2. Houses to be relocated
The consultant has cooperated with
RID to relocate local houses that
affect the construction.
The client (RID) had already
completed the compensation for the
relocation to the affected people.
Most of houses had already been
relocated except SRT’s house (in
2/3
13. RELOCATION FOR WATER
SUPPLY LINE
The consultant found that the existing
water supply line was obstruction for
the construction.
The consultant has cooperated with
RID and Thetsaban Pranakorn Sri
Ayutthaya Water to relocate the water
supply system.
The relocation for water supply is in
13/
14. KRA MANG SITE
cutting pipe line relocated pipe
line existing pipe line
14/
Tunnel
(PVC) (PVC) (PVC)
15. Change to HDPE pipe
HAN TRA SITE
15/
cutting pipe line relocated pipe
line existing pipe line
HDPE pipe line iron pipe line
18. RELOCATION FOR ELECTRIC
OVERHEAD LINE
The consultant found that the existing
electric overhead line was the
obstruction for the construction.
The consultant has cooperated with
RID, contractor and PEA for the
relocation of electric overhead lines.
PEA plans to commence the relocation
work once the contractor constructs
18/
23. TEMPORARY RELOCATION FOR
SRT’S OVERHEAD SIGNAL LINE
At Kra Mang site, the consultant
found that the existing SRT overhead
line was the obstruction for the
construction.
The consultant has cooperated with
RID and SRT for the relocation of
SRT’s overhead signal line.
The relocation of SRT overhead signal
23/
24. KRA MANG SITE
TEMPORARY RELOCATION FOR SRT SIGNAL
LINE
24/
existing cable line
relocation line
existing cable line
cutting line
29. SUMMARY OF RELOCATION WORKS
(UPDATE 16th JULY 2013)
29/
1 KRAMANG SITE STATUS NOTE
1.1
Houses to be
relocated
1.1
.1House No.1 Finish
Owner has received compensation
and relocated
1.1
.2House No.2 Finish
Owner has received compensation
and relocated
1.1
.3House No.3 On Hold
Owner has received compensation,
but requested
addition compensation
1.1
.4House No.4
In
Progres
s
Not yet start relocation works,
internal process by SRT.
30. 30/
2 Han Tra SITE STATUS NOTE
2.1
Houses to be
relocated
2.1
.1 House No.5 Finish
Owner has relocated voluntarily
without compensation
2.1
.2 House No.6 Finish
Owner has received compensation
and relocated
2.1
.3 House No.7 Finish
Owner has received compensation
and relocated
2.1
.4 House No.8 Finish
Owner has received
compensation and relocated
2.1
.5 Small Arbor No.9
Not Yet
Start
Owner has received compensation
and plan to start relocation
In
SUMMARY OF RELOCATION WORKS
(UPDATE 16th JULY 2013)