Today’s Presentation
• Background
• Phase 2 Objectives
• Actions to Date
• Outreach
• Phase 2 Highlights
• Projected Schedule
• Easy Ways to Be Involved
• Contact Information
2
Background
December 4, 2018
BOS approved “Phase 1”
revisions to achieve
targeted flexibility &
clarity in the land
development review
process.
3
Phase 2
Objectives
• Resolve Complex Phase 1
Issues/Vet
• Bring PFM into Alignment
with Codes
• Remove Replication
• Incorporate LTIs
• Add New and Updated
Guidelines
4
Actions to Date
• Developed a Phase 2
PFM Website.
• Completed: Spring P2
Package - July 16, 2019.
• In Progress: Winter P2
Package.
5
Outreach
6
PFM
Website
zMOD
Land Use
Attorneys zMOD
Citizen
Working
Group
ESI
BAC:
EQAC,GRB,
Tree
Commission
NAIOP
NVBIA
Zoning
Ordinance
ListServ
Outreach
7
ESRC
Technical
Advisory
Committee
Stakeholder
Committee
Steering
Committee
DPC
BOS Land
Use
Aides
PC Land
Use
Process
Review
Engineering Standards Review Committee
8
• Paul Johnson (NVBIA)
• Kevin Nelson
(VDOT/ESRC)
• Mark Liberati (Virginia
Association of Surveyors)
• Keith Sinclair (ESI)
• Theodore Britt (VSPE)
• James Clark (Heavy
Construction Contractors
Association)
• Howard Guba
(Citizen-at-Large)
• Michael Kitchen (NAIOP)
• Robert Kohnke (NVSWCD)
• Bryan Layman
(Associated Builders and
Contractors)
• Kevin Pullen (League of
Women Voters)
• Dr. Robert Norwood
(Citizen-at-Large)
• Paul Norsi
(Citizen-at-Large)
• Ned Poffenberger (Fairfax
County Federation of
Citizens Associations)
• Robert Scheller (WACEL)
• Bruce Titus (Fairfax Bar
Association)
Phase 2 HighlightsStreetLights
• Align PFM with
Regulations of
VDOT, Chapter
118.
• Incorporate the
Urban Design
Guidelines in CRAs,
CRDs & Mixed-Use
areas.
GeneralInformation
✓Modernize Street
Lights to Light
Emitting Diode
(LED) Fixtures.
StormDrainage
✓Provide alternative
pipe material for
storm sewer.
✓Require Dam Breach
Inundation Zone
maps with as-builts.
• Chapter 6 revisions
(In progress).
9
Phase 2 HighlightsStreets
• Point to VDOT
Standards to
facilitate design
& review of
streets.
• Define shared-
use path.
Trails&Recreation
• Update trails
information to
reflect the
Countywide
Trails Plan.
SanitarySewer
• Pressurized
sewer.
• Elevating
Manhole tops.
• Damaged Pipe
(replaced not
repaired).
10
Phase 2 HighlightsTreeConservation
• Clarify critical
root zone
requirement.
• Buffer
restoration
specifications
(In Progress).
Geotechnical
• Setting
residential
basement
elevation above
groundwater
table.
• Use of lime in
construction.
Geotechnical
• Exploration
requirements for
high bearing
structures.
• Exploration
requirements for
deep
foundations.
11
Projected
Schedule
Winter P2 Package:
➢Outreach: April
through December
2019.
➢Public hearings by
April 2020.
12
Easy Ways to Be Involved
Check out the PFM Project website.
Review the chapter edits - routinely.
Use the online feedback form or email.
Attend the public hearings.
13
Questions?
For more information:
PFM Project Phase 2 Website
https://www.fairfaxcounty.gov/landdevelopment/p
ublic-facilities-manual-flexibility-project
Contact:
Danielle.Badra@fairfaxcounty.gov
Don.Lacquement@fairfaxcounty.gov
14

Weitere ähnliche Inhalte

Ähnlich wie PFM Project Phase 2 Update

Public Facilities Manual Project NVBIA/NAIO Phase 2 Update - Nov. 21, 2019
Public Facilities Manual Project NVBIA/NAIO Phase 2 Update - Nov. 21, 2019Public Facilities Manual Project NVBIA/NAIO Phase 2 Update - Nov. 21, 2019
Public Facilities Manual Project NVBIA/NAIO Phase 2 Update - Nov. 21, 2019Fairfax County
 
