Created by ejlp12@gmail.com, June 2010 5 - Project Scope Management Project Management Training
Project Scope Management Monitoring & Controlling Processes Planning Processes Enter phase/ Start project Exit phase/ End project Initiating Processes Closing Processes Executing Processes
Project Scope Management Process to ensure that the project includes all-and-only the work required, to complete the project successfully Scope can refer to Product Scope &  Project Scope Scope Management Plan (part of Develop Project Mgmt Plan) How will I do the scope? Provides guidance on how project scope will be defines, documented, verified, managed, and controlled by project management team ,[object Object]
Attitude to say no to unnecessary scope. It should go to project approval process,[object Object]
Collect Requirement Techniques (1) INTERVIEWS: Directly talk with stakeholders FOCUS GROUPS: Interactive discussion with qualified Stakeholders & Subject matter experts FACILITATED WORKSHOPS: Focused cross functional stakeholders. JAD Joint application design,  QFD Quality function developmentHelps determine critical characteristic of new product developmentStart by collecting customer need - VOC: Voice of the Customers
Collect Requirement Techniques (2) GROUP CREATIVITY TECHNIQUES:  Brainstorming,  Nominal group technique: enhance brainstorming with voting and ranking Delphi Technique: some expert answer questionnaire and give anonimity feedback  Idea/mind mapping,  Affinity Diagram: sort idea into groups GROUP DECISION MAKING TECHNIQUES:  Unanimity,  Majority (>50%),  Plurality,  Dictatorship
Affinity Diagram Requirement sorted into groups by similarities Easier to see additional scope (risk) that have not been identified Image Source: PMP Exam Preparation 6th Edition, Rita Mulcahy
Collect Requirement Techniques (3) QUESTIONNAIRE AND SURVEYS: wide number of respondents OBSERVATION/JOB SHADOWING: viewing individual in their environment PROTOTYPES: early feedback by providing a working model
Balance Stakeholder’s Requirement There is a need to balance stakeholder’s requirement  Some issue are so complex they cannot be resolved by PM alone ,[object Object],business case,  project charter,  project scope statement,  project constraints ,[object Object]
Conflict resolution, team building, meeting, problem solving skills, escalation, approval from stakeholderStakeholder request to do or add something that is not related to the reason of project created should be rejected!
Requirement Document Output of the Collect Requirement process Helps make sure the requirements clear and unambiguous. How will we know if the work we do will acceptability meet this requirement? Rule of thumb Specific (Unambiguous) Measurable (How will we know we have finished?) Achievable (Can we do it?) Relevant (Is it the right thing to do?) Timed (When will we do it?)
5.2 Define Scope Process of developing a detailed description of the project and product Project scope statement may includes product scope, deliverables, product acceptance criteria, out of scope, additional risk, constraints & assumptions
Define Scope Concern with what is and is not included in the project and its deliverables You should maintain a realistic schedule and budget that can achieve the project’s scope Iteration process should be done to maintain it Looking for options to adjust the project Analyze the objective and description of the product stated by the customer/sponsor and turn them into tangible deliverables. Project lifecycle term Product Analysis
Project Scope Statement The primary result of the Define Scope process Along with the WBS and WBS dictionary, comprise the scope baseline is part of project management plan. May includes: Product scope Deliverables Product acceptance criteria What is not part of the project (out of scope) Additional risks Constraints and assumptions :Constraints: factors that limit the team’s optionsAssumptions: Things that assumed to be true (may not be true)
5.3 Create WBS Process of subdividing project deliverables and project work into smaller, more manageable components. ,[object Object]
Dividing work package into activities is part of the time management process (Define Activities),[object Object]
WBS Sample Image Source: Practice Standard for WBS 2nd Edition. PMI © 2006
WBS 100% rule: WBS includes 100% of the work defined by project scope and capture ALL deliverables (external, internal, interim) in term of work to be completed including project management. WBS creation method: Top-Down Bottom up WBS Standard WBS Templates Don’t mind with WBS view Outline View Tabular View Tree structure view (vertical, horizontal, centralized)
WBS Dictionary Sample Includes (but not limited to): Code of account identifier Description of work Responsible organization List of schedule milestone Associated schedule activities Resource required Cost estimates Quality requirements Acceptance criteria Technical references Contract Information Image Source: Practice Standard for WBS 2nd Edition. PMI © 2006
WBS Dictionary Sample (2) Source: http://www.brighthub.com/office/project-management/articles/52388.aspx
5.4 Verify Scope Process of formalizing acceptance of the completed project deliverables.
Verify Scope ,[object Object]
NOT making sure you have the right scope during project planning
But, to gain formal acceptance of deliverables during monitoring and control.Inspection = review, product reviews, audits, walkthroughs Measuring, examining, verifying to determine work and deliverables are meet requirement & product acceptance criteria

