SlideShare ist ein Scribd-Unternehmen logo
1 von 49
A Fairfax County, VA, publication
Department of Public Works and Environmental Services
Working for You!
July 29 and August 5, 2021
Public Presentation – Alternatives Analysis
Lake Accotink Dredging
DPWES Stormwater Planning Division
Project Background
2
Lake Accotink Dredging
Lake Siltation
 Lake Accotink has been dredged three times over the past 40 years.
 The most recent dredging was completed in May 2008.
 An average of 20,000 CY of sediment is deposited in the lake per year.
 The estimated average depth of the lake is less than 4 feet.
Park Master Plan Process
• Master Plan began Spring 2016.
• 5 Public Meetings/Workshops held with Community.
• 6 Lake Management Options were shared with the public.
• 90% of public comments favored having the lake.
Board of Supervisors Approval of Funding
• BOS approved request to seek funding for up to $30.5 million to
proceed with Lake Accotink Dredging in October 2019 .
DPWES Stormwater Planning Division
Project Overview
3
Lake Accotink Dredging
Description
• Dredge estimated 500,000 cubic yards of sediment
to restore lake to average 8 ft depth.
• Pump sediment to location within Wakefield or
Lake Accotink Park for dewatering and disposal.
• Establish maintenance dredging program to
sustain the lake.
• Retain aesthetic and recreation value of the lake.
DPWES Stormwater Planning Division
Project Team
4
Lake Accotink Dredging
Department of Public
Works & Environmental
Services
Charles Smith
Project Manager – Stormwater
Justin Pistore
Project Manager - Stormwater
Aaron George
Lake Management – Stormwater
Jay Horstman
Construction Management –
Capital Facilities
Tom Richardson
Sanitary Sewer Coordination –
Wastewater
Fairfax County Park
Authority
Valerie Maislin
Project Manager – Planning and
Development
Adam Wynn
Lake Accotink Park Master Plan
Project Manager – Planning and
Development
Dan Grulke
Lake Accotink Manager – Park
Services
Chris Goldbecker
Lake Front Park Manager – Park
Services
Amber Stramel
Area 2 Manager – Park Operations
Braddock District
Supervisor
Marcia Pape
Supervisor’s Aide
Arcadis
Team
Mike Wooden
Project Manager
Fernando Pasquel
Project Director
Akshay Kumar
Assistant Project Manager
Liz Hover
Materials Management
Amanda Kohler
Conveyance & Dewatering System
Shannon Dunn
Sediment Characterization & Water Quality
Susan Larcher
Public Outreach
Frank Graziano (WSSI)
Survey & Permitting
ECS
Geotechnical Analysis
Key Stakeholder
Groups
Friends of Lake Accotink Park
Friends of Accotink Creek
Save Lake Accotink
Homeowner & Civic
Associations
Mid-Atlantic Off-Road
Enthusiasts
Lake Accotink Dredging
Critical Players
DPWES Stormwater Planning Division
Project Schedule
5
Lake Accotink Dredging
 Data collection and survey – April 2021
 Alternatives Analysis – July 12, 2021
 Public Comment July 22 to August 22
 Public Meeting July 29 & August 5
 Concept Design and Value Engineering
Study – May 2022
 Final Design and Permitting – May 2023
 Begin Dredging – Fall 2023
 Complete Dredging – 2026
 Post Construction Monitoring – 2026 to
2031
Lake Accotink dredging operations June 21,
2006 – Photo by Fairfax County DPWES
© Arcadis 2021
Photo courtesy of Tom Kinder
Alternatives Analysis
July 29 and August 5, 2021
Lake Accotink
Dredging
Alternatives Analysis Report
Full Report Available on Project Website: https://www.fairfaxcounty.gov/publicworks/lake-accotink-dredging
1. Introduction
2. Summary of Existing Data
3. Evaluation Criteria
4. Development and Screening of Methods
5. Environmental and Cultural Resource Evaluation
6. Development and Screening of Alternatives
7. Analysis of Retained Alternatives
29 July 2021
© Arcadis 2021
Lake Accotink Information
Watershed Area 19,600 acres
Lake Area 55 acres
Average Sedimentation Rate 23,000 cubic yards per year
Previous Dredging Events 1960s, 1985, 2008
Nearby Land Use Parks, Residential, Light
Industrial
Surrounding Habitat Forests, marshes, and
ephemeral wetlands
All values are approximate
• Project to include dredging, sediment
transport, and disposal by truck
• Increase lake depth and overall
volume of the lake
• Facilitate retention of the aesthetic
and recreational value of the lake
• Provide a dredging maintenance
plan that allows the lake to remain a
valuable asset to the community
Objective and Scope
29 July 2021
Lake Accotink Existing
Conditions
Alternatives Analysis Report
Figure 1-2
Introduction
© Arcadis 2021
29 July 2021
© Arcadis 2021
Summary of Existing Data
© Arcadis 2021
Category Criteria
Park Management Long-Term Park Vision
Community
Recreational Use Restrictions During Construction
Community Considerations During Construction
Environment
Environmental Considerations
Floodplain Impacts
Sustainability
Construction and Dredging
Program Operation
Available Area and Accessibility
Site Preparation Requirements
Flexibility/Compatibility with Various Equipment
Efficient Water Return
Constructability
Long-Term Operation and Maintenance
Schedule
Costs
Evaluation Criteria
Sub-Criteria Developed for Each of the Components Evaluated
29 July 2021
© Arcadis 2021
Assumptions
29 July 2021
• Target Final Water Depth – 8 feet
• Dredge Volume – 450,000 to 500,00
cubic yards
• Construction Schedule – 3 years
• Dredging Schedule – 2 years
• Average Dredging Rate – 950 cubic
yards per day
Development and Screening of
Methods
Dredging
© Arcadis 2021
Dredging Methods
29 July 2021
Mechanical
Amphibious (Hybrid)
Hydraulic
8 cubic yard bucket
16 cubic yard bucket
8-inch dredge
14-inch dredge
© Arcadis 2021 29 July 2021
Dredging Method Evaluation Table
8-cubic-yard
bucket
16-cubic-yard
bucket
8-inch dredge
14-inch
dredge
Lost Use Days Minimizes days lost     
Reduced Use Minimizes reduced use of lake     
Existing Infrastructure Impacts Minimizes impacts to existing infrastructure     
Lake Use
Minimizes impacts to lake use due to dredging
activities (including aesthetic considerations)
    
Facilities Availability
Avoids closures of park facilities (e.g., marina,
parking)
    
Minimizes Noise
Comparison of relative proximity of potential
receptors     
Minimizes Odors/Dust
Comparison of relative proximity of potential
receptors     
Impacts to Aquatic Wildlife Minimizes impacts to aquatic wildlife     
Wetland Impacts Minimizes impacts to wetlands     
Impacts to Terrestrial Wildlife Minimizes impacts to terrestrial wildlife     
Minimize Floodplain Impacts --     
Minimizes Sediment
Resuspension
--     
Greenhouse Emissions Minimizes greenhouse gas emissions     
Preserving wetlands Minimizes impacts to wetlands     
Minimizes Clearing/Grading --     
Requires Updated Infrastructure
Minimizes required updates to existing
infrastructure     
Sediment Processing
Considerations
Adaptability to pipeline transport     
Maneuverability Around Dock/Dam --     
Dredge Equipment Accuracy --     
Separate debris removal step required     
Convertible for debris removal     
Availability --     
Seasonal Restrictions Seasonal impacts on dredge use     
Production Average sustained production rate     
Relative Costs --     
Criteria Sub-Criteria
Mechanical Hydraulic
Amphibious
Debris Compatibility








