SlideShare ist ein Scribd-Unternehmen logo
1 von 27
Downloaden Sie, um offline zu lesen
CE 5806 Project & Site Control




                        David Chua Kim Huat
                          Associate Professor
               E2-04-08, tel: 65162195 email: cvedavid

Assoc Prof David Chua Dept of Civil Engrg, NUS
Course Outline & Perspective
    Development and Organisation of Projects (week 1)
      –   Project phases; organisational concepts; contractual relationships
    Project Planning (week 1-3)
      –   Managerial philosophy and function of planning; network methods; resource
          levelling; linear scheduling;
    Project Control (week 4)
      –   Managerial philosophy and function of control; WBS; schedule and cost
                      philosoph     f nction control WBS sched le
          control; earned value
    Advanced Methods (week 5-7)
      –   Schedule compression; p
                         p         ; probabilistic methods; theory of constraints; lean
                                                          ;      y               ;
          construction; critical chain; interface management
    Productivity Improvement (week 8-9)
      –   Factors affecting productivity; concept of work flows, capacity and bottlenecks
    Site Control and Contract Management (week 10-12)
      –   Documentation and quality management; contract management – variation
          and extension of time; construction safety and health



Assoc Prof David Chua Dept of Civil Engrg, NUS
Control of Project Cost and Schedule

Key Issues:

1. Understand the key concepts in project control

2. Learn the earned value approach to project control & its
   importance

3. Know how to measure & track progress

4. Use h
4 U the WBS method to plan and organise project
               h d     l     d      i      j



Assoc Prof David Chua Dept of Civil Engrg, NUS
Managerial Function of Control
 Critical to effective management is the supplying of information
   – Type of information
   – Amount of information

 Timeliness of control system
   – Reporting period & delay in the reporting information; gives
                           dela                               gi es
     rise to time lag in control
   – Delay in reporting should be minimized to one or two weeks
   – Fast paced projects with many parties and contractual
     obligations must be more tightly monitored.
   – Amount of work progress may overwhelm scheduler.
                        p g        y
   – Too often costly (time, overheads). May become a nuisance.
   – Waiting too long to update may eliminate effectiveness of
     updating as a control tool – no time for corrective action
   – If delay, can supplement with rough and ready control systems
  Assoc Prof David Chua Dept of Civil Engrg, NUS
Managerial Function of Control
 Example of timeliness vs accuracy
   – Cost of materials can be reported at several stages and they
      affect the reliability of cost reports:
       When order is placed (commitment)
       Material delivered
       Material issued from stores
       Material actually used
       Invoice paid
                 p
   If wait till invoice – long delay and useless for control purposes
   Commitment stage – inaccurate because may not be used or
      delivered but timely
       These are then corrected at later stages


Assoc Prof David Chua Dept of Civil Engrg, NUS
Managerial Function of Control
 Level of detail
   – Cost information for control if collected using cost codes
     existing in the company s accounting system; can be a problem
                     company’s
   – Some activity based costing needed
                     Project No Area Operation Distribution Cost
                     08BE02     03   096600    01           $4 000
                                                            $4,000

   – Need to be balanced with the time to prepare; having
     approximately accurate information timely is more helpful
      pp          y                           y            p
     than accurate information 2 to 3 months after the event
   – Over controlled makes it cumbersome and expensive
       So h is
       S what i a good rule of thumb?
                        d l f h b?
    – 20 – 80% rule
       Critical items in greater detail, otherwise in summary level
       Critical items: high proportion or high escalation
  Assoc Prof David Chua Dept of Civil Engrg, NUS
Managerial Function of Control
 Data vs information
   – 100 page report on procurement or 10 lines printout that 5
     orders are likely to be late
   – Exception reporting, trouble spots and deviations

 Obj i vs subjective data and information
  Objective       bj i d         di f         i
   – Should be as objective as possible
   – If subjective estimates could lead to 90% syndrome:
       Project appears to progress well until it is 90% complete
          j                           ll    il i i          l
       Actual progress then has to catch up




  Assoc Prof David Chua Dept of Civil Engrg, NUS
Example of CSI (Construction Specifications Institute) Format
09600     Flooring

09610    Floor Treatment                 Slip - Resistant Floor Treatment
                                         Static - Resistant Floor Treatment
09620     Specialty Flooring             Asphalt Plank Flooring      Plastic Laminate Flooring
                                         Athletic Flooring
                                         Athl ti Fl    i

09630     Masonry Flooring              Brick Flooring              Marble Flooring
                                        Chemical - Resistant Brick Flooring
                                        Flagstone Flooring
                                           g             g          State Flooring
                                                                                 g
                                        Granite Flooring            Stone Flooring

09640     Wood Flooring                  Cushioned Wood Flooring Assemblies
                                         Mastic Set Wood Flooring Assemblies
                                         Resilient Wood Flooring Assemblies
                                         Wood Athletic Flooring       Wood Block Flooring
                                         Wood Composition Flooring    Wood Parquet Flooring
                                         Wood Strip Flooring

