Community Wind Project
              Development




                       Melissa Peterson,
Melissa Peterson
Windustry Program Analyst
                   Windustry Program Analyst
Feb 10th, 2009
Pre-Conference Workshop-CERTS
Community Based Energy Development
Outline
    About Windustry


    What is Community Wind? And why?


    Community Development Overview


    Steps for a Community Wind Project

        Project Planning and Management
    

        Wind Resource Assessment
    

        Siting and Permitting
    

        Leases/Easements
    

        Financing
    

        PPA
    

        Interconnection
    

        Construction
    

    Community Wind Resources

Windustry
    Non-profit organization based in

    Minneapolis, MN - work locally, regionally
    and nationally
    www.windustry.org

    Focus on community wind, landowner

    options, and rural economic development
    Provide landowner education, outreach and

    technical assistance
    Tailor our efforts for agricultural

    organizations, rural landowners &
    communities and local elected officials


    Mission Statement: “Windustry promotes progressive renewable energy
                       solutions and empowers communities to develop wind
                       energy as an environmentally sustainable, community-
                       owned asset. Through member supported outreach,
                       education and advocacy we work to remove the barriers to
                       broad community ownership of wind energy.”
What is Community Wind?
         Locally-owned, commercial-scale wind
         projects that optimize local benefits.
         Locally-owned means that one or more
         members of the local community has a
         significant direct financial stake in the
         project other than through land lease
         payments, tax revenue, or other
         payments in lieu of taxes. The term
         quot;community windquot; refers to the method
         and intention of development rather
         than the size of the project.
Benefits of Community Wind
    Economic Benefits                    Social Benefits
                                    

       Revitalizes Rural                     Promotes Energy
                                         

       Economies & Stimulates                Independence and
       the local economy                     National Security
       Stabilizes Energy Prices              Creates a New Crop
                                         

       Creates Jobs                          Promotes Local Ownership
                                         

                                             Galvanizes Support and
                                          

                                             Neutralizes Opposition
    Environmental Benefits


       Produces Clean Electricity.
     

       Keeps Water Sources
     

       Clean                             “Community wind helps get people connected to
       Protects Natural                  their energy use. Local energy production helps to
     
                                         build a better society, a better culture, and a better
       Resources
                                         planet.”
       Preserves Land
     
                                                     --David Benson, Nobles County
                                                     Commissioner & Farmer
Spectrum of Community Wind
                     Community Ownership

                          •   Groups of Local
                              landowners/investors
                          •   Private Schools
                          •   Public/Private
                              Partnerships




Public Ownership                                     Private Ownership
•   Municipal Utilities                              •   Individual Farmers
•   Public Schools                                   •   Local Businesses
•   Municipalities
Community Wind
    Project
  Development

                        Phase I
                    Project Planning


                         Phase II
                 Project Development &
                      Organization


                       Phase III
                      Construction


                      Phase IV
                     Operations &
                     Maintenance


                       Phase V
                   Decommissioning
Phase I-Project Planning
Identify your project goals and areas where you will
need to hire expertise
      Determine and prioritize your primary project goals, so that as key decisions
  

      arise you are able to make a sound decision and preserve your project
      objective
            What are your expertise and assets? Tax appetite? Big Energy User?
        

            Engineering or Technical expertise? Windy Land?
            Why do you want to participate in wind? Money? Energy Security?
        

            Environmental?
      Put together a reliable team and develop a governance structure
  

            CEO, Board Members, Project Manager & Key Consultants
        

      Choose an appropriate business structure for your team (LLC, LLP, Partnership,
  

      ‘S’ Corporation
Phase I-Project Planning
Identify an Appropriate Site Selection
 Strong Wind Resource

        Class 4 or higher
    


    Access to Transmission


        3-phase distribution or transmission line
    


    Appropriate Zoning


    Minimal Environmental Concerns


    Public Acceptance


    Land (leases/easements)

Phase I-Project Planning
   Raise seed capital to hire experts and perform feasibility
studies
   Experts for studies:

         Wind Resource
     

         Environmental & Cultural Resource Impact
     

         Interconnection Design
     

         Visual Assessment and Sound Assessments
     

         Others
     


     Feasibility Study
 
Feasibility Studies
    Description of the project       Sales Plan & Revenue
                                

                                     Schedule
    General Setting and Need

    for the Project                  Development Schedule
                                 
    Market Potential (current        and Production Plan

    and future)
                                     Projected Operating Costs
                                 
    Material & Equipment             and Net Revenue

    Procurement Plan
                                     Economic Feasibility
                                 
    Technical characteristics

                                     Financial Plan
    & Specifications             

                                     Management
    Development Schedule         

    and Production Plan              Requirements for Project
    Capital Requirements and

    Investment Schedule
Phase I-Project Planning
     Develop your project plan and timeline
       Project plan should identify team members, defined tasks,
 
       assigned tasks, completed tasks and adequate timeline
        Development Phase 1-
Preliminary Steps To Pursue in Parallel



                          Project Goals & Business Development



                                     Project Feasibility



                                          Site Selection



                                          Risk Factors



                                 Project Plan and Timeline
Phase I- Project Planning
Conduct a Wind Resource Assessment
 Initial Assessment
        Wind Maps
    

        Existing Data
    

    Detailed Site Characterization

        Computer Modeling
    

        Raw Data from Anemometer/Met tower
    

    Long-term Validation of data (historical reference)


    Detailed Cash Flow projections and Acquiring

    Financing
        Project ‘Bankability’
    

        Typically one plus years of data collection
    
1)Anemometer and Wind Direction Vane 2) Datalogger 3) MetTower
Wind Development Process
        Phase II- Project Development
                                    Turbine Selection and
    Land acquisition -          

                                    Purchasing
    Options/Easements
                                    Power Purchase
    Permitting /Siting          

                                    Agreement
    Studies

                                    Interconnection
      Transmission             

                                    Financing
        Interconnection         

                                      Final Feasibility
      Environmental/Wildlife
                                        Analysis
        Studies
                                      Risk Analysis
      Economic Feasibility

                                    Preconstruction
      Business Plan            
                                    engineering
        Feasibility
                                    Construction bidding
      Sound                    

      Telecommunications

      Shadow Flicker
Phase II- Land Acquisitions
    Main way for landowners to participate in wind energy

    development –including for community wind projects
        No cash outlay
    

        Low financial risk
    

    Landowners can provide their land to a community

    wind project
        Providing land in exchange for an equity share
    

        Leasing their land for monetary compensation
    

    Compensation varies widely based on turbine size,

    wind resource, price of energy and many other factors.
    Long term commitments – usually last 20 to 40 years.


