Contents
 Introduction
 Features
 Comparison
 Design concept
 Components
 Types of precast
system
 Design
consideration
 Equipments
 Assembling
 scheduling
 Advantages
 Limitations
 Conclusion
 references
2
Introduction
 The concept of precast structures also known
as prefabricated/ modular structures.
 The structural components are standardized
and produced in plants in a location away
from the building site.
 Then transported to the site for assembly.
 The components are manufactured by
industrial methods based on mass production
in order to build a large number of buildings
in a short time at low cost.
3
Features
 The division and specialization of the human
workforce.
 The use of tools, machinery, and other
equipment, usually automated, in the
production of standard, interchangeable parts
and products.
 Compared to site-cast concrete, precast
concrete erection is faster and less affected by
adverse weather conditions.
 Plant casting allows increased efficiency, high
quality control and greater control on finishes.
4
Comparison
Site-cast
 no transportation
 the size limitation is
depending on the
elevation capacity only
 lower quality because
directly affected by
weather
 proper, large free space
required
Precast at plant
 transportation and
elevation capacity limits
the size-
 higher, industrialized
quality – less affected by
weather
 no space requirement on
the site for fabrication
 unlimited opportunities of
architectural appearance
 option of standardized
components
5
Design concept for precast
concrete buildings
 The design
concept of
the precast
buildings is
based on
 1.build
ability.
 2.economy
3.standardiz
ation of
precast
components.
6
Precast concrete structural
elements
7
Precast slabs
Precast Beam & Girders
8
Precast Columns
Precast Walls
9
Precast stairs
Precast concrete Stairs
Steel plates supported on 2 steel
beams
Design considerations
 final position and loads
 transportation requirements – self load and
position during transportation
 storing requirements – self load and position
during storing – (avoid or store in the same
position as it transported / built in)
 lifting loads – distribution of lifting points –
optimal way of lifting (selection of lifting and
rigging tools)
 vulnerable points (e.g. edges) – reduction of
risk (e.g. rounded edges)
10
Types of pre cast system
1. Large-panel systems
2. Frame systems
3. Slab-column systems with walls
4. Mixed systems
11
 box-like structure.
 both vertical and
horizontal elements are
load-bearing.
 one-story high wall panels
(cross-wall system /
longitudinal wall system /
two way system).
 one-way or two way
slabs.
12
1. Large-panel systems
2. Frame systems
 Components are usually
linear elements.
 The beams are seated
on corbels of the pillars
usually with hinged-
joints (rigid connection
is also an option).
 Joints are filled with
concrete at the site.
13
3.Lift-slab systems
 - partially precast in plant
(pillars) / partially precast on-
site (slabs).
 - one or more storey high
pillars (max 5).
 - up to 30 storey high
constructions.
 - special designed joints and
temporary joints.
 -slabs are casted on the
ground (one on top of the
other) – then lifted with crane
or special elevators.
14
Lift-slab procedure
15
1. pillars and the first package (e.g. 5 pieces) of slabs
prepared at ground level
2. lifting boxes are mounted on the pillars + a single slab
lifted to the first floor level
3-8. boxes are sequentially raised to higher positions to
enable the slabs to be lifted to their required
final position - slabs are held in a relative (temporary)
positions by a pinning system
Planning traffic route
 How long transporter
vehicle is required?
 What is the required
load capacity of the
transporter vehicle?
 What is the maximum
vertical extension of the
shipment
 Routs on the site
16
• Is route permission
required?
Equipments
cranes:
 mobile crane
 tower crane (above
3stories)
lifting tools:
 spreader beams
 wire rope slings
rigging tools:
 eye bolt
 shakles
 hooks
17
Assembling….
18
Column to column connection
Beam to column connection
19
Beam-slab joints
20
21
Precast concrete structure consisting of
solid wall panels and hollow core slabs.
Wall to slab connection
Advantages
 Quick erection times
 Possibility of conversion, disassembling
and moving to another site
 Possibility of erection in areas where a
traditional construction practice is not
possible or difficult
 Low labor intensivity
 Reduce wastage of materials
 Easier management of construction sites
 Better overall construction quality
 Ideal fit for simple and complex structures
22
Limitations
 size of the units.
 location of window openings has a
limited variety.
 joint details are predefined.
 site access and storage capacity.
 require high quality control.
 enable interaction between design
phase and production planning.
 difficult to handling & transporting.
23
Scheduling
some approximate data for installation
 emplacement of hollow core floor slabs -
300 m2/day
 erection of pillars/columns - 8 pieces/day
 emplacement of beams - 15 pieces/day
 emplacement of double tee slabs - 25
pieces/day
 emplacement of walls - 15 pieces/day
 construction of stair and elevator shafts -
2 floors/day
24
Examples….
25
The hospital will feature multi-trade prefabricated racks in the corridors, an
approach that is still new in the U.S.
26
Miami Valley Hospital Dayton,OH
Conclusion
27
oThe use of prefabrication and preassembly is
estimated to have almost doubled in the last 15
years, increasing by 86%.
oThe use of precast concrete construction can
significantly reduce the amount of construction waste
generated on construction sites.
o Reduce adverse environmental impact on sites.
o Enhance quality control of concreting work.
o Reduce the amount of site labour.
o Increase worker safety .
o Other impediments to prefabrication and
preassembly are increased transportation
difficulties, greater inflexibility, and more advanced
procurement requirements.
References
 [1] Szőnyi L.: Construction of prefabricated reinforced concrete
buildings, 2011
 [2] Benett, D.: Concrete Elegance 2004. Concrete Centre, 2005
 [3] Precast Concrete Structures. www.paradigm.in 2012.10.10
 [4] S. Brzev, T. Guevara-Perez: Precast Concrete Construction.
http://business.management6.com/PRECAST-CONCRETE-
CONSTRUCTION-pdfe13174.
 [5] Sonjoy Deb: Precast Concrete for Building
Systemshttp://masterbuilder.co.in/Archives/Building%20Material
s/Concrete/Precast%20
Concrete%20for%20Building%20Systems.pdf 2012.10.10
 [6] Lift slab
systemhttp://webs.demasiado.com/forjados/patologia/lift_slab/as
pect/index.htm2012.10.23
 [7] http://www.liftplanner.net/steamdrum.html 2012.10.23
28
29
Questions ?.....
30
Thank you