Weitere ähnliche Inhalte

Was ist angesagt?

PMP Training - 08 project quality management
PMP Training - 08 project quality managementPMP Training - 08 project quality management
PMP Training - 08 project quality management
ejlp12
 

Was ist angesagt? (20)

Instructor Slides - PMP/CAPM PMBOK 6th Edition
Instructor Slides - PMP/CAPM PMBOK 6th EditionInstructor Slides - PMP/CAPM PMBOK 6th Edition
Instructor Slides - PMP/CAPM PMBOK 6th Edition
 
PMP PMBOK 6th
PMP PMBOK 6thPMP PMBOK 6th
PMP PMBOK 6th
 
Chap 8.2 Manage Quality
Chap 8.2 Manage QualityChap 8.2 Manage Quality
Chap 8.2 Manage Quality
 
Pmp integration management
Pmp integration managementPmp integration management
Pmp integration management
 
PMP Chap 7 - Project Cost Management - Part 2
PMP Chap 7 - Project Cost Management - Part 2PMP Chap 7 - Project Cost Management - Part 2
PMP Chap 7 - Project Cost Management - Part 2
 
Chap 8.1 Plan quality management
Chap 8.1 Plan quality managementChap 8.1 Plan quality management
Chap 8.1 Plan quality management
 
PMP Chap4-Project Integration Management Details: Part-2
PMP Chap4-Project Integration Management Details: Part-2PMP Chap4-Project Integration Management Details: Part-2
PMP Chap4-Project Integration Management Details: Part-2
 
Chap 10.1 Plan Communication Management
Chap 10.1  Plan Communication ManagementChap 10.1  Plan Communication Management
Chap 10.1 Plan Communication Management
 
PMP Training - 08 project quality management
PMP Training - 08 project quality managementPMP Training - 08 project quality management
PMP Training - 08 project quality management
 
Chap 5.4 Create WBS
Chap 5.4 Create WBSChap 5.4 Create WBS
Chap 5.4 Create WBS
 
PgMP Course Training Material Slides PowerPoint Presentation
PgMP Course Training Material Slides PowerPoint PresentationPgMP Course Training Material Slides PowerPoint Presentation
PgMP Course Training Material Slides PowerPoint Presentation
 
2_Project Scope Management
2_Project Scope Management2_Project Scope Management
2_Project Scope Management
 
05 project scope management
05 project scope management05 project scope management
05 project scope management
 
PMP Exam Flashcards common definitions 7th edition original v2.0
PMP Exam Flashcards common definitions 7th edition original v2.0PMP Exam Flashcards common definitions 7th edition original v2.0
PMP Exam Flashcards common definitions 7th edition original v2.0
 
Chap 4.6 Perform Integrated Change Control
Chap 4.6 Perform Integrated Change ControlChap 4.6 Perform Integrated Change Control
Chap 4.6 Perform Integrated Change Control
 
PMP
PMPPMP
PMP
 
Chap 9.4 Develop Team
Chap 9.4  Develop TeamChap 9.4  Develop Team
Chap 9.4 Develop Team
 
Chap 7.4 Control Cost
Chap 7.4   Control CostChap 7.4   Control Cost
Chap 7.4 Control Cost
 
PMP Chap 3 - Project Management Processes
PMP Chap 3 - Project Management ProcessesPMP Chap 3 - Project Management Processes
PMP Chap 3 - Project Management Processes
 
Chap 5.3 define scope
Chap 5.3 define scopeChap 5.3 define scope
Chap 5.3 define scope
 

Andere mochten auch

PMP Training - 01 introduction to framework
PMP Training - 01 introduction to frameworkPMP Training - 01 introduction to framework
PMP Training - 01 introduction to framework
ejlp12
 
Introduction to PMP
Introduction to PMPIntroduction to PMP
Introduction to PMP
Edureka!
 
