Introduction
5 July, 20162
1. What is a variation?
2. Why have a variation clause?
3. Do I have a variation?
a) Is the instruction outside of the scope of the Works?
b) Was the variation instructed 'correctly'?
4. When variations become necessary
a) Contractor's wider obligations
b) Other 'necessary' variations
5. Procedures for varying Works
6. Anti-oral variations
7. Agency
8. Omitting work
|
What is a variation?
constructiveblog.com3
• In a construction context - a change to the Works to be carried out under the
building contract
• Includes any change to the Works':
• quantity,
• quality, and/or
• (potentially) sequencing
|
What is a variation? – JCT Definition
constructiveblog.com4
JCT Intermediate Building Contract with contractor's design 2011
5.1 The term ‘Variation’ means:
5.1·1 the alteration or modification of the design, quality or quantity of the Works
including:
5.1.1.1 the addition, omission or substitution of any work;
5.1.1.2 the alteration of the kind or standard of any of the materials or goods
to be used in the Works;
5.1.1.3 the removal from the site of any work executed or Site Materials other
than work, materials or goods which are not in accordance with this Contract
(continued)
|
What is a variation? – JCT Definition continued
constructiveblog.com5
5.1.2 the imposition by the Employer of any obligations or restrictions in regard to the
matters set out in this clause 5·1·2 or the addition to or alteration or omission of any
such obligations or restrictions so imposed or imposed by the Employer in the
Contract Documents in regard to:
5.1.2.1 access to the site or use of any specific parts of the site;
5.1.2.2 limitations of working space;
5.1.2.3 limitations of working hours; or
5.1.2.4 the execution or completion of the work in any specific order."
• Defined as a 'Change' under the JCT Design and Build 2011
• JCT Minor Works contracts 2016
|
Why have a variation clause?
constructiveblog.com6
• Preserves the contract while allowing changes, which are often inevitable in long
term contracts. It therefore gives the Employer the flexibility to make changes so
that it can get the product it wants, within the timescale it requires and potentially
at the same or similar prices to that already agreed.
• Ensures that the contract is not frustrated, if it is impossible to carry out the
previously agreed work.
|
Do I have a variation? Ambiguity in the scope of works (1)
constructiveblog.com7
• Disputes often occur over whether or not particular works instructed by or on behalf
of the Employer already form part of the Works
• Contradictions between the different technical documents or gaps in what they are
describing can lead to uncertainty as to how the scope should be interpreted
• Generally speaking, to be included within the contract, work must be described in
some part of the contract documents, or be reasonably inferred from those
documents
• Important to consider the precise wording of the underlying requirement to carry out
the Works, as there may be differences in how "all encompassing" such wording
might be
|
Do I have a variation? Ambiguity in the scope of works (2)
and entitlement to payment
constructiveblog.com8
• Contract itself will typically provide some assistance as to how discrepancies are
resolved (such as a priorities clause) but common law principles of contract
interpretation will apply
• Entitlement to payment
• No automatic entitlement
• The contractor will have to show that, on a true construction of the contract, there is an
express or implied right to payment for the variation in question. That is:
• The work was outside the scope of the work the contractor agreed to carry out for the
contract sum; and
• The employer needs to have expressly or impliedly agreed to pay for it
• If the change to the scope is required because of a risk for which the contractor is
responsible then the Employer will not expect to pay for the variation
• Depends on the facts of the case
|
When variations become necessary - contractor’s wider
contractual obligations
constructiveblog.com9
• The Contractor may be obliged to undertake additional or altered works either in
order to satisfy its obligations as to the performance of the project or because it has
taken the risk in relation to certain risks arising, such as the discovery of
unexpected ground conditions
• Fitness for purpose warranty - where the technical scope is inadequate to achieve
the performance warranties something has to be changed. The Contractor will
otherwise be in breach
• MT Højgaard A/s v E.ON Climate and Renewables even though the scope of works
didn't achieve a specific performance, the Contractor had provided a 'fitness for
purpose' warranty – the Contractor was therefore obliged to expand the scope of
the works so as not to be in breach of the warranty
|
When variations become necessary – other 'necessary'
variations
constructiveblog.com10
• Change to the statutory regime (e.g. Building Regulations)
• The correction of errors in the description of the Works
• Situations may arise under a JCT Standard Building Contract with quantities
2011 where items of work that are required to be undertaken (and shown on the
drawings) are not included in the bill of quantities. Clause 2.14.1 states that
omission of such items will be automatically corrected and will be treated as a
variation (clause 2.14.3)
• Under the JCT Design and Build 2011, if a design error is identified in the
Employer’s Requirements then the Employer’s Requirements are treated as
being altered, unless the contractor has taken on responsibility for/ is warranting
the accuracy of the ERs…
|
Do I have a variation? Ambiguity in the instruction
constructiveblog.com11
• Was the varied work a change to the original contract or did it create a fresh
contract?
• Was the work ordered within the scope of the variations clause?
• Were the notice provisions (if there are any) complied with?
• Were the notice provisions a condition precedent?
• Not necessarily required to include information in the notice of which the other party is
already aware (Walter Lilly v Mackay)
• Does failure to comply with the notice provisions imply that the party varying the
contract didn't really mean to do so (an 'accidental' variation)?
• Can it be argued that the employer has waived any notice requirements or is
estopped from insisting on compliance with them?
|
Procedures for variation
constructiveblog.com12
• Depends on the wording in your contract, but it is best practice to deal with all
variations in writing
Clause 3.12.1 of the JCT Standard Building Contract with Quantities 2011 Edition
reads:
“Where the… Contract Administrator issues an instruction otherwise than in writing, it shall
be of no immediate effect but the Contractor shall confirm it in writing to the… Contract
Administrator within 7 days, and, if he does not dissent by notice to the Contractor within 7
days from receipt of the Contractor’s confirmation, it shall take effect as from the expiry of
the latter 7 day period.”
|
What is an Anti-Oral Variation Clause?
5 July, 201613
• Seeks to restrict any amendments to the agreement only to those variations agreed
by the parties in writing
• Often found in or alongside an 'entire agreement' clause. Subtle distinction.
• "No variation of this agreement shall be effective unless it is in writing and signed by the
parties (or their authorised representatives)."
|
Why use an Anti-Oral Variation Clause?
5 July, 201614
• Variations can be made either orally or also by conduct
• To exclude the possibility of informal or inadvertent variations being made to the
agreement
• Designed to prevent disputes arising out of informal exchanges that may waive
particular requirements, change deadlines etc.
• Historic position on AOV clauses traditionally unclear:
• United Bank Ltd v Asif - no oral variation of the written terms could have any legal effect
• World Online Telecom Ltd v I-Way - "[i]n a case like the present the parties have made
their own law by contracting, and can in principle unmake or remake it"
|
Globe Motors Inc v TRW Lucas Variety Electric Steering Ltd
[2016] (1)
5 July, 201615
• Contained the following clause:
"6.3 Entire Agreement; Amendment
This Agreement, which includes the Appendices hereto, is the only agreement between
the Parties relating to the subject matter hereof. It can only be amended by a written
document which (i) specifically refers to the provision of this Agreement to be amended
and (ii) is signed by both Parties."
• Court of Appeal addressed the conflicting case law of the past:
• "The parties have freedom to agree whatever terms they choose to undertake, and can
do so in a document, by word of mouth, or by conduct. The consequence in this context
is that in principle the fact that the parties' contract contains a clause such as Article 6.3
does not prevent them from later making a new contract varying the contract by an oral
agreement or by conduct."
|
Globe Motors Inc v TRW Lucas Variety Electric Steering Ltd
[2016] (2)
5 July, 201616
"The governing principle, in my view, is that of party autonomy. The principle of
freedom of contract entitles parties to agree [upon] whatever terms they choose,
subject to certain limits imposed by public policy ... The parties are therefore free to
include terms regulating the manner in which the contract can be varied, but just as
they can create obligations at will, so also can they discharge or vary them, at any
rate where to do so would not affect the rights of third parties. If there is an analogy
with the position of Parliament, it is in the principle that Parliament cannot bind its
successors."
|
What does this all mean?
14 June 201617
• Clarification but still only obiter commentary…
• Principle of freedom of contract has been favoured
over any policy arguments (i.e. promote certainty /
avoid frivolous claims of oral agreements)
• Never assume an anti-oral variation clause will be
effective
• Are anti-oral variation clauses effectively
pointless? No…
• Still have value for two reasons:
• Evidentiary value – harder to establish a variation
• Practical value – encourages good practices
|
Time bars to claims
constructiveblog.com18
• 20.1 of the FIDIC Conditions: if a contractor wishes to claim an extension of time
or additional payment it must give notice no later than 28 days after it became
aware, or should have become aware, of the event or circumstances giving rise to
any such claim
• NEC 3rd Clause 61.3: Contractor notifies PM within 8 weeks of becoming aware of
an event which has happened or which he expects to happen
|
Agency - who authorised the variation?
constructiveblog.com19
• A contract administrator acts as the employer’s agent when it orders additional or
changed works on its behalf
• The law of agency governs the instruction of variations and the contractor needs to
be alive to the question of whether the agent is acting with the principal’s (the
employer's) authorisation
• The contract between the employer and the contract administrator will often set
down limits and procedures for instructing changes
• If the contract administrator instructs a variation outside the limits of its discretion
(and it has not obtained express employer consent) then it is in breach of contract.
In those circumstances:
• The unauthorised instruction will bind the employer to pay the contractor on the basis of
the ostensible agency principle.
• The employer’s remedy is against the contract administrator, who will be in breach of its
obligations and therefore liable to compensate the employer for the additional project
costs incurred
|
Valuing a variation
constructiveblog.com20
• The contract may contain a mechanism to value the variation.
• For example, under clause 5.2.1 of the JCT SBC11 with quantities and with
approximate quantities, the value of any variation "shall be such amount as is
agreed by the Employer and the Contractor or, where not agreed... valued by the
Quantity Surveyor" in accordance with the valuation rules of the contract
• This contract also contains an alternative mechanism for valuation, where the
contract administrator may ask the contractor to submit a "Variation Quotation"
when the variation is instructed. If the quotation is accepted by the contract
administrator, it takes the place of a valuation under the valuation rules
• For other JCT forms, the concept of a "Variation Quotation" does not exist, but the
valuation rules are nevertheless set out expressly
|
Omitting Work (1)
constructiveblog.com21
• Usually the case that a contractor is entitled to perform all the contract work
• Contract clauses that permit omissions generally address situations where the
employer does not wish to have the work carried out at all, as opposed to where
the employer wants to take work away from the contractor and engage another
contractor to carry it out
• However, where the contract carries a power for the employer to order additional
work, there is no implied term that if the employer requires additional work, it must
employ the contractor to carry it out
• AMEC Building Ltd v Cadmus Investment Company The architect instructed the
omission of certain fitting out work covered by a provisional sum in the contract.
The court held that withdrawal was arbitrary and the contractor should be
compensated
|
Omitting Work (2)
constructiveblog.com22
• Abbey Developments Ltd v PP Brickwork Ltd The court held that the contractor had
a duty to carry out the work it contracted to do and a corresponding right to be able
to do so. Variation provisions of contracts that allow an employer to vary the work
should be construed carefully so as not to allow the contractor to be deprived of its
opportunity to carry out the work
• Trustees of Stratfield Saye Estate v AHL Construction One week into the works, the
employer cancelled the works. The contractor started an adjudication for
compensation for cancellation of the works. While the issue of enforceability of the
adjudicator's award was before the court, it also considered whether there was a
contract for a defined scope of work. The court approved Abbey Developments and
held that the employer's power to omit works was limited. The employer could not
change the basic nature of works by omission
|
For more information please contact
Olswang:
Changing Business.
www.olswang.com
Gareth (ap) Morgan
+44 20 7067 3535
gareth.ap.morgan@olswang.com
Louise Forbes
+44 20 7067 3632
louise.forbes@olswang.com
Brussels
+32 2 647 4772
London
+44 20 7067 3000
Madrid
+34 91 187 1920
Munich
+49 89 206 028 400
Singapore
+65 6720 8278
Paris
+33 17 091 8720
Thames Valley
+44 20 7071 7300

