Silver Line Update: Board Transportation Committee May 24, 2016
1. County of Fairfax, Virginia
Silver Line Update
Board Transportation Committee
May 24, 2016
Mark Canale
Fairfax County Department of Transportation
Department of Transportation
1
2. County of Fairfax, Virginia
Phase 1 Summary
• Art in Transit Completed
• Old Meadow Road Realignment – to be completed by
the end of 2017
• VDOT Punchlist Ongoing
• Phase 1 close out - $2.982B
Phase 2 Summary
Total Project Status (all bid packages)
• Overall Project – 33%
• Design – 98%
• Construction – 19%
Station Construction
• Reston Town Center Station – 5%
• Tower crane erected and pile driving
• Herndon Station – 15%
• Utility work and cast in place concrete
• Innovation Station – 29%
• Precast erection
• Dulles Airport Station – 20%
• Foundation and utility work
• Loudon Gateway Station – 2%
• Site clearing and excavation
• Ashburn Station – 0%
Aerial Guideway
• Caisson Foundations – 89%
• Columns – 78%
• Pier Caps – 71%
• Trackway Spans – 29%
• Column, pier caps, girder, straddle
bent and deck pours work ongoing
Rail Yard at Dulles Airport
• 100% Design Plans Submitted
• Installation of Stormwater Structures
• Site Clearing and Blasting
Phase 2 Cost Summary
Budget
• Total Budget - $2.778B
• Total Forecast - $2.778B
• Total Expenditures - $690M
Phase 2 Contingency Utilization
• Total Contingency - $551.5M
• Total Contingency Utilized - $76.2M
• Remaining Contingency - $475.3M
Department of Transportation
2
3. County of Fairfax, Virginia
Dulles Airport Station
Excavation, foundation walls, and aerial guideway piers and girders
Department of Transportation
3
6. County of Fairfax, Virginia
Sign removal on Saarinen Circle
Innovation Center Station
Concrete foundations, station support walls, and pre-cast erection
Department of Transportation
6