PMP Training - 07 project cost management
PMP Training - 07 project cost managementPMP Training - 07 project cost management
PMP Training - 07 project cost management
ejlp12
 
PMP Training - 10 project communication management
PMP Training - 10 project communication managementPMP Training - 10 project communication management
PMP Training - 10 project communication management
ejlp12
 
Seo goals & objectives 2 quarter 2012
Seo goals & objectives 2 quarter 2012Seo goals & objectives 2 quarter 2012
Seo goals & objectives 2 quarter 2012
EBY3081
 

Andere mochten auch (20)

Path to PMP
Path to PMPPath to PMP
Path to PMP
 
6- PMP Training - Cost Management
6- PMP Training - Cost Management6- PMP Training - Cost Management
6- PMP Training - Cost Management
 
PMP Training - 01 introduction to framework
PMP Training - 01 introduction to frameworkPMP Training - 01 introduction to framework
PMP Training - 01 introduction to framework
 
11- PMP Training - Procurement Management
11- PMP Training - Procurement Management 11- PMP Training - Procurement Management
11- PMP Training - Procurement Management
 
10- PMP Training - Risk Management
10- PMP Training - Risk Management 10- PMP Training - Risk Management
10- PMP Training - Risk Management
 
Introduction to PMP
Introduction to PMPIntroduction to PMP
Introduction to PMP
 
7- PMP Training - Quality Management
7- PMP Training - Quality Management7- PMP Training - Quality Management
7- PMP Training - Quality Management
 
9- PMP Training - Communication Management
9- PMP Training - Communication Management9- PMP Training - Communication Management
9- PMP Training - Communication Management
 
Learning pmp formulas the easy way
Learning pmp formulas the easy wayLearning pmp formulas the easy way
Learning pmp formulas the easy way
 
PMP Training - 07 project cost management
PMP Training - 07 project cost managementPMP Training - 07 project cost management
PMP Training - 07 project cost management
 
8- PMP Training - Human Resource Management
8- PMP Training - Human Resource Management8- PMP Training - Human Resource Management
8- PMP Training - Human Resource Management
 
PMP Training - 10 project communication management
PMP Training - 10 project communication managementPMP Training - 10 project communication management
PMP Training - 10 project communication management
 
5 phases of project management
5 phases of project management5 phases of project management
5 phases of project management
 
Seo goals & objectives 2 quarter 2012
Seo goals & objectives 2 quarter 2012Seo goals & objectives 2 quarter 2012
Seo goals & objectives 2 quarter 2012
 
02 project scope management
02 project scope management02 project scope management
02 project scope management
 
Defining clear project goals
Defining clear project goalsDefining clear project goals
Defining clear project goals
 
Pmbok 4th edition chapter 5 - Project Scope Management
Pmbok 4th edition   chapter 5 - Project Scope Management Pmbok 4th edition   chapter 5 - Project Scope Management
Pmbok 4th edition chapter 5 - Project Scope Management
 
Project ATOM Goals And Objectives
Project ATOM Goals And ObjectivesProject ATOM Goals And Objectives
Project ATOM Goals And Objectives
 
Objectives of Project evaluation
Objectives of Project evaluationObjectives of Project evaluation
Objectives of Project evaluation
 
Managing Virtual Project Teams
Managing Virtual Project TeamsManaging Virtual Project Teams
Managing Virtual Project Teams
 

Ähnlich wie PMP Training - 05 project scope management

2.05 scope management 1
2.05 scope management 12.05 scope management 1
2.05 scope management 1
reddvise
 
MBA 6941, Managing Project Teams 1 Course Learning Ou.docx
 MBA 6941, Managing Project Teams 1 Course Learning Ou.docx MBA 6941, Managing Project Teams 1 Course Learning Ou.docx
MBA 6941, Managing Project Teams 1 Course Learning Ou.docx
ShiraPrater50
 
2.1 integration management
2.1 integration management2.1 integration management
2.1 integration management
Irefuser1
 