Weitere ähnliche Inhalte

Was ist angesagt? (20)

PreCast Construction
PreCast ConstructionPreCast Construction
PreCast Construction
 
Prefabrication
PrefabricationPrefabrication
Prefabrication
 
Grid/ Waffle Slabs
Grid/ Waffle SlabsGrid/ Waffle Slabs
Grid/ Waffle Slabs
 
Precast concrete construction
Precast concrete constructionPrecast concrete construction
Precast concrete construction
 
Precast concrete construction
Precast concrete constructionPrecast concrete construction
Precast concrete construction
 
Slabs and types
Slabs and typesSlabs and types
Slabs and types
 
Long span structures in Concrete and Steel
Long span structures in Concrete and SteelLong span structures in Concrete and Steel
Long span structures in Concrete and Steel
 
High rise building construction
High rise building constructionHigh rise building construction
High rise building construction
 
Bc open pre fabricated construction system
Bc open pre fabricated construction systemBc open pre fabricated construction system
Bc open pre fabricated construction system
 
High-rise structural systems
High-rise structural systemsHigh-rise structural systems
High-rise structural systems
 
Space frames
Space framesSpace frames
Space frames
 
Prestressed Concrete
Prestressed ConcretePrestressed Concrete
Prestressed Concrete
 
Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concrete
 
Defects and remedies of building
Defects and remedies of buildingDefects and remedies of building
Defects and remedies of building
 
Prefabrication - building construction
Prefabrication - building constructionPrefabrication - building construction
Prefabrication - building construction
 
Prefabrication
PrefabricationPrefabrication
Prefabrication
 
PRE STRESSED CONCRETE
PRE STRESSED CONCRETEPRE STRESSED CONCRETE
PRE STRESSED CONCRETE
 
Diagrid structural system
Diagrid structural systemDiagrid structural system
Diagrid structural system
 
Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concrete
 
Shear wall
Shear wallShear wall
Shear wall
 

Andere mochten auch

PREFABRICATED STRUCTURES
PREFABRICATED STRUCTURESPREFABRICATED STRUCTURES
PREFABRICATED STRUCTURESRajendran s.
 