    Options for easements and leases are typical

    components of most wind energy projects, large and
    small.
Phase II- Permitting
    Permitting Wind Energy in Minnesota


          >5 MW permitted by PUC
      

          <5 MW permitted by local ordinances
      

          Project between 5 and 25 megawatts can, in lieu of PUC permitting, be permitted
      

          according to local ordinances if the applicable counties assume permitting
          responsibility and provide notice to the PUC.
    Federal permitting Agencies


          Federal Aviation Administration
      

          US Fish and Wildlife Service
      

                Bald and Golden Eagle Protection Act and/or Migratory Bird Treaty Act
             •

                Endangered Species Ace
             •

          US Forest Service or Bureau of Land Management
      

          Army Corp of Engineers
      

          Federal Communications Commission
      

          Others
      

    When federal agencies or federally managed lands and resources (monetary or otherwise)


    are involved, the requirements of the National Environmental Policy Act (NEPA) will apply.
Phase II- Siting
                                                     Factors to consider:
    Site Layout and Design                       

                                                         Land Use
         Setbacks                                     
     
                                                         Aesthetics
         Turbine Layouts                              
     
                                                         Property Values
              Single vs. Multiple Turbines            
           •

                                                         Sound
         Turbine Color and Signage                    
     
                                                         Public Safety
         Appropriate safety measures (fencing,        
     
                                                         Environmental and Cultural
         drainage, erosion controls)                  

                                                         Impacts
         Project Plans
     
                                                         Construction Impacts
              Construction                            
           •

              Wildlife Surveys
           •

              Roadway Maintenance
           •

              Site restoration
           •
Phase II- Turbine
       Selections/Procurement
    Based on wind resource, project goals, availability, operations &

    maintenance, and reliability
    Turbines


        Size (few kw to 3 MW)
     

        Design (Horizontal vs. Vertical Axis)
     

        Used/Re-manufactures Machines
     

    Cost (range from few thousand to few million)


        Typically manufactures require 10-25% down
     

        Lag time (few years, but beginning to change)
     
Phase II- Power Purchase
        Agreement
    Contract to buy the electricity generated by a wind project


          Secure long term stream of revenue through the sale of electricity
      

    Needed to secure any equity or debt financing


    Typically 20 years in length from project commercial operation date


          Provision that allow one or both parties to terminate if certain stipulations are not met
      

    Project Commissioning


          Number of steps that must be met in order for a project to become commercially operational.
      

          Assures that the seller will be able to provide the buyer power
                All testing and studies completed, Meets interconnection requirements, Communications
            •

                between systems, Size determination, Security, permits received
    Price range ( 4.0¢/kWh to 6.4¢/kWh). Based on wind resource, geographic region, financing,

    transmission resources, turbine performance.
    Curtailments provisions


          “Take or Pay”
      

    Transmission Upgrades


    Renewable Energy Credits (RECs)


    Insurance

Phase II- Interconnection
    The first step is to have conversations with those who have an understanding of the system in the

    area where you propose to connect your project.
    If applicable, the next step is to go through the Midwest Independent System Operator (MISO) In

    most cases you will likely need to complete a MISO study, which includes the following:
           Interconnection Application
      

          Feasibility Study
      

          System Impact Study
      

           Facility Study
      

           Interconnection Agreement
      

    Executing the agreements & constructing additional infrastructure to get power on the lines


    For one or two turbine projects, it is advisable to connect the project at distribution level voltages,

    reducing need to build substation
    Early and open communication with MISO is suggested


    MISO Queue Process


          Different for project > 20 MW and < 20 MW
      

          Feasibility study, System Impact Study, Facility Study
      

          Execute an Interconnection Agreement
      
Phase II- Finance
    Financial viability of your Project


    Equity and Debt


          Typically 10-15 year loans for conventional projects, up to 20 for bond financing
      

          Equity is up-front money into the project
      

    Getting a Loan


          Detailed Cost and Production Estimates
      

                 Proforma financial statements, use of incentives, information on owners, list of all permits/contracts, risk
             •

                 mitigation plans, construction plans, insurance
          Credit Guidelines
      

                 Majority lenders want equity contribution of 30 % of project costs
             •

          Evaluation
      

                 Accuracy and thoroughness of business plan
             •

                 Strength of cash flow and financial statements
             •

                 Adequate secured capital
             •

                 Strength of governing board
             •

                 Legal review of contracts, permits and easements
             •
Phase III-Construction
Phase III
  Site Preparation and Project Management


  Construction and Commissioning

Phase IV & V
Phase IV
    Ongoing Operations & Maintenance –


    20 to 30 years
Phase V
    Decommissioning and Removal of


    Wind Farm
Landowner Associations

    Started in Wyoming

        Also interest in NM, CO, MT, SD, IN
    


    Result of landowner concerns about

        Speculators profiting rather than the
    
        landowners
        A neighbor getting a better deal than you
    
        Compensation - getting good value for the
    
        resource and developable land
    Goal: Discover value of wind/land resource

    through developer competition & negotiate
    a solid deal
Trimont Area Wind Farm
    100 MW Wind Farm (67 1.5 MW GE Turbines)


    Organized by group of local farmers and landowners

    (Pre-development)
    Answered a RFP from Great River Energy to develop

    the project
    Sold it to PPM Energy


    Some opportunity for revenue in addition to lease

    payments
Landowner Associations:
        Activities and Work Products
    Assoc. markets the collective wind/land resource through

    an RFP
        Maps and photos of the area
    

        Wind data and environmental assessments
    

        Local regulations for siting
    

        Landowner expectations outlined
    

    Score responses to the RFP


    Select a developer to negotiate with

        All members vote
    

        Voting rights detailed in operating agreement
    

    Association and developer negotiate on common lease

    terms for all members
Landowner Associations:
        Benefits to Developers
    What do Assoc.’s offer developers?