Low Compatibility
Medium Compatibility
High Compatibility
© Arcadis 2021 29 July 2021
Key Takeaways
• All options are feasible
• Main challenges (red ratings)
– Hydraulic – debris handling
– Amphibious – production rate
– Mechanical – community and
floodplain impacts
Dredging Method Evaluation
Detailed Evaluation in Exhibit 1 of Alternatives Analysis Report
Dewatering
© Arcadis 2021
3.5 – 4.9 acres
PASSIVE (GEOTEXTILE TUBE)
Dewatering Methods
29 July 2021
PASSIVE WITH DESANDING
5.2 – 7.4 acres
MECHANICAL
3.2 – 5.8 acres
DRYING AGENT
Island Options Only
© Arcadis 2021
Dewatering Method Evaluations
29 July 2021
Key Takeaways
• Passive is simple and relatively
low-cost but needs large, flat area
• Mechanical can accommodate
higher throughput and creates
drier material but is higher cost
• Identify location to provide most
flexibility for contractor’s approach
Detailed Evaluation in Exhibit 2 of Alternatives Analysis Report
Disposal Location
© Arcadis 2021
Disposal Locations
29 July 2021
Island Expansion Bank Restoration County Use Offsite Reuse Offsite Landfill
© Arcadis 2021
Disposal Location Evaluation
29 July 2021
Key Takeaways
• All disposal locations can be
paired with any of the dredging
and dewatering options
• Offsite landfill and offsite reuse
have no public impacts but
have higher costs
• Onsite reuse has lower costs
but has public impacts
Detailed Evaluation in Exhibit 3 of Alternatives Analysis Report
Environmental and Cultural
Resource Evaluation
Details in Table 5-1 and Appendix C of Alternative Analysis Report
• Provided impacts likely a "Worst Case Scenario"
• No distinction between "temporary" vs "permanent" wetland impacts
• Permit will require avoidance and minimization, reducing noted impacts
• Largest dewatering site "impacts" are associated with use of the island or
settling basin
• Largest pipeline "impacts" are for alignments in stream valleys
• Largest tree "impacts" in stream valleys, maintenance area, settling basin
Potential Wetland and Vegetative Impacts
29 July 2021
© Arcadis 2021
Potential Cultural Resource Impacts
Details in Appendix D of Alternative Analysis Report
• Based on Virginia Department of Historic Resources (VDHR) database
review of previously recorded cultural resources within or adjacent to
potential alignments and dewatering sites
• Seven sites were identified, consisting of prehistoric lithic scatter, civil
war era features, and/or portions of the Orange & Alexandria rail bed
• No sites have been evaluated for listing in the National Register of
Historic Places (NRHP)
• Sites could also meet Fairfax County criteria for local significance
29 July 2021
© Arcadis 2021
Development and Screening of
Alternatives
Alternative Components
Detailed Evaluation in Exhibit 4 of
Alternatives Analysis Report
North of Braddock Road
1. Howrey Field
2. Wakefield Park Maintenance Facility
3. Wakefield Ball Fields
4. Dominion Energy (Dominion) Right-of-Way (ROW)
Lake Accotink Park
5. Lake Accotink Upper Settling Basin
6. Lake Accotink Island – Current Footprint
7. Lake Accotink Island – Expanded Footprint
Concrete Plant
8. Concrete Plant
Dewatering Locations
North of Braddock Road
1. Cross-County Trail
2. Queensberry Avenue
3. Flag Run / Port Royal Road
4. Flag Run / Interstate 495
Lake Accotink Park
5. Lake Accotink Trail
Concrete Plant
6. Amtrak ROW
7. Residential Route
Pipeline Alignments
29 July 2021
Detailed Evaluation in Exhibit 5 of
Alternatives Analysis Report
© Arcadis 2021
© Arcadis 2021
List of Potential Alternatives
29 July 2021
# ID Description
1 HF1 Howrey Field via Cross-County trail
2 HF2 Howrey Field via Queensberry Ave
3 HF3 Howrey Field via Flag Run/Port Royal Road
4 HF4 Howrey Field via Flag Run/I-495
5 WMF1 Wakefield Park Maintenance Facility via Cross-County Trail
6 WMF2 Wakefield Park Maintenance Facility via Queensberry Ave
7 WMF3
Wakefield Park Maintenance Facility via Flag Run/Port Royal
Road
8 WMF4 Wakefield Park Maintenance Facility via Flag Run/I-495
9 WB1 Wakefield Ball Fields via Cross-County Trail
10 WB2 Wakefield Ball Fields via Queensberry Ave
11 WB3 Wakefield Ball Fields via Flag Run/Port Royal Road
12 WB4 Wakefield Ball Fields via Flag Run/I-495
13 DOM1 Dominion Right-of-Way (ROW) via Cross-County Trail
14 DOM2 Dominion ROW via Queensberry Ave
15 DOM3 Dominion ROW via Flag Run/Port Royal Road
16 DOM4 Dominion ROW via Flag Run/I-495
17 USB Lake Accotink Upper Settling Basin
18 ICF Lake Accotink Island - Current Footprint
19 IXF Lake Accotink Island - Expanded Footprint
20 VCP1 Concrete Plant via Residential
21 VCP2 Concrete Plant via Amtrak ROW
HF
WB
I
Legend
Processing Area
HF = Howrey Field
WMF = Maintenance Area
WB = Ballfields
DOM = Dominion ROW
USB = Settling Basin
I = Island (IXF, ICF)
VPC = Concrete Plant
Main Pipeline Route
HF
USB
WMF
VCP
DOM
© Arcadis 2021
HF
WB
I
Legend
Processing Area
HF = Howrey Field
WMF = Maintenance Area
WB = Ballfields
DOM = Dominion ROW
USB = Settling Basin
I = Island (IXF, ICF)
VPC = Concrete Plant
Main Pipeline Route
HF
USB
WMF
VCP
DOM
Removed & Retained Alternatives in Report
29 July 2021
# ID Description
1 HF1 Howrey Field via Cross-County trail
2 HF2 Howrey Field via Queensberry Ave 1
3 HF3 Howrey Field via Flag Run/Port Royal Road
4 HF4 Howrey Field via Flag Run/I-495
5 WMF1 Wakefield Park Maintenance Facility via Cross-County Trail
6 WMF2 Wakefield Park Maintenance Facility via Queensberry Ave 1
7 WMF3
Wakefield Park Maintenance Facility via Flag Run/Port Royal
Road
8 WMF4 Wakefield Park Maintenance Facility via Flag Run/I-495
9 WB1 Wakefield Ball Fields via Cross-County Trail 2
10 WB2 Wakefield Ball Fields via Queensberry Ave 1, 2
11 WB3 Wakefield Ball Fields via Flag Run/Port Royal Road 2
12 WB4 Wakefield Ball Fields via Flag Run/I-495 2
13 DOM1 Dominion Right-of-Way (ROW) via Cross-County Trail
14 DOM2 Dominion ROW via Queensberry Ave 1
15 DOM3 Dominion ROW via Flag Run/Port Royal Road
16 DOM4 Dominion ROW via Flag Run/I-495
17 USB Lake Accotink Upper Settling Basin
18 ICF Lake Accotink Island - Current Footprint
19 IXF Lake Accotink Island - Expanded Footprint
20 VCP1 Concrete Plant via Residential 3
21 VCP2 Concrete Plant via Amtrak ROW 3
Rationale for alternatives removed from consideration:
1. Queensberry Ave removed from consideration due to impacts to community and cost
2. Wakefield Ball Fields removed from consideration due to legal impacts and inability to replace
facility that meets Title IX obligations
3. Concrete Plant removed from consideration as property owner is unable to accommodate
dewatering operations
X
X
X
X
X
Analysis of Retained Alternatives
© Arcadis 2021
Retained Alternatives Evaluation
29 July 2021
ID Alt # Description
HF1 1 Howrey Field via Cross-County trail
HF3 3 Howrey Field via Flag Run/Port Royal Road
HF4 4 Howrey Field via Flag Run/I-495
WMF1 5 Wakefield Park Maintenance Facility via Cross-County Trail
WMF3 7
Wakefield Park Maintenance Facility via Flag Run/Port Royal
Road
WMF4 8 Wakefield Park Maintenance Facility via Flag Run/I-495
DOM1 13 Dominion Right-of-Way (ROW) via Cross-County Trail
DOM3 15 Dominion ROW via Flag Run/Port Royal Road
DOM4 16 Dominion ROW via Flag Run/I-495
USB 17 Lake Accotink Upper Settling Basin
ICF 18 Lake Accotink Island - Current Footprint
IXF 19 Lake Accotink Island - Expanded Footprint
County Staff Recommend
Removal from Consideration
Dewatering
Location
Evaluation
See Exhibit 4 of Alternatives
Analysis for Detailed Evaluation
County
Staff
Recommend
Removal
from
Consideration
29 July 2021
Limits Park & Community
Impacts; Long-Term Use;
Restoration & Remobilization;
Extent of Clearing, Floodplain
33
Wakefield Park
Maintenance Facility
Areas
Type Acreages
Maximum Limits of Disturbance 7.7
Wetlands 0
Floodplain 2.6
Resource Protection Area 4.0
Method Compatibility*
Production (cy/day)
Slurry Solids
950
7%
950
15%
1250
7%
1250
15%
Passive Yes Yes No No
Passive w/ Desanding No No No No
Mechanical Maybe Yes No Maybe
Drying Agent No No
Rating Summary
*Based on current assumptions
From Alternative Analysis Report Figure 6-3
Unknown
• Extent of Braddock Rd Improvements
© Arcadis 2021
Wakefield Park Maintenance Facility
Slurry Transport Alignments
WMF1 - Cross-County
Trail
WMF3 - Flag Run/Port Royal Road WMF4 - Flag Run/I-495
Alignment
Length, mi. 1.3 1.9 1.9
Pipe Diameter, inches 12 to 14 16 to 18 16 to 18
Difference in Elevation1, ft. 17 110 110
No. of Utility Crossings2, ea. 17 55 19
No. of Water Features/ Trail Crossings 7 29 27
Notes:
1. Difference in elevation between highest and lowest point along the alignment.
2. Sewer, Stormwater, Electrical & Water.
29 July 2021
Detailed Evaluation in Exhibit 5 of Alternatives Analysis Report
10 August 2021 35
Dominion ROW
Areas
Type Acreages
Maximum Limits of Disturbance 10
Wetlands 0.2
Floodplain 6.2
Resource Protection Area 9.7
Method Compatibility*
Production (cy/day)
Slurry Solids
950
7%
950
15%
1250
7%
1250
15%
Passive Maybe Maybe No No
Passive w/ Desanding No No No No
Mechanical Maybe Maybe No Maybe
Drying Agent No No
*Based on current assumptions
Rating Summary
Clearing/Wetland Impacts;
Restoration & Remobilization
Floodplain; Truck Access
From Alternative Analysis Report Figure 6-5
Unknown
• Dominion requirements / use restrictions
© Arcadis 2021
DOM1 - Cross-County
Trail
DOM3 - Flag Run/Port
Royal Road
DOM4 - Flag Run/I-495
Alignment
Length, mi. 2.1 2.5 2.2
Pipe Diameter, inches 16 to 18 16 to 18 16 to 18
Difference in Elevation1, ft. 25 110 105
No. of Utility Crossings2, ea. 26 66 23
No. of Water Feature/Trail Crossings 18 41 35
Note:
1. Difference in elevation between highest and lowest point along the alignment.
2. Sewer, Stormwater, Electrical & Water.
29 July 2021
Detailed Evaluation in Exhibit 5 of Alternatives Analysis Report
Dominion ROW Slurry Transport Alignments
10 August 2021 37
Upper Settling Basin
Areas
Type Acreages
Maximum Limits of Disturbance 6.7
Wetlands 4.1
Floodplain 0
Resource Protection Area 6.7
Method Compatibility*
Production (cy/day)
Slurry Solids
950
7%
950
15%
1250
7%
1250
15%
Passive Maybe Maybe No No
Passive w/ Desanding No No No No
Mechanical Maybe Maybe No Maybe
Drying Agent No No
*Based on current assumptions
Rating Summary
Improve Infrastructure; Outside
Floodplain; Water Return;
Restoration & Remobilization
Trail & Wetland Impacts, Grading;
Soil Condition, Community Impacts,
Site Preparation; Accessibility
From Alternative Analysis Report Figure 6-6
Unknown
• Surface/Subsurface Conditions
• Embankment Stability
© Arcadis 2021
Upper Settling Basin – Trail Alignment
Alignment
Length, mi. 0.7
Pipe Diameter, inches 14 to 16
Difference in Elevation1, ft. 70
No. of Utility Crossings2, ea. 9
No. of Water Feature/Trail Crossings 15
Notes:
1. Difference in elevation between highest and lowest point along the alignment.
2. Sewer, Stormwater, Electrical & Water.
29 July 2021
High Compatibility Medlium Low Compatibility
Detailed Evaluation in Exhibit 5 of Alternatives Analysis Report
Upper Settling Basin Slurry Transport Alignment
10 August 2021 39
Howrey Field
Areas
Type Acreages
Maximum Limits of Disturbance 7.5
Wetlands 0
Floodplain 4.5
Resource Protection Area 3.7
Method Compatibility*
Production (cy/day)
Slurry Solids
950
7%
950
15%
1250
7%
1250
15%
Passive Maybe Maybe No No
Passive w/ Desanding No No No No
Mechanical Maybe Maybe No Maybe
Drying Agent No No
*Based on current assumptions
Rating Summary
Accessibility; Truck Traffic
Park Use; Memorial; Restoration
& Remobilization; Floodplain;
Return Water
From Alternative Analysis Report Figure 6-2
Howrey Field
Unknown
• Extent of Braddock Rd Improvements
Howrey Field Slurry Transport Alignments
Type HF1 - Cross-County
Trail
HF3 - Flag Run/Port Royal Road HF4 - Flag Run/I-495
Alignment
Length, mi. 1.3 2.2 2.2
Pipe Diameter, inches 12 to 14 16 to 18 16 to 18
Difference in Elevation1, ft. 15 105 110
No. of Utility Crossings2, ea. 27 59 37
No. of Water Feature/Trail Crossings 8 32 29
Note:
1. Difference in elevation between highest and lowest point along the alignment.
2. Sewer, Stormwater, Electrical & Water. 29 July 2021
Detailed Evaluation in Exhibit 5 of Alternatives Analysis Report
10 August 2021 41
Lake Accotink Island
(Current Footprint)
Areas
Type Acreages
Maximum Limits of Disturbance 3.3
Wetlands 3.0
Floodplain 3.3
Resource Protection Area 3.3
Method Compatibility*
Production (cy/day)
Slurry Solids
950
7%
950
15%
1250
7%
1250
15%
Passive No No No No
Passive w/ Desanding No No No No
Mechanical No No No No
Drying Agent
Yes – if barge
transport
Yes – if barge
transport
*Based on current assumptions
Rating Summary
No Pipeline; Water Return
Park and Environmental Impacts,
Accessibility, Truck Traffic,
Floodplain
From Alternative Analysis Report Figure 6-7
Unknown
• Surface/subsurface conditions of island
10 August 2021 42
Lake Accotink Island
(Expanded Footprint)
Areas
Type Acreages
Maximum Limits of Disturbance 10
Wetlands 4.4
Floodplain 9.6
Resource Protection Area 10
Method Compatibility*
Production (cy/day)
Slurry Solids
950
7%
950
15%
1250
7%
1250
15%
Passive Yes Yes Yes Yes
Passive w/ Desanding Maybe Maybe Maybe Maybe
Mechanical No No No No
Drying Agent
Yes – if barge
transport
Yes – if barge
transport
*Based on current assumptions
Rating Summary
No Pipeline, Water Return,
Method Compatibility
Park and Environmental Impacts,
Site Preparation, Accessibility,
Truck Traffic, Floodplain, Cost
From Alternative Analysis Report Figure 6-8
Unknown
• Surface/subsurface condition of island and land bridge
area
ID Alt # Description
HF1 1 Howrey Field via Cross-County trail
HF3 3 Howrey Field via Flag Run/Port Royal Road
HF4 4 Howrey Park via Flag Run/I-495
WMF1 5 Wakefield Park Maintenance Facility via Cross-County Trail
WMF3 7
Wakefield Park Maintenance Facility via Flag Run/Port Royal
Road
WMF4 8 Wakefield Park Maintenance Facility via Flag Run/I-495
DOM1 13 Dominion Right-of-Way (ROW) via Cross-County Trail
DOM3 15 Dominion ROW via Flag Run/Port Royal Road
DOM4 16 Dominion ROW via Flag Run/I-495
USB 17 Lake Accotink Upper Settling Basin
ICF 18 Lake Accotink Island - Current Footprint
IXF 19 Lake Accotink Island - Expanded Footprint
Retained Alternatives Evaluation
29 July 2021
County Staff Recommend
Removal from Consideration
© Arcadis 2021
© Arcadis 2021
Arcadis. Improving quality of life.
Thank You For Your Time!
DPWES Stormwater Planning Division
Staff Recommendations
45
Lake Accotink Dredging
 Dredging: Pursue hydraulic dredging with mechanical
debris removal.
 Pipeline:
 Pursue lowest impact/cost pipeline alternative: along
CCT, lake perimeter trail or Flag Run/Port Royal Road
or Beltway.
 Retain flexibility during design for permanent and
temporary pipeline options.
 Dewatering:
 Retain consideration for four potential locations
during design for maximum flexibility, impact
minimization, cost efficiency:
 Dominion Energy ROW – Wakefield Park
 Settling Basin – Lake Accotink Park
 Maintenance Area – Wakefield Park
 Lake Island – Lake Accotink Park
DPWES Stormwater Planning Division
Staff Recommendations
46
Lake Accotink Dredging
DPWES Stormwater Planning Division
Staff Recommendations
47
Lake Accotink Dredging
DPWES Stormwater Planning Division
Discussion
Discussion & Questions
48
Native mussels below Lake Accotink dam –
Photo by Friends of Accotink Creek
Lake Accotink Dredging
Community stewardship – Photo by Friends
of Lake Accotink Park
Cardboard boat regatta – Photo
by Friends of Lake Accotink Park
Mallard ducks – Photo by Fairfax
County Park Authority
DPWES Stormwater Planning Division 49
Lake Accotink Dredging
Thanks for Attending!!
The window for comments will be open until
Sunday, August 22, 2021.
Public Input Webpage: https://publicinput.com/R018
For Additional Information, to Comment or Sign up for Email
Updates, Please Visit the Project Web Page:
https://www.fairfaxcounty.gov/publicworks/lake-accotink-
dredging