ALL ABOUT PRECAST
ALL ABOUT PRECASTALL ABOUT PRECAST
ALL ABOUT PRECASTjagrutib22
 
PREFABRICATED CONSTRUCTION CASE STUDY: THE HEMISPHERE
PREFABRICATED CONSTRUCTION CASE STUDY: THE HEMISPHEREPREFABRICATED CONSTRUCTION CASE STUDY: THE HEMISPHERE
PREFABRICATED CONSTRUCTION CASE STUDY: THE HEMISPHEREShivangi Saini
 
Virtual Outriggers in Tall Buildings
Virtual Outriggers in Tall BuildingsVirtual Outriggers in Tall Buildings
Virtual Outriggers in Tall BuildingsAndrew J Horton
 
Presentation. _ JKR Lawatan kilang HCPS
Presentation. _ JKR Lawatan kilang HCPSPresentation. _ JKR Lawatan kilang HCPS
Presentation. _ JKR Lawatan kilang HCPSTeow Beng Hur
 
Building Construction 1 - Experiencing Construction
Building Construction 1 - Experiencing ConstructionBuilding Construction 1 - Experiencing Construction
Building Construction 1 - Experiencing Constructionjisunfoo
 
1.6 _Important element required to complete a building
1.6  _Important element required to complete a building1.6  _Important element required to complete a building
1.6 _Important element required to complete a buildingTeow Beng Hur
 
HC PRECAST SYSTEM's Technical Property
HC PRECAST SYSTEM's Technical PropertyHC PRECAST SYSTEM's Technical Property
HC PRECAST SYSTEM's Technical PropertyTeow Beng Hur
 
Onshore modules construction – a fabricator’s view
Onshore modules construction – a fabricator’s viewOnshore modules construction – a fabricator’s view
Onshore modules construction – a fabricator’s viewMerrylyn Yeo
 
A study on the construction process (Precast concrete, In-situ cast concrete,...
A study on the construction process (Precast concrete, In-situ cast concrete,...A study on the construction process (Precast concrete, In-situ cast concrete,...
A study on the construction process (Precast concrete, In-situ cast concrete,...Bhaddin Al-Naqshabandi
 
analysis of high rise building
analysis of high rise buildinganalysis of high rise building
analysis of high rise buildingishant_kukreja
 
High Rise Building Research Document
High Rise Building Research DocumentHigh Rise Building Research Document
High Rise Building Research DocumentNicholas Socrates
 
Structural systems in high rise buildings
Structural systems in high rise buildingsStructural systems in high rise buildings
Structural systems in high rise buildingsKarthik Suresh
 
Building construction-report (1)
Building construction-report (1)Building construction-report (1)
Building construction-report (1)Soh Shing
 

Andere mochten auch (18)

PREFABRICATED STRUCTURES
PREFABRICATED STRUCTURESPREFABRICATED STRUCTURES
PREFABRICATED STRUCTURES
 
ALL ABOUT PRECAST
ALL ABOUT PRECASTALL ABOUT PRECAST
ALL ABOUT PRECAST
 
PREFABRICATED CONSTRUCTION CASE STUDY: THE HEMISPHERE
PREFABRICATED CONSTRUCTION CASE STUDY: THE HEMISPHEREPREFABRICATED CONSTRUCTION CASE STUDY: THE HEMISPHERE
PREFABRICATED CONSTRUCTION CASE STUDY: THE HEMISPHERE
 
Prefabricated structure
Prefabricated structurePrefabricated structure
Prefabricated structure
 
Virtual Outriggers in Tall Buildings
Virtual Outriggers in Tall BuildingsVirtual Outriggers in Tall Buildings
Virtual Outriggers in Tall Buildings
 