Project management lecture 11 slide 11
Project management lecture 11 slide 11Project management lecture 11 slide 11
Project management lecture 11 slide 11
beautyshine
 

Ähnlich wie PMP Training - 05 project scope management (20)

04 projectintegrationmanagement
04 projectintegrationmanagement04 projectintegrationmanagement
04 projectintegrationmanagement
 
5 scope
5 scope5 scope
5 scope
 
Pmp chapter(5) Scope Management
Pmp chapter(5) Scope ManagementPmp chapter(5) Scope Management
Pmp chapter(5) Scope Management
 
2.05 scope management 1
2.05 scope management 12.05 scope management 1
2.05 scope management 1
 
Chapter 2 Work Break down Structure1.ppt
Chapter 2 Work Break down Structure1.pptChapter 2 Work Break down Structure1.ppt
Chapter 2 Work Break down Structure1.ppt
 
Chapter 2 Work Break down Structure (1).ppt
Chapter 2 Work Break down Structure (1).pptChapter 2 Work Break down Structure (1).ppt
Chapter 2 Work Break down Structure (1).ppt
 
2. project scope management
2. project scope management2. project scope management
2. project scope management
 
CAPM Week 2 Chapter 5
CAPM Week 2 Chapter 5CAPM Week 2 Chapter 5
CAPM Week 2 Chapter 5
 
3&4. project scope management at project.ppt
3&4. project scope management at project.ppt3&4. project scope management at project.ppt
3&4. project scope management at project.ppt
 
MBA 6941, Managing Project Teams 1 Course Learning Ou.docx
 MBA 6941, Managing Project Teams 1 Course Learning Ou.docx MBA 6941, Managing Project Teams 1 Course Learning Ou.docx
MBA 6941, Managing Project Teams 1 Course Learning Ou.docx
 
Scope and Time Management
Scope and Time ManagementScope and Time Management
Scope and Time Management
 
2. Project Scope Management.ppt
2. Project Scope Management.ppt2. Project Scope Management.ppt
2. Project Scope Management.ppt
 
Lec 08 project scope_management
Lec 08 project scope_managementLec 08 project scope_management
Lec 08 project scope_management
 
Pmp scope chapter 5
Pmp scope chapter 5Pmp scope chapter 5
Pmp scope chapter 5
 
Ch05
Ch05Ch05
Ch05
 
ICB Competence, Project Standards
ICB Competence, Project StandardsICB Competence, Project Standards
ICB Competence, Project Standards
 
2.1 integration management
2.1 integration management2.1 integration management
2.1 integration management
 
Project Scope Management Knowledge Area
Project Scope Management Knowledge AreaProject Scope Management Knowledge Area
Project Scope Management Knowledge Area
 
Project management lecture 11 slide 11
Project management lecture 11 slide 11Project management lecture 11 slide 11
Project management lecture 11 slide 11
 
Online PMP Training Material for PMP Exam - Scope Management Knowledge Area
Online PMP Training Material for PMP Exam - Scope Management Knowledge AreaOnline PMP Training Material for PMP Exam - Scope Management Knowledge Area
Online PMP Training Material for PMP Exam - Scope Management Knowledge Area
 

Mehr von ejlp12

Arah pengembangan core network architecture (Indonesia)
Arah pengembangan core network architecture (Indonesia)Arah pengembangan core network architecture (Indonesia)
Arah pengembangan core network architecture (Indonesia)
ejlp12
 

Mehr von ejlp12 (20)

Introduction to Docker storage, volume and image
Introduction to Docker storage, volume and imageIntroduction to Docker storage, volume and image
Introduction to Docker storage, volume and image
 
Java troubleshooting thread dump
Java troubleshooting thread dumpJava troubleshooting thread dump
Java troubleshooting thread dump
 
RESTful web service with JBoss Fuse
RESTful web service with JBoss FuseRESTful web service with JBoss Fuse
RESTful web service with JBoss Fuse
 
WebSphere Application Server Information Resources
WebSphere Application Server Information ResourcesWebSphere Application Server Information Resources
WebSphere Application Server Information Resources
 