Weitere ähnliche Inhalte

Was ist angesagt?

Sunset Hills Road Drainage Improvement Project
Sunset Hills Road Drainage Improvement ProjectSunset Hills Road Drainage Improvement Project
Sunset Hills Road Drainage Improvement ProjectFairfax County
 
Arcadis Design Lake Accotink Dredging Public Meeting December 2020
Arcadis Design Lake Accotink Dredging Public Meeting December 2020 Arcadis Design Lake Accotink Dredging Public Meeting December 2020
Arcadis Design Lake Accotink Dredging Public Meeting December 2020 Fairfax County
 
Stormwater Wastewater Consolidation
Stormwater Wastewater ConsolidationStormwater Wastewater Consolidation
Stormwater Wastewater ConsolidationFairfax County
 
Dead Run Stream Restoration Segment 2 – 3
Dead Run Stream Restoration Segment 2 – 3Dead Run Stream Restoration Segment 2 – 3
Dead Run Stream Restoration Segment 2 – 3Fairfax County
 
Little Pimmit Run Community Meeting 10-4-2021
Little Pimmit Run Community Meeting 10-4-2021Little Pimmit Run Community Meeting 10-4-2021
Little Pimmit Run Community Meeting 10-4-2021Fairfax County
 
Huntsman Lake Dredging January 2015
Huntsman Lake Dredging January 2015Huntsman Lake Dredging January 2015
Huntsman Lake Dredging January 2015Fairfax County
 
Springfield Estates Pump Station Gravity Sewer Replacement - Community Meeting
Springfield Estates Pump Station Gravity Sewer Replacement - Community MeetingSpringfield Estates Pump Station Gravity Sewer Replacement - Community Meeting
Springfield Estates Pump Station Gravity Sewer Replacement - Community MeetingFairfax County
 
Draft Chesapeake Bay TMDL Action Plan Public Meeting
Draft Chesapeake Bay TMDL Action Plan Public MeetingDraft Chesapeake Bay TMDL Action Plan Public Meeting
Draft Chesapeake Bay TMDL Action Plan Public MeetingFairfax County
 
Turkey Run at Truro Subdivision Stream Restoration
Turkey Run at Truro Subdivision Stream RestorationTurkey Run at Truro Subdivision Stream Restoration
Turkey Run at Truro Subdivision Stream RestorationFairfax County
 
