This document provides information about alternatives being considered for dredging Lake Accotink in Fairfax County, VA. It summarizes the project background, including previous dredging events and sediment deposition rates. It then discusses the development and screening of various dredging, dewatering, disposal location, and pipeline route alternatives. Key factors like impacts to the community, environment, and costs were considered. The document retains several processing area, dewatering location, and pipeline route alternatives for further analysis to identify a preferred alternative for dredging Lake Accotink.
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Lake Accotink Dredging Alternatives Analysis
1. A Fairfax County, VA, publication
Department of Public Works and Environmental Services
Working for You!
July 29 and August 5, 2021
Public Presentation – Alternatives Analysis
Lake Accotink Dredging
2. DPWES Stormwater Planning Division
Project Background
2
Lake Accotink Dredging
Lake Siltation
Lake Accotink has been dredged three times over the past 40 years.
The most recent dredging was completed in May 2008.
An average of 20,000 CY of sediment is deposited in the lake per year.
The estimated average depth of the lake is less than 4 feet.
Park Master Plan Process
• Master Plan began Spring 2016.
• 5 Public Meetings/Workshops held with Community.
• 6 Lake Management Options were shared with the public.
• 90% of public comments favored having the lake.
Board of Supervisors Approval of Funding
• BOS approved request to seek funding for up to $30.5 million to
proceed with Lake Accotink Dredging in October 2019 .
3. DPWES Stormwater Planning Division
Project Overview
3
Lake Accotink Dredging
Description
• Dredge estimated 500,000 cubic yards of sediment
to restore lake to average 8 ft depth.
• Pump sediment to location within Wakefield or
Lake Accotink Park for dewatering and disposal.
• Establish maintenance dredging program to
sustain the lake.
• Retain aesthetic and recreation value of the lake.
4. DPWES Stormwater Planning Division
Project Team
4
Lake Accotink Dredging
Department of Public
Works & Environmental
Services
Charles Smith
Project Manager – Stormwater
Justin Pistore
Project Manager - Stormwater
Aaron George
Lake Management – Stormwater
Jay Horstman
Construction Management –
Capital Facilities
Tom Richardson
Sanitary Sewer Coordination –
Wastewater
Fairfax County Park
Authority
Valerie Maislin
Project Manager – Planning and
Development
Adam Wynn
Lake Accotink Park Master Plan
Project Manager – Planning and
Development
Dan Grulke
Lake Accotink Manager – Park
Services
Chris Goldbecker
Lake Front Park Manager – Park
Services
Amber Stramel
Area 2 Manager – Park Operations
Braddock District
Supervisor
Marcia Pape
Supervisor’s Aide
Arcadis
Team
Mike Wooden
Project Manager
Fernando Pasquel
Project Director
Akshay Kumar
Assistant Project Manager
Liz Hover
Materials Management
Amanda Kohler
Conveyance & Dewatering System
Shannon Dunn
Sediment Characterization & Water Quality
Susan Larcher
Public Outreach
Frank Graziano (WSSI)
Survey & Permitting
ECS
Geotechnical Analysis
Key Stakeholder
Groups
Friends of Lake Accotink Park
Friends of Accotink Creek
Save Lake Accotink
Homeowner & Civic
Associations
Mid-Atlantic Off-Road
Enthusiasts
Lake Accotink Dredging
Critical Players
5. DPWES Stormwater Planning Division
Project Schedule
5
Lake Accotink Dredging
Data collection and survey – April 2021
Alternatives Analysis – July 12, 2021
Public Comment July 22 to August 22
Public Meeting July 29 & August 5
Concept Design and Value Engineering
Study – May 2022
Final Design and Permitting – May 2023
Begin Dredging – Fall 2023
Complete Dredging – 2026
Post Construction Monitoring – 2026 to
2031
Lake Accotink dredging operations June 21,
2006 – Photo by Fairfax County DPWES
33. Limits Park & Community
Impacts; Long-Term Use;
Restoration & Remobilization;
Extent of Clearing, Floodplain
33
Wakefield Park
Maintenance Facility
Areas
Type Acreages
Maximum Limits of Disturbance 7.7
Wetlands 0
Floodplain 2.6
Resource Protection Area 4.0
Method Compatibility*
Production (cy/day)
Slurry Solids
950
7%
950
15%
1250
7%
1250
15%
Passive Yes Yes No No
Passive w/ Desanding No No No No
Mechanical Maybe Yes No Maybe
Drying Agent No No
Rating Summary
*Based on current assumptions
From Alternative Analysis Report Figure 6-3
Unknown
• Extent of Braddock Rd Improvements
35. 10 August 2021 35
Dominion ROW
Areas
Type Acreages
Maximum Limits of Disturbance 10
Wetlands 0.2
Floodplain 6.2
Resource Protection Area 9.7
Method Compatibility*
Production (cy/day)
Slurry Solids
950
7%
950
15%
1250
7%
1250
15%
Passive Maybe Maybe No No
Passive w/ Desanding No No No No
Mechanical Maybe Maybe No Maybe
Drying Agent No No