Weitere ähnliche Inhalte

Was ist angesagt?

GCC2015 Course_Day2
GCC2015 Course_Day2GCC2015 Course_Day2
GCC2015 Course_Day2JB Nartey
 
Fidic contracts 2017 - Notable Changes
Fidic contracts 2017 - Notable ChangesFidic contracts 2017 - Notable Changes
Fidic contracts 2017 - Notable ChangesCNC
 
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias TanFIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias TanAdrias TAN
 
Variations in works contracts
Variations in works contractsVariations in works contracts
Variations in works contractsDr K M SONI
 
Construction Claims Explained
Construction Claims ExplainedConstruction Claims Explained
Construction Claims Explainedclaimsconsultancy
 
Ss training fidic moustafa ismail 2017 _ lec. 1
Ss training fidic moustafa ismail  2017 _ lec. 1Ss training fidic moustafa ismail  2017 _ lec. 1
Ss training fidic moustafa ismail 2017 _ lec. 1Moustafa Ismail Abu Dief
 
EOT Related Cost Compensation Determination
EOT Related Cost Compensation DeterminationEOT Related Cost Compensation Determination
EOT Related Cost Compensation DeterminationVimal Daluwatta
 
FIDIC SIlver Book in Power Projects
FIDIC SIlver Book in Power ProjectsFIDIC SIlver Book in Power Projects
FIDIC SIlver Book in Power ProjectsFrancis Ho
 
Contract payment and variation
Contract payment and variationContract payment and variation
Contract payment and variationVj NiroSh
 
PP2 Seminar - Determination of Contractor's Employment by Employer
PP2 Seminar - Determination of Contractor's Employment by EmployerPP2 Seminar - Determination of Contractor's Employment by Employer
PP2 Seminar - Determination of Contractor's Employment by EmployerTrace96
 
#FIDIC Understanding Basics# By SN Panigrahi
#FIDIC Understanding Basics# By SN Panigrahi#FIDIC Understanding Basics# By SN Panigrahi
#FIDIC Understanding Basics# By SN PanigrahiSN Panigrahi, PMP
 
Commercial and Legal Aspects of Liquidated Damages and Penalties
Commercial and Legal Aspects of Liquidated Damages and PenaltiesCommercial and Legal Aspects of Liquidated Damages and Penalties
Commercial and Legal Aspects of Liquidated Damages and PenaltiesAMILA GAYAN
 
Extension of time in construction contracts
Extension of time in construction contractsExtension of time in construction contracts
Extension of time in construction contractsKheng Hoe Advocates
 
Fidic conditions of contract presentation
Fidic conditions of contract presentationFidic conditions of contract presentation
Fidic conditions of contract presentationJeff B
 

Was ist angesagt? (20)