Columbia Road/Randolph Court Stream Restoration July 2015
Columbia Road/Randolph Court Stream Restoration July 2015Columbia Road/Randolph Court Stream Restoration July 2015
Columbia Road/Randolph Court Stream Restoration July 2015Fairfax County
 
Dead Run Segment One Stream Restoration Project
Dead Run Segment One Stream Restoration ProjectDead Run Segment One Stream Restoration Project
Dead Run Segment One Stream Restoration ProjectFairfax County
 
Huntington Levee Community Meeting: Oct. 26. 2016
Huntington Levee Community Meeting: Oct. 26. 2016Huntington Levee Community Meeting: Oct. 26. 2016
Huntington Levee Community Meeting: Oct. 26. 2016Fairfax County
 
Flatlick Branch Phase II Stream Restoration Project
Flatlick Branch Phase II Stream Restoration ProjectFlatlick Branch Phase II Stream Restoration Project
Flatlick Branch Phase II Stream Restoration ProjectFairfax County
 
Crook at Mantua Elementary School Stream Restoration
Crook at Mantua Elementary School Stream RestorationCrook at Mantua Elementary School Stream Restoration
Crook at Mantua Elementary School Stream RestorationFairfax County
 
Pike Branch at Wilton Road Stream Stabilization Project
Pike Branch at Wilton Road Stream Stabilization ProjectPike Branch at Wilton Road Stream Stabilization Project
Pike Branch at Wilton Road Stream Stabilization ProjectFairfax County
 
Crook Branch at Mantua Elementary School Stream Restoration Community Meeting...
Crook Branch at Mantua Elementary School Stream Restoration Community Meeting...Crook Branch at Mantua Elementary School Stream Restoration Community Meeting...
Crook Branch at Mantua Elementary School Stream Restoration Community Meeting...Fairfax County
 
Pike Branch Tributary at Ridgeview Park - October 2015
Pike Branch Tributary at Ridgeview Park - October 2015Pike Branch Tributary at Ridgeview Park - October 2015
Pike Branch Tributary at Ridgeview Park - October 2015Fairfax County
 
Cameron Run Tributary At La Vista Drive: Stream Restoration
Cameron Run Tributary At La Vista Drive: Stream RestorationCameron Run Tributary At La Vista Drive: Stream Restoration
Cameron Run Tributary At La Vista Drive: Stream RestorationFairfax County
 
Tucker Avenue Neighborhood Stormwater Improvement Preliminary Design Review
Tucker Avenue Neighborhood  Stormwater Improvement Preliminary Design ReviewTucker Avenue Neighborhood  Stormwater Improvement Preliminary Design Review
Tucker Avenue Neighborhood Stormwater Improvement Preliminary Design ReviewFairfax County
 
Annual Contract for Stream and Water Quality Improvements: Golden Woods Pond ...
Annual Contract for Stream and Water Quality Improvements: Golden Woods Pond ...Annual Contract for Stream and Water Quality Improvements: Golden Woods Pond ...
Annual Contract for Stream and Water Quality Improvements: Golden Woods Pond ...Fairfax County
 

Was ist angesagt? (20)

Sunset Hills Road Drainage Improvement Project
Sunset Hills Road Drainage Improvement ProjectSunset Hills Road Drainage Improvement Project
Sunset Hills Road Drainage Improvement Project
 
Arcadis Design Lake Accotink Dredging Public Meeting December 2020
Arcadis Design Lake Accotink Dredging Public Meeting December 2020 Arcadis Design Lake Accotink Dredging Public Meeting December 2020
Arcadis Design Lake Accotink Dredging Public Meeting December 2020
 
Stormwater Wastewater Consolidation
Stormwater Wastewater ConsolidationStormwater Wastewater Consolidation
Stormwater Wastewater Consolidation
 
Dead Run Stream Restoration Segment 2 – 3
Dead Run Stream Restoration Segment 2 – 3Dead Run Stream Restoration Segment 2 – 3
Dead Run Stream Restoration Segment 2 – 3
 
Little Pimmit Run Community Meeting 10-4-2021
Little Pimmit Run Community Meeting 10-4-2021Little Pimmit Run Community Meeting 10-4-2021
Little Pimmit Run Community Meeting 10-4-2021
 
Huntsman Lake Dredging January 2015
Huntsman Lake Dredging January 2015Huntsman Lake Dredging January 2015
Huntsman Lake Dredging January 2015
 
Springfield Estates Pump Station Gravity Sewer Replacement - Community Meeting
Springfield Estates Pump Station Gravity Sewer Replacement - Community MeetingSpringfield Estates Pump Station Gravity Sewer Replacement - Community Meeting
Springfield Estates Pump Station Gravity Sewer Replacement - Community Meeting
 
Draft Chesapeake Bay TMDL Action Plan Public Meeting
Draft Chesapeake Bay TMDL Action Plan Public MeetingDraft Chesapeake Bay TMDL Action Plan Public Meeting
Draft Chesapeake Bay TMDL Action Plan Public Meeting
 
Turkey Run at Truro Subdivision Stream Restoration
Turkey Run at Truro Subdivision Stream RestorationTurkey Run at Truro Subdivision Stream Restoration
Turkey Run at Truro Subdivision Stream Restoration
 
Columbia Road/Randolph Court Stream Restoration July 2015
Columbia Road/Randolph Court Stream Restoration July 2015Columbia Road/Randolph Court Stream Restoration July 2015
Columbia Road/Randolph Court Stream Restoration July 2015
 
Dead Run Segment One Stream Restoration Project
Dead Run Segment One Stream Restoration ProjectDead Run Segment One Stream Restoration Project
Dead Run Segment One Stream Restoration Project
 
Huntington Levee Community Meeting: Oct. 26. 2016
Huntington Levee Community Meeting: Oct. 26. 2016Huntington Levee Community Meeting: Oct. 26. 2016
Huntington Levee Community Meeting: Oct. 26. 2016
 
Flatlick Branch Phase II Stream Restoration Project
Flatlick Branch Phase II Stream Restoration ProjectFlatlick Branch Phase II Stream Restoration Project
Flatlick Branch Phase II Stream Restoration Project
 
Crook at Mantua Elementary School Stream Restoration
Crook at Mantua Elementary School Stream RestorationCrook at Mantua Elementary School Stream Restoration
Crook at Mantua Elementary School Stream Restoration
 
Pike Branch at Wilton Road Stream Stabilization Project
Pike Branch at Wilton Road Stream Stabilization ProjectPike Branch at Wilton Road Stream Stabilization Project
Pike Branch at Wilton Road Stream Stabilization Project
 
Crook Branch at Mantua Elementary School Stream Restoration Community Meeting...
Crook Branch at Mantua Elementary School Stream Restoration Community Meeting...Crook Branch at Mantua Elementary School Stream Restoration Community Meeting...
Crook Branch at Mantua Elementary School Stream Restoration Community Meeting...
 
Pike Branch Tributary at Ridgeview Park - October 2015
Pike Branch Tributary at Ridgeview Park - October 2015Pike Branch Tributary at Ridgeview Park - October 2015
Pike Branch Tributary at Ridgeview Park - October 2015
 
Cameron Run Tributary At La Vista Drive: Stream Restoration
Cameron Run Tributary At La Vista Drive: Stream RestorationCameron Run Tributary At La Vista Drive: Stream Restoration
Cameron Run Tributary At La Vista Drive: Stream Restoration
 
Tucker Avenue Neighborhood Stormwater Improvement Preliminary Design Review
Tucker Avenue Neighborhood  Stormwater Improvement Preliminary Design ReviewTucker Avenue Neighborhood  Stormwater Improvement Preliminary Design Review
Tucker Avenue Neighborhood Stormwater Improvement Preliminary Design Review
 
Annual Contract for Stream and Water Quality Improvements: Golden Woods Pond ...
Annual Contract for Stream and Water Quality Improvements: Golden Woods Pond ...Annual Contract for Stream and Water Quality Improvements: Golden Woods Pond ...
Annual Contract for Stream and Water Quality Improvements: Golden Woods Pond ...
 

Ähnlich wie Lake Accotink Dredging Alternatives Analysis

LMPP Final Presentation_FINAL1
LMPP Final Presentation_FINAL1LMPP Final Presentation_FINAL1
LMPP Final Presentation_FINAL1Theodore McNeal
 
Hunting Creek at Fairchild MVCCA-Meeting March 7, 2018
Hunting Creek at Fairchild MVCCA-Meeting March 7, 2018Hunting Creek at Fairchild MVCCA-Meeting March 7, 2018
Hunting Creek at Fairchild MVCCA-Meeting March 7, 2018Fairfax County
 
Presentation-Orange-County-Great-Park-Storm-Water-Reuse-Pond-System-June-2014
Presentation-Orange-County-Great-Park-Storm-Water-Reuse-Pond-System-June-2014Presentation-Orange-County-Great-Park-Storm-Water-Reuse-Pond-System-June-2014
Presentation-Orange-County-Great-Park-Storm-Water-Reuse-Pond-System-June-2014Joseph Merzlak
 
Dead Run Segments 2/3 Stream Restoration Project Public Meeting
Dead Run Segments 2/3 Stream Restoration Project Public MeetingDead Run Segments 2/3 Stream Restoration Project Public Meeting
Dead Run Segments 2/3 Stream Restoration Project Public MeetingFairfax County
 
Dead Run Stream Restoration Public Meeting June 9, 2015
Dead Run Stream Restoration Public Meeting June 9, 2015Dead Run Stream Restoration Public Meeting June 9, 2015
Dead Run Stream Restoration Public Meeting June 9, 2015Fairfax County
 
Long Branch Central Watershed Management Area 03-03-2021
Long Branch Central Watershed Management Area 03-03-2021Long Branch Central Watershed Management Area 03-03-2021
Long Branch Central Watershed Management Area 03-03-2021Fairfax County
 
Dead Run Stream Restoration Public Meeting May 19, 2015
Dead Run Stream Restoration Public Meeting May 19, 2015Dead Run Stream Restoration Public Meeting May 19, 2015
Dead Run Stream Restoration Public Meeting May 19, 2015Fairfax County
 
Paul Spring Branch at Sherwood Hall Stream Restoration Project
Paul Spring Branch at Sherwood Hall Stream Restoration ProjectPaul Spring Branch at Sherwood Hall Stream Restoration Project
Paul Spring Branch at Sherwood Hall Stream Restoration ProjectFairfax County
 
Sustainable Public Works: Benefits of Taking Envision Beyond the Boundary of ...
Sustainable Public Works: Benefits of Taking Envision Beyond the Boundary of ...Sustainable Public Works: Benefits of Taking Envision Beyond the Boundary of ...
Sustainable Public Works: Benefits of Taking Envision Beyond the Boundary of ...Youn Sim, Ph.D., P.E.
 