        Create blocks of land owned by landowners who are
    
        educated on wind energy and interested in wind
        development
        Minimizes costs to developer
    

             Only one door to knock on, and it is full of ready and willing
         •

             landowners
        Political strength of a significant number of landowners
    
        who support wind development in the area
        Reduces local opposition to the wind project
    
Major Points to Keep in Mind
    Expansion of community wind due to improving economics,

    innovative business models and effective public policies
    Economic, social and environmental advantages accrue to local

    community
        Community wind has 5 times the economic impact on local value added,
    
        and 3.4 times the impact on local job creation, relative to a corporate-
        owned development.
        http://cda.mrs.umn.edu/~kildegac/CV/Papers/IREE.pdf
    Involve your neighbors and the public

        Be prepared to explain how the project will help keep their power costs
    
        down
        Answer their basic questions
    

        Take into account their concerns and work with them to build a level of
    
        comfort and support
Major Points to
        Keep in Mind
    Projects take hard work,


    innovation, champions
    and public policy support
        Planning and development typically takes several
    
        years
        Dedicated team of professionals with consultants
    
        in business, finance, easements, PPAs,
        engineering, construction & project management
    Provide major new economic

    opportunities connecting main street
    America with a new industry
(800) 946-3640
                              toll free
                           Melissa’s phone (612) 870-3465
                           e-mail melissa@windustry.org


                          www.windustry.org


“Community wind helps get people connected to their energy
use. Local energy production helps to build a better society, a
better culture, and a better planet.”
--David Benson, Nobles County Commissioner & Farmer

Weitere ähnliche Inhalte

Was ist angesagt?

Leed 2009 for neighborhood development rating system
Leed 2009 for neighborhood development rating systemLeed 2009 for neighborhood development rating system
Leed 2009 for neighborhood development rating system
whit1
 
How to find a professional local partner in Ukraine
How to find a professional local partner in UkraineHow to find a professional local partner in Ukraine
How to find a professional local partner in Ukraine
Dmitry Lukomskiy
 
Presentation to the Coast Community Builders Association
 Presentation to the Coast Community Builders Association Presentation to the Coast Community Builders Association
Presentation to the Coast Community Builders Association
popereel
 
Keer2012: Design For The Hypernanotech Age
Keer2012: Design For The Hypernanotech AgeKeer2012: Design For The Hypernanotech Age
Keer2012: Design For The Hypernanotech Age
IIT Institute of Design
 

Was ist angesagt? (18)

Leed 2009 for neighborhood development rating system
Leed 2009 for neighborhood development rating systemLeed 2009 for neighborhood development rating system
Leed 2009 for neighborhood development rating system
 
How to find a professional local partner in Ukraine
How to find a professional local partner in UkraineHow to find a professional local partner in Ukraine
How to find a professional local partner in Ukraine
 
Global Geothermal Summit, Oct. 12, 2011
Global Geothermal Summit, Oct. 12, 2011Global Geothermal Summit, Oct. 12, 2011
Global Geothermal Summit, Oct. 12, 2011
 
Team 2
Team 2Team 2
Team 2
 
Group 8
Group 8Group 8
Group 8
 
DDC Regional BRAC Overview
DDC Regional BRAC OverviewDDC Regional BRAC Overview
DDC Regional BRAC Overview
 
Successful Apartment Living (Part 2)
Successful Apartment Living (Part 2)Successful Apartment Living (Part 2)
Successful Apartment Living (Part 2)
 
Wes water mgmt presentation final v4.0 dec 2011
Wes water mgmt presentation final   v4.0 dec 2011Wes water mgmt presentation final   v4.0 dec 2011
Wes water mgmt presentation final v4.0 dec 2011
 
Presentation to the Coast Community Builders Association
 Presentation to the Coast Community Builders Association Presentation to the Coast Community Builders Association
Presentation to the Coast Community Builders Association
 
Business leaders' briefing 12 september 2012 newcastle gateshead initiative f...
Business leaders' briefing 12 september 2012 newcastle gateshead initiative f...Business leaders' briefing 12 september 2012 newcastle gateshead initiative f...
Business leaders' briefing 12 september 2012 newcastle gateshead initiative f...
 
Marisa meizlish papua project
Marisa meizlish   papua projectMarisa meizlish   papua project
Marisa meizlish papua project
 
Keer2012: Design For The Hypernanotech Age
Keer2012: Design For The Hypernanotech AgeKeer2012: Design For The Hypernanotech Age
Keer2012: Design For The Hypernanotech Age
 
Willbros - D.A. Davidson Conference Presentation
Willbros - D.A. Davidson Conference PresentationWillbros - D.A. Davidson Conference Presentation
Willbros - D.A. Davidson Conference Presentation
 
Sba 2012 year-in-review - 1-15-13
Sba   2012 year-in-review - 1-15-13Sba   2012 year-in-review - 1-15-13
Sba 2012 year-in-review - 1-15-13
 
Hoffman, LLC Natri 2008 Presentation
Hoffman, LLC   Natri 2008 PresentationHoffman, LLC   Natri 2008 Presentation
Hoffman, LLC Natri 2008 Presentation
 
Willbros Group at D.A. Davidson's 11th Annual Engineering & Construction Con...
Willbros Group at  D.A. Davidson's 11th Annual Engineering & Construction Con...Willbros Group at  D.A. Davidson's 11th Annual Engineering & Construction Con...
Willbros Group at D.A. Davidson's 11th Annual Engineering & Construction Con...
 