WebSphere Application Server Family (Editions Comparison)
WebSphere Application Server Family (Editions Comparison)WebSphere Application Server Family (Editions Comparison)
WebSphere Application Server Family (Editions Comparison)
 
Linux container & docker
Linux container & dockerLinux container & docker
Linux container & docker
 
BPEL, BPEL vs ESB (Integration)
BPEL, BPEL vs ESB (Integration)BPEL, BPEL vs ESB (Integration)
BPEL, BPEL vs ESB (Integration)
 
BPMN Introduction
BPMN IntroductionBPMN Introduction
BPMN Introduction
 
JBoss Data Virtualization (JDV) Sample Physical Deployment Architecture
JBoss Data Virtualization (JDV) Sample Physical Deployment ArchitectureJBoss Data Virtualization (JDV) Sample Physical Deployment Architecture
JBoss Data Virtualization (JDV) Sample Physical Deployment Architecture
 
WebSphere Application Server Topology Options
WebSphere Application Server Topology OptionsWebSphere Application Server Topology Options
WebSphere Application Server Topology Options
 
IBM WebSphere Application Server version to version comparison
IBM WebSphere Application Server version to version comparisonIBM WebSphere Application Server version to version comparison
IBM WebSphere Application Server version to version comparison
 
IBM WebSphere Application Server (Clustering) Concept
IBM WebSphere Application Server (Clustering) ConceptIBM WebSphere Application Server (Clustering) Concept
IBM WebSphere Application Server (Clustering) Concept
 
IBM WebSphere MQ Introduction
IBM WebSphere MQ Introduction IBM WebSphere MQ Introduction
IBM WebSphere MQ Introduction
 
Java EE Introduction
Java EE IntroductionJava EE Introduction
Java EE Introduction
 
Introduction to Apache Cordova (Phonegap)
Introduction to Apache Cordova (Phonegap)Introduction to Apache Cordova (Phonegap)
Introduction to Apache Cordova (Phonegap)
 
Introduction to jQuery Mobile
Introduction to jQuery MobileIntroduction to jQuery Mobile
Introduction to jQuery Mobile
 
Introduction to JPA (JPA version 2.0)
Introduction to JPA (JPA version 2.0)Introduction to JPA (JPA version 2.0)
Introduction to JPA (JPA version 2.0)
 
Introduction to JavaBeans Activation Framework v1.1
Introduction to JavaBeans Activation Framework v1.1Introduction to JavaBeans Activation Framework v1.1
Introduction to JavaBeans Activation Framework v1.1
 
Arah pengembangan core network architecture (Indonesia)
Arah pengembangan core network architecture (Indonesia)Arah pengembangan core network architecture (Indonesia)
Arah pengembangan core network architecture (Indonesia)
 
GSM/UMTS network architecture tutorial (Indonesia)
GSM/UMTS network architecture tutorial (Indonesia)GSM/UMTS network architecture tutorial (Indonesia)
GSM/UMTS network architecture tutorial (Indonesia)
 

Kürzlich hochgeladen

Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...
Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...
Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...
amitlee9823
 
Call Now ☎️🔝 9332606886🔝 Call Girls ❤ Service In Bhilwara Female Escorts Serv...
Call Now ☎️🔝 9332606886🔝 Call Girls ❤ Service In Bhilwara Female Escorts Serv...Call Now ☎️🔝 9332606886🔝 Call Girls ❤ Service In Bhilwara Female Escorts Serv...
Call Now ☎️🔝 9332606886🔝 Call Girls ❤ Service In Bhilwara Female Escorts Serv...
Anamikakaur10
 
Call Girls In Nangloi Rly Metro ꧂…….95996 … 13876 Enjoy ꧂Escort
Call Girls In Nangloi Rly Metro ꧂…….95996 … 13876 Enjoy ꧂EscortCall Girls In Nangloi Rly Metro ꧂…….95996 … 13876 Enjoy ꧂Escort
Call Girls In Nangloi Rly Metro ꧂…….95996 … 13876 Enjoy ꧂Escort
dlhescort
 
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
daisycvs
 
Call Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service NoidaCall Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service Noida
dlhescort
 
Call Girls From Raj Nagar Extension Ghaziabad❤️8448577510 ⊹Best Escorts Servi...
Call Girls From Raj Nagar Extension Ghaziabad❤️8448577510 ⊹Best Escorts Servi...Call Girls From Raj Nagar Extension Ghaziabad❤️8448577510 ⊹Best Escorts Servi...
Call Girls From Raj Nagar Extension Ghaziabad❤️8448577510 ⊹Best Escorts Servi...
lizamodels9
 
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service BangaloreCall Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
amitlee9823
 
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
dlhescort
 

Kürzlich hochgeladen (20)

Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st CenturyFamous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Century
 
Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...
Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...
Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...
 