Presentation. _ JKR Lawatan kilang HCPS
Presentation. _ JKR Lawatan kilang HCPSPresentation. _ JKR Lawatan kilang HCPS
Presentation. _ JKR Lawatan kilang HCPS
 
Presentation 2016
Presentation  2016Presentation  2016
Presentation 2016
 
Building Construction 1 - Experiencing Construction
Building Construction 1 - Experiencing ConstructionBuilding Construction 1 - Experiencing Construction
Building Construction 1 - Experiencing Construction
 
1.6 _Important element required to complete a building
1.6  _Important element required to complete a building1.6  _Important element required to complete a building
1.6 _Important element required to complete a building
 
HC PRECAST SYSTEM's Technical Property
HC PRECAST SYSTEM's Technical PropertyHC PRECAST SYSTEM's Technical Property
HC PRECAST SYSTEM's Technical Property
 
Onshore modules construction – a fabricator’s view
Onshore modules construction – a fabricator’s viewOnshore modules construction – a fabricator’s view
Onshore modules construction – a fabricator’s view
 
INDUSTRIALISED BUILDING SYSTEMS & MODULAR COORDINATION
INDUSTRIALISED BUILDING SYSTEMS & MODULAR COORDINATIONINDUSTRIALISED BUILDING SYSTEMS & MODULAR COORDINATION
INDUSTRIALISED BUILDING SYSTEMS & MODULAR COORDINATION
 
A study on the construction process (Precast concrete, In-situ cast concrete,...
A study on the construction process (Precast concrete, In-situ cast concrete,...A study on the construction process (Precast concrete, In-situ cast concrete,...
A study on the construction process (Precast concrete, In-situ cast concrete,...
 
High rise structure & core
High rise  structure & coreHigh rise  structure & core
High rise structure & core
 
analysis of high rise building
analysis of high rise buildinganalysis of high rise building
analysis of high rise building
 
High Rise Building Research Document
High Rise Building Research DocumentHigh Rise Building Research Document
High Rise Building Research Document
 
Structural systems in high rise buildings
Structural systems in high rise buildingsStructural systems in high rise buildings
Structural systems in high rise buildings
 
Building construction-report (1)
Building construction-report (1)Building construction-report (1)
Building construction-report (1)
 

Ähnlich wie Prefabricated structures

Precast modular structures
Precast modular structuresPrecast modular structures
Precast modular structuresAnirudh Gupta
 
study of usage factor in low cost construction
study of usage factor in low cost constructionstudy of usage factor in low cost construction
study of usage factor in low cost constructionManisha Singh
 
prefabricatedstructures-140331011852-phpapp01 (1) (1).pptx
prefabricatedstructures-140331011852-phpapp01 (1) (1).pptxprefabricatedstructures-140331011852-phpapp01 (1) (1).pptx
prefabricatedstructures-140331011852-phpapp01 (1) (1).pptxMuthuMari88
 
Pre fabricated structures
Pre fabricated structuresPre fabricated structures
Pre fabricated structuresjamali husain
 
documents.pub_pre-fabricated-structures.pdf
documents.pub_pre-fabricated-structures.pdfdocuments.pub_pre-fabricated-structures.pdf
documents.pub_pre-fabricated-structures.pdfBiswaKeshanPanda1
 
Pre-Cast Technology: An Initial Step to Sustainable Development
Pre-Cast Technology: An Initial Step to Sustainable DevelopmentPre-Cast Technology: An Initial Step to Sustainable Development
Pre-Cast Technology: An Initial Step to Sustainable Developmentijsrd.com
 
Precast Construction technology
Precast Construction technologyPrecast Construction technology
Precast Construction technologyGedalaJairam
 
Composite construction in Bridge Deck systems by Suhas Khedkar Kishore Saxena
Composite construction in Bridge Deck systems by Suhas Khedkar Kishore SaxenaComposite construction in Bridge Deck systems by Suhas Khedkar Kishore Saxena
Composite construction in Bridge Deck systems by Suhas Khedkar Kishore SaxenaSuhas Khedkar
 