Why you should consider stakeholder involvement in your planning.
Why you should consider stakeholder involvement in your planning.Why you should consider stakeholder involvement in your planning.
Why you should consider stakeholder involvement in your planning.
 
Innovative schemes for financing adaptation and enhancing technology transfer
Innovative schemes for financing adaptation and enhancing technology transferInnovative schemes for financing adaptation and enhancing technology transfer
Innovative schemes for financing adaptation and enhancing technology transfer
 

Andere mochten auch

Knowledge Management During Pretrial Patent Litigation : Secrets of the Super...
Knowledge Management During Pretrial Patent Litigation : Secrets of the Super...Knowledge Management During Pretrial Patent Litigation : Secrets of the Super...
Knowledge Management During Pretrial Patent Litigation : Secrets of the Super...
Professor Jon Cavicchi, UNH School of Law
 
Aitkin Eco-Affordable & FSC-Certified Home
Aitkin Eco-Affordable & FSC-Certified HomeAitkin Eco-Affordable & FSC-Certified Home
Aitkin Eco-Affordable & FSC-Certified Home
University of Minnesota
 
Small Wind 101: An Overview of Small-Scale Wind Electric Systems
Small Wind 101: An Overview of Small-Scale Wind Electric SystemsSmall Wind 101: An Overview of Small-Scale Wind Electric Systems
Small Wind 101: An Overview of Small-Scale Wind Electric Systems
University of Minnesota
 

Andere mochten auch (20)

Music lawresearch
Music lawresearchMusic lawresearch
Music lawresearch
 
Elk River - Energy City: One City's Attempt to Make a Difference
Elk River - Energy City: One City's Attempt to Make a DifferenceElk River - Energy City: One City's Attempt to Make a Difference
Elk River - Energy City: One City's Attempt to Make a Difference
 
Demystifying The SSRN Process
Demystifying The SSRN ProcessDemystifying The SSRN Process
Demystifying The SSRN Process
 
2025 Minnesota Energy Action Plan
2025 Minnesota Energy Action Plan2025 Minnesota Energy Action Plan
2025 Minnesota Energy Action Plan
 
Librarians as Archivists and Defenders of IP Rights
Librarians as Archivists and Defenders of IP RightsLibrarians as Archivists and Defenders of IP Rights
Librarians as Archivists and Defenders of IP Rights
 
Woodbury Community Solar Garden Workshop & Developer Fair
Woodbury Community Solar Garden Workshop & Developer FairWoodbury Community Solar Garden Workshop & Developer Fair
Woodbury Community Solar Garden Workshop & Developer Fair
 
Entertainment Industry News and Data
Entertainment Industry News and DataEntertainment Industry News and Data
Entertainment Industry News and Data
 
Benefits and Challenges of OER
Benefits and Challenges of OER Benefits and Challenges of OER
Benefits and Challenges of OER
 
International Patent Law Research :Tools and Strategies
International Patent Law Research :Tools and StrategiesInternational Patent Law Research :Tools and Strategies
International Patent Law Research :Tools and Strategies
 
Pierce Law IP Library Celebrates Inventorship from Patent Models to Video Te...
Pierce Law  IP Library Celebrates Inventorship from Patent Models to Video Te...Pierce Law  IP Library Celebrates Inventorship from Patent Models to Video Te...
Pierce Law IP Library Celebrates Inventorship from Patent Models to Video Te...
 
Querying Patent Data for Empirical Scholarship : Tools and Strategies
Querying Patent Data for Empirical Scholarship : Tools and StrategiesQuerying Patent Data for Empirical Scholarship : Tools and Strategies
Querying Patent Data for Empirical Scholarship : Tools and Strategies
 
Deptartment of State at UNH Law : LIBRARIANS AND ARCHIVISTS AS DEFENDERS OF I...
Deptartment of State at UNH Law : LIBRARIANS AND ARCHIVISTS AS DEFENDERS OF I...Deptartment of State at UNH Law : LIBRARIANS AND ARCHIVISTS AS DEFENDERS OF I...
Deptartment of State at UNH Law : LIBRARIANS AND ARCHIVISTS AS DEFENDERS OF I...
 
Minnesota's Guaranteed Energy Savings Program
Minnesota's Guaranteed Energy Savings ProgramMinnesota's Guaranteed Energy Savings Program
Minnesota's Guaranteed Energy Savings Program
 
Finding IP Jobs Using the Web
Finding IP Jobs Using the WebFinding IP Jobs Using the Web
Finding IP Jobs Using the Web
 
Knowledge Management During Pretrial Patent Litigation : Secrets of the Super...
Knowledge Management During Pretrial Patent Litigation : Secrets of the Super...Knowledge Management During Pretrial Patent Litigation : Secrets of the Super...
Knowledge Management During Pretrial Patent Litigation : Secrets of the Super...
 