Call Now ☎️🔝 9332606886🔝 Call Girls ❤ Service In Bhilwara Female Escorts Serv...
Call Now ☎️🔝 9332606886🔝 Call Girls ❤ Service In Bhilwara Female Escorts Serv...Call Now ☎️🔝 9332606886🔝 Call Girls ❤ Service In Bhilwara Female Escorts Serv...
Call Now ☎️🔝 9332606886🔝 Call Girls ❤ Service In Bhilwara Female Escorts Serv...
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and pains
 
Call Girls In Nangloi Rly Metro ꧂…….95996 … 13876 Enjoy ꧂Escort
Call Girls In Nangloi Rly Metro ꧂…….95996 … 13876 Enjoy ꧂EscortCall Girls In Nangloi Rly Metro ꧂…….95996 … 13876 Enjoy ꧂Escort
Call Girls In Nangloi Rly Metro ꧂…….95996 … 13876 Enjoy ꧂Escort
 
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
 
Cheap Rate Call Girls In Noida Sector 62 Metro 959961乂3876
Cheap Rate Call Girls In Noida Sector 62 Metro 959961乂3876Cheap Rate Call Girls In Noida Sector 62 Metro 959961乂3876
Cheap Rate Call Girls In Noida Sector 62 Metro 959961乂3876
 
Call Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service NoidaCall Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service Noida
 
Malegaon Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort Service
Malegaon Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort ServiceMalegaon Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort Service
Malegaon Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort Service
 
Whitefield CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
Whitefield CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRLWhitefield CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
Whitefield CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
 
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
 
Call Girls From Raj Nagar Extension Ghaziabad❤️8448577510 ⊹Best Escorts Servi...
Call Girls From Raj Nagar Extension Ghaziabad❤️8448577510 ⊹Best Escorts Servi...Call Girls From Raj Nagar Extension Ghaziabad❤️8448577510 ⊹Best Escorts Servi...
Call Girls From Raj Nagar Extension Ghaziabad❤️8448577510 ⊹Best Escorts Servi...
 
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60% in 6 Months
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60%  in 6 MonthsSEO Case Study: How I Increased SEO Traffic & Ranking by 50-60%  in 6 Months
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60% in 6 Months
 
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRLBAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
 
Falcon Invoice Discounting: Empowering Your Business Growth
Falcon Invoice Discounting: Empowering Your Business GrowthFalcon Invoice Discounting: Empowering Your Business Growth
Falcon Invoice Discounting: Empowering Your Business Growth
 
(Anamika) VIP Call Girls Napur Call Now 8617697112 Napur Escorts 24x7
(Anamika) VIP Call Girls Napur Call Now 8617697112 Napur Escorts 24x7(Anamika) VIP Call Girls Napur Call Now 8617697112 Napur Escorts 24x7
(Anamika) VIP Call Girls Napur Call Now 8617697112 Napur Escorts 24x7
 
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service BangaloreCall Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
 
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
 
Uneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration PresentationUneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration Presentation
 
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service AvailableCall Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
 