Cl presentation
Cl presentationCl presentation
Cl presentation
 
GCC2015 Course_Day2
GCC2015 Course_Day2GCC2015 Course_Day2
GCC2015 Course_Day2
 
Fidic contracts 2017 - Notable Changes
Fidic contracts 2017 - Notable ChangesFidic contracts 2017 - Notable Changes
Fidic contracts 2017 - Notable Changes
 
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias TanFIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
 
FIDIC 2017 Yellow and Silver in EPC and PPP Contracts
FIDIC 2017 Yellow and Silver in EPC and PPP ContractsFIDIC 2017 Yellow and Silver in EPC and PPP Contracts
FIDIC 2017 Yellow and Silver in EPC and PPP Contracts
 
Variations in works contracts
Variations in works contractsVariations in works contracts
Variations in works contracts
 
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
Extension of Time (EOT) & Related Costs in Construction - Presentation SlidesExtension of Time (EOT) & Related Costs in Construction - Presentation Slides
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
 
Construction Claims Explained
Construction Claims ExplainedConstruction Claims Explained
Construction Claims Explained
 
Fundamentals of Construction Contracts - English, ver. 2021
Fundamentals of Construction Contracts - English, ver. 2021Fundamentals of Construction Contracts - English, ver. 2021
Fundamentals of Construction Contracts - English, ver. 2021
 
Ss training fidic moustafa ismail 2017 _ lec. 1
Ss training fidic moustafa ismail  2017 _ lec. 1Ss training fidic moustafa ismail  2017 _ lec. 1
Ss training fidic moustafa ismail 2017 _ lec. 1
 
EOT Related Cost Compensation Determination
EOT Related Cost Compensation DeterminationEOT Related Cost Compensation Determination
EOT Related Cost Compensation Determination
 
FIDIC SIlver Book in Power Projects
FIDIC SIlver Book in Power ProjectsFIDIC SIlver Book in Power Projects
FIDIC SIlver Book in Power Projects
 
Fidic contracts management introduction
Fidic contracts management introductionFidic contracts management introduction
Fidic contracts management introduction
 
Contract payment and variation
Contract payment and variationContract payment and variation
Contract payment and variation
 
PP2 Seminar - Determination of Contractor's Employment by Employer
PP2 Seminar - Determination of Contractor's Employment by EmployerPP2 Seminar - Determination of Contractor's Employment by Employer
PP2 Seminar - Determination of Contractor's Employment by Employer
 
An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...
An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...
An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...
 
#FIDIC Understanding Basics# By SN Panigrahi
#FIDIC Understanding Basics# By SN Panigrahi#FIDIC Understanding Basics# By SN Panigrahi
#FIDIC Understanding Basics# By SN Panigrahi
 
Commercial and Legal Aspects of Liquidated Damages and Penalties
Commercial and Legal Aspects of Liquidated Damages and PenaltiesCommercial and Legal Aspects of Liquidated Damages and Penalties
Commercial and Legal Aspects of Liquidated Damages and Penalties
 
Extension of time in construction contracts
Extension of time in construction contractsExtension of time in construction contracts
Extension of time in construction contracts
 
Fidic conditions of contract presentation
Fidic conditions of contract presentationFidic conditions of contract presentation
Fidic conditions of contract presentation
 

Ähnlich wie Variations and their Consequences - Olswang Construction Law Masterclass - 5 July 2016

Variation: it’s Regulation & Management under the MDB-FIDIC (2006) & the PPA ...
Variation: it’s Regulation & Management under the MDB-FIDIC (2006) & the PPA ...Variation: it’s Regulation & Management under the MDB-FIDIC (2006) & the PPA ...
Variation: it’s Regulation & Management under the MDB-FIDIC (2006) & the PPA ...MMS presentation firm
 
CCDC2 - A Focus on 3 Topics Using Case Studies
CCDC2 - A Focus on 3 Topics Using Case StudiesCCDC2 - A Focus on 3 Topics Using Case Studies
CCDC2 - A Focus on 3 Topics Using Case StudiesSamantha Ip
 
Construction Law - Presentation - Construction Contractual Claims
Construction Law - Presentation - Construction Contractual ClaimsConstruction Law - Presentation - Construction Contractual Claims
Construction Law - Presentation - Construction Contractual ClaimsYee Len Wan
 
Extra Work, Changes and Termination of the Contract
Extra Work, Changes and Termination of the ContractExtra Work, Changes and Termination of the Contract
Extra Work, Changes and Termination of the ContractSHKLaw
 
Construction Law Presentation
Construction Law PresentationConstruction Law Presentation
Construction Law Presentationelliotfus
 
Planning and development club - May 2017, Nottingham
Planning and development club - May 2017, NottinghamPlanning and development club - May 2017, Nottingham
Planning and development club - May 2017, NottinghamBrowne Jacobson LLP
 
Legal Implications And Pitfalls Of Drafting Technical Documentation
Legal Implications And Pitfalls Of Drafting Technical DocumentationLegal Implications And Pitfalls Of Drafting Technical Documentation
Legal Implications And Pitfalls Of Drafting Technical Documentationlisaabe
 
05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITIONByishimoBTCChef
 
Terminating a Construction Contract: Getting it Right
Terminating a Construction Contract: Getting it RightTerminating a Construction Contract: Getting it Right
Terminating a Construction Contract: Getting it RightFrancis Ho
 
Construction contract
Construction contract Construction contract
Construction contract Rakshith Reddy
 
Top 20 Standard Contract Clauses Every Manager Should Know
Top 20 Standard Contract Clauses Every Manager Should KnowTop 20 Standard Contract Clauses Every Manager Should Know
Top 20 Standard Contract Clauses Every Manager Should KnowSHAZEBALIKHAN1
 
CONTRACT ADMINISTRATION Updated.pptx
CONTRACT ADMINISTRATION Updated.pptxCONTRACT ADMINISTRATION Updated.pptx
CONTRACT ADMINISTRATION Updated.pptxAditya Mane
 
2017 Annual IFRS Update
2017 Annual IFRS Update2017 Annual IFRS Update
2017 Annual IFRS UpdatePaul Rhodes
 
Post Award Requirements and Issues Change Orders 2012 fedcon
Post Award Requirements and Issues Change Orders 2012 fedconPost Award Requirements and Issues Change Orders 2012 fedcon
Post Award Requirements and Issues Change Orders 2012 fedconNC Military Business Center
 
FM Forum - Termination & TUPE
FM Forum - Termination & TUPEFM Forum - Termination & TUPE
FM Forum - Termination & TUPELewis Silkin
 

Ähnlich wie Variations and their Consequences - Olswang Construction Law Masterclass - 5 July 2016 (20)

Variation: it’s Regulation & Management under the MDB-FIDIC (2006) & the PPA ...
Variation: it’s Regulation & Management under the MDB-FIDIC (2006) & the PPA ...Variation: it’s Regulation & Management under the MDB-FIDIC (2006) & the PPA ...
Variation: it’s Regulation & Management under the MDB-FIDIC (2006) & the PPA ...
 