09650     Resilient Flooring
09660     Static Control Flooring
09670     Fluid-Applied Flooring
09680     Carpet
09690     Flooring Restoration



        Assoc Prof David Chua Dept of Civil Engrg, NUS
Approach to Control
 Variance Analysis Method                       What is the problem with this method?
    – Measures the difference
       between two factors, e.g.                  Historic backward looking
       between actual and planned
    – Examples:                                   Not effectively used to p
                                                                 y         portray
                                                                                 y
    Planned vs actual start                        performance
    Planned vs actual finish
    Duration,
    Duration milestones
    Budgeted vs actual cost
    Manhours, unit cost, % complete
    Measured value vs actual cost
    M       d l              l




Assoc Prof David Chua Dept of Civil Engrg, NUS
Approach to Control
 Key questions that must be                      – Is the rate of work accelerating or
  answered:                                          decelerating as it should?
     – What happened in the past?                 Rate of build up of work – cost and
     Are we on schedule?                             progress
     If variation, where, why, who?               S-charts
     What effect and what can be done?
     Is work within budget? Etc                   Thus, need to be forward
                                                    looking, predicting, surfacing
     – What is going to happen in the               trends and sensitive enough
       future?
       f                                            to pick up adverse
     Are we going to be on schedule,                performance as soon as it
       budget?                                      occurs so that something can
     Important to be aware of trends in                              y
                                                    be done to rectify it
       early stage to influence outcome
     What is final cost and completion
       date?


 Assoc Prof David Chua Dept of Civil Engrg, NUS
Approach to Control
 Data not effectively used to give integrated control
     Planned vs actual does not really tell PM whether more or less
        than budgeted have been expended.
     Why??

Example:
Activity budgeted cost     cum. Budget          actual         cum. cost   variance   cum. variance
           in period
              p            to date              cost to date   to date     p
                                                                           period     to date
A          $60,000         $135,000             $66,000        $150,000    -$6,000    -$15,000
B          $45,000         $90,000              $39,000        $99,000     $6,000     $9,000


 Does not show whether expenditure results in planned work
  completed
 Simply – variance in cost could be cost related or schedule related
      Assoc Prof David Chua Dept of Civil Engrg, NUS
Approach to Control
      $60,000 for A may represent the 500 units of excavation
      $66,000 is the actual cost of quantity not specified
      Say it is for 540 units and the estimated excavation cost is $120/unit
      Work completed is worth $64,800, thus +ve variance of $1,200
      $64,800 is the earned value

Example:
Activity budgeted cost     cum. Budget          actual         cum. cost   variance   cum. variance
           in period       to date              cost to date   to date     period     to date
A          $60,000         $135,000             $66,000        $150,000    -$6,000    -$15,000
B          $45,000         $90,000              $39,000        $99,000     $6,000     $9,000

       Three sets of data available that needs to be integrated to give
          effective control
       1. Planned
       2.
       2 Actual
       3. Value earned (“earned value”)
      Assoc Prof David Chua Dept of Civil Engrg, NUS
Earned Value Approach
Example:
Activity budgeted cost     cum. Budget          actual         cum. cost   variance   cum. variance
              p
           in period       to date              cost to date   to date     p
                                                                           period     to date
A          $60,000         $135,000             $66,000        $150,000    -$6,000    -$15,000
B          $45,000         $90,000              $39,000        $99,000     $6,000     $9,000
                                                         Quantities: 540 units
                                                         Cost: $120/unit
                                                         Earned value= $64,800
Variance in cost = Earned value – Actual cost
                 = $64,800 - $66,000
                 = -$1,200
Meaning the concrete put in cost $1,200 more than it should

                                       Variance in schedule = Earned value – budget cost
  How much is planned?                                      = $64,800 - $60,000
  How much is done?                                         = $4 800
                                                              $4,800
  How much ahead?                       Meaning $4,400 more work was completed than planned
      Assoc Prof David Chua Dept of Civil Engrg, NUS
Key Cost Measures


  ACWP: actual cost of work performed
      – amount reported as actually expended in completing work performed
  BCWP: budgeted cost of work performed
      – budgeted amount of cost for work completed
      – “earned value of work performed”
  BCWS: budgeted cost of work scheduled
      – budgeted amount of cost for the work scheduled to be p
           g                                                 performed


  Variance Measures                                     Alternatively
      – Cost variance = BCWP - ACWP
              va a ce     CW     CW                      C
                                                         CPI = BCWP/ACWP
                                                                  CW / CW
      – Performance variance = BCWP - BCWS               SPI = BCWP/BCWS
         0 is favourable                                 1 is favourable



Assoc Prof David Chua Dept of Civil Engrg, NUS
Earned Value Approach                                          Usual to use labour
                                                                hours for weighted value
                                                                             g
                                                                for performance
                                                                measurement
  Project A example