PRE-CAST-CONSTRUCTION-Expertcivil.pptx
PRE-CAST-CONSTRUCTION-Expertcivil.pptxPRE-CAST-CONSTRUCTION-Expertcivil.pptx
PRE-CAST-CONSTRUCTION-Expertcivil.pptxatiulla001
 
CT III IBS Formwork System
CT III IBS Formwork System CT III IBS Formwork System
CT III IBS Formwork System ashleyyeap
 
Chapters-3,4,5.pptx
Chapters-3,4,5.pptxChapters-3,4,5.pptx
Chapters-3,4,5.pptxssuserc0bf9b
 
PRE-CAST-CONSTRUCTION.pptx
PRE-CAST-CONSTRUCTION.pptxPRE-CAST-CONSTRUCTION.pptx
PRE-CAST-CONSTRUCTION.pptxLokeswarSaha1
 
An Introduction to Prefabricated structures
An Introduction to Prefabricated structuresAn Introduction to Prefabricated structures
An Introduction to Prefabricated structuresSofia Rajesh
 
PRE-CAST-CONSTRUCTION.pptx
PRE-CAST-CONSTRUCTION.pptxPRE-CAST-CONSTRUCTION.pptx
PRE-CAST-CONSTRUCTION.pptxVinayak247538
 
Construction Technology
Construction TechnologyConstruction Technology
Construction TechnologySwapnilGorade1
 
national building code
national building codenational building code
national building codeRuhiya Garg
 
Pre fabricatted and pre engineered building
Pre fabricatted and pre engineered buildingPre fabricatted and pre engineered building
Pre fabricatted and pre engineered buildingAnchitSharma17
 
CONSTRUCTION TECHNOLOGY
CONSTRUCTION TECHNOLOGY CONSTRUCTION TECHNOLOGY
CONSTRUCTION TECHNOLOGY VISHNU VIJAYAN
 

Ähnlich wie Prefabricated structures (20)

Precast modular structures
Precast modular structuresPrecast modular structures
Precast modular structures
 
study of usage factor in low cost construction
study of usage factor in low cost constructionstudy of usage factor in low cost construction
study of usage factor in low cost construction
 
Tos syllabus
Tos syllabusTos syllabus
Tos syllabus
 
prefabricatedstructures-140331011852-phpapp01 (1) (1).pptx
prefabricatedstructures-140331011852-phpapp01 (1) (1).pptxprefabricatedstructures-140331011852-phpapp01 (1) (1).pptx
prefabricatedstructures-140331011852-phpapp01 (1) (1).pptx
 
Pre fabricated structures
Pre fabricated structuresPre fabricated structures
Pre fabricated structures
 
documents.pub_pre-fabricated-structures.pdf
documents.pub_pre-fabricated-structures.pdfdocuments.pub_pre-fabricated-structures.pdf
documents.pub_pre-fabricated-structures.pdf
 
Pre-Cast Technology: An Initial Step to Sustainable Development
Pre-Cast Technology: An Initial Step to Sustainable DevelopmentPre-Cast Technology: An Initial Step to Sustainable Development
Pre-Cast Technology: An Initial Step to Sustainable Development
 
Precast Construction technology
Precast Construction technologyPrecast Construction technology
Precast Construction technology
 
Composite construction in Bridge Deck systems by Suhas Khedkar Kishore Saxena
Composite construction in Bridge Deck systems by Suhas Khedkar Kishore SaxenaComposite construction in Bridge Deck systems by Suhas Khedkar Kishore Saxena
Composite construction in Bridge Deck systems by Suhas Khedkar Kishore Saxena
 
PRE-CAST-CONSTRUCTION-Expertcivil.pptx
PRE-CAST-CONSTRUCTION-Expertcivil.pptxPRE-CAST-CONSTRUCTION-Expertcivil.pptx
PRE-CAST-CONSTRUCTION-Expertcivil.pptx
 
CT III IBS Formwork System
CT III IBS Formwork System CT III IBS Formwork System
CT III IBS Formwork System
 