TOPIC7.pdf
TOPIC7.pdfTOPIC7.pdf
TOPIC7.pdf
 
CCDC2 - A Focus on 3 Topics Using Case Studies
CCDC2 - A Focus on 3 Topics Using Case StudiesCCDC2 - A Focus on 3 Topics Using Case Studies
CCDC2 - A Focus on 3 Topics Using Case Studies
 
Construction Law - Presentation - Construction Contractual Claims
Construction Law - Presentation - Construction Contractual ClaimsConstruction Law - Presentation - Construction Contractual Claims
Construction Law - Presentation - Construction Contractual Claims
 
Extra Work, Changes and Termination of the Contract
Extra Work, Changes and Termination of the ContractExtra Work, Changes and Termination of the Contract
Extra Work, Changes and Termination of the Contract
 
Construction Law Presentation
Construction Law PresentationConstruction Law Presentation
Construction Law Presentation
 
Planning and development club - May 2017, Nottingham
Planning and development club - May 2017, NottinghamPlanning and development club - May 2017, Nottingham
Planning and development club - May 2017, Nottingham
 
Implications of different_types_of_variation_under_fidic_1999_redbook
Implications of different_types_of_variation_under_fidic_1999_redbookImplications of different_types_of_variation_under_fidic_1999_redbook
Implications of different_types_of_variation_under_fidic_1999_redbook
 
Evergreen Clause Fundamentals
Evergreen Clause FundamentalsEvergreen Clause Fundamentals
Evergreen Clause Fundamentals
 
Legal Implications And Pitfalls Of Drafting Technical Documentation
Legal Implications And Pitfalls Of Drafting Technical DocumentationLegal Implications And Pitfalls Of Drafting Technical Documentation
Legal Implications And Pitfalls Of Drafting Technical Documentation
 
Let's pick a TE&A news!
Let's pick a TE&A news! Let's pick a TE&A news!
Let's pick a TE&A news!
 
05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION
 
Terminating a Construction Contract: Getting it Right
Terminating a Construction Contract: Getting it RightTerminating a Construction Contract: Getting it Right
Terminating a Construction Contract: Getting it Right
 
Construction contract
Construction contract Construction contract
Construction contract
 
Top 20 Standard Contract Clauses Every Manager Should Know
Top 20 Standard Contract Clauses Every Manager Should KnowTop 20 Standard Contract Clauses Every Manager Should Know
Top 20 Standard Contract Clauses Every Manager Should Know
 
CONTRACT ADMINISTRATION Updated.pptx
CONTRACT ADMINISTRATION Updated.pptxCONTRACT ADMINISTRATION Updated.pptx
CONTRACT ADMINISTRATION Updated.pptx
 
Contracts and-tenders
Contracts and-tendersContracts and-tenders
Contracts and-tenders
 
2017 Annual IFRS Update
2017 Annual IFRS Update2017 Annual IFRS Update
2017 Annual IFRS Update
 
Post Award Requirements and Issues Change Orders 2012 fedcon
Post Award Requirements and Issues Change Orders 2012 fedconPost Award Requirements and Issues Change Orders 2012 fedcon
Post Award Requirements and Issues Change Orders 2012 fedcon
 
FM Forum - Termination & TUPE
FM Forum - Termination & TUPEFM Forum - Termination & TUPE
FM Forum - Termination & TUPE
 

Mehr von Francis Ho

COP26: Eating for the Planet
COP26: Eating for the PlanetCOP26: Eating for the Planet
COP26: Eating for the PlanetFrancis Ho
 
City of London Law Society - Submittal to BEIS on Statutory Retention Deposit...
City of London Law Society - Submittal to BEIS on Statutory Retention Deposit...City of London Law Society - Submittal to BEIS on Statutory Retention Deposit...
City of London Law Society - Submittal to BEIS on Statutory Retention Deposit...Francis Ho
 
City of London Law Society - Construction Law Committee - Response to Retenti...
City of London Law Society - Construction Law Committee - Response to Retenti...City of London Law Society - Construction Law Committee - Response to Retenti...
City of London Law Society - Construction Law Committee - Response to Retenti...Francis Ho
 
How will Brexit impact on Construction?
How will Brexit impact on Construction?How will Brexit impact on Construction?
How will Brexit impact on Construction?Francis Ho
 
Construction Insolvency
Construction InsolvencyConstruction Insolvency
Construction InsolvencyFrancis Ho
 
The Management of Complex Contracts
The Management of Complex ContractsThe Management of Complex Contracts
The Management of Complex ContractsFrancis Ho
 
Key Developments in Emerging Markets
Key Developments in Emerging MarketsKey Developments in Emerging Markets
Key Developments in Emerging MarketsFrancis Ho
 
Using Two-Stage Tendering Effectively
Using Two-Stage Tendering EffectivelyUsing Two-Stage Tendering Effectively
Using Two-Stage Tendering EffectivelyFrancis Ho
 
Managing the Risks of Delay in Construction Projects
Managing the Risks of Delay in Construction ProjectsManaging the Risks of Delay in Construction Projects
Managing the Risks of Delay in Construction ProjectsFrancis Ho
 
It Pays to Be Right: Payment in Construction Contracts
It Pays to Be Right: Payment in Construction ContractsIt Pays to Be Right: Payment in Construction Contracts
It Pays to Be Right: Payment in Construction ContractsFrancis Ho
 
Adjudication: Tips, Traps and Tactics
Adjudication: Tips, Traps and TacticsAdjudication: Tips, Traps and Tactics
Adjudication: Tips, Traps and TacticsFrancis Ho
 
Contractual Options for Procuring Major Projects in the UK
Contractual Options for Procuring Major Projects in the UKContractual Options for Procuring Major Projects in the UK
Contractual Options for Procuring Major Projects in the UKFrancis Ho
 
Introductory Note on International Construction Contracts
Introductory Note on International Construction ContractsIntroductory Note on International Construction Contracts
Introductory Note on International Construction ContractsFrancis Ho
 
Works Insurance and Latent Defects Insurance
Works Insurance and Latent Defects InsuranceWorks Insurance and Latent Defects Insurance
Works Insurance and Latent Defects InsuranceFrancis Ho
 
Third Party Rights and Why They Matter
Third Party Rights and Why They MatterThird Party Rights and Why They Matter
Third Party Rights and Why They MatterFrancis Ho
 
A Practical Guide to the Construction (Design and Management) Regulations 2015
A Practical Guide to the Construction (Design and Management) Regulations 2015A Practical Guide to the Construction (Design and Management) Regulations 2015
A Practical Guide to the Construction (Design and Management) Regulations 2015Francis Ho
 
Construction Dispute Resolution and Avoidance in a Boom Market
Construction Dispute Resolution and Avoidance in a Boom MarketConstruction Dispute Resolution and Avoidance in a Boom Market
Construction Dispute Resolution and Avoidance in a Boom MarketFrancis Ho
 
Letters of Intent
Letters of IntentLetters of Intent
Letters of IntentFrancis Ho
 
Collateral Warranties and Third Party Rights
Collateral Warranties and Third Party RightsCollateral Warranties and Third Party Rights
Collateral Warranties and Third Party RightsFrancis Ho
 
Early Dispute Resolution in the Construction Industry
Early Dispute Resolution in the Construction IndustryEarly Dispute Resolution in the Construction Industry
Early Dispute Resolution in the Construction IndustryFrancis Ho
 

Mehr von Francis Ho (20)

COP26: Eating for the Planet
COP26: Eating for the PlanetCOP26: Eating for the Planet
COP26: Eating for the Planet
 
City of London Law Society - Submittal to BEIS on Statutory Retention Deposit...
City of London Law Society - Submittal to BEIS on Statutory Retention Deposit...City of London Law Society - Submittal to BEIS on Statutory Retention Deposit...
City of London Law Society - Submittal to BEIS on Statutory Retention Deposit...
 
City of London Law Society - Construction Law Committee - Response to Retenti...
City of London Law Society - Construction Law Committee - Response to Retenti...City of London Law Society - Construction Law Committee - Response to Retenti...
City of London Law Society - Construction Law Committee - Response to Retenti...
 