*Based on current assumptions
Rating Summary
Clearing/Wetland Impacts;
Restoration & Remobilization
Floodplain; Truck Access
From Alternative Analysis Report Figure 6-5
Unknown
• Dominion requirements / use restrictions
37. 10 August 2021 37
Upper Settling Basin
Areas
Type Acreages
Maximum Limits of Disturbance 6.7
Wetlands 4.1
Floodplain 0
Resource Protection Area 6.7
Method Compatibility*
Production (cy/day)
Slurry Solids
950
7%
950
15%
1250
7%
1250
15%
Passive Maybe Maybe No No
Passive w/ Desanding No No No No
Mechanical Maybe Maybe No Maybe
Drying Agent No No
*Based on current assumptions
Rating Summary
Improve Infrastructure; Outside
Floodplain; Water Return;
Restoration & Remobilization
Trail & Wetland Impacts, Grading;
Soil Condition, Community Impacts,
Site Preparation; Accessibility
From Alternative Analysis Report Figure 6-6
Unknown
• Surface/Subsurface Conditions
• Embankment Stability
39. 10 August 2021 39
Howrey Field
Areas
Type Acreages
Maximum Limits of Disturbance 7.5
Wetlands 0
Floodplain 4.5
Resource Protection Area 3.7
Method Compatibility*
Production (cy/day)
Slurry Solids
950
7%
950
15%
1250
7%
1250
15%
Passive Maybe Maybe No No
Passive w/ Desanding No No No No
Mechanical Maybe Maybe No Maybe
Drying Agent No No
*Based on current assumptions
Rating Summary
Accessibility; Truck Traffic
Park Use; Memorial; Restoration
& Remobilization; Floodplain;
Return Water
From Alternative Analysis Report Figure 6-2
Howrey Field
Unknown
• Extent of Braddock Rd Improvements
40. Howrey Field Slurry Transport Alignments
Type HF1 - Cross-County
Trail
HF3 - Flag Run/Port Royal Road HF4 - Flag Run/I-495
Alignment
Length, mi. 1.3 2.2 2.2
Pipe Diameter, inches 12 to 14 16 to 18 16 to 18
Difference in Elevation1, ft. 15 105 110
No. of Utility Crossings2, ea. 27 59 37
No. of Water Feature/Trail Crossings 8 32 29
Note:
1. Difference in elevation between highest and lowest point along the alignment.
2. Sewer, Stormwater, Electrical & Water. 29 July 2021
Detailed Evaluation in Exhibit 5 of Alternatives Analysis Report
41. 10 August 2021 41
Lake Accotink Island
(Current Footprint)
Areas
Type Acreages
Maximum Limits of Disturbance 3.3
Wetlands 3.0
Floodplain 3.3
Resource Protection Area 3.3
Method Compatibility*
Production (cy/day)
Slurry Solids
950
7%
950
15%
1250
7%
1250
15%
Passive No No No No
Passive w/ Desanding No No No No
Mechanical No No No No
Drying Agent
Yes – if barge
transport
Yes – if barge
transport
*Based on current assumptions
Rating Summary
No Pipeline; Water Return
Park and Environmental Impacts,
Accessibility, Truck Traffic,
Floodplain
From Alternative Analysis Report Figure 6-7
Unknown
• Surface/subsurface conditions of island
42. 10 August 2021 42
Lake Accotink Island
(Expanded Footprint)
Areas
Type Acreages
Maximum Limits of Disturbance 10
Wetlands 4.4
Floodplain 9.6
Resource Protection Area 10
Method Compatibility*
Production (cy/day)
Slurry Solids
950
7%
950
15%
1250
7%
1250
15%
Passive Yes Yes Yes Yes
Passive w/ Desanding Maybe Maybe Maybe Maybe
Mechanical No No No No
Drying Agent
Yes – if barge
transport
Yes – if barge
transport
*Based on current assumptions
Rating Summary
No Pipeline, Water Return,
Method Compatibility
Park and Environmental Impacts,
Site Preparation, Accessibility,
Truck Traffic, Floodplain, Cost
From Alternative Analysis Report Figure 6-8
Unknown
• Surface/subsurface condition of island and land bridge
area
45. DPWES Stormwater Planning Division
Staff Recommendations
45
Lake Accotink Dredging
Dredging: Pursue hydraulic dredging with mechanical
debris removal.
Pipeline:
Pursue lowest impact/cost pipeline alternative: along
CCT, lake perimeter trail or Flag Run/Port Royal Road
or Beltway.
Retain flexibility during design for permanent and
temporary pipeline options.
Dewatering:
Retain consideration for four potential locations
during design for maximum flexibility, impact
minimization, cost efficiency:
Dominion Energy ROW – Wakefield Park
Settling Basin – Lake Accotink Park
Maintenance Area – Wakefield Park
Lake Island – Lake Accotink Park
48. DPWES Stormwater Planning Division
Discussion
Discussion & Questions
48
Native mussels below Lake Accotink dam –
Photo by Friends of Accotink Creek
Lake Accotink Dredging
Community stewardship – Photo by Friends
of Lake Accotink Park
Cardboard boat regatta – Photo
by Friends of Lake Accotink Park
Mallard ducks – Photo by Fairfax
County Park Authority
49. DPWES Stormwater Planning Division 49
Lake Accotink Dredging
Thanks for Attending!!
The window for comments will be open until
Sunday, August 22, 2021.
Public Input Webpage: https://publicinput.com/R018
For Additional Information, to Comment or Sign up for Email
Updates, Please Visit the Project Web Page:
https://www.fairfaxcounty.gov/publicworks/lake-accotink-
dredging