Lake Accotink Dredging Public Meeting Presentation December 2020
Lake Accotink Dredging Public Meeting Presentation December 2020Lake Accotink Dredging Public Meeting Presentation December 2020
Lake Accotink Dredging Public Meeting Presentation December 2020Fairfax County
 
Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Fairfax County
 
Baron-Jamaica Bay Task force 17Nov22.pdf
Baron-Jamaica Bay Task force 17Nov22.pdfBaron-Jamaica Bay Task force 17Nov22.pdf
Baron-Jamaica Bay Task force 17Nov22.pdfecowatchers
 
Quander Road Outfall and Stream Restoration
Quander Road Outfall and Stream RestorationQuander Road Outfall and Stream Restoration
Quander Road Outfall and Stream RestorationFairfax County
 
WATERSHED MANAGEMENT AT BHARANANGANAM PANCHAYATH OF KOTTAYAM DISTRICT,INDIA
WATERSHED MANAGEMENT AT BHARANANGANAM PANCHAYATH OF KOTTAYAM DISTRICT,INDIAWATERSHED MANAGEMENT AT BHARANANGANAM PANCHAYATH OF KOTTAYAM DISTRICT,INDIA
WATERSHED MANAGEMENT AT BHARANANGANAM PANCHAYATH OF KOTTAYAM DISTRICT,INDIAIRJET Journal
 
Rabbit Branch at Collingham Drive Stream Restoration Information Meeting - Ju...
Rabbit Branch at Collingham Drive Stream Restoration Information Meeting - Ju...Rabbit Branch at Collingham Drive Stream Restoration Information Meeting - Ju...
Rabbit Branch at Collingham Drive Stream Restoration Information Meeting - Ju...Fairfax County
 
Long Branch Central Watershed Management Area Project Overview October 26, 2020
Long Branch Central Watershed Management Area Project Overview October 26, 2020Long Branch Central Watershed Management Area Project Overview October 26, 2020
Long Branch Central Watershed Management Area Project Overview October 26, 2020Fairfax County
 
Bay Delta Conservation Plan - Paul Helliker, Department of Water Resources - ...
Bay Delta Conservation Plan - Paul Helliker, Department of Water Resources - ...Bay Delta Conservation Plan - Paul Helliker, Department of Water Resources - ...
Bay Delta Conservation Plan - Paul Helliker, Department of Water Resources - ...San Diego County Water Authority
 

Ähnlich wie Lake Accotink Dredging Alternatives Analysis (20)

LMPP Final Presentation_FINAL1
LMPP Final Presentation_FINAL1LMPP Final Presentation_FINAL1
LMPP Final Presentation_FINAL1
 
Hunting Creek at Fairchild MVCCA-Meeting March 7, 2018
Hunting Creek at Fairchild MVCCA-Meeting March 7, 2018Hunting Creek at Fairchild MVCCA-Meeting March 7, 2018
Hunting Creek at Fairchild MVCCA-Meeting March 7, 2018
 
Presentation-Orange-County-Great-Park-Storm-Water-Reuse-Pond-System-June-2014
Presentation-Orange-County-Great-Park-Storm-Water-Reuse-Pond-System-June-2014Presentation-Orange-County-Great-Park-Storm-Water-Reuse-Pond-System-June-2014
Presentation-Orange-County-Great-Park-Storm-Water-Reuse-Pond-System-June-2014
 
Dead Run Segments 2/3 Stream Restoration Project Public Meeting
Dead Run Segments 2/3 Stream Restoration Project Public MeetingDead Run Segments 2/3 Stream Restoration Project Public Meeting
Dead Run Segments 2/3 Stream Restoration Project Public Meeting
 
Dead Run Stream Restoration Public Meeting June 9, 2015
Dead Run Stream Restoration Public Meeting June 9, 2015Dead Run Stream Restoration Public Meeting June 9, 2015
Dead Run Stream Restoration Public Meeting June 9, 2015
 
Long Branch Central Watershed Management Area 03-03-2021
Long Branch Central Watershed Management Area 03-03-2021Long Branch Central Watershed Management Area 03-03-2021
Long Branch Central Watershed Management Area 03-03-2021
 
OWLS 2013: ATLANTA SPOTLIGHT
OWLS 2013: ATLANTA SPOTLIGHT OWLS 2013: ATLANTA SPOTLIGHT
OWLS 2013: ATLANTA SPOTLIGHT
 
Dead Run Stream Restoration Public Meeting May 19, 2015
Dead Run Stream Restoration Public Meeting May 19, 2015Dead Run Stream Restoration Public Meeting May 19, 2015
Dead Run Stream Restoration Public Meeting May 19, 2015
 
Paul Spring Branch at Sherwood Hall Stream Restoration Project
Paul Spring Branch at Sherwood Hall Stream Restoration ProjectPaul Spring Branch at Sherwood Hall Stream Restoration Project
Paul Spring Branch at Sherwood Hall Stream Restoration Project
 
Sustainable Public Works: Benefits of Taking Envision Beyond the Boundary of ...
Sustainable Public Works: Benefits of Taking Envision Beyond the Boundary of ...Sustainable Public Works: Benefits of Taking Envision Beyond the Boundary of ...
Sustainable Public Works: Benefits of Taking Envision Beyond the Boundary of ...
 
Lake Accotink Dredging Public Meeting Presentation December 2020
Lake Accotink Dredging Public Meeting Presentation December 2020Lake Accotink Dredging Public Meeting Presentation December 2020
Lake Accotink Dredging Public Meeting Presentation December 2020
 
Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022
 
Baron-Jamaica Bay Task force 17Nov22.pdf
Baron-Jamaica Bay Task force 17Nov22.pdfBaron-Jamaica Bay Task force 17Nov22.pdf
Baron-Jamaica Bay Task force 17Nov22.pdf
 
Quander Road Outfall and Stream Restoration
Quander Road Outfall and Stream RestorationQuander Road Outfall and Stream Restoration
Quander Road Outfall and Stream Restoration
 
WATERSHED MANAGEMENT AT BHARANANGANAM PANCHAYATH OF KOTTAYAM DISTRICT,INDIA
WATERSHED MANAGEMENT AT BHARANANGANAM PANCHAYATH OF KOTTAYAM DISTRICT,INDIAWATERSHED MANAGEMENT AT BHARANANGANAM PANCHAYATH OF KOTTAYAM DISTRICT,INDIA
WATERSHED MANAGEMENT AT BHARANANGANAM PANCHAYATH OF KOTTAYAM DISTRICT,INDIA
 
Storm Water Utility Dev. and Master Plans
Storm Water Utility Dev. and Master PlansStorm Water Utility Dev. and Master Plans
Storm Water Utility Dev. and Master Plans
 
Rabbit Branch at Collingham Drive Stream Restoration Information Meeting - Ju...
Rabbit Branch at Collingham Drive Stream Restoration Information Meeting - Ju...Rabbit Branch at Collingham Drive Stream Restoration Information Meeting - Ju...
Rabbit Branch at Collingham Drive Stream Restoration Information Meeting - Ju...
 
Long Branch Central Watershed Management Area Project Overview October 26, 2020
Long Branch Central Watershed Management Area Project Overview October 26, 2020Long Branch Central Watershed Management Area Project Overview October 26, 2020
Long Branch Central Watershed Management Area Project Overview October 26, 2020
 
PIC 2 Display Boards
PIC 2 Display BoardsPIC 2 Display Boards
PIC 2 Display Boards
 
Bay Delta Conservation Plan - Paul Helliker, Department of Water Resources - ...
Bay Delta Conservation Plan - Paul Helliker, Department of Water Resources - ...Bay Delta Conservation Plan - Paul Helliker, Department of Water Resources - ...
Bay Delta Conservation Plan - Paul Helliker, Department of Water Resources - ...
 

