Route 50 Sidewalk from Annandale Road to Cherry Street

83 Aufrufe

Veröffentlicht am

The scope of this project included the construction of approximately 1,500 linear feet of six-foot wide concrete sidewalk, curb and gutter, pedestrian curb ramp, pavement mill and overlay, pavement markings and signage, storm drainage improvements and pedestrian signal installations.

  • Als Erste(r) kommentieren

  • Gehören Sie zu den Ersten, denen das gefällt!

Route 50 Sidewalk from Annandale Road to Cherry Street

  1. 1. A Fairfax County, VA, publication Department of Public Works and Environmental Services Working for You! Route 50 Sidewalk from Annandale Road to Cherry Street Project No. 1400059-2012 Contract No. CN17102044 VDOT UPC No. 108501 Providence District July 30, 2019
  2. 2. Route 50 from Annandale Road to Cherry Street Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch
  3. 3. Project Details Route 50 Sidewalk from Annandale Road to Cherry Street Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch Description: The Route 50 sidewalk from Annandale Road to Cherry Street project was substantially completed on June 13, 2019. The scope of this project was the construction of approximately 1500 LF of 6-foot wide concrete sidewalk, curb & gutter, pedestrian curb ramp, pavement mill and overlay, pavement markings and signage, storm drainage improvements and pedestrian signal installations. Project Team:  Project Manager, FCDOT – Mohammod El Kaissi  Project Engineer, UDCD – Fasika Metafria  Project Inspector, RK&K – Rick L. Richardson and Abdallah Saad  Land Survey Branch, UDCD – Christopher J. Jensen
  4. 4. Route 50 Sidewalk from Annandale Road to Cherry Street Providence District , Tax Map 50-4 Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch Project Location ANNANDALE ROAD TO CHERRY STREET PROJECT SITE
  5. 5. Route 50 Sidewalk from Annandale Road to Cherry Street Installation of Storm Drainage Improvements Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch
  6. 6. Route 50 Sidewalk from Annandale Road to Cherry Street Installation of the Concrete Sidewalk Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch
  7. 7. Route 50 Sidewalk from Annandale Road to Cherry Street Installation of Concrete Curb Ramp and Sidewalk Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch
  8. 8. Route 50 Sidewalk from Annandale Road to Cherry Street Installation of Pedestrian Signal Improvement Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch
  9. 9. Route 50 Sidewalk from Annandale Road to Cherry Street Installation of Pedestrian Crosswalk Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch
  10. 10. Before After Route 50 Sidewalk from Annandale Road to Cherry Street Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch
  11. 11. Additional Information For additional Information, please call www.fairfaxcounty.gov/publicworks Route 50 Sidewalk from Annandale Road to Cherry Street Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch Matthew Kaiser, Public Information Officer 703-324-8455, TTY 711 Matthew.kaiser@fairfaxcounty.gov

×