SlideShare ist ein Scribd-Unternehmen logo
1 von 16
Dulles Corridor Metrorail Project
Board Transportation Committee Update
Mark Canale, Fairfax County Project Manager
Fairfax County Department of Transportation
May 9, 2017
Phase 1
• Old Meadow Road Realignment – in design, construction completion
scheduled for the end of 2018
• VDOT punchlist ongoing
• Phase 1 close out - $2.982B
Phase 2
• Package A (Rail line, system, and stations)– 59%
• Package B (Rail yard at Dulles) – 46%
• Contractual Substantial Completion – August 2019
• WMATA to establish Revenue Operations Date
2
Phase 2 – Station Construction
• Reston Town Center Station – Precast erection and structural steel
• Herndon Station – Structural steel for roof, precast detailing, north
and south pavilion construction
• Innovation Station – Precast detailing, structural steel painting,
electrical and plumbing, pedestrian bridge assembly for north and
south pavilions
• Dulles Airport Station – Precast and structural steel erection, station
mechanical/electrical/plumbing rough in work, tunnel tie-in
• Loudoun Gateway Station – Station precast erection
• Ashburn Station - Station foundation and support walls
3
Phase 2 – Aerial Guideway
• Columns and Pier Caps – 100%
• Deck Spans Poured – 77%
• Trackway Spans
• Aerial track supports, and deck pours work ongoing
4
Phase 2 – Rail Yard at Dulles Airport
• 100% Design Plans Submitted
• Installation of stormwater, sanitary, duct bank structures, and
retaining wall - ongoing
• Final grading, utilities and yard layout continues
• Structural steel erection for Service and Inspection and Maintenance
buildings - ongoing
• Foundation work for Transit Police and Train Wash Facility buildings -
ongoing
5
Phase 2 – Cost Summary
Budget
• Total Budget $2.778B
• Total Forecast $2.778B
• Total Expenditures $1.1B
Contingency Utilization
• Total Contingency $561.3M
• Total Contingency Utilized $131.3M
• Remaining Contingency $430M
6
Herndon Metrorail Garage
Total Project Estimate: $44.5M
Schedule
Bid Opening: July 2016
Construction Award: October 2016
Construction (new garage): November 2016 – January 2019
Construction (existing garage): February 2019 – March 2019
Ready for Occupancy: April 2019 7
Herndon Metrorail Garage
8
Innovation Metrorail Garage
Total Project Estimate: $52 million
Schedule
Bid Opening: December 2016 - February 2017
Construction Award: March - April 2017
Construction: April 2017
Ready for Occupancy: April/May 2019
9
Innovation Metrorail Garage
10
Reston Town Center Station
11
Herndon Station
12
Innovation Center Station
13
Dulles Airport Station
14
West Segment
15
QUESTIONS?
16

Weitere ähnliche Inhalte

Was ist angesagt?

Was ist angesagt? (20)

Silver Line Update: Board Transportation Committee May 24, 2016
Silver Line Update: Board Transportation Committee May 24, 2016Silver Line Update: Board Transportation Committee May 24, 2016
Silver Line Update: Board Transportation Committee May 24, 2016
 
Silver Line Update-Board Transportation Committee: Oct. 13, 2015
Silver Line Update-Board Transportation Committee: Oct. 13, 2015Silver Line Update-Board Transportation Committee: Oct. 13, 2015
Silver Line Update-Board Transportation Committee: Oct. 13, 2015
 
Silver Line Update: Dec. 1, 2015
Silver Line Update: Dec. 1, 2015Silver Line Update: Dec. 1, 2015
Silver Line Update: Dec. 1, 2015
 
Silver Line Phase 1 Status Report-Sept. 16, 2014
Silver Line Phase 1 Status Report-Sept. 16, 2014Silver Line Phase 1 Status Report-Sept. 16, 2014
Silver Line Phase 1 Status Report-Sept. 16, 2014
 
Transportation Priorities Plan: Future Updates
Transportation Priorities Plan: Future UpdatesTransportation Priorities Plan: Future Updates
Transportation Priorities Plan: Future Updates
 
Citizens Information Meeting: Lee Chapel Road Walkway
Citizens Information Meeting: Lee Chapel Road WalkwayCitizens Information Meeting: Lee Chapel Road Walkway
Citizens Information Meeting: Lee Chapel Road Walkway
 
Dulles Metrorail Silver Line Phase 2 Status and Funding Update
Dulles Metrorail Silver Line Phase 2 Status and Funding UpdateDulles Metrorail Silver Line Phase 2 Status and Funding Update
Dulles Metrorail Silver Line Phase 2 Status and Funding Update
 