Mehr von Fairfax County

Merrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementMerrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementFairfax County
 
SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS Fairfax County
 
Clarks Crossing Road Improvements 05-13-22
 Clarks Crossing Road Improvements 05-13-22 Clarks Crossing Road Improvements 05-13-22
Clarks Crossing Road Improvements 05-13-22Fairfax County
 
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxTysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxFairfax County
 
Lorton Volunteer Fire Station #19
Lorton Volunteer Fire Station  #19 Lorton Volunteer Fire Station  #19
Lorton Volunteer Fire Station #19 Fairfax County
 
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationScotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationFairfax County
 
Sully Community Center Construction Progress
Sully Community Center Construction ProgressSully Community Center Construction Progress
Sully Community Center Construction ProgressFairfax County
 
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxRiverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxFairfax County
 
Burke VRE Connector Phase IV
Burke VRE Connector Phase IVBurke VRE Connector Phase IV
Burke VRE Connector Phase IVFairfax County
 
Workhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxWorkhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxFairfax County
 
Workhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilWorkhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilFairfax County
 
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptxFairfax County
 
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT Fairfax County
 
Reston Arts Community Center Feasibility - Wrap Up
 Reston Arts Community Center Feasibility - Wrap Up Reston Arts Community Center Feasibility - Wrap Up
Reston Arts Community Center Feasibility - Wrap UpFairfax County
 
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Fairfax County
 
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Fairfax County
 
Oak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectOak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectFairfax County
 
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Fairfax County
 
Reston Arts Center Feasibility - Focus Group Visual Arts
Reston Arts Center Feasibility -  Focus Group Visual ArtsReston Arts Center Feasibility -  Focus Group Visual Arts
Reston Arts Center Feasibility - Focus Group Visual ArtsFairfax County
 
Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022
Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022
Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022Fairfax County
 

Mehr von Fairfax County (20)

Merrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementMerrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer Replacement
 
SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS
 
Clarks Crossing Road Improvements 05-13-22
 Clarks Crossing Road Improvements 05-13-22 Clarks Crossing Road Improvements 05-13-22
Clarks Crossing Road Improvements 05-13-22
 
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxTysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
 
Lorton Volunteer Fire Station #19
Lorton Volunteer Fire Station  #19 Lorton Volunteer Fire Station  #19
Lorton Volunteer Fire Station #19
 
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationScotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
 
Sully Community Center Construction Progress
Sully Community Center Construction ProgressSully Community Center Construction Progress
Sully Community Center Construction Progress
 
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxRiverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
 
Burke VRE Connector Phase IV
Burke VRE Connector Phase IVBurke VRE Connector Phase IV
Burke VRE Connector Phase IV
 
Workhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxWorkhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick Offpptx
 
Workhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilWorkhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing Council
 
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
 
Reston Arts Community Center Feasibility - Wrap Up
 Reston Arts Community Center Feasibility - Wrap Up Reston Arts Community Center Feasibility - Wrap Up
Reston Arts Community Center Feasibility - Wrap Up
 
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
 
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
 
Oak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectOak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction Project
 
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
 
Reston Arts Center Feasibility - Focus Group Visual Arts
Reston Arts Center Feasibility -  Focus Group Visual ArtsReston Arts Center Feasibility -  Focus Group Visual Arts
Reston Arts Center Feasibility - Focus Group Visual Arts
 
Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022
Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022
Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022
 

Kürzlich hochgeladen

UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduitsrknatarajan
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...ranjana rawat
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdfKamal Acharya
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGMANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGSIVASHANKAR N
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdfKamal Acharya
 
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsRussian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 

Kürzlich hochgeladen (20)

UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGMANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
 
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsRussian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 