Arboretum community meeting 2020 01-14
Arboretum  community meeting 2020 01-14Arboretum  community meeting 2020 01-14
Arboretum community meeting 2020 01-14RamaChilamkurthy
 
NVBIA NAIOP Update July 14, 2016
NVBIA NAIOP Update July 14, 2016NVBIA NAIOP Update July 14, 2016
NVBIA NAIOP Update July 14, 2016Fairfax County
 
Workhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxWorkhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxFairfax County
 
Adding Flexibility to Fairfax County's Public Facilities Manual (PFM)
Adding Flexibility to Fairfax County's Public Facilities Manual (PFM)Adding Flexibility to Fairfax County's Public Facilities Manual (PFM)
Adding Flexibility to Fairfax County's Public Facilities Manual (PFM)Fairfax County
 
Parkville Downtown Masterplan
Parkville Downtown MasterplanParkville Downtown Masterplan
Parkville Downtown MasterplanBNIM
 
Public Facilities Manual Flexibility Project - Phase 2 Update
Public Facilities Manual Flexibility Project - Phase 2 UpdatePublic Facilities Manual Flexibility Project - Phase 2 Update
Public Facilities Manual Flexibility Project - Phase 2 UpdateFairfax County
 
Fairfax County's Public Facilities Manual (PFM): Update to the Providence Dis...
Fairfax County's Public Facilities Manual (PFM): Update to the Providence Dis...Fairfax County's Public Facilities Manual (PFM): Update to the Providence Dis...
Fairfax County's Public Facilities Manual (PFM): Update to the Providence Dis...Fairfax County
 
Public Facilities Manual Flexibility Project : Update to the Development Proc...
Public Facilities Manual Flexibility Project : Update to the Development Proc...Public Facilities Manual Flexibility Project : Update to the Development Proc...
Public Facilities Manual Flexibility Project : Update to the Development Proc...Fairfax County
 
ULI in Action on Transportation and Infrastructure: A Catalyst for Sustainabl...
ULI in Action on Transportation and Infrastructure: A Catalyst for Sustainabl...ULI in Action on Transportation and Infrastructure: A Catalyst for Sustainabl...
ULI in Action on Transportation and Infrastructure: A Catalyst for Sustainabl...Virtual ULI
 
New direction power point
New direction power pointNew direction power point
New direction power pointvocbc
 
Day 2: Plan to Project Process
Day 2: Plan to Project ProcessDay 2: Plan to Project Process
Day 2: Plan to Project ProcessNAP Global Network
 
Downtown Lynn Team of Advisors Kickoff Meeting Presentation, November 21, 2012
Downtown Lynn Team of Advisors Kickoff Meeting Presentation, November 21, 2012Downtown Lynn Team of Advisors Kickoff Meeting Presentation, November 21, 2012
Downtown Lynn Team of Advisors Kickoff Meeting Presentation, November 21, 2012Metropolitan Area Planning Council
 
Community Presentation - October 2017
Community Presentation - October 2017Community Presentation - October 2017
Community Presentation - October 2017Cami Crawford
 
DOE Sun Shot Initiative Rooftop Solar Challenge
DOE Sun Shot Initiative Rooftop Solar ChallengeDOE Sun Shot Initiative Rooftop Solar Challenge
DOE Sun Shot Initiative Rooftop Solar ChallengeTNenergy
 
CREATING A STANDARDISED APPROACH TO REGIONAL ENVIRONMENTAL MANAGEMENT
CREATING A STANDARDISED APPROACH TO REGIONAL ENVIRONMENTAL MANAGEMENTCREATING A STANDARDISED APPROACH TO REGIONAL ENVIRONMENTAL MANAGEMENT
CREATING A STANDARDISED APPROACH TO REGIONAL ENVIRONMENTAL MANAGEMENTiQHub
 

Ähnlich wie PFM Project Phase 2 Update (20)

Public Facilities Manual Project NVBIA/NAIO Phase 2 Update - Nov. 21, 2019
Public Facilities Manual Project NVBIA/NAIO Phase 2 Update - Nov. 21, 2019Public Facilities Manual Project NVBIA/NAIO Phase 2 Update - Nov. 21, 2019
Public Facilities Manual Project NVBIA/NAIO Phase 2 Update - Nov. 21, 2019
 