      Master Activities       Estimated           Scheduled        Scheduled Estimated
                              Man hours
                              Man-hours             Start            Finish      Cost
                                                 (end of day)     (end of day) ($1000)
     Site earth works             450                  0               20         40
     Structural works            1,000                10               40         90
     Mechanical i i
     M h i l piping              1,500
                                 1 500                20               70        350
     Control systems              750                 40               80        140
     Reactor Towers               400                 50               80        120
     Systems Check
      y                           300                 80               95         60
                                                                     Total       800




Assoc Prof David Chua Dept of Civil Engrg, NUS
Accumulative BCWS
   Assumed equally distributed
                                              1000's    0   10   20       30         40    50    60    70    80    90    95sum
site earth
    k
works             0                      20       40    0   20   20                                                              40
structural
works            10                      40       90        0    30       30         30                                          90
mechanical
piping           20                      70      350              0       70         70    70    70    70                     350
control
systems          40                      80      140                                 0    35    35    35     35               140
reactor towers   50                      80      120                                       0    40    40     40               120
systems check    80                      95       60                                                          0    40    20    60
                                              BCWS      0   20   50     100      100      105   145   145    75    40    20   800
                                              accum.    0   20   70     170      270      375   520   665   740   780   800

                                                                      BCWS

                                   900

                                   800

                                   700

                                   600
                  BCWS ($1000's)




                                   500

                                   400

                                   300

                                   200

                                   100

                                     0
                                         0             20        40                  60          80         100
                                                                      Project Days
At end of day 40
                   Master Activities             % complete   Actual Cost
                                                               ($1000)
              Site earth works                      100           45
              Structural works                       85          110
              Mechanical piping                     20            65
              Control systems                        5            10
              Reactor towers                          -            -
              Systems Check                           -            -

 Determine progress of project in terms of cost and schedule.

 ACWP = $230 k

 BCWP =                 100% x 40k             40 k
                         85% x 90k             76.5 k
                         20% x 350k            70 k
                          5% x 140k             7 k
                                total        $193.5 k




Assoc Prof David Chua Dept of Civil Engrg, NUS
Schedule and Cost Variances
                                                                          $270K

                                                      BCWS

                              900
                                                                           ACWP
                              800

                              700                                                 BCWS
                              600
                                         Ahead
             BCWS ($1000's)




                                                                             BCWP
                              500

                              400

                              300
             B




                              200
                                                                          Behind
                              100

                                0
                                    0   20       40                  60     80           100
                                             8 days   Project Days
                                             behind


                                                           $193.5K
                                                           $193 5K                $ 30
                                                                                  $230K

Assoc Prof David Chua Dept of Civil Engrg, NUS
Actual progress compared with ES and LS curves



                                                  BCWS

                              900

                              800
                                                                                          Projected
                              700
                                                                         ES        LS     completion
                                                                                              p
                              600
             BCWS ($1000's)




                              500

                              400
                                                                      Actual progress
                              300
             B




                              200

                              100

                                0
                                    0   20   40                  60           80        100
                                                  Project Days




Assoc Prof David Chua Dept of Civil Engrg, NUS
Measurement of Work Completed
    Units completed               Applicable to tasks that are repetitive and require
                                      uniform effort

                                   Number of precast beams to install for floor
                                      = 120
                                   Number of beams installed = 75
                                   % complete = 75/120*100% = 62.5%



    Start/Finish                  Applicable to activities of uncertain duration with no
                                       well-defined intermediate milestones.
                                   Start activities are given a percent complete
                                       say 20 30% f l
                                           20-30% for long activities
                                                                ti iti



    Supervisor Opinion            Informed judgement concerning completion status
                                             j g                  g     p
                                   Dewatering, constructing temporary facilities,
                                       landscaping are usually judged this way
Assoc Prof David Chua Dept of Civil Engrg, NUS
Incremental milestone approach:
 Applicable to activities which have multiple units of work
     with several sequential tasks
 e.g. form, reinforce & pour concrete footings


 Foundation:                               Example: 150 footings
 Excavation             5%                 Excavation – 20 footings:          20*5%      =1
 Formwork50%                               Formwork – 10 footings:            10*55% = 5.5 55
 Rebar/embeds           20%                Rebar/embeds – 8 footings:         8*75%      =6
 Pour & finish          10%                Pour & finish – 30 footings:       30*85% = 25.5
 Strip & finish         10%                Strip & finish – 20 footings:      20*95% = 19
 Backfill                5%
                                           Backfill – 10 footings:                       = 10
                                                                      Total:
                                                                      67 footings out of 150
                                                                      = 67/150*100% = 44.7%




Assoc Prof David Chua Dept of Civil Engrg, NUS
Measurement of Work Completed


    Cost ratio           Applicable to tasks that are continuous and where costs bear
                             a strong relationship to total effort required


                                                 actual cost or work hours to date
                                  % complete 
                                                      forecast to completion
                                                      f       t        l ti


    Weighted or          Progress correlated to weight of material or some other units.
     equivalent
         i l t
     units




