1. Dulles Corridor Metrorail Project
Silver Line Phase 2 Implementation
Board Transportation Committee Update
February 12, 2019
Mark Canale, Fairfax County Project Manager
Fairfax County Department of Transportation
2. 2
Project Status
Phase 1
• Old Meadow Road Realignment – 100% design complete.
• Construction completion scheduled for Summer 2019.
• VDOT punch list ongoing – MWAA and Bechtel to complete
• Phase 1 close out - $2.982B (no change)
Phase 2
• Overall Phase 2 – 92% complete
• Package A (Rail line, system, and stations) – 92%
• Package B (Rail yard at Dulles) – 96%
• Contractual Substantial Completion – August 2019
• WMATA Board to establish Revenue Operations Date
* First trains pushed along the tracks February 6, 2019
3. 3
• Budget
• Total Budget $2.778B
• Total Forecast $2.778B
• Total Expenditures $1.868B
• Contingency Utilization
• Total Contingency $551.5M
• Total Contingency Utilized $258.3M
• Remaining Contingency $293.2M
Phase 2 – Cost Summary
4. 4
• Reston Town Center Station – Mechanical/electrical/plumbing
rough-in, elevator and escalator detailing.
• Herndon Station – Mechanical/electrical rough-in, station ceiling
grid, elevator/escalator work, pedestrian bridge to existing
garage.
• Innovation Station – Detailing for pavilion and escalators, station
finishes, ceiling panel installation, electrical rough-in and
plumbing continues.
Phase 2 – Station Construction
5. 5
• Dulles Airport Station – Station lighting, ceiling grid framing,
canopy trim, and platform paver installation.
• Loudoun Gateway Station – Vault roof skylight framing and
glazing, pedestrian bridge ceiling installation trim work, and MEP
rough-in.
• Ashburn Station - Station roof work, MEP rough-in, escalator and
elevator work, and pedestrian bridge detailing.
Phase 2 – Station Construction
6. 6
• Rail and switches made ready for trains to be pulled to access
test sections of at-grade guideway
• Greenway median rail and switches installation continues
• TPSS and station equipment tested and final connection
verification
• Aerial guideway from TPSS 17 to Innovation Center Station
verified and ready for train movement and dynamic testing
Phase 2 – Aerial, Track, Utilities, Systems
7. 7
• Bio retention ponds and perimeter fence installation
ongoing.
• MEP work for Service and Inspection Building,
Maintenance Way Building, Warehouse Building, and Train
Wash Facility.
• Ongoing – Testing of Yard Train Control cabling, switch and
signal installation
Phase 2 – Rail Yard at Dulles Airport
8. 8
• Total Project Estimate: $44.5M
• Construction Progress: 97% complete
• Existing garage repair work initiated in November 2018
Schedule
• Construction Award: October 2016
• Construction (new garage): November 2016 – March 2019
• Construction (existing garage): October 2018 – Summer 2019
• Ready for Occupancy: April 2019
Herndon Metrorail Garage
11. 11
• Total Project Estimate: $52 million
• Construction Progress: 65% complete
Schedule
• Construction Award: March 2017
• Construction Start: April 2017
• Precast Erection Start: April 5, 2018
• Ready for Occupancy: Prior to Revenue Operation
• MEP work re-initiated inside the structure
• Caisson remediation nearing completion
Innovation Metrorail Garage