How will Brexit impact on Construction?
How will Brexit impact on Construction?How will Brexit impact on Construction?
How will Brexit impact on Construction?
 
Construction Insolvency
Construction InsolvencyConstruction Insolvency
Construction Insolvency
 
The Management of Complex Contracts
The Management of Complex ContractsThe Management of Complex Contracts
The Management of Complex Contracts
 
Key Developments in Emerging Markets
Key Developments in Emerging MarketsKey Developments in Emerging Markets
Key Developments in Emerging Markets
 
Using Two-Stage Tendering Effectively
Using Two-Stage Tendering EffectivelyUsing Two-Stage Tendering Effectively
Using Two-Stage Tendering Effectively
 
Managing the Risks of Delay in Construction Projects
Managing the Risks of Delay in Construction ProjectsManaging the Risks of Delay in Construction Projects
Managing the Risks of Delay in Construction Projects
 
It Pays to Be Right: Payment in Construction Contracts
It Pays to Be Right: Payment in Construction ContractsIt Pays to Be Right: Payment in Construction Contracts
It Pays to Be Right: Payment in Construction Contracts
 
Adjudication: Tips, Traps and Tactics
Adjudication: Tips, Traps and TacticsAdjudication: Tips, Traps and Tactics
Adjudication: Tips, Traps and Tactics
 
Contractual Options for Procuring Major Projects in the UK
Contractual Options for Procuring Major Projects in the UKContractual Options for Procuring Major Projects in the UK
Contractual Options for Procuring Major Projects in the UK
 
Introductory Note on International Construction Contracts
Introductory Note on International Construction ContractsIntroductory Note on International Construction Contracts
Introductory Note on International Construction Contracts
 
Works Insurance and Latent Defects Insurance
Works Insurance and Latent Defects InsuranceWorks Insurance and Latent Defects Insurance
Works Insurance and Latent Defects Insurance
 
Third Party Rights and Why They Matter
Third Party Rights and Why They MatterThird Party Rights and Why They Matter
Third Party Rights and Why They Matter
 
A Practical Guide to the Construction (Design and Management) Regulations 2015
A Practical Guide to the Construction (Design and Management) Regulations 2015A Practical Guide to the Construction (Design and Management) Regulations 2015
A Practical Guide to the Construction (Design and Management) Regulations 2015
 
Construction Dispute Resolution and Avoidance in a Boom Market
Construction Dispute Resolution and Avoidance in a Boom MarketConstruction Dispute Resolution and Avoidance in a Boom Market
Construction Dispute Resolution and Avoidance in a Boom Market
 
Letters of Intent
Letters of IntentLetters of Intent
Letters of Intent
 
Collateral Warranties and Third Party Rights
Collateral Warranties and Third Party RightsCollateral Warranties and Third Party Rights
Collateral Warranties and Third Party Rights
 
Early Dispute Resolution in the Construction Industry
Early Dispute Resolution in the Construction IndustryEarly Dispute Resolution in the Construction Industry
Early Dispute Resolution in the Construction Industry
 

Kürzlich hochgeladen

Low Rate ✨➥9582086666▻✨Call Girls In Gurgaon Sector 21 (Gurgaon)
Low Rate ✨➥9582086666▻✨Call Girls In Gurgaon Sector 21 (Gurgaon)Low Rate ✨➥9582086666▻✨Call Girls In Gurgaon Sector 21 (Gurgaon)
Low Rate ✨➥9582086666▻✨Call Girls In Gurgaon Sector 21 (Gurgaon)delhi24hrs1
 
Yedi Mavi TOBB Zeytinburnu - Listing Turkey
Yedi Mavi TOBB Zeytinburnu - Listing TurkeyYedi Mavi TOBB Zeytinburnu - Listing Turkey
Yedi Mavi TOBB Zeytinburnu - Listing TurkeyListing Turkey
 
Kohinoor Courtyard One Wakad Pune | Elegant Living Spaces
Kohinoor Courtyard One Wakad Pune | Elegant Living SpacesKohinoor Courtyard One Wakad Pune | Elegant Living Spaces
Kohinoor Courtyard One Wakad Pune | Elegant Living Spacesaidasheikh47
 
BPTP THE AMAARIO Luxury Project Invest Like Royalty in Sector 37D Gurgaon Dwa...
BPTP THE AMAARIO Luxury Project Invest Like Royalty in Sector 37D Gurgaon Dwa...BPTP THE AMAARIO Luxury Project Invest Like Royalty in Sector 37D Gurgaon Dwa...
BPTP THE AMAARIO Luxury Project Invest Like Royalty in Sector 37D Gurgaon Dwa...ApartmentWala1
 
Call girls in Shakti Nagar Delhi~8447779280°/=@/ Short 1500 Night 6000}ESCORT...
Call girls in Shakti Nagar Delhi~8447779280°/=@/ Short 1500 Night 6000}ESCORT...Call girls in Shakti Nagar Delhi~8447779280°/=@/ Short 1500 Night 6000}ESCORT...
Call girls in Shakti Nagar Delhi~8447779280°/=@/ Short 1500 Night 6000}ESCORT...asmaqueen5
 
Explore Dual Citizenship in Africa | Citizenship Benefits & Requirements
Explore Dual Citizenship in Africa | Citizenship Benefits & RequirementsExplore Dual Citizenship in Africa | Citizenship Benefits & Requirements
Explore Dual Citizenship in Africa | Citizenship Benefits & Requirementsmarketingkingdomofku
 
Call Girls In Sarai Rohilla ☎️8447779280{Sarai Rohilla Escort Service In Delh...
Call Girls In Sarai Rohilla ☎️8447779280{Sarai Rohilla Escort Service In Delh...Call Girls In Sarai Rohilla ☎️8447779280{Sarai Rohilla Escort Service In Delh...
Call Girls In Sarai Rohilla ☎️8447779280{Sarai Rohilla Escort Service In Delh...asmaqueen5
 
Jaipur Escorts 🥰 8617370543 Call Girls Offer VIP Hot Girls
Jaipur Escorts 🥰 8617370543 Call Girls Offer VIP Hot GirlsJaipur Escorts 🥰 8617370543 Call Girls Offer VIP Hot Girls
Jaipur Escorts 🥰 8617370543 Call Girls Offer VIP Hot GirlsDeepika Singh
 
Retail Space for Lease - 1221 W. Main St., Sun Prairie, WI
Retail Space for Lease - 1221 W. Main St., Sun Prairie, WIRetail Space for Lease - 1221 W. Main St., Sun Prairie, WI
Retail Space for Lease - 1221 W. Main St., Sun Prairie, WILee & Associates of Madison, WI
 
Ganga Platinum Kharadi Pune brochure.pdf
Ganga Platinum Kharadi Pune brochure.pdfGanga Platinum Kharadi Pune brochure.pdf
Ganga Platinum Kharadi Pune brochure.pdfsabhyara24
 
Best Interior Design Services in Haldwani
Best Interior Design Services in HaldwaniBest Interior Design Services in Haldwani
Best Interior Design Services in HaldwaniGeomatrix
 
Call girls In Rana Pratap Bagh {Delhi ↫8447779280↬Escort Service (Delhi)
Call girls In Rana Pratap Bagh {Delhi ↫8447779280↬Escort Service (Delhi)Call girls In Rana Pratap Bagh {Delhi ↫8447779280↬Escort Service (Delhi)
Call girls In Rana Pratap Bagh {Delhi ↫8447779280↬Escort Service (Delhi)asmaqueen5
 