Lake Accotink Dredging Alternatives Analysis

  • 1. A Fairfax County, VA, publication Department of Public Works and Environmental Services Working for You! July 29 and August 5, 2021 Public Presentation – Alternatives Analysis Lake Accotink Dredging
  • 2. DPWES Stormwater Planning Division Project Background 2 Lake Accotink Dredging Lake Siltation  Lake Accotink has been dredged three times over the past 40 years.  The most recent dredging was completed in May 2008.  An average of 20,000 CY of sediment is deposited in the lake per year.  The estimated average depth of the lake is less than 4 feet. Park Master Plan Process • Master Plan began Spring 2016. • 5 Public Meetings/Workshops held with Community. • 6 Lake Management Options were shared with the public. • 90% of public comments favored having the lake. Board of Supervisors Approval of Funding • BOS approved request to seek funding for up to $30.5 million to proceed with Lake Accotink Dredging in October 2019 .
  • 3. DPWES Stormwater Planning Division Project Overview 3 Lake Accotink Dredging Description • Dredge estimated 500,000 cubic yards of sediment to restore lake to average 8 ft depth. • Pump sediment to location within Wakefield or Lake Accotink Park for dewatering and disposal. • Establish maintenance dredging program to sustain the lake. • Retain aesthetic and recreation value of the lake.
  • 4. DPWES Stormwater Planning Division Project Team 4 Lake Accotink Dredging Department of Public Works & Environmental Services Charles Smith Project Manager – Stormwater Justin Pistore Project Manager - Stormwater Aaron George Lake Management – Stormwater Jay Horstman Construction Management – Capital Facilities Tom Richardson Sanitary Sewer Coordination – Wastewater Fairfax County Park Authority Valerie Maislin Project Manager – Planning and Development Adam Wynn Lake Accotink Park Master Plan Project Manager – Planning and Development Dan Grulke Lake Accotink Manager – Park Services Chris Goldbecker Lake Front Park Manager – Park Services Amber Stramel Area 2 Manager – Park Operations Braddock District Supervisor Marcia Pape Supervisor’s Aide Arcadis Team Mike Wooden Project Manager Fernando Pasquel Project Director Akshay Kumar Assistant Project Manager Liz Hover Materials Management Amanda Kohler Conveyance & Dewatering System Shannon Dunn Sediment Characterization & Water Quality Susan Larcher Public Outreach Frank Graziano (WSSI) Survey & Permitting ECS Geotechnical Analysis Key Stakeholder Groups Friends of Lake Accotink Park Friends of Accotink Creek Save Lake Accotink Homeowner & Civic Associations Mid-Atlantic Off-Road Enthusiasts Lake Accotink Dredging Critical Players
  • 5. DPWES Stormwater Planning Division Project Schedule 5 Lake Accotink Dredging  Data collection and survey – April 2021  Alternatives Analysis – July 12, 2021  Public Comment July 22 to August 22  Public Meeting July 29 & August 5  Concept Design and Value Engineering Study – May 2022  Final Design and Permitting – May 2023  Begin Dredging – Fall 2023  Complete Dredging – 2026  Post Construction Monitoring – 2026 to 2031 Lake Accotink dredging operations June 21, 2006 – Photo by Fairfax County DPWES
  • 6. © Arcadis 2021 Photo courtesy of Tom Kinder Alternatives Analysis July 29 and August 5, 2021 Lake Accotink Dredging
  • 7. Alternatives Analysis Report Full Report Available on Project Website: https://www.fairfaxcounty.gov/publicworks/lake-accotink-dredging 1. Introduction 2. Summary of Existing Data 3. Evaluation Criteria 4. Development and Screening of Methods 5. Environmental and Cultural Resource Evaluation 6. Development and Screening of Alternatives 7. Analysis of Retained Alternatives 29 July 2021 © Arcadis 2021
  • 8. Lake Accotink Information Watershed Area 19,600 acres Lake Area 55 acres Average Sedimentation Rate 23,000 cubic yards per year Previous Dredging Events 1960s, 1985, 2008 Nearby Land Use Parks, Residential, Light Industrial Surrounding Habitat Forests, marshes, and ephemeral wetlands All values are approximate • Project to include dredging, sediment transport, and disposal by truck • Increase lake depth and overall volume of the lake • Facilitate retention of the aesthetic and recreational value of the lake • Provide a dredging maintenance plan that allows the lake to remain a valuable asset to the community Objective and Scope 29 July 2021 Lake Accotink Existing Conditions Alternatives Analysis Report Figure 1-2 Introduction © Arcadis 2021
  • 9. 29 July 2021 © Arcadis 2021 Summary of Existing Data
  • 10. © Arcadis 2021 Category Criteria Park Management Long-Term Park Vision Community Recreational Use Restrictions During Construction Community Considerations During Construction Environment Environmental Considerations Floodplain Impacts Sustainability Construction and Dredging Program Operation Available Area and Accessibility Site Preparation Requirements Flexibility/Compatibility with Various Equipment Efficient Water Return Constructability Long-Term Operation and Maintenance Schedule Costs Evaluation Criteria Sub-Criteria Developed for Each of the Components Evaluated 29 July 2021
  • 11. © Arcadis 2021 Assumptions 29 July 2021 • Target Final Water Depth – 8 feet • Dredge Volume – 450,000 to 500,00 cubic yards • Construction Schedule – 3 years • Dredging Schedule – 2 years • Average Dredging Rate – 950 cubic yards per day
  • 14. © Arcadis 2021 Dredging Methods 29 July 2021 Mechanical Amphibious (Hybrid) Hydraulic 8 cubic yard bucket 16 cubic yard bucket 8-inch dredge 14-inch dredge
  • 15. © Arcadis 2021 29 July 2021 Dredging Method Evaluation Table 8-cubic-yard bucket 16-cubic-yard bucket 8-inch dredge 14-inch dredge Lost Use Days Minimizes days lost      Reduced Use Minimizes reduced use of lake      Existing Infrastructure Impacts Minimizes impacts to existing infrastructure      Lake Use Minimizes impacts to lake use due to dredging activities (including aesthetic considerations)      Facilities Availability Avoids closures of park facilities (e.g., marina, parking)      Minimizes Noise Comparison of relative proximity of potential receptors      Minimizes Odors/Dust Comparison of relative proximity of potential receptors      Impacts to Aquatic Wildlife Minimizes impacts to aquatic wildlife      Wetland Impacts Minimizes impacts to wetlands      Impacts to Terrestrial Wildlife Minimizes impacts to terrestrial wildlife      Minimize Floodplain Impacts --      Minimizes Sediment Resuspension --      Greenhouse Emissions Minimizes greenhouse gas emissions      Preserving wetlands Minimizes impacts to wetlands      Minimizes Clearing/Grading --      Requires Updated Infrastructure Minimizes required updates to existing infrastructure      Sediment Processing Considerations Adaptability to pipeline transport      Maneuverability Around Dock/Dam --      Dredge Equipment Accuracy --      Separate debris removal step required      Convertible for debris removal      Availability --      Seasonal Restrictions Seasonal impacts on dredge use      Production Average sustained production rate      Relative Costs --      Criteria Sub-Criteria Mechanical Hydraulic Amphibious Debris Compatibility         Low Compatibility Medium Compatibility High Compatibility
  • 16. © Arcadis 2021 29 July 2021 Key Takeaways • All options are feasible • Main challenges (red ratings) – Hydraulic – debris handling – Amphibious – production rate – Mechanical – community and floodplain impacts Dredging Method Evaluation Detailed Evaluation in Exhibit 1 of Alternatives Analysis Report
  • 18. © Arcadis 2021 3.5 – 4.9 acres PASSIVE (GEOTEXTILE TUBE) Dewatering Methods 29 July 2021 PASSIVE WITH DESANDING 5.2 – 7.4 acres MECHANICAL 3.2 – 5.8 acres DRYING AGENT Island Options Only
  • 19. © Arcadis 2021 Dewatering Method Evaluations 29 July 2021 Key Takeaways • Passive is simple and relatively low-cost but needs large, flat area • Mechanical can accommodate higher throughput and creates drier material but is higher cost • Identify location to provide most flexibility for contractor’s approach Detailed Evaluation in Exhibit 2 of Alternatives Analysis Report
  • 21. © Arcadis 2021 Disposal Locations 29 July 2021 Island Expansion Bank Restoration County Use Offsite Reuse Offsite Landfill
  • 22. © Arcadis 2021 Disposal Location Evaluation 29 July 2021 Key Takeaways • All disposal locations can be paired with any of the dredging and dewatering options • Offsite landfill and offsite reuse have no public impacts but have higher costs • Onsite reuse has lower costs but has public impacts Detailed Evaluation in Exhibit 3 of Alternatives Analysis Report
  • 24. Details in Table 5-1 and Appendix C of Alternative Analysis Report • Provided impacts likely a "Worst Case Scenario" • No distinction between "temporary" vs "permanent" wetland impacts • Permit will require avoidance and minimization, reducing noted impacts • Largest dewatering site "impacts" are associated with use of the island or settling basin • Largest pipeline "impacts" are for alignments in stream valleys • Largest tree "impacts" in stream valleys, maintenance area, settling basin Potential Wetland and Vegetative Impacts 29 July 2021 © Arcadis 2021
  • 25. Potential Cultural Resource Impacts Details in Appendix D of Alternative Analysis Report • Based on Virginia Department of Historic Resources (VDHR) database review of previously recorded cultural resources within or adjacent to potential alignments and dewatering sites • Seven sites were identified, consisting of prehistoric lithic scatter, civil war era features, and/or portions of the Orange & Alexandria rail bed • No sites have been evaluated for listing in the National Register of Historic Places (NRHP) • Sites could also meet Fairfax County criteria for local significance 29 July 2021 © Arcadis 2021
  • 26. Development and Screening of Alternatives
  • 27. Alternative Components Detailed Evaluation in Exhibit 4 of Alternatives Analysis Report North of Braddock Road 1. Howrey Field 2. Wakefield Park Maintenance Facility 3. Wakefield Ball Fields 4. Dominion Energy (Dominion) Right-of-Way (ROW) Lake Accotink Park 5. Lake Accotink Upper Settling Basin 6. Lake Accotink Island – Current Footprint 7. Lake Accotink Island – Expanded Footprint Concrete Plant 8. Concrete Plant Dewatering Locations North of Braddock Road 1. Cross-County Trail 2. Queensberry Avenue 3. Flag Run / Port Royal Road 4. Flag Run / Interstate 495 Lake Accotink Park 5. Lake Accotink Trail Concrete Plant 6. Amtrak ROW 7. Residential Route Pipeline Alignments 29 July 2021 Detailed Evaluation in Exhibit 5 of Alternatives Analysis Report © Arcadis 2021
  • 28. © Arcadis 2021 List of Potential Alternatives 29 July 2021 # ID Description 1 HF1 Howrey Field via Cross-County trail 2 HF2 Howrey Field via Queensberry Ave 3 HF3 Howrey Field via Flag Run/Port Royal Road 4 HF4 Howrey Field via Flag Run/I-495 5 WMF1 Wakefield Park Maintenance Facility via Cross-County Trail 6 WMF2 Wakefield Park Maintenance Facility via Queensberry Ave 7 WMF3 Wakefield Park Maintenance Facility via Flag Run/Port Royal Road 8 WMF4 Wakefield Park Maintenance Facility via Flag Run/I-495 9 WB1 Wakefield Ball Fields via Cross-County Trail 10 WB2 Wakefield Ball Fields via Queensberry Ave 11 WB3 Wakefield Ball Fields via Flag Run/Port Royal Road 12 WB4 Wakefield Ball Fields via Flag Run/I-495 13 DOM1 Dominion Right-of-Way (ROW) via Cross-County Trail 14 DOM2 Dominion ROW via Queensberry Ave 15 DOM3 Dominion ROW via Flag Run/Port Royal Road 16 DOM4 Dominion ROW via Flag Run/I-495 17 USB Lake Accotink Upper Settling Basin 18 ICF Lake Accotink Island - Current Footprint 19 IXF Lake Accotink Island - Expanded Footprint 20 VCP1 Concrete Plant via Residential 21 VCP2 Concrete Plant via Amtrak ROW HF WB I Legend Processing Area HF = Howrey Field WMF = Maintenance Area WB = Ballfields DOM = Dominion ROW USB = Settling Basin I = Island (IXF, ICF) VPC = Concrete Plant Main Pipeline Route HF USB WMF VCP DOM