Assoc Prof David Chua Dept of Civil Engrg, NUS
Project A example
     Master Activities        Weighted Value      Unit   Quantity at    Quantity    Actual
                               (man-hours)               completion    completed   man hours
1.0 Site earth works               450
1.1 Site grading                   200            m3       5,000         4,000        150
1.2 Compacted building             180            m3       10,000        7,500        150
fill
1.3 Fencing                         70             m        800           610          60


      Master Activities          Weighted Value                        Man-hrs     Actual man
                                  (
                                  (man-hours))                         earned        hours
1.0 Site earth works                  450
1.1 Site grading                      200       4000/5000 x 200          160          150
1.2 Compacted building fill           180       7500/10000 x 180         135          150
1.3 Fencingg                          70          610/800 x 70          53.4          60
                                                      Total             348.4         360

                          Percent complete = 348.4/450 = 77.4%
                          Productivity = 348.4/360 = 96.8%

 Assoc Prof David Chua Dept of Civil Engrg, NUS
Network-
     Network-based Control System

     Requires a well-defined work                      Work breakdown structure -
      plan,
      plan budget and schedule                           smallest unit is the work package
       – provides the benchmarks for                      – work defined in sufficient detail
           control                                          to be be measured, budgeted,
 Must be developed with inputs                             scheduled and controlled
  from people performing the work                         – several WPs in one activity or
                                                            single WP comprising several
 Must be communicated to all
                                                            activities
  participants
                                                      Difference between network
 To be effective, must be simple to
                                                       approach and cost accounting
  administer and easily understood                     approach
  by all participants
                                                      Efficiency of system
                                                          – decide on level of detail, quantity
                                                             of information, frequency of
                                                             collection
                                                               ll i

    Assoc Prof David Chua Dept of Civil Engrg, NUS
Work Breakdown Structure
                                          Building


Site work         Foundations             Structure       Curtain wall    Finishes   Electrical


    Survey         Excavation           Piles         Pile caps      Ground beams


                   Test piles          Area 1         Area 2


            Drive piles         Inspect         Clean       Rebar        Pour concrete



 WBS used in planning stage to identify tasks and subtasks
 Assign responsibilities, achieve management control
 No fixed rule for level of detail and breakdown structure

    Assoc Prof David Chua Dept of Civil Engrg, NUS
WBS Hierarchy
                                          Power S
                                                Station


Boiler house      Turbine house          Coal handling          Water cooling
                                             plant                 plant




      Cooling             Condenser         Turbine blocks    Retaining walls
     water pipes          foundations



                   Foundations         Columns       Machine platform


            Rebar           Prepare Formwork           Erect formwork


    Assoc Prof David Chua Dept of Civil Engrg, NUS
WBS with organisation structure


                                        Oranizational structure
                         ucture
              eakdown Stru
       Work Bre




Assoc Prof David Chua Dept of Civil Engrg, NUS

Weitere ähnliche Inhalte

Ähnlich wie (07) 5806 project control

CV_Clayton_David_2016 new
CV_Clayton_David_2016 newCV_Clayton_David_2016 new
CV_Clayton_David_2016 newDavid Clayton
 
PJM6000Project Management PracticesWeek 5Deb Cote,.docx
PJM6000Project Management PracticesWeek 5Deb Cote,.docxPJM6000Project Management PracticesWeek 5Deb Cote,.docx
PJM6000Project Management PracticesWeek 5Deb Cote,.docxARIV4
 
PJM6000Project Management PracticesWeek 5Deb Cote,.docx
PJM6000Project Management PracticesWeek 5Deb Cote,.docxPJM6000Project Management PracticesWeek 5Deb Cote,.docx
PJM6000Project Management PracticesWeek 5Deb Cote,.docxstilliegeorgiana
 
ادارة تكلفة المشروع
ادارة تكلفة المشروع ادارة تكلفة المشروع
ادارة تكلفة المشروع Mohamed Dahi
 
Melbourne streamlining earned value with hd published
Melbourne streamlining earned value with hd publishedMelbourne streamlining earned value with hd published
Melbourne streamlining earned value with hd publishedInSync Conference
 
Estimating software development
Estimating software developmentEstimating software development
Estimating software developmentJane Prusakova
 
Sonny james daigrepont_resume' (6)
Sonny james daigrepont_resume' (6)Sonny james daigrepont_resume' (6)
Sonny james daigrepont_resume' (6)Sonny Daigrepont
 
The project plan
The project planThe project plan
The project planVatsalaPG
 
014 changes-cost overrun measurement
014 changes-cost overrun measurement014 changes-cost overrun measurement
014 changes-cost overrun measurementDrFereydounDejahang
 
014 changes-cost overrun measurement
014 changes-cost overrun measurement014 changes-cost overrun measurement
014 changes-cost overrun measurementDr Fereidoun Dejahang
 
014 changes-cost overrun measurement
014 changes-cost overrun measurement014 changes-cost overrun measurement
014 changes-cost overrun measurementdrdej19
 
014 changes-cost overrun measurement
014 changes-cost overrun measurement014 changes-cost overrun measurement
014 changes-cost overrun measurementDr Fereidoun Dejahang
 
014 changes-cost overrun measurement
014 changes-cost overrun measurement014 changes-cost overrun measurement
014 changes-cost overrun measurementDrFereydounDejahang
 
014 changes-cost overrun measurement
014 changes-cost overrun measurement014 changes-cost overrun measurement
014 changes-cost overrun measurementDr Fereidoun Dejahang
 
Lss pharma presentation2-2006
Lss pharma presentation2-2006Lss pharma presentation2-2006
Lss pharma presentation2-2006Omnex Inc.
 