Aitkin Eco-Affordable & FSC-Certified Home
Aitkin Eco-Affordable & FSC-Certified HomeAitkin Eco-Affordable & FSC-Certified Home
Aitkin Eco-Affordable & FSC-Certified Home
 
Capacitizing Yourself as an Art Law Professional
Capacitizing Yourself as an Art Law ProfessionalCapacitizing Yourself as an Art Law Professional
Capacitizing Yourself as an Art Law Professional
 
Harmoney Food Cooperative Solar Awning Project in Bemidji, MN
Harmoney Food Cooperative Solar Awning Project in Bemidji, MNHarmoney Food Cooperative Solar Awning Project in Bemidji, MN
Harmoney Food Cooperative Solar Awning Project in Bemidji, MN
 
Small Wind 101: An Overview of Small-Scale Wind Electric Systems
Small Wind 101: An Overview of Small-Scale Wind Electric SystemsSmall Wind 101: An Overview of Small-Scale Wind Electric Systems
Small Wind 101: An Overview of Small-Scale Wind Electric Systems
 
Licensing Resources
Licensing ResourcesLicensing Resources
Licensing Resources
 

Ähnlich wie Community Wind Development

GoM decommissioning conference
GoM decommissioning conferenceGoM decommissioning conference
GoM decommissioning conference
Dean Murphy
 
How to Save a Planet - On a Budget: Hour 2: Public Private Partnerships for R...
How to Save a Planet - On a Budget: Hour 2: Public Private Partnerships for R...How to Save a Planet - On a Budget: Hour 2: Public Private Partnerships for R...
How to Save a Planet - On a Budget: Hour 2: Public Private Partnerships for R...
Social Media Today
 
Global Energy Group Capability Profile
Global Energy Group Capability ProfileGlobal Energy Group Capability Profile
Global Energy Group Capability Profile
andrewmatheson
 
Dan Sugarman Sustainable City Network Webinar
Dan Sugarman Sustainable City Network WebinarDan Sugarman Sustainable City Network Webinar
Dan Sugarman Sustainable City Network Webinar
unitedwaterslides
 
Navitas Slides
Navitas SlidesNavitas Slides
Navitas Slides
saketvora
 
2009 curran
2009 curran2009 curran
2009 curran
Ngy Ea
 
Whm Group Quals
Whm Group QualsWhm Group Quals
Whm Group Quals
lexlion
 
Environmental Impact Report 101 Workshop (2/5/13)
Environmental Impact Report 101 Workshop (2/5/13)Environmental Impact Report 101 Workshop (2/5/13)
Environmental Impact Report 101 Workshop (2/5/13)
gbeltalliance
 

Ähnlich wie Community Wind Development (20)

NYSERDA Multifamily Performance Program
NYSERDA Multifamily Performance ProgramNYSERDA Multifamily Performance Program
NYSERDA Multifamily Performance Program
 
An introduction to project finance
An introduction to project financeAn introduction to project finance
An introduction to project finance
 
Geronimo Wind Development Model
Geronimo Wind Development ModelGeronimo Wind Development Model
Geronimo Wind Development Model
 
Geronimo Wind Development Model
Geronimo Wind Development ModelGeronimo Wind Development Model
Geronimo Wind Development Model
 
Jeffs justin
Jeffs justinJeffs justin
Jeffs justin
 
GoM decommissioning conference
GoM decommissioning conferenceGoM decommissioning conference
GoM decommissioning conference
 
How to Save a Planet - On a Budget: Hour 2: Public Private Partnerships for R...
How to Save a Planet - On a Budget: Hour 2: Public Private Partnerships for R...How to Save a Planet - On a Budget: Hour 2: Public Private Partnerships for R...
How to Save a Planet - On a Budget: Hour 2: Public Private Partnerships for R...
 
Global Energy Group Capability Profile
Global Energy Group Capability ProfileGlobal Energy Group Capability Profile
Global Energy Group Capability Profile
 
Planning a Small Wind Turbine Project
Planning a Small Wind Turbine ProjectPlanning a Small Wind Turbine Project
Planning a Small Wind Turbine Project
 
Dan Sugarman Sustainable City Network Webinar
Dan Sugarman Sustainable City Network WebinarDan Sugarman Sustainable City Network Webinar
Dan Sugarman Sustainable City Network Webinar
 
Navigant - Kinross - De-Risking Renewable Energy Projects
Navigant - Kinross - De-Risking Renewable Energy ProjectsNavigant - Kinross - De-Risking Renewable Energy Projects
Navigant - Kinross - De-Risking Renewable Energy Projects
 
Navitas Slides
Navitas SlidesNavitas Slides
Navitas Slides
 
Day1- session 2: RCREEE Planned Activities in Support of the Development and ...
Day1- session 2: RCREEE Planned Activities in Support of the Development and ...Day1- session 2: RCREEE Planned Activities in Support of the Development and ...
Day1- session 2: RCREEE Planned Activities in Support of the Development and ...
 
2009 curran
2009 curran2009 curran
2009 curran
 
Whm Group Quals
Whm Group QualsWhm Group Quals
Whm Group Quals
 
Environmental Impact Report 101 Workshop (2/5/13)
Environmental Impact Report 101 Workshop (2/5/13)Environmental Impact Report 101 Workshop (2/5/13)
Environmental Impact Report 101 Workshop (2/5/13)
 
Deltek Overview For NDIA V3.01 Ckb
Deltek Overview For NDIA V3.01 CkbDeltek Overview For NDIA V3.01 Ckb
Deltek Overview For NDIA V3.01 Ckb
 
CleanTech Open Overview
CleanTech Open OverviewCleanTech Open Overview
CleanTech Open Overview
 
Real Estate Sustainability
Real Estate SustainabilityReal Estate Sustainability
Real Estate Sustainability
 
Decommissioning & Abandonment Conference Brochure
Decommissioning & Abandonment Conference BrochureDecommissioning & Abandonment Conference Brochure
Decommissioning & Abandonment Conference Brochure
 

Mehr von University of Minnesota

AdoptingSolarWindMN_ConsumerResearch_DanThiede_Aug2014
AdoptingSolarWindMN_ConsumerResearch_DanThiede_Aug2014AdoptingSolarWindMN_ConsumerResearch_DanThiede_Aug2014
AdoptingSolarWindMN_ConsumerResearch_DanThiede_Aug2014
University of Minnesota
 

Mehr von University of Minnesota (20)