Transform 66: Inside the Beltway
Transform 66: Inside the BeltwayTransform 66: Inside the Beltway
Transform 66: Inside the Beltway
 
Fairfax County Capital Bikeshare - TAC Presentation: June 21, 2016
Fairfax County Capital Bikeshare - TAC Presentation: June 21, 2016 Fairfax County Capital Bikeshare - TAC Presentation: June 21, 2016
Fairfax County Capital Bikeshare - TAC Presentation: June 21, 2016
 
Springfield Multi-Use Parking Garage: Public Information Meeting Aug. 17, 2016
Springfield Multi-Use Parking Garage: Public Information Meeting Aug. 17, 2016Springfield Multi-Use Parking Garage: Public Information Meeting Aug. 17, 2016
Springfield Multi-Use Parking Garage: Public Information Meeting Aug. 17, 2016
 
Implementation of HB2 (2014) and HB 1887 (2015)
Implementation of HB2 (2014) and HB 1887 (2015)Implementation of HB2 (2014) and HB 1887 (2015)
Implementation of HB2 (2014) and HB 1887 (2015)
 
Fairfax Commercial and Industrial Property Tax for Transportation
Fairfax Commercial and Industrial Property Tax for TransportationFairfax Commercial and Industrial Property Tax for Transportation
Fairfax Commercial and Industrial Property Tax for Transportation
 
I-66 Inside the Beltway Framework Document
I-66 Inside the Beltway Framework DocumentI-66 Inside the Beltway Framework Document
I-66 Inside the Beltway Framework Document
 
Silver Line Update - Feb. 12, 2016
Silver Line Update - Feb. 12, 2016Silver Line Update - Feb. 12, 2016
Silver Line Update - Feb. 12, 2016
 
VDRPT Route 1 Multimodal Alternatives Analysis
VDRPT Route 1 Multimodal Alternatives AnalysisVDRPT Route 1 Multimodal Alternatives Analysis
VDRPT Route 1 Multimodal Alternatives Analysis
 
Shirley Gate Road Extended Corridor Planning Study
Shirley Gate Road Extended Corridor Planning StudyShirley Gate Road Extended Corridor Planning Study
Shirley Gate Road Extended Corridor Planning Study
 
Beulah Road Walkway
Beulah Road WalkwayBeulah Road Walkway
Beulah Road Walkway
 
Silver Line Update: Board Transportation Committee: Dec. 13, 2016
Silver Line Update: Board Transportation Committee: Dec. 13, 2016Silver Line Update: Board Transportation Committee: Dec. 13, 2016
Silver Line Update: Board Transportation Committee: Dec. 13, 2016
 
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages Herndon ...
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages Herndon ...Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages Herndon ...
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages Herndon ...
 
Proposed Bicycle Facilities: VDOT Summer 2015 Repaving-Franconia Road
Proposed Bicycle Facilities: VDOT Summer 2015 Repaving-Franconia RoadProposed Bicycle Facilities: VDOT Summer 2015 Repaving-Franconia Road
Proposed Bicycle Facilities: VDOT Summer 2015 Repaving-Franconia Road
 

Ähnlich wie Agenda Item 7: Silver Line Phase II Implementation

North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinarNorth West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
Association for Project Management
 
Mount Dennis Station and EMSF Open House - March 2017
Mount Dennis Station and EMSF Open House - March 2017Mount Dennis Station and EMSF Open House - March 2017
Mount Dennis Station and EMSF Open House - March 2017
Crosstown TO
 
Leaside - Laird Construction Liaison Committee Meeting - June 2017
Leaside - Laird Construction Liaison Committee Meeting - June 2017Leaside - Laird Construction Liaison Committee Meeting - June 2017
Leaside - Laird Construction Liaison Committee Meeting - June 2017
Crosstown TO
 
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
Crosstown TO
 

Ähnlich wie Agenda Item 7: Silver Line Phase II Implementation (20)

Dulles Corridor Metrorail Project: Board Transportation Committee Update- Jul...
Dulles Corridor Metrorail Project: Board Transportation Committee Update- Jul...Dulles Corridor Metrorail Project: Board Transportation Committee Update- Jul...
Dulles Corridor Metrorail Project: Board Transportation Committee Update- Jul...
 
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation : Boar...
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation : Boar...Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation : Boar...
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation : Boar...
 