Cms Solution 07162010
Cms Solution 07162010Cms Solution 07162010
Cms Solution 07162010larrybaker90
 

Ähnlich wie (07) 5806 project control (20)

CV_Clayton_David_2016 new
CV_Clayton_David_2016 newCV_Clayton_David_2016 new
CV_Clayton_David_2016 new
 
Value chain analysis 4
Value chain analysis 4Value chain analysis 4
Value chain analysis 4
 
PJM6000Project Management PracticesWeek 5Deb Cote,.docx
PJM6000Project Management PracticesWeek 5Deb Cote,.docxPJM6000Project Management PracticesWeek 5Deb Cote,.docx
PJM6000Project Management PracticesWeek 5Deb Cote,.docx
 
PJM6000Project Management PracticesWeek 5Deb Cote,.docx
PJM6000Project Management PracticesWeek 5Deb Cote,.docxPJM6000Project Management PracticesWeek 5Deb Cote,.docx
PJM6000Project Management PracticesWeek 5Deb Cote,.docx
 
ادارة تكلفة المشروع
ادارة تكلفة المشروع ادارة تكلفة المشروع
ادارة تكلفة المشروع
 
Cms solution 08072010
Cms solution 08072010Cms solution 08072010
Cms solution 08072010
 
Franchise
FranchiseFranchise
Franchise
 
Melbourne streamlining earned value with hd published
Melbourne streamlining earned value with hd publishedMelbourne streamlining earned value with hd published
Melbourne streamlining earned value with hd published
 
Estimating software development
Estimating software developmentEstimating software development
Estimating software development
 
Sonny james daigrepont_resume' (6)
Sonny james daigrepont_resume' (6)Sonny james daigrepont_resume' (6)
Sonny james daigrepont_resume' (6)
 
The project plan
The project planThe project plan
The project plan
 
014 changes-cost overrun measurement
014 changes-cost overrun measurement014 changes-cost overrun measurement
014 changes-cost overrun measurement
 
014 changes-cost overrun measurement
014 changes-cost overrun measurement014 changes-cost overrun measurement
014 changes-cost overrun measurement
 
014 changes-cost overrun measurement
014 changes-cost overrun measurement014 changes-cost overrun measurement
014 changes-cost overrun measurement
 
014 changes-cost overrun measurement
014 changes-cost overrun measurement014 changes-cost overrun measurement
014 changes-cost overrun measurement
 
014 changes-cost overrun measurement
014 changes-cost overrun measurement014 changes-cost overrun measurement
014 changes-cost overrun measurement
 
014 changes-cost overrun measurement
014 changes-cost overrun measurement014 changes-cost overrun measurement
014 changes-cost overrun measurement
 
Lss pharma presentation2-2006
Lss pharma presentation2-2006Lss pharma presentation2-2006
Lss pharma presentation2-2006
 
Cms Solution 07162010
Cms Solution 07162010Cms Solution 07162010
Cms Solution 07162010
 
The Role of Evaluation in Strengthening Agricultural R&D in Sub-Saharan Afric...
The Role of Evaluation in Strengthening Agricultural R&D in Sub-Saharan Afric...The Role of Evaluation in Strengthening Agricultural R&D in Sub-Saharan Afric...
The Role of Evaluation in Strengthening Agricultural R&D in Sub-Saharan Afric...
 

Kürzlich hochgeladen

How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxmanuelaromero2013
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Educationpboyjonauth
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeThiyagu K
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Celine George
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docxPoojaSen20
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionSafetyChain Software
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13Steve Thomason
 
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991RKavithamani
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Krashi Coaching
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfciinovamais
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingTechSoup
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdfSoniaTolstoy
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application ) Sakshi Ghasle
 
Student login on Anyboli platform.helpin
Student login on Anyboli platform.helpinStudent login on Anyboli platform.helpin
Student login on Anyboli platform.helpinRaunakKeshri1
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxiammrhaywood
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdfssuser54595a
 

Kürzlich hochgeladen (20)

Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1
 
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptx
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Education
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and Mode
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docx
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory Inspection
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13
 
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
 
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptxINDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
 
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdfTataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy Consulting
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application )
 
Student login on Anyboli platform.helpin
Student login on Anyboli platform.helpinStudent login on Anyboli platform.helpin
Student login on Anyboli platform.helpin
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
 