Low Rate ✨➥9711108085▻✨Call Girls In East Of Kailash (E.K) (Delhi)
Low Rate ✨➥9711108085▻✨Call Girls In East Of Kailash (E.K) (Delhi)Low Rate ✨➥9711108085▻✨Call Girls In East Of Kailash (E.K) (Delhi)
Low Rate ✨➥9711108085▻✨Call Girls In East Of Kailash (E.K) (Delhi)delhi24hrs1
 
Bptp The Amaario Launch Luxury Project Sector 37D Gurgaon Dwarka Expressway...
Bptp The Amaario Launch  Luxury Project  Sector 37D Gurgaon Dwarka Expressway...Bptp The Amaario Launch  Luxury Project  Sector 37D Gurgaon Dwarka Expressway...
Bptp The Amaario Launch Luxury Project Sector 37D Gurgaon Dwarka Expressway...ApartmentWala1
 
Low rate ↬Call girls in Sabzi Mandi Delhi | 8447779280}Escort Service In All ...
Low rate ↬Call girls in Sabzi Mandi Delhi | 8447779280}Escort Service In All ...Low rate ↬Call girls in Sabzi Mandi Delhi | 8447779280}Escort Service In All ...
Low rate ↬Call girls in Sabzi Mandi Delhi | 8447779280}Escort Service In All ...asmaqueen5
 
Kalpataru Exquisite Wakad Pune E-Brochure.pdf
Kalpataru Exquisite Wakad Pune  E-Brochure.pdfKalpataru Exquisite Wakad Pune  E-Brochure.pdf
Kalpataru Exquisite Wakad Pune E-Brochure.pdfManishSaxena95
 
Listing Turkey - 2024 - May Featured Portfolio
Listing Turkey - 2024 - May Featured PortfolioListing Turkey - 2024 - May Featured Portfolio
Listing Turkey - 2024 - May Featured PortfolioListing Turkey
 
Low Rate Call girls in Sant Nagar{Delhi }8447779280} Service Escorts In South...
Low Rate Call girls in Sant Nagar{Delhi }8447779280} Service Escorts In South...Low Rate Call girls in Sant Nagar{Delhi }8447779280} Service Escorts In South...
Low Rate Call girls in Sant Nagar{Delhi }8447779280} Service Escorts In South...asmaqueen5
 
Cheap Rate ✨➥9582086666▻✨Call Girls In Gurgaon Sector 1 (Gurgaon)
Cheap Rate ✨➥9582086666▻✨Call Girls In Gurgaon Sector 1 (Gurgaon)Cheap Rate ✨➥9582086666▻✨Call Girls In Gurgaon Sector 1 (Gurgaon)
Cheap Rate ✨➥9582086666▻✨Call Girls In Gurgaon Sector 1 (Gurgaon)delhi24hrs1
 
Rohan Harita Tathawade Pune Brochure.pdf
Rohan Harita Tathawade Pune Brochure.pdfRohan Harita Tathawade Pune Brochure.pdf
Rohan Harita Tathawade Pune Brochure.pdfabbu831446
 

Kürzlich hochgeladen (20)

Low Rate ✨➥9582086666▻✨Call Girls In Gurgaon Sector 21 (Gurgaon)
Low Rate ✨➥9582086666▻✨Call Girls In Gurgaon Sector 21 (Gurgaon)Low Rate ✨➥9582086666▻✨Call Girls In Gurgaon Sector 21 (Gurgaon)
Low Rate ✨➥9582086666▻✨Call Girls In Gurgaon Sector 21 (Gurgaon)
 
Yedi Mavi TOBB Zeytinburnu - Listing Turkey
Yedi Mavi TOBB Zeytinburnu - Listing TurkeyYedi Mavi TOBB Zeytinburnu - Listing Turkey
Yedi Mavi TOBB Zeytinburnu - Listing Turkey
 
Kohinoor Courtyard One Wakad Pune | Elegant Living Spaces
Kohinoor Courtyard One Wakad Pune | Elegant Living SpacesKohinoor Courtyard One Wakad Pune | Elegant Living Spaces
Kohinoor Courtyard One Wakad Pune | Elegant Living Spaces
 
BPTP THE AMAARIO Luxury Project Invest Like Royalty in Sector 37D Gurgaon Dwa...
BPTP THE AMAARIO Luxury Project Invest Like Royalty in Sector 37D Gurgaon Dwa...BPTP THE AMAARIO Luxury Project Invest Like Royalty in Sector 37D Gurgaon Dwa...
BPTP THE AMAARIO Luxury Project Invest Like Royalty in Sector 37D Gurgaon Dwa...
 
Call girls in Shakti Nagar Delhi~8447779280°/=@/ Short 1500 Night 6000}ESCORT...
Call girls in Shakti Nagar Delhi~8447779280°/=@/ Short 1500 Night 6000}ESCORT...Call girls in Shakti Nagar Delhi~8447779280°/=@/ Short 1500 Night 6000}ESCORT...
Call girls in Shakti Nagar Delhi~8447779280°/=@/ Short 1500 Night 6000}ESCORT...
 
Explore Dual Citizenship in Africa | Citizenship Benefits & Requirements
Explore Dual Citizenship in Africa | Citizenship Benefits & RequirementsExplore Dual Citizenship in Africa | Citizenship Benefits & Requirements
Explore Dual Citizenship in Africa | Citizenship Benefits & Requirements
 
Call Girls In Sarai Rohilla ☎️8447779280{Sarai Rohilla Escort Service In Delh...
Call Girls In Sarai Rohilla ☎️8447779280{Sarai Rohilla Escort Service In Delh...Call Girls In Sarai Rohilla ☎️8447779280{Sarai Rohilla Escort Service In Delh...
Call Girls In Sarai Rohilla ☎️8447779280{Sarai Rohilla Escort Service In Delh...
 
Jaipur Escorts 🥰 8617370543 Call Girls Offer VIP Hot Girls
Jaipur Escorts 🥰 8617370543 Call Girls Offer VIP Hot GirlsJaipur Escorts 🥰 8617370543 Call Girls Offer VIP Hot Girls
Jaipur Escorts 🥰 8617370543 Call Girls Offer VIP Hot Girls
 
Retail Space for Lease - 1221 W. Main St., Sun Prairie, WI
Retail Space for Lease - 1221 W. Main St., Sun Prairie, WIRetail Space for Lease - 1221 W. Main St., Sun Prairie, WI
Retail Space for Lease - 1221 W. Main St., Sun Prairie, WI
 
Ganga Platinum Kharadi Pune brochure.pdf
Ganga Platinum Kharadi Pune brochure.pdfGanga Platinum Kharadi Pune brochure.pdf
Ganga Platinum Kharadi Pune brochure.pdf
 
Best Interior Design Services in Haldwani
Best Interior Design Services in HaldwaniBest Interior Design Services in Haldwani
Best Interior Design Services in Haldwani
 
Call girls In Rana Pratap Bagh {Delhi ↫8447779280↬Escort Service (Delhi)
Call girls In Rana Pratap Bagh {Delhi ↫8447779280↬Escort Service (Delhi)Call girls In Rana Pratap Bagh {Delhi ↫8447779280↬Escort Service (Delhi)
Call girls In Rana Pratap Bagh {Delhi ↫8447779280↬Escort Service (Delhi)
 
Low Rate ✨➥9711108085▻✨Call Girls In East Of Kailash (E.K) (Delhi)
Low Rate ✨➥9711108085▻✨Call Girls In East Of Kailash (E.K) (Delhi)Low Rate ✨➥9711108085▻✨Call Girls In East Of Kailash (E.K) (Delhi)
Low Rate ✨➥9711108085▻✨Call Girls In East Of Kailash (E.K) (Delhi)
 
Bptp The Amaario Launch Luxury Project Sector 37D Gurgaon Dwarka Expressway...
Bptp The Amaario Launch  Luxury Project  Sector 37D Gurgaon Dwarka Expressway...Bptp The Amaario Launch  Luxury Project  Sector 37D Gurgaon Dwarka Expressway...
Bptp The Amaario Launch Luxury Project Sector 37D Gurgaon Dwarka Expressway...
 