Arboretum community meeting 2020 01-14
Arboretum  community meeting 2020 01-14Arboretum  community meeting 2020 01-14
Arboretum community meeting 2020 01-14
 
NVBIA NAIOP Update July 14, 2016
NVBIA NAIOP Update July 14, 2016NVBIA NAIOP Update July 14, 2016
NVBIA NAIOP Update July 14, 2016
 
Workhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxWorkhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick Offpptx
 
Adding Flexibility to Fairfax County's Public Facilities Manual (PFM)
Adding Flexibility to Fairfax County's Public Facilities Manual (PFM)Adding Flexibility to Fairfax County's Public Facilities Manual (PFM)
Adding Flexibility to Fairfax County's Public Facilities Manual (PFM)
 
Parkville Downtown Masterplan
Parkville Downtown MasterplanParkville Downtown Masterplan
Parkville Downtown Masterplan
 
Public Facilities Manual Flexibility Project - Phase 2 Update
Public Facilities Manual Flexibility Project - Phase 2 UpdatePublic Facilities Manual Flexibility Project - Phase 2 Update
Public Facilities Manual Flexibility Project - Phase 2 Update
 
Fairfax County's Public Facilities Manual (PFM): Update to the Providence Dis...
Fairfax County's Public Facilities Manual (PFM): Update to the Providence Dis...Fairfax County's Public Facilities Manual (PFM): Update to the Providence Dis...
Fairfax County's Public Facilities Manual (PFM): Update to the Providence Dis...
 
Public Facilities Manual Flexibility Project : Update to the Development Proc...
Public Facilities Manual Flexibility Project : Update to the Development Proc...Public Facilities Manual Flexibility Project : Update to the Development Proc...
Public Facilities Manual Flexibility Project : Update to the Development Proc...
 
ULI in Action on Transportation and Infrastructure: A Catalyst for Sustainabl...
ULI in Action on Transportation and Infrastructure: A Catalyst for Sustainabl...ULI in Action on Transportation and Infrastructure: A Catalyst for Sustainabl...
ULI in Action on Transportation and Infrastructure: A Catalyst for Sustainabl...
 
New direction power point
New direction power pointNew direction power point
New direction power point
 
Middleburg Heights Community Master Plan presentation
Middleburg Heights Community Master Plan presentationMiddleburg Heights Community Master Plan presentation
Middleburg Heights Community Master Plan presentation
 
SCOPING.ppt
SCOPING.pptSCOPING.ppt
SCOPING.ppt
 
Day 2: Plan to Project Process
Day 2: Plan to Project ProcessDay 2: Plan to Project Process
Day 2: Plan to Project Process
 
Downtown Lynn Team of Advisors Kickoff Meeting Presentation, November 21, 2012
Downtown Lynn Team of Advisors Kickoff Meeting Presentation, November 21, 2012Downtown Lynn Team of Advisors Kickoff Meeting Presentation, November 21, 2012
Downtown Lynn Team of Advisors Kickoff Meeting Presentation, November 21, 2012
 
Community Presentation - October 2017
Community Presentation - October 2017Community Presentation - October 2017
Community Presentation - October 2017
 
Broadview Heights Master Plan: Public Meeting #3
Broadview Heights Master Plan: Public Meeting #3Broadview Heights Master Plan: Public Meeting #3
Broadview Heights Master Plan: Public Meeting #3
 
City of Maple Heights Zoning Map Updates
City of Maple Heights Zoning Map UpdatesCity of Maple Heights Zoning Map Updates
City of Maple Heights Zoning Map Updates
 
DOE Sun Shot Initiative Rooftop Solar Challenge
DOE Sun Shot Initiative Rooftop Solar ChallengeDOE Sun Shot Initiative Rooftop Solar Challenge
DOE Sun Shot Initiative Rooftop Solar Challenge
 
CREATING A STANDARDISED APPROACH TO REGIONAL ENVIRONMENTAL MANAGEMENT
CREATING A STANDARDISED APPROACH TO REGIONAL ENVIRONMENTAL MANAGEMENTCREATING A STANDARDISED APPROACH TO REGIONAL ENVIRONMENTAL MANAGEMENT
CREATING A STANDARDISED APPROACH TO REGIONAL ENVIRONMENTAL MANAGEMENT
 