(07) 5806 project control

  • 1. CE 5806 Project & Site Control David Chua Kim Huat Associate Professor E2-04-08, tel: 65162195 email: cvedavid Assoc Prof David Chua Dept of Civil Engrg, NUS
  • 2. Course Outline & Perspective  Development and Organisation of Projects (week 1) – Project phases; organisational concepts; contractual relationships  Project Planning (week 1-3) – Managerial philosophy and function of planning; network methods; resource levelling; linear scheduling;  Project Control (week 4) – Managerial philosophy and function of control; WBS; schedule and cost philosoph f nction control WBS sched le control; earned value  Advanced Methods (week 5-7) – Schedule compression; p p ; probabilistic methods; theory of constraints; lean ; y ; construction; critical chain; interface management  Productivity Improvement (week 8-9) – Factors affecting productivity; concept of work flows, capacity and bottlenecks  Site Control and Contract Management (week 10-12) – Documentation and quality management; contract management – variation and extension of time; construction safety and health Assoc Prof David Chua Dept of Civil Engrg, NUS
  • 3. Control of Project Cost and Schedule Key Issues: 1. Understand the key concepts in project control 2. Learn the earned value approach to project control & its importance 3. Know how to measure & track progress 4. Use h 4 U the WBS method to plan and organise project h d l d i j Assoc Prof David Chua Dept of Civil Engrg, NUS
  • 4. Managerial Function of Control  Critical to effective management is the supplying of information – Type of information – Amount of information  Timeliness of control system – Reporting period & delay in the reporting information; gives dela gi es rise to time lag in control – Delay in reporting should be minimized to one or two weeks – Fast paced projects with many parties and contractual obligations must be more tightly monitored. – Amount of work progress may overwhelm scheduler. p g y – Too often costly (time, overheads). May become a nuisance. – Waiting too long to update may eliminate effectiveness of updating as a control tool – no time for corrective action – If delay, can supplement with rough and ready control systems Assoc Prof David Chua Dept of Civil Engrg, NUS
  • 5. Managerial Function of Control  Example of timeliness vs accuracy – Cost of materials can be reported at several stages and they affect the reliability of cost reports: When order is placed (commitment) Material delivered Material issued from stores Material actually used Invoice paid p If wait till invoice – long delay and useless for control purposes Commitment stage – inaccurate because may not be used or delivered but timely These are then corrected at later stages Assoc Prof David Chua Dept of Civil Engrg, NUS
  • 6. Managerial Function of Control  Level of detail – Cost information for control if collected using cost codes existing in the company s accounting system; can be a problem company’s – Some activity based costing needed Project No Area Operation Distribution Cost 08BE02 03 096600 01 $4 000 $4,000 – Need to be balanced with the time to prepare; having approximately accurate information timely is more helpful pp y y p than accurate information 2 to 3 months after the event – Over controlled makes it cumbersome and expensive So h is S what i a good rule of thumb? d l f h b? – 20 – 80% rule Critical items in greater detail, otherwise in summary level Critical items: high proportion or high escalation Assoc Prof David Chua Dept of Civil Engrg, NUS
  • 7. Managerial Function of Control  Data vs information – 100 page report on procurement or 10 lines printout that 5 orders are likely to be late – Exception reporting, trouble spots and deviations  Obj i vs subjective data and information Objective bj i d di f i – Should be as objective as possible – If subjective estimates could lead to 90% syndrome: Project appears to progress well until it is 90% complete j ll il i i l Actual progress then has to catch up Assoc Prof David Chua Dept of Civil Engrg, NUS
  • 8. Example of CSI (Construction Specifications Institute) Format 09600 Flooring 09610 Floor Treatment Slip - Resistant Floor Treatment Static - Resistant Floor Treatment 09620 Specialty Flooring Asphalt Plank Flooring Plastic Laminate Flooring Athletic Flooring Athl ti Fl i 09630 Masonry Flooring Brick Flooring Marble Flooring Chemical - Resistant Brick Flooring Flagstone Flooring g g State Flooring g Granite Flooring Stone Flooring 09640 Wood Flooring Cushioned Wood Flooring Assemblies Mastic Set Wood Flooring Assemblies Resilient Wood Flooring Assemblies Wood Athletic Flooring Wood Block Flooring Wood Composition Flooring Wood Parquet Flooring Wood Strip Flooring 09650 Resilient Flooring 09660 Static Control Flooring 09670 Fluid-Applied Flooring 09680 Carpet 09690 Flooring Restoration Assoc Prof David Chua Dept of Civil Engrg, NUS