Low rate ↬Call girls in Sabzi Mandi Delhi | 8447779280}Escort Service In All ...
Low rate ↬Call girls in Sabzi Mandi Delhi | 8447779280}Escort Service In All ...Low rate ↬Call girls in Sabzi Mandi Delhi | 8447779280}Escort Service In All ...
Low rate ↬Call girls in Sabzi Mandi Delhi | 8447779280}Escort Service In All ...
 
Kalpataru Exquisite Wakad Pune E-Brochure.pdf
Kalpataru Exquisite Wakad Pune  E-Brochure.pdfKalpataru Exquisite Wakad Pune  E-Brochure.pdf
Kalpataru Exquisite Wakad Pune E-Brochure.pdf
 
Listing Turkey - 2024 - May Featured Portfolio
Listing Turkey - 2024 - May Featured PortfolioListing Turkey - 2024 - May Featured Portfolio
Listing Turkey - 2024 - May Featured Portfolio
 
Low Rate Call girls in Sant Nagar{Delhi }8447779280} Service Escorts In South...
Low Rate Call girls in Sant Nagar{Delhi }8447779280} Service Escorts In South...Low Rate Call girls in Sant Nagar{Delhi }8447779280} Service Escorts In South...
Low Rate Call girls in Sant Nagar{Delhi }8447779280} Service Escorts In South...
 
Cheap Rate ✨➥9582086666▻✨Call Girls In Gurgaon Sector 1 (Gurgaon)
Cheap Rate ✨➥9582086666▻✨Call Girls In Gurgaon Sector 1 (Gurgaon)Cheap Rate ✨➥9582086666▻✨Call Girls In Gurgaon Sector 1 (Gurgaon)
Cheap Rate ✨➥9582086666▻✨Call Girls In Gurgaon Sector 1 (Gurgaon)
 
Rohan Harita Tathawade Pune Brochure.pdf
Rohan Harita Tathawade Pune Brochure.pdfRohan Harita Tathawade Pune Brochure.pdf
Rohan Harita Tathawade Pune Brochure.pdf
 

Variations and their Consequences - Olswang Construction Law Masterclass - 5 July 2016