Mehr von Fairfax County

Merrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementMerrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementFairfax County
 
SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS Fairfax County
 
Clarks Crossing Road Improvements 05-13-22
 Clarks Crossing Road Improvements 05-13-22 Clarks Crossing Road Improvements 05-13-22
Clarks Crossing Road Improvements 05-13-22Fairfax County
 
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxTysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxFairfax County
 
Lorton Volunteer Fire Station #19
Lorton Volunteer Fire Station  #19 Lorton Volunteer Fire Station  #19
Lorton Volunteer Fire Station #19 Fairfax County
 
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationScotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationFairfax County
 
Sully Community Center Construction Progress
Sully Community Center Construction ProgressSully Community Center Construction Progress
Sully Community Center Construction ProgressFairfax County
 
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxRiverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxFairfax County
 
Burke VRE Connector Phase IV
Burke VRE Connector Phase IVBurke VRE Connector Phase IV
Burke VRE Connector Phase IVFairfax County
 
Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Fairfax County
 
Workhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilWorkhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilFairfax County
 
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptxFairfax County
 
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT Fairfax County
 
Reston Arts Community Center Feasibility - Wrap Up
 Reston Arts Community Center Feasibility - Wrap Up Reston Arts Community Center Feasibility - Wrap Up
Reston Arts Community Center Feasibility - Wrap UpFairfax County
 
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Fairfax County
 
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Fairfax County
 
Oak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectOak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectFairfax County
 
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Fairfax County
 
Reston Arts Center Feasibility - Focus Group Visual Arts
Reston Arts Center Feasibility -  Focus Group Visual ArtsReston Arts Center Feasibility -  Focus Group Visual Arts
Reston Arts Center Feasibility - Focus Group Visual ArtsFairfax County
 
Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022
Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022
Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022Fairfax County
 

Mehr von Fairfax County (20)

Merrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementMerrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer Replacement
 
SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS
 
Clarks Crossing Road Improvements 05-13-22
 Clarks Crossing Road Improvements 05-13-22 Clarks Crossing Road Improvements 05-13-22
Clarks Crossing Road Improvements 05-13-22
 
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxTysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
 
Lorton Volunteer Fire Station #19
Lorton Volunteer Fire Station  #19 Lorton Volunteer Fire Station  #19
Lorton Volunteer Fire Station #19
 
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationScotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
 
Sully Community Center Construction Progress
Sully Community Center Construction ProgressSully Community Center Construction Progress
Sully Community Center Construction Progress
 
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxRiverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
 
Burke VRE Connector Phase IV
Burke VRE Connector Phase IVBurke VRE Connector Phase IV
Burke VRE Connector Phase IV
 
Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022
 
Workhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilWorkhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing Council
 
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
 
Reston Arts Community Center Feasibility - Wrap Up
 Reston Arts Community Center Feasibility - Wrap Up Reston Arts Community Center Feasibility - Wrap Up
Reston Arts Community Center Feasibility - Wrap Up
 
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
 
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
 
Oak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectOak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction Project
 
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
 
Reston Arts Center Feasibility - Focus Group Visual Arts
Reston Arts Center Feasibility -  Focus Group Visual ArtsReston Arts Center Feasibility -  Focus Group Visual Arts
Reston Arts Center Feasibility - Focus Group Visual Arts
 
Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022
Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022
Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022
 

Kürzlich hochgeladen

KAHULUGAN AT KAHALAGAHAN NG GAWAING PANSIBIKO.pptx
KAHULUGAN AT KAHALAGAHAN NG GAWAING PANSIBIKO.pptxKAHULUGAN AT KAHALAGAHAN NG GAWAING PANSIBIKO.pptx
KAHULUGAN AT KAHALAGAHAN NG GAWAING PANSIBIKO.pptxjohnandrewcarlos
 
30042024_First India Newspaper Jaipur.pdf
30042024_First India Newspaper Jaipur.pdf30042024_First India Newspaper Jaipur.pdf
30042024_First India Newspaper Jaipur.pdfFIRST INDIA
 
Kishan Reddy Report To People (2019-24).pdf
Kishan Reddy Report To People (2019-24).pdfKishan Reddy Report To People (2019-24).pdf
Kishan Reddy Report To People (2019-24).pdfKISHAN REDDY OFFICE
 