Minnesota Brightfields Study Results
Minnesota Brightfields Study ResultsMinnesota Brightfields Study Results
Minnesota Brightfields Study Results
 
Pathways to Electric Vehicle Adoption Event
Pathways to Electric Vehicle Adoption EventPathways to Electric Vehicle Adoption Event
Pathways to Electric Vehicle Adoption Event
 
Solar Advancement for Schools and Institutions
Solar Advancement for Schools and InstitutionsSolar Advancement for Schools and Institutions
Solar Advancement for Schools and Institutions
 
Solar Plus Storage at Hartley Nature Center in Duluth, MN
Solar Plus Storage at Hartley Nature Center in Duluth, MNSolar Plus Storage at Hartley Nature Center in Duluth, MN
Solar Plus Storage at Hartley Nature Center in Duluth, MN
 
Metro CERT 2017 Annual Event
Metro CERT 2017 Annual EventMetro CERT 2017 Annual Event
Metro CERT 2017 Annual Event
 
Biomass for Poultry: A Minnesota Case Study
Biomass for Poultry: A Minnesota Case StudyBiomass for Poultry: A Minnesota Case Study
Biomass for Poultry: A Minnesota Case Study
 
Financing Opportunities: PACE, MDA, and USDA
Financing Opportunities: PACE, MDA, and USDAFinancing Opportunities: PACE, MDA, and USDA
Financing Opportunities: PACE, MDA, and USDA
 
Biomass Opportunities for Agricultural Operations: Feed, Fuel, and Bedding
Biomass Opportunities for Agricultural Operations: Feed, Fuel, and BeddingBiomass Opportunities for Agricultural Operations: Feed, Fuel, and Bedding
Biomass Opportunities for Agricultural Operations: Feed, Fuel, and Bedding
 
Minneapolis Benchmarking Report Presentation
Minneapolis Benchmarking Report PresentationMinneapolis Benchmarking Report Presentation
Minneapolis Benchmarking Report Presentation
 
AdoptingSolarWindMN_ConsumerResearch_DanThiede_Aug2014
AdoptingSolarWindMN_ConsumerResearch_DanThiede_Aug2014AdoptingSolarWindMN_ConsumerResearch_DanThiede_Aug2014
AdoptingSolarWindMN_ConsumerResearch_DanThiede_Aug2014
 
St. Cloud, MN: The Path to Energy Neutral
St. Cloud, MN: The Path to Energy NeutralSt. Cloud, MN: The Path to Energy Neutral
St. Cloud, MN: The Path to Energy Neutral
 
Shoreview: Community Solar Gardens 101
Shoreview: Community Solar Gardens 101Shoreview: Community Solar Gardens 101
Shoreview: Community Solar Gardens 101
 
NRRI Presentation on Biomass and Deployable Housing
NRRI Presentation on Biomass and Deployable HousingNRRI Presentation on Biomass and Deployable Housing
NRRI Presentation on Biomass and Deployable Housing
 
Is a community solar garden subscription right for your local government?
Is a community solar garden subscription right for your local government?Is a community solar garden subscription right for your local government?
Is a community solar garden subscription right for your local government?
 
USDA Rural Development Program Summary 2016
USDA Rural Development Program Summary 2016USDA Rural Development Program Summary 2016
USDA Rural Development Program Summary 2016
 
Energy Efficient Dairy Production Technologies
Energy Efficient Dairy Production TechnologiesEnergy Efficient Dairy Production Technologies
Energy Efficient Dairy Production Technologies
 
CERTs - All about Community Solar Gardens in Minnesota
CERTs - All about Community Solar Gardens in MinnesotaCERTs - All about Community Solar Gardens in Minnesota
CERTs - All about Community Solar Gardens in Minnesota
 
Bemidji Guaranteed Energy Savings Program
Bemidji Guaranteed Energy Savings ProgramBemidji Guaranteed Energy Savings Program
Bemidji Guaranteed Energy Savings Program
 
Peter lindstrom-si-presentation
Peter lindstrom-si-presentationPeter lindstrom-si-presentation
Peter lindstrom-si-presentation
 
Minneapolis Neighborhoods Community Solar Presentation
Minneapolis Neighborhoods Community Solar PresentationMinneapolis Neighborhoods Community Solar Presentation
Minneapolis Neighborhoods Community Solar Presentation
 

Kürzlich hochgeladen

IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI Solutions
Enterprise Knowledge
 

Kürzlich hochgeladen (20)

GenAI Risks & Security Meetup 01052024.pdf
GenAI Risks & Security Meetup 01052024.pdfGenAI Risks & Security Meetup 01052024.pdf
GenAI Risks & Security Meetup 01052024.pdf
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI Solutions
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected Worker
 
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfThe Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
 
Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024
 
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
 
Exploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone ProcessorsExploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone Processors
 
What Are The Drone Anti-jamming Systems Technology?
What Are The Drone Anti-jamming Systems Technology?What Are The Drone Anti-jamming Systems Technology?
What Are The Drone Anti-jamming Systems Technology?
 
presentation ICT roal in 21st century education
presentation ICT roal in 21st century educationpresentation ICT roal in 21st century education
presentation ICT roal in 21st century education
 
Data Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonData Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt Robison
 
Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organization
 
[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf
 
Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...
 
How to convert PDF to text with Nanonets
How to convert PDF to text with NanonetsHow to convert PDF to text with Nanonets
How to convert PDF to text with Nanonets
 
2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...
 