PMP Training - 05 project scope management

  • 1. Created by ejlp12@gmail.com, June 2010 5 - Project Scope Management Project Management Training
  • 2. Project Scope Management Monitoring & Controlling Processes Planning Processes Enter phase/ Start project Exit phase/ End project Initiating Processes Closing Processes Executing Processes
  • 3.
  • 4.
  • 5. Collect Requirement Techniques (1) INTERVIEWS: Directly talk with stakeholders FOCUS GROUPS: Interactive discussion with qualified Stakeholders & Subject matter experts FACILITATED WORKSHOPS: Focused cross functional stakeholders. JAD Joint application design, QFD Quality function developmentHelps determine critical characteristic of new product developmentStart by collecting customer need - VOC: Voice of the Customers
  • 6. Collect Requirement Techniques (2) GROUP CREATIVITY TECHNIQUES: Brainstorming, Nominal group technique: enhance brainstorming with voting and ranking Delphi Technique: some expert answer questionnaire and give anonimity feedback Idea/mind mapping, Affinity Diagram: sort idea into groups GROUP DECISION MAKING TECHNIQUES: Unanimity, Majority (>50%), Plurality, Dictatorship
  • 7. Affinity Diagram Requirement sorted into groups by similarities Easier to see additional scope (risk) that have not been identified Image Source: PMP Exam Preparation 6th Edition, Rita Mulcahy
  • 8. Collect Requirement Techniques (3) QUESTIONNAIRE AND SURVEYS: wide number of respondents OBSERVATION/JOB SHADOWING: viewing individual in their environment PROTOTYPES: early feedback by providing a working model
  • 9.
  • 10. Conflict resolution, team building, meeting, problem solving skills, escalation, approval from stakeholderStakeholder request to do or add something that is not related to the reason of project created should be rejected!
  • 11. Requirement Document Output of the Collect Requirement process Helps make sure the requirements clear and unambiguous. How will we know if the work we do will acceptability meet this requirement? Rule of thumb Specific (Unambiguous) Measurable (How will we know we have finished?) Achievable (Can we do it?) Relevant (Is it the right thing to do?) Timed (When will we do it?)
  • 12. 5.2 Define Scope Process of developing a detailed description of the project and product Project scope statement may includes product scope, deliverables, product acceptance criteria, out of scope, additional risk, constraints & assumptions
  • 13. Define Scope Concern with what is and is not included in the project and its deliverables You should maintain a realistic schedule and budget that can achieve the project’s scope Iteration process should be done to maintain it Looking for options to adjust the project Analyze the objective and description of the product stated by the customer/sponsor and turn them into tangible deliverables. Project lifecycle term Product Analysis
  • 14. Project Scope Statement The primary result of the Define Scope process Along with the WBS and WBS dictionary, comprise the scope baseline is part of project management plan. May includes: Product scope Deliverables Product acceptance criteria What is not part of the project (out of scope) Additional risks Constraints and assumptions :Constraints: factors that limit the team’s optionsAssumptions: Things that assumed to be true (may not be true)
  • 15.
  • 16.
  • 17. WBS Sample Image Source: Practice Standard for WBS 2nd Edition. PMI © 2006
  • 18. WBS 100% rule: WBS includes 100% of the work defined by project scope and capture ALL deliverables (external, internal, interim) in term of work to be completed including project management. WBS creation method: Top-Down Bottom up WBS Standard WBS Templates Don’t mind with WBS view Outline View Tabular View Tree structure view (vertical, horizontal, centralized)
  • 19. WBS Dictionary Sample Includes (but not limited to): Code of account identifier Description of work Responsible organization List of schedule milestone Associated schedule activities Resource required Cost estimates Quality requirements Acceptance criteria Technical references Contract Information Image Source: Practice Standard for WBS 2nd Edition. PMI © 2006
  • 20. WBS Dictionary Sample (2) Source: http://www.brighthub.com/office/project-management/articles/52388.aspx
  • 21. 5.4 Verify Scope Process of formalizing acceptance of the completed project deliverables.
  • 22.
  • 23. NOT making sure you have the right scope during project planning
  • 24. But, to gain formal acceptance of deliverables during monitoring and control.Inspection = review, product reviews, audits, walkthroughs Measuring, examining, verifying to determine work and deliverables are meet requirement & product acceptance criteria
  • 25. Control Scope Process of monitoring the status of the project and product scope and managing changes to the scope baseline The cause and degree of variance relative to the scope baseline Decide corrective/preventive action required
  • 26. Control Scope Relation with Perform Integrated Change Control Process Need for scope change during Control Scope Potential impact to scope found in Control Cost, Control Schedule, etc. Perform Integrated Change Control * Accept or reject the change? * Return to Control Scope to process the approved change Image redrawn from: PMP Exam Preparation 6th Edition, Rita Mulcahy
  • 27. Next topic: Project Time Management Thank You