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project - Silver Line Phase 2 ImplementationDulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
 
Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project: Silver Line Phase 2 ImplementationDulles Corridor Metrorail Project: Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation
 
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project - Silver Line Phase 2 ImplementationDulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
 
Silver Line Update: Board Transportation Committee: Feb. 7, 2017
Silver Line Update: Board Transportation Committee: Feb. 7, 2017Silver Line Update: Board Transportation Committee: Feb. 7, 2017
Silver Line Update: Board Transportation Committee: Feb. 7, 2017
 
Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation - BTC U...
Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation - BTC U...Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation - BTC U...
Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation - BTC U...
 
Silver Line Phase 1-Status Report: May 6, 2014
Silver Line Phase 1-Status Report: May 6, 2014Silver Line Phase 1-Status Report: May 6, 2014
Silver Line Phase 1-Status Report: May 6, 2014
 
Silver Line Update: Board Transportation Committee May 24, 2016
Silver Line Update: Board Transportation Committee May 24, 2016Silver Line Update: Board Transportation Committee May 24, 2016
Silver Line Update: Board Transportation Committee May 24, 2016
 
Silver Line Phase 1-Status Report: Sept. 2013
Silver Line Phase 1-Status Report: Sept. 2013Silver Line Phase 1-Status Report: Sept. 2013
Silver Line Phase 1-Status Report: Sept. 2013
 
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinarNorth West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
 
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinarNorth West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
 
Telegraph Road Walkway Phase 1 August 2020
Telegraph Road Walkway Phase 1 August 2020Telegraph Road Walkway Phase 1 August 2020
Telegraph Road Walkway Phase 1 August 2020
 
Western works final
Western works final Western works final
Western works final
 
Mount Dennis Station and EMSF Open House - March 2017
Mount Dennis Station and EMSF Open House - March 2017Mount Dennis Station and EMSF Open House - March 2017
Mount Dennis Station and EMSF Open House - March 2017
 
Dulles Rail Phase 1-Status Report: June 21, 2013
Dulles Rail Phase 1-Status Report: June 21, 2013Dulles Rail Phase 1-Status Report: June 21, 2013
Dulles Rail Phase 1-Status Report: June 21, 2013
 
Silver Line Phase 1-Status Report: Feb. 4, 2014
Silver Line Phase 1-Status Report: Feb. 4, 2014Silver Line Phase 1-Status Report: Feb. 4, 2014
Silver Line Phase 1-Status Report: Feb. 4, 2014
 
Leaside - Laird Construction Liaison Committee Meeting - June 2017
Leaside - Laird Construction Liaison Committee Meeting - June 2017Leaside - Laird Construction Liaison Committee Meeting - June 2017
Leaside - Laird Construction Liaison Committee Meeting - June 2017
 
Public Information Meeting: Realignment of Old Courthouse Road at Besley Road
Public Information Meeting: Realignment of Old Courthouse Road at Besley RoadPublic Information Meeting: Realignment of Old Courthouse Road at Besley Road
Public Information Meeting: Realignment of Old Courthouse Road at Besley Road
 
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
 

Mehr von Fairfax County

Mehr von Fairfax County (20)

Merrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementMerrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer Replacement
 
SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS
 
Clarks Crossing Road Improvements 05-13-22
 Clarks Crossing Road Improvements 05-13-22 Clarks Crossing Road Improvements 05-13-22
Clarks Crossing Road Improvements 05-13-22
 
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxTysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
 
Lorton Volunteer Fire Station #19
Lorton Volunteer Fire Station  #19 Lorton Volunteer Fire Station  #19
Lorton Volunteer Fire Station #19
 
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationScotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
 
Sully Community Center Construction Progress
Sully Community Center Construction ProgressSully Community Center Construction Progress
Sully Community Center Construction Progress
 
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxRiverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
 
Burke VRE Connector Phase IV
Burke VRE Connector Phase IVBurke VRE Connector Phase IV
Burke VRE Connector Phase IV
 
Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022
 
Workhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxWorkhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick Offpptx
 
Workhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilWorkhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing Council
 
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
 
Reston Arts Community Center Feasibility - Wrap Up
 Reston Arts Community Center Feasibility - Wrap Up Reston Arts Community Center Feasibility - Wrap Up
Reston Arts Community Center Feasibility - Wrap Up
 
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
 
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
 
Oak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectOak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction Project
 
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
 
Reston Arts Center Feasibility - Focus Group Visual Arts
Reston Arts Center Feasibility -  Focus Group Visual ArtsReston Arts Center Feasibility -  Focus Group Visual Arts
Reston Arts Center Feasibility - Focus Group Visual Arts
 