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
 
Evaluating the top large language models.pdf
Evaluating the top large language models.pdfEvaluating the top large language models.pdf
Evaluating the top large language models.pdf
 
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
 
Handwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsHandwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed texts
 

Community Wind Development

  • 1. Community Wind Project Development Melissa Peterson, Melissa Peterson Windustry Program Analyst Windustry Program Analyst Feb 10th, 2009 Pre-Conference Workshop-CERTS Community Based Energy Development
  • 2. Outline About Windustry  What is Community Wind? And why?  Community Development Overview  Steps for a Community Wind Project  Project Planning and Management  Wind Resource Assessment  Siting and Permitting  Leases/Easements  Financing  PPA  Interconnection  Construction  Community Wind Resources 
  • 3. Windustry Non-profit organization based in  Minneapolis, MN - work locally, regionally and nationally www.windustry.org  Focus on community wind, landowner  options, and rural economic development Provide landowner education, outreach and  technical assistance Tailor our efforts for agricultural  organizations, rural landowners & communities and local elected officials Mission Statement: “Windustry promotes progressive renewable energy solutions and empowers communities to develop wind energy as an environmentally sustainable, community- owned asset. Through member supported outreach, education and advocacy we work to remove the barriers to broad community ownership of wind energy.”
  • 4. What is Community Wind? Locally-owned, commercial-scale wind projects that optimize local benefits. Locally-owned means that one or more members of the local community has a significant direct financial stake in the project other than through land lease payments, tax revenue, or other payments in lieu of taxes. The term quot;community windquot; refers to the method and intention of development rather than the size of the project.
  • 5. Benefits of Community Wind Economic Benefits Social Benefits   Revitalizes Rural Promotes Energy   Economies & Stimulates Independence and the local economy National Security Stabilizes Energy Prices Creates a New Crop   Creates Jobs Promotes Local Ownership   Galvanizes Support and  Neutralizes Opposition Environmental Benefits  Produces Clean Electricity.  Keeps Water Sources  Clean “Community wind helps get people connected to Protects Natural their energy use. Local energy production helps to  build a better society, a better culture, and a better Resources planet.” Preserves Land  --David Benson, Nobles County Commissioner & Farmer
  • 6.
  • 7. Spectrum of Community Wind Community Ownership • Groups of Local landowners/investors • Private Schools • Public/Private Partnerships Public Ownership Private Ownership • Municipal Utilities • Individual Farmers • Public Schools • Local Businesses • Municipalities
  • 8. Community Wind Project Development Phase I Project Planning Phase II Project Development & Organization Phase III Construction Phase IV Operations & Maintenance Phase V Decommissioning
  • 9. Phase I-Project Planning Identify your project goals and areas where you will need to hire expertise Determine and prioritize your primary project goals, so that as key decisions  arise you are able to make a sound decision and preserve your project objective What are your expertise and assets? Tax appetite? Big Energy User?  Engineering or Technical expertise? Windy Land? Why do you want to participate in wind? Money? Energy Security?  Environmental? Put together a reliable team and develop a governance structure  CEO, Board Members, Project Manager & Key Consultants  Choose an appropriate business structure for your team (LLC, LLP, Partnership,  ‘S’ Corporation
  • 10. Phase I-Project Planning Identify an Appropriate Site Selection  Strong Wind Resource Class 4 or higher  Access to Transmission  3-phase distribution or transmission line  Appropriate Zoning  Minimal Environmental Concerns  Public Acceptance  Land (leases/easements) 
  • 11. Phase I-Project Planning Raise seed capital to hire experts and perform feasibility studies  Experts for studies: Wind Resource  Environmental & Cultural Resource Impact  Interconnection Design  Visual Assessment and Sound Assessments  Others  Feasibility Study 
  • 12. Feasibility Studies Description of the project Sales Plan & Revenue   Schedule General Setting and Need  for the Project Development Schedule  Market Potential (current and Production Plan  and future) Projected Operating Costs  Material & Equipment and Net Revenue  Procurement Plan Economic Feasibility  Technical characteristics  Financial Plan & Specifications  Management Development Schedule   and Production Plan Requirements for Project Capital Requirements and  Investment Schedule
  • 13. Phase I-Project Planning Develop your project plan and timeline Project plan should identify team members, defined tasks,  assigned tasks, completed tasks and adequate timeline Development Phase 1- Preliminary Steps To Pursue in Parallel Project Goals & Business Development Project Feasibility Site Selection Risk Factors Project Plan and Timeline
  • 14. Phase I- Project Planning Conduct a Wind Resource Assessment  Initial Assessment Wind Maps  Existing Data  Detailed Site Characterization  Computer Modeling  Raw Data from Anemometer/Met tower  Long-term Validation of data (historical reference)  Detailed Cash Flow projections and Acquiring  Financing Project ‘Bankability’  Typically one plus years of data collection 
  • 15. 1)Anemometer and Wind Direction Vane 2) Datalogger 3) MetTower
  • 16. Wind Development Process Phase II- Project Development Turbine Selection and Land acquisition -   Purchasing Options/Easements Power Purchase Permitting /Siting   Agreement Studies  Interconnection  Transmission  Financing Interconnection   Final Feasibility  Environmental/Wildlife Analysis Studies  Risk Analysis  Economic Feasibility Preconstruction  Business Plan  engineering Feasibility Construction bidding  Sound   Telecommunications  Shadow Flicker
  • 17. Phase II- Land Acquisitions Main way for landowners to participate in wind energy  development –including for community wind projects No cash outlay  Low financial risk  Landowners can provide their land to a community  wind project Providing land in exchange for an equity share  Leasing their land for monetary compensation  Compensation varies widely based on turbine size,  wind resource, price of energy and many other factors. Long term commitments – usually last 20 to 40 years.  Options for easements and leases are typical  components of most wind energy projects, large and small.
