4. Marco Pittaluga
FOSTEr in MED Financial Manager
F0573r 1n M3D
• Total budget: € 4.500.000
• Programme contribution: € 4.050.000 (90%)
• Project co-financing: € 450.000 (10%)
Duration: 36 + 8 months
(December 2012 - July 2016)
5. Marco Pittaluga
FOSTEr in MED Financial Manager
UNICA € 1.033.581,76
ASCAME € 459.199,27
CSPI € 346.065,25
CEEBA € 659.289,13
IRI € 651.259,98
RSS € 524.472,88
CCI € 433.516,22
RAS € 392.615,51
tot € 4.500.000,00
Suddivisione per partner
6. Marco Pittaluga
FOSTEr in MED Financial Manager
Human
Resources € 2.069.358,86
Travel € 263.378,77
Infra structures € 443.035,83
Equipments and
supplies € 17.028,59
Subcontracted
services € 1.277.197,95
Contingency € 170.126,00
Administrative
costs € 259.874,00
tot € 4.500.000,00
Suddivisione per categoria
di costo
8. Marco Pittaluga
FOSTEr in MED Financial Manager
Meetings and events
• 1 Kick off Conference
• 7 Management and coordination meetings
• 2 Context Analisys Workshops
• 4 Technical and Scientific Committee meetings
• 1 Territorial Animation Workshop
• 3 Communication and Capitalization Conferences
• 1 Final Conference
• 1 Pilot Projects presentation conference
• 18 Training Paths – 540 hrs – 450 people
• 60 school seminars
13. Marco Pittaluga
FOSTEr in MED Financial Manager
Partnerhip involvement and
concept note drafting: June
2011
14. Marco Pittaluga
FOSTEr in MED Financial Manager
Partnerhip involvement and
concept note drafting: June
2011
June 2011 – June 2016
•Sent E-mail: 10933
•Received E-mail: 6984