Kürzlich hochgeladen

THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...
THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...
THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...
Faga1939
 
{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...
{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...
{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...
hyt3577
 
call girls inMahavir Nagar (delhi) call me [🔝9953056974🔝] escort service 24X7
call girls inMahavir Nagar  (delhi) call me [🔝9953056974🔝] escort service 24X7call girls inMahavir Nagar  (delhi) call me [🔝9953056974🔝] escort service 24X7
call girls inMahavir Nagar (delhi) call me [🔝9953056974🔝] escort service 24X7
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
The political system of the united kingdom
The political system of the united kingdomThe political system of the united kingdom
The political system of the united kingdom
lunadelior
 
9953056974 Call Girls In Pratap Nagar, Escorts (Delhi) NCR
9953056974 Call Girls In Pratap Nagar, Escorts (Delhi) NCR9953056974 Call Girls In Pratap Nagar, Escorts (Delhi) NCR
9953056974 Call Girls In Pratap Nagar, Escorts (Delhi) NCR
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 

Kürzlich hochgeladen (20)

THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...
THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...
THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...
 
{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...
{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...
{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...
 
China's soft power in 21st century .pptx
China's soft power in 21st century   .pptxChina's soft power in 21st century   .pptx
China's soft power in 21st century .pptx
 
06052024_First India Newspaper Jaipur.pdf
06052024_First India Newspaper Jaipur.pdf06052024_First India Newspaper Jaipur.pdf
06052024_First India Newspaper Jaipur.pdf
 
Unveiling the Characteristics of Political Institutions_ A Comprehensive Anal...
Unveiling the Characteristics of Political Institutions_ A Comprehensive Anal...Unveiling the Characteristics of Political Institutions_ A Comprehensive Anal...
Unveiling the Characteristics of Political Institutions_ A Comprehensive Anal...
 
10052024_First India Newspaper Jaipur.pdf
10052024_First India Newspaper Jaipur.pdf10052024_First India Newspaper Jaipur.pdf
10052024_First India Newspaper Jaipur.pdf
 
Transformative Leadership: N Chandrababu Naidu and TDP's Vision for Innovatio...
Transformative Leadership: N Chandrababu Naidu and TDP's Vision for Innovatio...Transformative Leadership: N Chandrababu Naidu and TDP's Vision for Innovatio...
Transformative Leadership: N Chandrababu Naidu and TDP's Vision for Innovatio...
 
America Is the Target; Israel Is the Front Line _ Andy Blumenthal _ The Blogs...
America Is the Target; Israel Is the Front Line _ Andy Blumenthal _ The Blogs...America Is the Target; Israel Is the Front Line _ Andy Blumenthal _ The Blogs...
America Is the Target; Israel Is the Front Line _ Andy Blumenthal _ The Blogs...
 
*Navigating Electoral Terrain: TDP's Performance under N Chandrababu Naidu's ...
*Navigating Electoral Terrain: TDP's Performance under N Chandrababu Naidu's ...*Navigating Electoral Terrain: TDP's Performance under N Chandrababu Naidu's ...
*Navigating Electoral Terrain: TDP's Performance under N Chandrababu Naidu's ...
 
05052024_First India Newspaper Jaipur.pdf
05052024_First India Newspaper Jaipur.pdf05052024_First India Newspaper Jaipur.pdf
05052024_First India Newspaper Jaipur.pdf
 
04052024_First India Newspaper Jaipur.pdf
04052024_First India Newspaper Jaipur.pdf04052024_First India Newspaper Jaipur.pdf
04052024_First India Newspaper Jaipur.pdf
 
KING VISHNU BHAGWANON KA BHAGWAN PARAMATMONKA PARATOMIC PARAMANU KASARVAMANVA...
KING VISHNU BHAGWANON KA BHAGWAN PARAMATMONKA PARATOMIC PARAMANU KASARVAMANVA...KING VISHNU BHAGWANON KA BHAGWAN PARAMATMONKA PARATOMIC PARAMANU KASARVAMANVA...
KING VISHNU BHAGWANON KA BHAGWAN PARAMATMONKA PARATOMIC PARAMANU KASARVAMANVA...
 
