSTA DI STRUTTURE INTELAIATE IN C.A./C...UNA FORMULAZIONE DEL DEGRADO DELLA RISPOSTA DI STRUTTURE INTELAIATE IN C.A./C...
UNA FORMULAZIONE DEL DEGRADO DELLA RISPOSTA DI STRUTTURE INTELAIATE IN C.A./C...Franco Bontempi Org Didattica
 

Mehr von Franco Bontempi Org Didattica (20)

50 anni.Image.Marked.pdf
50 anni.Image.Marked.pdf50 anni.Image.Marked.pdf
50 anni.Image.Marked.pdf
 
4. Comportamento di elementi inflessi.pdf
4. Comportamento di elementi inflessi.pdf4. Comportamento di elementi inflessi.pdf
4. Comportamento di elementi inflessi.pdf
 
Calcolo della precompressione: DOMINI e STRAUS7
Calcolo della precompressione: DOMINI e STRAUS7Calcolo della precompressione: DOMINI e STRAUS7
Calcolo della precompressione: DOMINI e STRAUS7
 
II evento didattica 5 aprile 2022 TECNICA DELLE COSTRUZIONI.pdf
II evento didattica 5 aprile 2022 TECNICA DELLE COSTRUZIONI.pdfII evento didattica 5 aprile 2022 TECNICA DELLE COSTRUZIONI.pdf
II evento didattica 5 aprile 2022 TECNICA DELLE COSTRUZIONI.pdf
 
ICAR 09_incontro del 5 aprile 2022_secondo annuncio.pdf
ICAR 09_incontro del 5 aprile 2022_secondo annuncio.pdfICAR 09_incontro del 5 aprile 2022_secondo annuncio.pdf
ICAR 09_incontro del 5 aprile 2022_secondo annuncio.pdf
 
Structural health monitoring of a cable-stayed bridge with Bayesian neural ne...
Structural health monitoring of a cable-stayed bridge with Bayesian neural ne...Structural health monitoring of a cable-stayed bridge with Bayesian neural ne...
Structural health monitoring of a cable-stayed bridge with Bayesian neural ne...
 
Soft computing based multilevel strategy for bridge integrity monitoring
Soft computing based multilevel strategy for bridge integrity monitoringSoft computing based multilevel strategy for bridge integrity monitoring
Soft computing based multilevel strategy for bridge integrity monitoring
 
Systemic approach for the maintenance of complex structural systems
Systemic approach for the maintenance of complex structural systemsSystemic approach for the maintenance of complex structural systems
Systemic approach for the maintenance of complex structural systems
 
Elenco studenti esaminandi
Elenco studenti esaminandiElenco studenti esaminandi
Elenco studenti esaminandi
 
Costruzione di ponti in cemento armato.
Costruzione di ponti in cemento armato.Costruzione di ponti in cemento armato.
Costruzione di ponti in cemento armato.
 
Costruzione di ponti in acciaio
Costruzione di ponti in acciaioCostruzione di ponti in acciaio
Costruzione di ponti in acciaio
 
Costruzione di Ponti - Ceradini
Costruzione di Ponti - CeradiniCostruzione di Ponti - Ceradini
Costruzione di Ponti - Ceradini
 
The role of softening in the numerical analysis of R.C. framed structures
The role of softening in the numerical analysis of R.C. framed structuresThe role of softening in the numerical analysis of R.C. framed structures
The role of softening in the numerical analysis of R.C. framed structures
 
Reliability of material and geometrically non-linear reinforced and prestress...
Reliability of material and geometrically non-linear reinforced and prestress...Reliability of material and geometrically non-linear reinforced and prestress...
Reliability of material and geometrically non-linear reinforced and prestress...
 
Probabilistic Service Life Assessment and Maintenance Planning of Concrete St...
Probabilistic Service Life Assessment and Maintenance Planning of Concrete St...Probabilistic Service Life Assessment and Maintenance Planning of Concrete St...
Probabilistic Service Life Assessment and Maintenance Planning of Concrete St...
 
Cellular Automata Approach to Durability Analysis of Concrete Structures in A...
Cellular Automata Approach to Durability Analysis of Concrete Structures in A...Cellular Automata Approach to Durability Analysis of Concrete Structures in A...
Cellular Automata Approach to Durability Analysis of Concrete Structures in A...
 
UNA FORMULAZIONE DEL DEGRADO DELLA RISPOSTA DI STRUTTURE INTELAIATE IN C.A./C...
UNA FORMULAZIONE DEL DEGRADO DELLA RISPOSTA DI STRUTTURE INTELAIATE IN C.A./C...UNA FORMULAZIONE DEL DEGRADO DELLA RISPOSTA DI STRUTTURE INTELAIATE IN C.A./C...
UNA FORMULAZIONE DEL DEGRADO DELLA RISPOSTA DI STRUTTURE INTELAIATE IN C.A./C...
 
Esami a distanza. Severgnini. Corriere della sera.
Esami a distanza. Severgnini. Corriere della sera.Esami a distanza. Severgnini. Corriere della sera.
Esami a distanza. Severgnini. Corriere della sera.
 
Tdc prova 2022 01-26
Tdc prova 2022 01-26Tdc prova 2022 01-26
Tdc prova 2022 01-26
 
Risultati
RisultatiRisultati
Risultati
 

Kürzlich hochgeladen

Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon AUnboundStockton
 
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991RKavithamani
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfsanyamsingh5019
 
URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppCeline George
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentInMediaRes1
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdfSoniaTolstoy
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsanshu789521
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxiammrhaywood
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptxVS Mahajan Coaching Centre
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxGaneshChakor2
 
Micromeritics - Fundamental and Derived Properties of Powders
Micromeritics - Fundamental and Derived Properties of PowdersMicromeritics - Fundamental and Derived Properties of Powders
Micromeritics - Fundamental and Derived Properties of PowdersChitralekhaTherkar
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxheathfieldcps1
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxNirmalaLoungPoorunde1
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...EduSkills OECD
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Sapana Sha
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introductionMaksud Ahmed
 
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting DataJhengPantaleon
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3JemimahLaneBuaron
 

Kürzlich hochgeladen (20)

Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon A
 
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdf
 
URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website App
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media Component
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha elections
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
 
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdfTataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptx
 
Micromeritics - Fundamental and Derived Properties of Powders
Micromeritics - Fundamental and Derived Properties of PowdersMicromeritics - Fundamental and Derived Properties of Powders
Micromeritics - Fundamental and Derived Properties of Powders
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptx
 
Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introduction
 
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3
 

Approccio sistemico per la sicurezza delle gallerie in caso di incendio