Group_5_US-China Trade War to understand the trade
Group_5_US-China Trade War to understand the tradeGroup_5_US-China Trade War to understand the trade
Group_5_US-China Trade War to understand the tradeRahatulAshafeen
 
04052024_First India Newspaper Jaipur.pdf
04052024_First India Newspaper Jaipur.pdf04052024_First India Newspaper Jaipur.pdf
04052024_First India Newspaper Jaipur.pdfFIRST INDIA
 
2024 03 13 AZ GOP LD4 Gen Meeting Minutes_FINAL.docx
2024 03 13 AZ GOP LD4 Gen Meeting Minutes_FINAL.docx2024 03 13 AZ GOP LD4 Gen Meeting Minutes_FINAL.docx
2024 03 13 AZ GOP LD4 Gen Meeting Minutes_FINAL.docxkfjstone13
 
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 48 (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 48 (Gurgaon)Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 48 (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 48 (Gurgaon)Delhi Call girls
 
Transformative Leadership: N Chandrababu Naidu and TDP's Vision for Innovatio...
Transformative Leadership: N Chandrababu Naidu and TDP's Vision for Innovatio...Transformative Leadership: N Chandrababu Naidu and TDP's Vision for Innovatio...
Transformative Leadership: N Chandrababu Naidu and TDP's Vision for Innovatio...srinuseo15
 
BDSM⚡Call Girls in Indirapuram Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Indirapuram Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Indirapuram Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Indirapuram Escorts >༒8448380779 Escort ServiceDelhi Call girls
 
2024 04 03 AZ GOP LD4 Gen Meeting Minutes FINAL.docx
2024 04 03 AZ GOP LD4 Gen Meeting Minutes FINAL.docx2024 04 03 AZ GOP LD4 Gen Meeting Minutes FINAL.docx
2024 04 03 AZ GOP LD4 Gen Meeting Minutes FINAL.docxkfjstone13
 
Verified Love Spells in Little Rock, AR (310) 882-6330 Get My Ex-Lover Back
Verified Love Spells in Little Rock, AR (310) 882-6330 Get My Ex-Lover BackVerified Love Spells in Little Rock, AR (310) 882-6330 Get My Ex-Lover Back
Verified Love Spells in Little Rock, AR (310) 882-6330 Get My Ex-Lover BackPsychicRuben LoveSpells
 
Nara Chandrababu Naidu's Visionary Policies For Andhra Pradesh's Development
Nara Chandrababu Naidu's Visionary Policies For Andhra Pradesh's DevelopmentNara Chandrababu Naidu's Visionary Policies For Andhra Pradesh's Development
Nara Chandrababu Naidu's Visionary Policies For Andhra Pradesh's Developmentnarsireddynannuri1
 
TDP As the Party of Hope For AP Youth Under N Chandrababu Naidu’s Leadership
TDP As the Party of Hope For AP Youth Under N Chandrababu Naidu’s LeadershipTDP As the Party of Hope For AP Youth Under N Chandrababu Naidu’s Leadership
TDP As the Party of Hope For AP Youth Under N Chandrababu Naidu’s Leadershipanjanibaddipudi1
 
AI as Research Assistant: Upscaling Content Analysis to Identify Patterns of ...
AI as Research Assistant: Upscaling Content Analysis to Identify Patterns of ...AI as Research Assistant: Upscaling Content Analysis to Identify Patterns of ...
AI as Research Assistant: Upscaling Content Analysis to Identify Patterns of ...Axel Bruns
 
WhatsApp 📞 8448380779 ✅Call Girls In Chaura Sector 22 ( Noida)
WhatsApp 📞 8448380779 ✅Call Girls In Chaura Sector 22 ( Noida)WhatsApp 📞 8448380779 ✅Call Girls In Chaura Sector 22 ( Noida)
WhatsApp 📞 8448380779 ✅Call Girls In Chaura Sector 22 ( Noida)Delhi Call girls
 
THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...
THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...
THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...Faga1939
 
{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...
{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...
{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...hyt3577
 
BDSM⚡Call Girls in Sector 135 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 135 Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Sector 135 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 135 Noida Escorts >༒8448380779 Escort ServiceDelhi Call girls
 