  • 1. Gareth (ap) Morgan and Louise Forbes gareth.ap.morgan@olswang.com louise.forbes@olswang.com Construction Law Masterclass 5 July 2016 Variations and their consequences
  • 2. | Introduction 5 July, 20162 1. What is a variation? 2. Why have a variation clause? 3. Do I have a variation? a) Is the instruction outside of the scope of the Works? b) Was the variation instructed 'correctly'? 4. When variations become necessary a) Contractor's wider obligations b) Other 'necessary' variations 5. Procedures for varying Works 6. Anti-oral variations 7. Agency 8. Omitting work
  • 3. | What is a variation? constructiveblog.com3 • In a construction context - a change to the Works to be carried out under the building contract • Includes any change to the Works': • quantity, • quality, and/or • (potentially) sequencing
  • 4. | What is a variation? – JCT Definition constructiveblog.com4 JCT Intermediate Building Contract with contractor's design 2011 5.1 The term ‘Variation’ means: 5.1·1 the alteration or modification of the design, quality or quantity of the Works including: 5.1.1.1 the addition, omission or substitution of any work; 5.1.1.2 the alteration of the kind or standard of any of the materials or goods to be used in the Works; 5.1.1.3 the removal from the site of any work executed or Site Materials other than work, materials or goods which are not in accordance with this Contract (continued)
  • 5. | What is a variation? – JCT Definition continued constructiveblog.com5 5.1.2 the imposition by the Employer of any obligations or restrictions in regard to the matters set out in this clause 5·1·2 or the addition to or alteration or omission of any such obligations or restrictions so imposed or imposed by the Employer in the Contract Documents in regard to: 5.1.2.1 access to the site or use of any specific parts of the site; 5.1.2.2 limitations of working space; 5.1.2.3 limitations of working hours; or 5.1.2.4 the execution or completion of the work in any specific order." • Defined as a 'Change' under the JCT Design and Build 2011 • JCT Minor Works contracts 2016
  • 6. | Why have a variation clause? constructiveblog.com6 • Preserves the contract while allowing changes, which are often inevitable in long term contracts. It therefore gives the Employer the flexibility to make changes so that it can get the product it wants, within the timescale it requires and potentially at the same or similar prices to that already agreed. • Ensures that the contract is not frustrated, if it is impossible to carry out the previously agreed work.
  • 7. | Do I have a variation? Ambiguity in the scope of works (1) constructiveblog.com7 • Disputes often occur over whether or not particular works instructed by or on behalf of the Employer already form part of the Works • Contradictions between the different technical documents or gaps in what they are describing can lead to uncertainty as to how the scope should be interpreted • Generally speaking, to be included within the contract, work must be described in some part of the contract documents, or be reasonably inferred from those documents • Important to consider the precise wording of the underlying requirement to carry out the Works, as there may be differences in how "all encompassing" such wording might be
  • 8. | Do I have a variation? Ambiguity in the scope of works (2) and entitlement to payment constructiveblog.com8 • Contract itself will typically provide some assistance as to how discrepancies are resolved (such as a priorities clause) but common law principles of contract interpretation will apply • Entitlement to payment • No automatic entitlement • The contractor will have to show that, on a true construction of the contract, there is an express or implied right to payment for the variation in question. That is: • The work was outside the scope of the work the contractor agreed to carry out for the contract sum; and • The employer needs to have expressly or impliedly agreed to pay for it • If the change to the scope is required because of a risk for which the contractor is responsible then the Employer will not expect to pay for the variation • Depends on the facts of the case
  • 9. | When variations become necessary - contractor’s wider contractual obligations constructiveblog.com9 • The Contractor may be obliged to undertake additional or altered works either in order to satisfy its obligations as to the performance of the project or because it has taken the risk in relation to certain risks arising, such as the discovery of unexpected ground conditions • Fitness for purpose warranty - where the technical scope is inadequate to achieve the performance warranties something has to be changed. The Contractor will otherwise be in breach • MT Højgaard A/s v E.ON Climate and Renewables even though the scope of works didn't achieve a specific performance, the Contractor had provided a 'fitness for purpose' warranty – the Contractor was therefore obliged to expand the scope of the works so as not to be in breach of the warranty
  • 10. | When variations become necessary – other 'necessary' variations constructiveblog.com10 • Change to the statutory regime (e.g. Building Regulations) • The correction of errors in the description of the Works • Situations may arise under a JCT Standard Building Contract with quantities 2011 where items of work that are required to be undertaken (and shown on the drawings) are not included in the bill of quantities. Clause 2.14.1 states that omission of such items will be automatically corrected and will be treated as a variation (clause 2.14.3) • Under the JCT Design and Build 2011, if a design error is identified in the Employer’s Requirements then the Employer’s Requirements are treated as being altered, unless the contractor has taken on responsibility for/ is warranting the accuracy of the ERs…
  • 11. | Do I have a variation? Ambiguity in the instruction constructiveblog.com11 • Was the varied work a change to the original contract or did it create a fresh contract? • Was the work ordered within the scope of the variations clause? • Were the notice provisions (if there are any) complied with? • Were the notice provisions a condition precedent? • Not necessarily required to include information in the notice of which the other party is already aware (Walter Lilly v Mackay) • Does failure to comply with the notice provisions imply that the party varying the contract didn't really mean to do so (an 'accidental' variation)? • Can it be argued that the employer has waived any notice requirements or is estopped from insisting on compliance with them?
  • 12. | Procedures for variation constructiveblog.com12 • Depends on the wording in your contract, but it is best practice to deal with all variations in writing Clause 3.12.1 of the JCT Standard Building Contract with Quantities 2011 Edition reads: “Where the… Contract Administrator issues an instruction otherwise than in writing, it shall be of no immediate effect but the Contractor shall confirm it in writing to the… Contract Administrator within 7 days, and, if he does not dissent by notice to the Contractor within 7 days from receipt of the Contractor’s confirmation, it shall take effect as from the expiry of the latter 7 day period.”
  • 13. | What is an Anti-Oral Variation Clause? 5 July, 201613 • Seeks to restrict any amendments to the agreement only to those variations agreed by the parties in writing • Often found in or alongside an 'entire agreement' clause. Subtle distinction. • "No variation of this agreement shall be effective unless it is in writing and signed by the parties (or their authorised representatives)."
  • 14. | Why use an Anti-Oral Variation Clause? 5 July, 201614 • Variations can be made either orally or also by conduct • To exclude the possibility of informal or inadvertent variations being made to the agreement • Designed to prevent disputes arising out of informal exchanges that may waive particular requirements, change deadlines etc. • Historic position on AOV clauses traditionally unclear: • United Bank Ltd v Asif - no oral variation of the written terms could have any legal effect • World Online Telecom Ltd v I-Way - "[i]n a case like the present the parties have made their own law by contracting, and can in principle unmake or remake it"
  • 15. | Globe Motors Inc v TRW Lucas Variety Electric Steering Ltd [2016] (1) 5 July, 201615 • Contained the following clause: "6.3 Entire Agreement; Amendment This Agreement, which includes the Appendices hereto, is the only agreement between the Parties relating to the subject matter hereof. It can only be amended by a written document which (i) specifically refers to the provision of this Agreement to be amended and (ii) is signed by both Parties." • Court of Appeal addressed the conflicting case law of the past: • "The parties have freedom to agree whatever terms they choose to undertake, and can do so in a document, by word of mouth, or by conduct. The consequence in this context is that in principle the fact that the parties' contract contains a clause such as Article 6.3 does not prevent them from later making a new contract varying the contract by an oral agreement or by conduct."
  • 16. | Globe Motors Inc v TRW Lucas Variety Electric Steering Ltd [2016] (2) 5 July, 201616 "The governing principle, in my view, is that of party autonomy. The principle of freedom of contract entitles parties to agree [upon] whatever terms they choose, subject to certain limits imposed by public policy ... The parties are therefore free to include terms regulating the manner in which the contract can be varied, but just as they can create obligations at will, so also can they discharge or vary them, at any rate where to do so would not affect the rights of third parties. If there is an analogy with the position of Parliament, it is in the principle that Parliament cannot bind its successors."
  • 17. | What does this all mean? 14 June 201617 • Clarification but still only obiter commentary… • Principle of freedom of contract has been favoured over any policy arguments (i.e. promote certainty / avoid frivolous claims of oral agreements) • Never assume an anti-oral variation clause will be effective • Are anti-oral variation clauses effectively pointless? No… • Still have value for two reasons: • Evidentiary value – harder to establish a variation • Practical value – encourages good practices
  • 18. | Time bars to claims constructiveblog.com18 • 20.1 of the FIDIC Conditions: if a contractor wishes to claim an extension of time or additional payment it must give notice no later than 28 days after it became aware, or should have become aware, of the event or circumstances giving rise to any such claim • NEC 3rd Clause 61.3: Contractor notifies PM within 8 weeks of becoming aware of an event which has happened or which he expects to happen
  • 19. | Agency - who authorised the variation? constructiveblog.com19 • A contract administrator acts as the employer’s agent when it orders additional or changed works on its behalf • The law of agency governs the instruction of variations and the contractor needs to be alive to the question of whether the agent is acting with the principal’s (the employer's) authorisation • The contract between the employer and the contract administrator will often set down limits and procedures for instructing changes • If the contract administrator instructs a variation outside the limits of its discretion (and it has not obtained express employer consent) then it is in breach of contract. In those circumstances: • The unauthorised instruction will bind the employer to pay the contractor on the basis of the ostensible agency principle. • The employer’s remedy is against the contract administrator, who will be in breach of its obligations and therefore liable to compensate the employer for the additional project costs incurred
  • 20. | Valuing a variation constructiveblog.com20 • The contract may contain a mechanism to value the variation. • For example, under clause 5.2.1 of the JCT SBC11 with quantities and with approximate quantities, the value of any variation "shall be such amount as is agreed by the Employer and the Contractor or, where not agreed... valued by the Quantity Surveyor" in accordance with the valuation rules of the contract • This contract also contains an alternative mechanism for valuation, where the contract administrator may ask the contractor to submit a "Variation Quotation" when the variation is instructed. If the quotation is accepted by the contract administrator, it takes the place of a valuation under the valuation rules • For other JCT forms, the concept of a "Variation Quotation" does not exist, but the valuation rules are nevertheless set out expressly
  • 21. | Omitting Work (1) constructiveblog.com21 • Usually the case that a contractor is entitled to perform all the contract work • Contract clauses that permit omissions generally address situations where the employer does not wish to have the work carried out at all, as opposed to where the employer wants to take work away from the contractor and engage another contractor to carry it out • However, where the contract carries a power for the employer to order additional work, there is no implied term that if the employer requires additional work, it must employ the contractor to carry it out • AMEC Building Ltd v Cadmus Investment Company The architect instructed the omission of certain fitting out work covered by a provisional sum in the contract. The court held that withdrawal was arbitrary and the contractor should be compensated
  • 22. | Omitting Work (2) constructiveblog.com22 • Abbey Developments Ltd v PP Brickwork Ltd The court held that the contractor had a duty to carry out the work it contracted to do and a corresponding right to be able to do so. Variation provisions of contracts that allow an employer to vary the work should be construed carefully so as not to allow the contractor to be deprived of its opportunity to carry out the work • Trustees of Stratfield Saye Estate v AHL Construction One week into the works, the employer cancelled the works. The contractor started an adjudication for compensation for cancellation of the works. While the issue of enforceability of the adjudicator's award was before the court, it also considered whether there was a contract for a defined scope of work. The court approved Abbey Developments and held that the employer's power to omit works was limited. The employer could not change the basic nature of works by omission
  • 23. | For more information please contact Olswang: Changing Business. www.olswang.com Gareth (ap) Morgan +44 20 7067 3535 gareth.ap.morgan@olswang.com Louise Forbes +44 20 7067 3632 louise.forbes@olswang.com Brussels +32 2 647 4772 London +44 20 7067 3000 Madrid +34 91 187 1920 Munich +49 89 206 028 400 Singapore +65 6720 8278 Paris +33 17 091 8720 Thames Valley +44 20 7071 7300