Chapters-3,4,5.pptx
Chapters-3,4,5.pptxChapters-3,4,5.pptx
Chapters-3,4,5.pptx
 
PRE-CAST-CONSTRUCTION.pptx
PRE-CAST-CONSTRUCTION.pptxPRE-CAST-CONSTRUCTION.pptx
PRE-CAST-CONSTRUCTION.pptx
 
An Introduction to Prefabricated structures
An Introduction to Prefabricated structuresAn Introduction to Prefabricated structures
An Introduction to Prefabricated structures
 
PRE-CAST-CONSTRUCTION.pptx
PRE-CAST-CONSTRUCTION.pptxPRE-CAST-CONSTRUCTION.pptx
PRE-CAST-CONSTRUCTION.pptx
 
Construction Technology
Construction TechnologyConstruction Technology
Construction Technology
 
national building code
national building codenational building code
national building code
 
Pre fabricatted and pre engineered building
Pre fabricatted and pre engineered buildingPre fabricatted and pre engineered building
Pre fabricatted and pre engineered building
 
CONSTRUCTION TECHNOLOGY
CONSTRUCTION TECHNOLOGY CONSTRUCTION TECHNOLOGY
CONSTRUCTION TECHNOLOGY
 
CCTVHeadquarters.pdf
CCTVHeadquarters.pdfCCTVHeadquarters.pdf
CCTVHeadquarters.pdf
 

Kürzlich hochgeladen

Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringmulugeta48
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdfKamal Acharya
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdfKamal Acharya
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Christo Ananth
 
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELLPVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELLManishPatel169454
 
Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...Christo Ananth
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756dollysharma2066
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . pptDineshKumar4165
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 

Kürzlich hochgeladen (20)

(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
NFPA 5000 2024 standard .
NFPA 5000 2024 standard                                  .NFPA 5000 2024 standard                                  .
NFPA 5000 2024 standard .
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineering
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELLPVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
 
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
 
Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...
 