  • 29. © Arcadis 2021 HF WB I Legend Processing Area HF = Howrey Field WMF = Maintenance Area WB = Ballfields DOM = Dominion ROW USB = Settling Basin I = Island (IXF, ICF) VPC = Concrete Plant Main Pipeline Route HF USB WMF VCP DOM Removed & Retained Alternatives in Report 29 July 2021 # ID Description 1 HF1 Howrey Field via Cross-County trail 2 HF2 Howrey Field via Queensberry Ave 1 3 HF3 Howrey Field via Flag Run/Port Royal Road 4 HF4 Howrey Field via Flag Run/I-495 5 WMF1 Wakefield Park Maintenance Facility via Cross-County Trail 6 WMF2 Wakefield Park Maintenance Facility via Queensberry Ave 1 7 WMF3 Wakefield Park Maintenance Facility via Flag Run/Port Royal Road 8 WMF4 Wakefield Park Maintenance Facility via Flag Run/I-495 9 WB1 Wakefield Ball Fields via Cross-County Trail 2 10 WB2 Wakefield Ball Fields via Queensberry Ave 1, 2 11 WB3 Wakefield Ball Fields via Flag Run/Port Royal Road 2 12 WB4 Wakefield Ball Fields via Flag Run/I-495 2 13 DOM1 Dominion Right-of-Way (ROW) via Cross-County Trail 14 DOM2 Dominion ROW via Queensberry Ave 1 15 DOM3 Dominion ROW via Flag Run/Port Royal Road 16 DOM4 Dominion ROW via Flag Run/I-495 17 USB Lake Accotink Upper Settling Basin 18 ICF Lake Accotink Island - Current Footprint 19 IXF Lake Accotink Island - Expanded Footprint 20 VCP1 Concrete Plant via Residential 3 21 VCP2 Concrete Plant via Amtrak ROW 3 Rationale for alternatives removed from consideration: 1. Queensberry Ave removed from consideration due to impacts to community and cost 2. Wakefield Ball Fields removed from consideration due to legal impacts and inability to replace facility that meets Title IX obligations 3. Concrete Plant removed from consideration as property owner is unable to accommodate dewatering operations X X X X X
  • 30. Analysis of Retained Alternatives
  • 31. © Arcadis 2021 Retained Alternatives Evaluation 29 July 2021 ID Alt # Description HF1 1 Howrey Field via Cross-County trail HF3 3 Howrey Field via Flag Run/Port Royal Road HF4 4 Howrey Field via Flag Run/I-495 WMF1 5 Wakefield Park Maintenance Facility via Cross-County Trail WMF3 7 Wakefield Park Maintenance Facility via Flag Run/Port Royal Road WMF4 8 Wakefield Park Maintenance Facility via Flag Run/I-495 DOM1 13 Dominion Right-of-Way (ROW) via Cross-County Trail DOM3 15 Dominion ROW via Flag Run/Port Royal Road DOM4 16 Dominion ROW via Flag Run/I-495 USB 17 Lake Accotink Upper Settling Basin ICF 18 Lake Accotink Island - Current Footprint IXF 19 Lake Accotink Island - Expanded Footprint County Staff Recommend Removal from Consideration
  • 32. Dewatering Location Evaluation See Exhibit 4 of Alternatives Analysis for Detailed Evaluation County Staff Recommend Removal from Consideration 29 July 2021
  • 33. Limits Park & Community Impacts; Long-Term Use; Restoration & Remobilization; Extent of Clearing, Floodplain 33 Wakefield Park Maintenance Facility Areas Type Acreages Maximum Limits of Disturbance 7.7 Wetlands 0 Floodplain 2.6 Resource Protection Area 4.0 Method Compatibility* Production (cy/day) Slurry Solids 950 7% 950 15% 1250 7% 1250 15% Passive Yes Yes No No Passive w/ Desanding No No No No Mechanical Maybe Yes No Maybe Drying Agent No No Rating Summary *Based on current assumptions From Alternative Analysis Report Figure 6-3 Unknown • Extent of Braddock Rd Improvements
  • 34. © Arcadis 2021 Wakefield Park Maintenance Facility Slurry Transport Alignments WMF1 - Cross-County Trail WMF3 - Flag Run/Port Royal Road WMF4 - Flag Run/I-495 Alignment Length, mi. 1.3 1.9 1.9 Pipe Diameter, inches 12 to 14 16 to 18 16 to 18 Difference in Elevation1, ft. 17 110 110 No. of Utility Crossings2, ea. 17 55 19 No. of Water Features/ Trail Crossings 7 29 27 Notes: 1. Difference in elevation between highest and lowest point along the alignment. 2. Sewer, Stormwater, Electrical & Water. 29 July 2021 Detailed Evaluation in Exhibit 5 of Alternatives Analysis Report
  • 35. 10 August 2021 35 Dominion ROW Areas Type Acreages Maximum Limits of Disturbance 10 Wetlands 0.2 Floodplain 6.2 Resource Protection Area 9.7 Method Compatibility* Production (cy/day) Slurry Solids 950 7% 950 15% 1250 7% 1250 15% Passive Maybe Maybe No No Passive w/ Desanding No No No No Mechanical Maybe Maybe No Maybe Drying Agent No No *Based on current assumptions Rating Summary Clearing/Wetland Impacts; Restoration & Remobilization Floodplain; Truck Access From Alternative Analysis Report Figure 6-5 Unknown • Dominion requirements / use restrictions
  • 36. © Arcadis 2021 DOM1 - Cross-County Trail DOM3 - Flag Run/Port Royal Road DOM4 - Flag Run/I-495 Alignment Length, mi. 2.1 2.5 2.2 Pipe Diameter, inches 16 to 18 16 to 18 16 to 18 Difference in Elevation1, ft. 25 110 105 No. of Utility Crossings2, ea. 26 66 23 No. of Water Feature/Trail Crossings 18 41 35 Note: 1. Difference in elevation between highest and lowest point along the alignment. 2. Sewer, Stormwater, Electrical & Water. 29 July 2021 Detailed Evaluation in Exhibit 5 of Alternatives Analysis Report Dominion ROW Slurry Transport Alignments
  • 37. 10 August 2021 37 Upper Settling Basin Areas Type Acreages Maximum Limits of Disturbance 6.7 Wetlands 4.1 Floodplain 0 Resource Protection Area 6.7 Method Compatibility* Production (cy/day) Slurry Solids 950 7% 950 15% 1250 7% 1250 15% Passive Maybe Maybe No No Passive w/ Desanding No No No No Mechanical Maybe Maybe No Maybe Drying Agent No No *Based on current assumptions Rating Summary Improve Infrastructure; Outside Floodplain; Water Return; Restoration & Remobilization Trail & Wetland Impacts, Grading; Soil Condition, Community Impacts, Site Preparation; Accessibility From Alternative Analysis Report Figure 6-6 Unknown • Surface/Subsurface Conditions • Embankment Stability
  • 38. © Arcadis 2021 Upper Settling Basin – Trail Alignment Alignment Length, mi. 0.7 Pipe Diameter, inches 14 to 16 Difference in Elevation1, ft. 70 No. of Utility Crossings2, ea. 9 No. of Water Feature/Trail Crossings 15 Notes: 1. Difference in elevation between highest and lowest point along the alignment. 2. Sewer, Stormwater, Electrical & Water. 29 July 2021 High Compatibility Medlium Low Compatibility Detailed Evaluation in Exhibit 5 of Alternatives Analysis Report Upper Settling Basin Slurry Transport Alignment
  • 39. 10 August 2021 39 Howrey Field Areas Type Acreages Maximum Limits of Disturbance 7.5 Wetlands 0 Floodplain 4.5 Resource Protection Area 3.7 Method Compatibility* Production (cy/day) Slurry Solids 950 7% 950 15% 1250 7% 1250 15% Passive Maybe Maybe No No Passive w/ Desanding No No No No Mechanical Maybe Maybe No Maybe Drying Agent No No *Based on current assumptions Rating Summary Accessibility; Truck Traffic Park Use; Memorial; Restoration & Remobilization; Floodplain; Return Water From Alternative Analysis Report Figure 6-2 Howrey Field Unknown • Extent of Braddock Rd Improvements
  • 40. Howrey Field Slurry Transport Alignments Type HF1 - Cross-County Trail HF3 - Flag Run/Port Royal Road HF4 - Flag Run/I-495 Alignment Length, mi. 1.3 2.2 2.2 Pipe Diameter, inches 12 to 14 16 to 18 16 to 18 Difference in Elevation1, ft. 15 105 110 No. of Utility Crossings2, ea. 27 59 37 No. of Water Feature/Trail Crossings 8 32 29 Note: 1. Difference in elevation between highest and lowest point along the alignment. 2. Sewer, Stormwater, Electrical & Water. 29 July 2021 Detailed Evaluation in Exhibit 5 of Alternatives Analysis Report
  • 41. 10 August 2021 41 Lake Accotink Island (Current Footprint) Areas Type Acreages Maximum Limits of Disturbance 3.3 Wetlands 3.0 Floodplain 3.3 Resource Protection Area 3.3 Method Compatibility* Production (cy/day) Slurry Solids 950 7% 950 15% 1250 7% 1250 15% Passive No No No No Passive w/ Desanding No No No No Mechanical No No No No Drying Agent Yes – if barge transport Yes – if barge transport *Based on current assumptions Rating Summary No Pipeline; Water Return Park and Environmental Impacts, Accessibility, Truck Traffic, Floodplain From Alternative Analysis Report Figure 6-7 Unknown • Surface/subsurface conditions of island
  • 42. 10 August 2021 42 Lake Accotink Island (Expanded Footprint) Areas Type Acreages Maximum Limits of Disturbance 10 Wetlands 4.4 Floodplain 9.6 Resource Protection Area 10 Method Compatibility* Production (cy/day) Slurry Solids 950 7% 950 15% 1250 7% 1250 15% Passive Yes Yes Yes Yes Passive w/ Desanding Maybe Maybe Maybe Maybe Mechanical No No No No Drying Agent Yes – if barge transport Yes – if barge transport *Based on current assumptions Rating Summary No Pipeline, Water Return, Method Compatibility Park and Environmental Impacts, Site Preparation, Accessibility, Truck Traffic, Floodplain, Cost From Alternative Analysis Report Figure 6-8 Unknown • Surface/subsurface condition of island and land bridge area
  • 43. ID Alt # Description HF1 1 Howrey Field via Cross-County trail HF3 3 Howrey Field via Flag Run/Port Royal Road HF4 4 Howrey Park via Flag Run/I-495 WMF1 5 Wakefield Park Maintenance Facility via Cross-County Trail WMF3 7 Wakefield Park Maintenance Facility via Flag Run/Port Royal Road WMF4 8 Wakefield Park Maintenance Facility via Flag Run/I-495 DOM1 13 Dominion Right-of-Way (ROW) via Cross-County Trail DOM3 15 Dominion ROW via Flag Run/Port Royal Road DOM4 16 Dominion ROW via Flag Run/I-495 USB 17 Lake Accotink Upper Settling Basin ICF 18 Lake Accotink Island - Current Footprint IXF 19 Lake Accotink Island - Expanded Footprint Retained Alternatives Evaluation 29 July 2021 County Staff Recommend Removal from Consideration © Arcadis 2021
  • 44. © Arcadis 2021 Arcadis. Improving quality of life. Thank You For Your Time!
  • 45. DPWES Stormwater Planning Division Staff Recommendations 45 Lake Accotink Dredging  Dredging: Pursue hydraulic dredging with mechanical debris removal.  Pipeline:  Pursue lowest impact/cost pipeline alternative: along CCT, lake perimeter trail or Flag Run/Port Royal Road or Beltway.  Retain flexibility during design for permanent and temporary pipeline options.  Dewatering:  Retain consideration for four potential locations during design for maximum flexibility, impact minimization, cost efficiency:  Dominion Energy ROW – Wakefield Park  Settling Basin – Lake Accotink Park  Maintenance Area – Wakefield Park  Lake Island – Lake Accotink Park
  • 46. DPWES Stormwater Planning Division Staff Recommendations 46 Lake Accotink Dredging
  • 47. DPWES Stormwater Planning Division Staff Recommendations 47 Lake Accotink Dredging
  • 48. DPWES Stormwater Planning Division Discussion Discussion & Questions 48 Native mussels below Lake Accotink dam – Photo by Friends of Accotink Creek Lake Accotink Dredging Community stewardship – Photo by Friends of Lake Accotink Park Cardboard boat regatta – Photo by Friends of Lake Accotink Park Mallard ducks – Photo by Fairfax County Park Authority
  • 49. DPWES Stormwater Planning Division 49 Lake Accotink Dredging Thanks for Attending!! The window for comments will be open until Sunday, August 22, 2021. Public Input Webpage: https://publicinput.com/R018 For Additional Information, to Comment or Sign up for Email Updates, Please Visit the Project Web Page: https://www.fairfaxcounty.gov/publicworks/lake-accotink- dredging

Hinweis der Redaktion

  1. Construction: FY2018 = July 2018
  2. Construction: FY2018 = July 2018
  3. Construction: FY2018 = July 2018
  4. Construction: FY2018 = July 2018
  5. Construction: FY2018 = July 2018
  6. Construction: FY2018 = July 2018
  7. Construction: FY2018 = July 2018
  8. Construction: FY2018 = July 2018
  9. Construction: FY2018 = July 2018