BDSM⚡Call Girls in Greater Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Greater Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Greater Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Greater Noida Escorts >༒8448380779 Escort ServiceDelhi Call girls
 
Pakistan PMLN Election Manifesto 2024.pdf
Pakistan PMLN Election Manifesto 2024.pdfPakistan PMLN Election Manifesto 2024.pdf
Pakistan PMLN Election Manifesto 2024.pdfFahimUddin61
 

Kürzlich hochgeladen (20)

KAHULUGAN AT KAHALAGAHAN NG GAWAING PANSIBIKO.pptx
KAHULUGAN AT KAHALAGAHAN NG GAWAING PANSIBIKO.pptxKAHULUGAN AT KAHALAGAHAN NG GAWAING PANSIBIKO.pptx
KAHULUGAN AT KAHALAGAHAN NG GAWAING PANSIBIKO.pptx
 
30042024_First India Newspaper Jaipur.pdf
30042024_First India Newspaper Jaipur.pdf30042024_First India Newspaper Jaipur.pdf
30042024_First India Newspaper Jaipur.pdf
 
Kishan Reddy Report To People (2019-24).pdf
Kishan Reddy Report To People (2019-24).pdfKishan Reddy Report To People (2019-24).pdf
Kishan Reddy Report To People (2019-24).pdf
 
Group_5_US-China Trade War to understand the trade
Group_5_US-China Trade War to understand the tradeGroup_5_US-China Trade War to understand the trade
Group_5_US-China Trade War to understand the trade
 
04052024_First India Newspaper Jaipur.pdf
04052024_First India Newspaper Jaipur.pdf04052024_First India Newspaper Jaipur.pdf
04052024_First India Newspaper Jaipur.pdf
 
2024 03 13 AZ GOP LD4 Gen Meeting Minutes_FINAL.docx
2024 03 13 AZ GOP LD4 Gen Meeting Minutes_FINAL.docx2024 03 13 AZ GOP LD4 Gen Meeting Minutes_FINAL.docx
2024 03 13 AZ GOP LD4 Gen Meeting Minutes_FINAL.docx
 
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 48 (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 48 (Gurgaon)Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 48 (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 48 (Gurgaon)
 
Transformative Leadership: N Chandrababu Naidu and TDP's Vision for Innovatio...
Transformative Leadership: N Chandrababu Naidu and TDP's Vision for Innovatio...Transformative Leadership: N Chandrababu Naidu and TDP's Vision for Innovatio...
Transformative Leadership: N Chandrababu Naidu and TDP's Vision for Innovatio...
 
BDSM⚡Call Girls in Indirapuram Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Indirapuram Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Indirapuram Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Indirapuram Escorts >༒8448380779 Escort Service
 
2024 04 03 AZ GOP LD4 Gen Meeting Minutes FINAL.docx
2024 04 03 AZ GOP LD4 Gen Meeting Minutes FINAL.docx2024 04 03 AZ GOP LD4 Gen Meeting Minutes FINAL.docx
2024 04 03 AZ GOP LD4 Gen Meeting Minutes FINAL.docx
 
Verified Love Spells in Little Rock, AR (310) 882-6330 Get My Ex-Lover Back
Verified Love Spells in Little Rock, AR (310) 882-6330 Get My Ex-Lover BackVerified Love Spells in Little Rock, AR (310) 882-6330 Get My Ex-Lover Back
Verified Love Spells in Little Rock, AR (310) 882-6330 Get My Ex-Lover Back
 
Nara Chandrababu Naidu's Visionary Policies For Andhra Pradesh's Development
Nara Chandrababu Naidu's Visionary Policies For Andhra Pradesh's DevelopmentNara Chandrababu Naidu's Visionary Policies For Andhra Pradesh's Development
Nara Chandrababu Naidu's Visionary Policies For Andhra Pradesh's Development
 
TDP As the Party of Hope For AP Youth Under N Chandrababu Naidu’s Leadership
TDP As the Party of Hope For AP Youth Under N Chandrababu Naidu’s LeadershipTDP As the Party of Hope For AP Youth Under N Chandrababu Naidu’s Leadership
TDP As the Party of Hope For AP Youth Under N Chandrababu Naidu’s Leadership
 
AI as Research Assistant: Upscaling Content Analysis to Identify Patterns of ...
AI as Research Assistant: Upscaling Content Analysis to Identify Patterns of ...AI as Research Assistant: Upscaling Content Analysis to Identify Patterns of ...
AI as Research Assistant: Upscaling Content Analysis to Identify Patterns of ...
 