  • 9. Approach to Control  Variance Analysis Method What is the problem with this method? – Measures the difference between two factors, e.g.  Historic backward looking between actual and planned – Examples:  Not effectively used to p y portray y Planned vs actual start performance Planned vs actual finish Duration, Duration milestones Budgeted vs actual cost Manhours, unit cost, % complete Measured value vs actual cost M d l l Assoc Prof David Chua Dept of Civil Engrg, NUS
  • 10. Approach to Control  Key questions that must be – Is the rate of work accelerating or answered: decelerating as it should? – What happened in the past? Rate of build up of work – cost and Are we on schedule? progress If variation, where, why, who? S-charts What effect and what can be done? Is work within budget? Etc Thus, need to be forward looking, predicting, surfacing – What is going to happen in the trends and sensitive enough future? f to pick up adverse Are we going to be on schedule, performance as soon as it budget? occurs so that something can Important to be aware of trends in y be done to rectify it early stage to influence outcome What is final cost and completion date? Assoc Prof David Chua Dept of Civil Engrg, NUS
  • 11. Approach to Control  Data not effectively used to give integrated control Planned vs actual does not really tell PM whether more or less than budgeted have been expended. Why?? Example: Activity budgeted cost cum. Budget actual cum. cost variance cum. variance in period p to date cost to date to date p period to date A $60,000 $135,000 $66,000 $150,000 -$6,000 -$15,000 B $45,000 $90,000 $39,000 $99,000 $6,000 $9,000  Does not show whether expenditure results in planned work completed  Simply – variance in cost could be cost related or schedule related Assoc Prof David Chua Dept of Civil Engrg, NUS
  • 12. Approach to Control $60,000 for A may represent the 500 units of excavation $66,000 is the actual cost of quantity not specified Say it is for 540 units and the estimated excavation cost is $120/unit Work completed is worth $64,800, thus +ve variance of $1,200 $64,800 is the earned value Example: Activity budgeted cost cum. Budget actual cum. cost variance cum. variance in period to date cost to date to date period to date A $60,000 $135,000 $66,000 $150,000 -$6,000 -$15,000 B $45,000 $90,000 $39,000 $99,000 $6,000 $9,000 Three sets of data available that needs to be integrated to give effective control 1. Planned 2. 2 Actual 3. Value earned (“earned value”) Assoc Prof David Chua Dept of Civil Engrg, NUS
  • 13. Earned Value Approach Example: Activity budgeted cost cum. Budget actual cum. cost variance cum. variance p in period to date cost to date to date p period to date A $60,000 $135,000 $66,000 $150,000 -$6,000 -$15,000 B $45,000 $90,000 $39,000 $99,000 $6,000 $9,000 Quantities: 540 units Cost: $120/unit Earned value= $64,800 Variance in cost = Earned value – Actual cost = $64,800 - $66,000 = -$1,200 Meaning the concrete put in cost $1,200 more than it should Variance in schedule = Earned value – budget cost How much is planned? = $64,800 - $60,000 How much is done? = $4 800 $4,800 How much ahead? Meaning $4,400 more work was completed than planned Assoc Prof David Chua Dept of Civil Engrg, NUS
  • 14. Key Cost Measures  ACWP: actual cost of work performed – amount reported as actually expended in completing work performed  BCWP: budgeted cost of work performed – budgeted amount of cost for work completed – “earned value of work performed”  BCWS: budgeted cost of work scheduled – budgeted amount of cost for the work scheduled to be p g performed  Variance Measures Alternatively – Cost variance = BCWP - ACWP va a ce CW CW C CPI = BCWP/ACWP CW / CW – Performance variance = BCWP - BCWS SPI = BCWP/BCWS  0 is favourable  1 is favourable Assoc Prof David Chua Dept of Civil Engrg, NUS
  • 15. Earned Value Approach Usual to use labour hours for weighted value g for performance measurement Project A example Master Activities Estimated Scheduled Scheduled Estimated Man hours Man-hours Start Finish Cost (end of day) (end of day) ($1000) Site earth works 450 0 20 40 Structural works 1,000 10 40 90 Mechanical i i M h i l piping 1,500 1 500 20 70 350 Control systems 750 40 80 140 Reactor Towers 400 50 80 120 Systems Check y 300 80 95 60 Total 800 Assoc Prof David Chua Dept of Civil Engrg, NUS
  • 16. Accumulative BCWS Assumed equally distributed 1000's 0 10 20 30 40 50 60 70 80 90 95sum site earth k works 0 20 40 0 20 20 40 structural works 10 40 90 0 30 30 30 90 mechanical piping 20 70 350 0 70 70 70 70 70 350 control systems 40 80 140 0 35 35 35 35 140 reactor towers 50 80 120 0 40 40 40 120 systems check 80 95 60 0 40 20 60 BCWS 0 20 50 100 100 105 145 145 75 40 20 800 accum. 0 20 70 170 270 375 520 665 740 780 800 BCWS 900 800 700 600 BCWS ($1000's) 500 400 300 200 100 0 0 20 40 60 80 100 Project Days