  • 18. Phase II- Permitting Permitting Wind Energy in Minnesota  >5 MW permitted by PUC  <5 MW permitted by local ordinances  Project between 5 and 25 megawatts can, in lieu of PUC permitting, be permitted  according to local ordinances if the applicable counties assume permitting responsibility and provide notice to the PUC. Federal permitting Agencies  Federal Aviation Administration  US Fish and Wildlife Service  Bald and Golden Eagle Protection Act and/or Migratory Bird Treaty Act • Endangered Species Ace • US Forest Service or Bureau of Land Management  Army Corp of Engineers  Federal Communications Commission  Others  When federal agencies or federally managed lands and resources (monetary or otherwise)  are involved, the requirements of the National Environmental Policy Act (NEPA) will apply.
  • 19. Phase II- Siting Factors to consider: Site Layout and Design   Land Use Setbacks   Aesthetics Turbine Layouts   Property Values Single vs. Multiple Turbines  • Sound Turbine Color and Signage   Public Safety Appropriate safety measures (fencing,   Environmental and Cultural drainage, erosion controls)  Impacts Project Plans  Construction Impacts Construction  • Wildlife Surveys • Roadway Maintenance • Site restoration •
  • 20. Phase II- Turbine Selections/Procurement Based on wind resource, project goals, availability, operations &  maintenance, and reliability Turbines  Size (few kw to 3 MW)  Design (Horizontal vs. Vertical Axis)  Used/Re-manufactures Machines  Cost (range from few thousand to few million)  Typically manufactures require 10-25% down  Lag time (few years, but beginning to change) 
  • 21. Phase II- Power Purchase Agreement Contract to buy the electricity generated by a wind project  Secure long term stream of revenue through the sale of electricity  Needed to secure any equity or debt financing  Typically 20 years in length from project commercial operation date  Provision that allow one or both parties to terminate if certain stipulations are not met  Project Commissioning  Number of steps that must be met in order for a project to become commercially operational.  Assures that the seller will be able to provide the buyer power All testing and studies completed, Meets interconnection requirements, Communications • between systems, Size determination, Security, permits received Price range ( 4.0¢/kWh to 6.4¢/kWh). Based on wind resource, geographic region, financing,  transmission resources, turbine performance. Curtailments provisions  “Take or Pay”  Transmission Upgrades  Renewable Energy Credits (RECs)  Insurance 
  • 22. Phase II- Interconnection The first step is to have conversations with those who have an understanding of the system in the  area where you propose to connect your project. If applicable, the next step is to go through the Midwest Independent System Operator (MISO) In  most cases you will likely need to complete a MISO study, which includes the following: Interconnection Application  Feasibility Study  System Impact Study  Facility Study  Interconnection Agreement  Executing the agreements & constructing additional infrastructure to get power on the lines  For one or two turbine projects, it is advisable to connect the project at distribution level voltages,  reducing need to build substation Early and open communication with MISO is suggested  MISO Queue Process  Different for project > 20 MW and < 20 MW  Feasibility study, System Impact Study, Facility Study  Execute an Interconnection Agreement 
  • 23. Phase II- Finance Financial viability of your Project  Equity and Debt  Typically 10-15 year loans for conventional projects, up to 20 for bond financing  Equity is up-front money into the project  Getting a Loan  Detailed Cost and Production Estimates  Proforma financial statements, use of incentives, information on owners, list of all permits/contracts, risk • mitigation plans, construction plans, insurance Credit Guidelines  Majority lenders want equity contribution of 30 % of project costs • Evaluation  Accuracy and thoroughness of business plan • Strength of cash flow and financial statements • Adequate secured capital • Strength of governing board • Legal review of contracts, permits and easements •
  • 24. Phase III-Construction Phase III Site Preparation and Project Management  Construction and Commissioning 
  • 25. Phase IV & V Phase IV Ongoing Operations & Maintenance –  20 to 30 years Phase V Decommissioning and Removal of  Wind Farm
  • 26. Landowner Associations Started in Wyoming  Also interest in NM, CO, MT, SD, IN  Result of landowner concerns about  Speculators profiting rather than the  landowners A neighbor getting a better deal than you  Compensation - getting good value for the  resource and developable land Goal: Discover value of wind/land resource  through developer competition & negotiate a solid deal
  • 27. Trimont Area Wind Farm 100 MW Wind Farm (67 1.5 MW GE Turbines)  Organized by group of local farmers and landowners  (Pre-development) Answered a RFP from Great River Energy to develop  the project Sold it to PPM Energy  Some opportunity for revenue in addition to lease  payments
  • 28. Landowner Associations: Activities and Work Products Assoc. markets the collective wind/land resource through  an RFP Maps and photos of the area  Wind data and environmental assessments  Local regulations for siting  Landowner expectations outlined  Score responses to the RFP  Select a developer to negotiate with  All members vote  Voting rights detailed in operating agreement  Association and developer negotiate on common lease  terms for all members
  • 29. Landowner Associations: Benefits to Developers What do Assoc.’s offer developers?  Create blocks of land owned by landowners who are  educated on wind energy and interested in wind development Minimizes costs to developer  Only one door to knock on, and it is full of ready and willing • landowners Political strength of a significant number of landowners  who support wind development in the area Reduces local opposition to the wind project 
  • 30. Major Points to Keep in Mind Expansion of community wind due to improving economics,  innovative business models and effective public policies Economic, social and environmental advantages accrue to local  community Community wind has 5 times the economic impact on local value added,  and 3.4 times the impact on local job creation, relative to a corporate- owned development. http://cda.mrs.umn.edu/~kildegac/CV/Papers/IREE.pdf Involve your neighbors and the public  Be prepared to explain how the project will help keep their power costs  down Answer their basic questions  Take into account their concerns and work with them to build a level of  comfort and support
  • 31. Major Points to Keep in Mind Projects take hard work,  innovation, champions and public policy support Planning and development typically takes several  years Dedicated team of professionals with consultants  in business, finance, easements, PPAs, engineering, construction & project management Provide major new economic  opportunities connecting main street America with a new industry
  • 32. (800) 946-3640 toll free Melissa’s phone (612) 870-3465 e-mail melissa@windustry.org www.windustry.org “Community wind helps get people connected to their energy use. Local energy production helps to build a better society, a better culture, and a better planet.” --David Benson, Nobles County Commissioner & Farmer