1. ETF outside works and schedule
FIRST PHASE:
sector B, tower ground and first floors
=> starting date 10/02 - estimated end date: 20/04
SECOND PHASE:
sector B0 and C0 (corridor), including Villa Gualino façade looking in the
inner yard court
=> starting date : 27/04 - estimated ending date: 06/07
THIRD PHASE:
sector D
=> starting date 4/05 - estimated end date: 25/05
2. ETF inside works and schedule
Reception area:
start = beginning of February 2014 // end = end of April 2014
•
1st step - construction of the false ceiling and wooden floor near the window
•
2dn step - construction of false ceiling and wooden floor were the reception
desk is at the moment
•
3th step - technical works
•
4th step - assembly of new wooden walls and reception desk
reception and surveillance daily activities will not suffer interruptions.
New multi-functioning room (canteen, cafeteria area):
start = 15 March 2014 // end = June 2014
•
1st step - reallocation of Library and publications shelves
•
2nd step - reallocate of all furniture but the meeting room
•
3th step - structural/building works (plasterboards walls) and technical works
such as lighting, ventilation, water connection, etc
•
4th step - provision of new appropriate furniture for the canteen/cafeteria