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 

Prefabricated structures

  • 1. 1 PRE FABRICATED MODULAR STRUCTURES GUIDED BY: SOUMYA MISS ASST PROFFESSOR, UKFCET, KOLLAM PRESENTED BY: FAIZAL.A.M 7TH SEMESTER CIVIL ENGINEERING UKFCET, KOLLAM
  • 2. Contents  Introduction  Features  Comparison  Design concept  Components  Types of precast system  Design consideration  Equipments  Assembling  scheduling  Advantages  Limitations  Conclusion  references 2
  • 3. Introduction  The concept of precast structures also known as prefabricated/ modular structures.  The structural components are standardized and produced in plants in a location away from the building site.  Then transported to the site for assembly.  The components are manufactured by industrial methods based on mass production in order to build a large number of buildings in a short time at low cost. 3
  • 4. Features  The division and specialization of the human workforce.  The use of tools, machinery, and other equipment, usually automated, in the production of standard, interchangeable parts and products.  Compared to site-cast concrete, precast concrete erection is faster and less affected by adverse weather conditions.  Plant casting allows increased efficiency, high quality control and greater control on finishes. 4
  • 5. Comparison Site-cast  no transportation  the size limitation is depending on the elevation capacity only  lower quality because directly affected by weather  proper, large free space required Precast at plant  transportation and elevation capacity limits the size-  higher, industrialized quality – less affected by weather  no space requirement on the site for fabrication  unlimited opportunities of architectural appearance  option of standardized components 5
  • 6. Design concept for precast concrete buildings  The design concept of the precast buildings is based on  1.build ability.  2.economy 3.standardiz ation of precast components. 6
  • 7. Precast concrete structural elements 7 Precast slabs Precast Beam & Girders
  • 9. 9 Precast stairs Precast concrete Stairs Steel plates supported on 2 steel beams
  • 10. Design considerations  final position and loads  transportation requirements – self load and position during transportation  storing requirements – self load and position during storing – (avoid or store in the same position as it transported / built in)  lifting loads – distribution of lifting points – optimal way of lifting (selection of lifting and rigging tools)  vulnerable points (e.g. edges) – reduction of risk (e.g. rounded edges) 10
  • 11. Types of pre cast system 1. Large-panel systems 2. Frame systems 3. Slab-column systems with walls 4. Mixed systems 11
  • 12.  box-like structure.  both vertical and horizontal elements are load-bearing.  one-story high wall panels (cross-wall system / longitudinal wall system / two way system).  one-way or two way slabs. 12 1. Large-panel systems
  • 13. 2. Frame systems  Components are usually linear elements.  The beams are seated on corbels of the pillars usually with hinged- joints (rigid connection is also an option).  Joints are filled with concrete at the site. 13
  • 14. 3.Lift-slab systems  - partially precast in plant (pillars) / partially precast on- site (slabs).  - one or more storey high pillars (max 5).  - up to 30 storey high constructions.  - special designed joints and temporary joints.  -slabs are casted on the ground (one on top of the other) – then lifted with crane or special elevators. 14
  • 15. Lift-slab procedure 15 1. pillars and the first package (e.g. 5 pieces) of slabs prepared at ground level 2. lifting boxes are mounted on the pillars + a single slab lifted to the first floor level 3-8. boxes are sequentially raised to higher positions to enable the slabs to be lifted to their required final position - slabs are held in a relative (temporary) positions by a pinning system
  • 16. Planning traffic route  How long transporter vehicle is required?  What is the required load capacity of the transporter vehicle?  What is the maximum vertical extension of the shipment  Routs on the site 16 • Is route permission required?
  • 17. Equipments cranes:  mobile crane  tower crane (above 3stories) lifting tools:  spreader beams  wire rope slings rigging tools:  eye bolt  shakles  hooks 17
  • 19. Beam to column connection 19
  • 21. 21 Precast concrete structure consisting of solid wall panels and hollow core slabs. Wall to slab connection
  • 22. Advantages  Quick erection times  Possibility of conversion, disassembling and moving to another site  Possibility of erection in areas where a traditional construction practice is not possible or difficult  Low labor intensivity  Reduce wastage of materials  Easier management of construction sites  Better overall construction quality  Ideal fit for simple and complex structures 22
  • 23. Limitations  size of the units.  location of window openings has a limited variety.  joint details are predefined.  site access and storage capacity.  require high quality control.  enable interaction between design phase and production planning.  difficult to handling & transporting. 23
  • 24. Scheduling some approximate data for installation  emplacement of hollow core floor slabs - 300 m2/day  erection of pillars/columns - 8 pieces/day  emplacement of beams - 15 pieces/day  emplacement of double tee slabs - 25 pieces/day  emplacement of walls - 15 pieces/day  construction of stair and elevator shafts - 2 floors/day 24
  • 25. Examples…. 25 The hospital will feature multi-trade prefabricated racks in the corridors, an approach that is still new in the U.S.
  • 27. Conclusion 27 oThe use of prefabrication and preassembly is estimated to have almost doubled in the last 15 years, increasing by 86%. oThe use of precast concrete construction can significantly reduce the amount of construction waste generated on construction sites. o Reduce adverse environmental impact on sites. o Enhance quality control of concreting work. o Reduce the amount of site labour. o Increase worker safety . o Other impediments to prefabrication and preassembly are increased transportation difficulties, greater inflexibility, and more advanced procurement requirements.
  • 28. References  [1] Szőnyi L.: Construction of prefabricated reinforced concrete buildings, 2011  [2] Benett, D.: Concrete Elegance 2004. Concrete Centre, 2005  [3] Precast Concrete Structures. www.paradigm.in 2012.10.10  [4] S. Brzev, T. Guevara-Perez: Precast Concrete Construction. http://business.management6.com/PRECAST-CONCRETE- CONSTRUCTION-pdfe13174.  [5] Sonjoy Deb: Precast Concrete for Building Systemshttp://masterbuilder.co.in/Archives/Building%20Material s/Concrete/Precast%20 Concrete%20for%20Building%20Systems.pdf 2012.10.10  [6] Lift slab systemhttp://webs.demasiado.com/forjados/patologia/lift_slab/as pect/index.htm2012.10.23  [7] http://www.liftplanner.net/steamdrum.html 2012.10.23 28