Politician uddhav thackeray biography- Full Details
Politician uddhav thackeray biography- Full DetailsPolitician uddhav thackeray biography- Full Details
Politician uddhav thackeray biography- Full Details
 
422524114-Patriarchy-Kamla-Bhasin gg.pdf
422524114-Patriarchy-Kamla-Bhasin gg.pdf422524114-Patriarchy-Kamla-Bhasin gg.pdf
422524114-Patriarchy-Kamla-Bhasin gg.pdf
 
declarationleaders_sd_re_greens_theleft_5.pdf
declarationleaders_sd_re_greens_theleft_5.pdfdeclarationleaders_sd_re_greens_theleft_5.pdf
declarationleaders_sd_re_greens_theleft_5.pdf
 
call girls inMahavir Nagar (delhi) call me [🔝9953056974🔝] escort service 24X7
call girls inMahavir Nagar  (delhi) call me [🔝9953056974🔝] escort service 24X7call girls inMahavir Nagar  (delhi) call me [🔝9953056974🔝] escort service 24X7
call girls inMahavir Nagar (delhi) call me [🔝9953056974🔝] escort service 24X7
 
The political system of the united kingdom
The political system of the united kingdomThe political system of the united kingdom
The political system of the united kingdom
 
Dubai Call Girls Pinky O525547819 Call Girl's In Dubai
Dubai Call Girls Pinky O525547819 Call Girl's In DubaiDubai Call Girls Pinky O525547819 Call Girl's In Dubai
Dubai Call Girls Pinky O525547819 Call Girl's In Dubai
 
9953056974 Call Girls In Pratap Nagar, Escorts (Delhi) NCR
9953056974 Call Girls In Pratap Nagar, Escorts (Delhi) NCR9953056974 Call Girls In Pratap Nagar, Escorts (Delhi) NCR
9953056974 Call Girls In Pratap Nagar, Escorts (Delhi) NCR
 
Job-Oriеntеd Courses That Will Boost Your Career in 2024
Job-Oriеntеd Courses That Will Boost Your Career in 2024Job-Oriеntеd Courses That Will Boost Your Career in 2024
Job-Oriеntеd Courses That Will Boost Your Career in 2024
 

Agenda Item 7: Silver Line Phase II Implementation

  • 1. Dulles Corridor Metrorail Project Board Transportation Committee Update Mark Canale, Fairfax County Project Manager Fairfax County Department of Transportation May 9, 2017
  • 2. Phase 1 • Old Meadow Road Realignment – in design, construction completion scheduled for the end of 2018 • VDOT punchlist ongoing • Phase 1 close out - $2.982B Phase 2 • Package A (Rail line, system, and stations)– 59% • Package B (Rail yard at Dulles) – 46% • Contractual Substantial Completion – August 2019 • WMATA to establish Revenue Operations Date 2
  • 3. Phase 2 – Station Construction • Reston Town Center Station – Precast erection and structural steel • Herndon Station – Structural steel for roof, precast detailing, north and south pavilion construction • Innovation Station – Precast detailing, structural steel painting, electrical and plumbing, pedestrian bridge assembly for north and south pavilions • Dulles Airport Station – Precast and structural steel erection, station mechanical/electrical/plumbing rough in work, tunnel tie-in • Loudoun Gateway Station – Station precast erection • Ashburn Station - Station foundation and support walls 3
  • 4. Phase 2 – Aerial Guideway • Columns and Pier Caps – 100% • Deck Spans Poured – 77% • Trackway Spans • Aerial track supports, and deck pours work ongoing 4
  • 5. Phase 2 – Rail Yard at Dulles Airport • 100% Design Plans Submitted • Installation of stormwater, sanitary, duct bank structures, and retaining wall - ongoing • Final grading, utilities and yard layout continues • Structural steel erection for Service and Inspection and Maintenance buildings - ongoing • Foundation work for Transit Police and Train Wash Facility buildings - ongoing 5
  • 6. Phase 2 – Cost Summary Budget • Total Budget $2.778B • Total Forecast $2.778B • Total Expenditures $1.1B Contingency Utilization • Total Contingency $561.3M • Total Contingency Utilized $131.3M • Remaining Contingency $430M 6
  • 7. Herndon Metrorail Garage Total Project Estimate: $44.5M Schedule Bid Opening: July 2016 Construction Award: October 2016 Construction (new garage): November 2016 – January 2019 Construction (existing garage): February 2019 – March 2019 Ready for Occupancy: April 2019 7
  • 9. Innovation Metrorail Garage Total Project Estimate: $52 million Schedule Bid Opening: December 2016 - February 2017 Construction Award: March - April 2017 Construction: April 2017 Ready for Occupancy: April/May 2019 9
  • 11. Reston Town Center Station 11