WhatsApp 📞 8448380779 ✅Call Girls In Chaura Sector 22 ( Noida)
WhatsApp 📞 8448380779 ✅Call Girls In Chaura Sector 22 ( Noida)WhatsApp 📞 8448380779 ✅Call Girls In Chaura Sector 22 ( Noida)
WhatsApp 📞 8448380779 ✅Call Girls In Chaura Sector 22 ( Noida)
 
THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...
THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...
THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...
 
{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...
{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...
{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...
 
BDSM⚡Call Girls in Sector 135 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 135 Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Sector 135 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 135 Noida Escorts >༒8448380779 Escort Service
 
BDSM⚡Call Girls in Greater Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Greater Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Greater Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Greater Noida Escorts >༒8448380779 Escort Service
 
Pakistan PMLN Election Manifesto 2024.pdf
Pakistan PMLN Election Manifesto 2024.pdfPakistan PMLN Election Manifesto 2024.pdf
Pakistan PMLN Election Manifesto 2024.pdf
 

PFM Project Phase 2 Update

  • 1. Public Facilities Manual Project Phase 2 Update Don Lacquement, Project Manager Danielle Badra, Outreach Coordinator Land Development Services
  • 2. Today’s Presentation • Background • Phase 2 Objectives • Actions to Date • Outreach • Phase 2 Highlights • Projected Schedule • Easy Ways to Be Involved • Contact Information 2
  • 3. Background December 4, 2018 BOS approved “Phase 1” revisions to achieve targeted flexibility & clarity in the land development review process. 3
  • 4. Phase 2 Objectives • Resolve Complex Phase 1 Issues/Vet • Bring PFM into Alignment with Codes • Remove Replication • Incorporate LTIs • Add New and Updated Guidelines 4
  • 5. Actions to Date • Developed a Phase 2 PFM Website. • Completed: Spring P2 Package - July 16, 2019. • In Progress: Winter P2 Package. 5
  • 8. Engineering Standards Review Committee 8 • Paul Johnson (NVBIA) • Kevin Nelson (VDOT/ESRC) • Mark Liberati (Virginia Association of Surveyors) • Keith Sinclair (ESI) • Theodore Britt (VSPE) • James Clark (Heavy Construction Contractors Association) • Howard Guba (Citizen-at-Large) • Michael Kitchen (NAIOP) • Robert Kohnke (NVSWCD) • Bryan Layman (Associated Builders and Contractors) • Kevin Pullen (League of Women Voters) • Dr. Robert Norwood (Citizen-at-Large) • Paul Norsi (Citizen-at-Large) • Ned Poffenberger (Fairfax County Federation of Citizens Associations) • Robert Scheller (WACEL) • Bruce Titus (Fairfax Bar Association)
  • 9. Phase 2 HighlightsStreetLights • Align PFM with Regulations of VDOT, Chapter 118. • Incorporate the Urban Design Guidelines in CRAs, CRDs & Mixed-Use areas. GeneralInformation ✓Modernize Street Lights to Light Emitting Diode (LED) Fixtures. StormDrainage ✓Provide alternative pipe material for storm sewer. ✓Require Dam Breach Inundation Zone maps with as-builts. • Chapter 6 revisions (In progress). 9
  • 10. Phase 2 HighlightsStreets • Point to VDOT Standards to facilitate design & review of streets. • Define shared- use path. Trails&Recreation • Update trails information to reflect the Countywide Trails Plan. SanitarySewer • Pressurized sewer. • Elevating Manhole tops. • Damaged Pipe (replaced not repaired). 10
  • 11. Phase 2 HighlightsTreeConservation • Clarify critical root zone requirement. • Buffer restoration specifications (In Progress). Geotechnical • Setting residential basement elevation above groundwater table. • Use of lime in construction. Geotechnical • Exploration requirements for high bearing structures. • Exploration requirements for deep foundations. 11
  • 12. Projected Schedule Winter P2 Package: ➢Outreach: April through December 2019. ➢Public hearings by April 2020. 12
  • 13. Easy Ways to Be Involved Check out the PFM Project website. Review the chapter edits - routinely. Use the online feedback form or email. Attend the public hearings. 13