  • 17. At end of day 40 Master Activities % complete Actual Cost ($1000) Site earth works 100 45 Structural works 85 110 Mechanical piping 20 65 Control systems 5 10 Reactor towers - - Systems Check - - Determine progress of project in terms of cost and schedule. ACWP = $230 k BCWP = 100% x 40k 40 k 85% x 90k 76.5 k 20% x 350k 70 k 5% x 140k 7 k total $193.5 k Assoc Prof David Chua Dept of Civil Engrg, NUS
  • 18. Schedule and Cost Variances $270K BCWS 900 ACWP 800 700 BCWS 600 Ahead BCWS ($1000's) BCWP 500 400 300 B 200 Behind 100 0 0 20 40 60 80 100 8 days Project Days behind $193.5K $193 5K $ 30 $230K Assoc Prof David Chua Dept of Civil Engrg, NUS
  • 19. Actual progress compared with ES and LS curves BCWS 900 800 Projected 700 ES LS completion p 600 BCWS ($1000's) 500 400 Actual progress 300 B 200 100 0 0 20 40 60 80 100 Project Days Assoc Prof David Chua Dept of Civil Engrg, NUS
  • 20. Measurement of Work Completed  Units completed Applicable to tasks that are repetitive and require uniform effort Number of precast beams to install for floor = 120 Number of beams installed = 75 % complete = 75/120*100% = 62.5%  Start/Finish Applicable to activities of uncertain duration with no well-defined intermediate milestones. Start activities are given a percent complete say 20 30% f l 20-30% for long activities ti iti  Supervisor Opinion Informed judgement concerning completion status j g g p Dewatering, constructing temporary facilities, landscaping are usually judged this way Assoc Prof David Chua Dept of Civil Engrg, NUS
  • 21. Incremental milestone approach: Applicable to activities which have multiple units of work with several sequential tasks e.g. form, reinforce & pour concrete footings Foundation: Example: 150 footings Excavation 5% Excavation – 20 footings: 20*5% =1 Formwork50% Formwork – 10 footings: 10*55% = 5.5 55 Rebar/embeds 20% Rebar/embeds – 8 footings: 8*75% =6 Pour & finish 10% Pour & finish – 30 footings: 30*85% = 25.5 Strip & finish 10% Strip & finish – 20 footings: 20*95% = 19 Backfill 5% Backfill – 10 footings: = 10 Total: 67 footings out of 150 = 67/150*100% = 44.7% Assoc Prof David Chua Dept of Civil Engrg, NUS
  • 22. Measurement of Work Completed  Cost ratio Applicable to tasks that are continuous and where costs bear a strong relationship to total effort required actual cost or work hours to date % complete  forecast to completion f t l ti  Weighted or Progress correlated to weight of material or some other units. equivalent i l t units Assoc Prof David Chua Dept of Civil Engrg, NUS
  • 23. Project A example Master Activities Weighted Value Unit Quantity at Quantity Actual (man-hours) completion completed man hours 1.0 Site earth works 450 1.1 Site grading 200 m3 5,000 4,000 150 1.2 Compacted building 180 m3 10,000 7,500 150 fill 1.3 Fencing 70 m 800 610 60 Master Activities Weighted Value Man-hrs Actual man ( (man-hours)) earned hours 1.0 Site earth works 450 1.1 Site grading 200 4000/5000 x 200 160 150 1.2 Compacted building fill 180 7500/10000 x 180 135 150 1.3 Fencingg 70 610/800 x 70 53.4 60 Total 348.4 360 Percent complete = 348.4/450 = 77.4% Productivity = 348.4/360 = 96.8% Assoc Prof David Chua Dept of Civil Engrg, NUS
  • 24. Network- Network-based Control System  Requires a well-defined work  Work breakdown structure - plan, plan budget and schedule smallest unit is the work package – provides the benchmarks for – work defined in sufficient detail control to be be measured, budgeted,  Must be developed with inputs scheduled and controlled from people performing the work – several WPs in one activity or single WP comprising several  Must be communicated to all activities participants  Difference between network  To be effective, must be simple to approach and cost accounting administer and easily understood approach by all participants  Efficiency of system – decide on level of detail, quantity of information, frequency of collection ll i Assoc Prof David Chua Dept of Civil Engrg, NUS
  • 25. Work Breakdown Structure Building Site work Foundations Structure Curtain wall Finishes Electrical Survey Excavation Piles Pile caps Ground beams Test piles Area 1 Area 2 Drive piles Inspect Clean Rebar Pour concrete  WBS used in planning stage to identify tasks and subtasks  Assign responsibilities, achieve management control  No fixed rule for level of detail and breakdown structure Assoc Prof David Chua Dept of Civil Engrg, NUS
  • 26. WBS Hierarchy Power S Station Boiler house Turbine house Coal handling Water cooling plant plant Cooling Condenser Turbine blocks Retaining walls water pipes foundations Foundations Columns Machine platform Rebar Prepare Formwork Erect formwork Assoc Prof David Chua Dept of Civil Engrg, NUS
  • 27. WBS with organisation structure Oranizational structure ucture eakdown Stru Work Bre Assoc Prof David Chua Dept of Civil Engrg, NUS