SUBMITTED BY:
ANIL YADAV
ASHOK PERSHAD
DHIRAJ GAUR
MANOJ
MUKUL VERMA
FIDIC
Fédération Internationale Des Ingénieurs-Conseils - FIDIC
FIDIC is the French acronym for the International Federation of
Consulting Engineers.
FIDIC was founded in 1913 to promote the professional interests
of the member associations and to disseminate information of
interest to members of its component national associations
Today FIDIC membership numbers more than 60 countries and
represents most of the private practice consulting engineers in
the world. Only associations of consulting engineers are eligible
for FIDIC membership.
During the past half century, the International Federation of
Consulting Engineers (FIDIC) has devoted itself to the
compilation of management documents for all kinds of projects,
among which the FIDIC Conditions of Contract are of the highest
influence and are the most popular application.
New Edition FIDIC
The new models include :
FIDIC Conditions of Contract for Construction, the (New
Red Book)
FIDIC Conditions of Contract for Plant and Design/Build,
the (New Yellow Book)
FIDIC Conditions of Contract for EPC Turnkey Projects,
the (Silver Book)
FIDIC Short Form of Contract, the (Green Book)
FIDIC Conditions of Contract (new edition) raised a higher
requirement to the Parties concerned in the area of contract
management 12
APPLICATION
Applicability under Various Project Delivery and Contracting System:
 1. The “New Red Book” can be used in any kind of Engineering
Construction Contract.
 2. The “New Yellow Book” applies to the lump sum contract project
where the Contractor takes participation in the design work.
 3. The “Silver Book” applies to the turnkey projects of infrastructures or
large-scale factories, where the Contractor takes on more work and risk
while the Employer’s participation is small (private financing or
government financing), but it is strictly defined upon the investment
and construction period.
 4. The “Green Book” can be used in all kinds of small-scale projects.
 5. Altogether, these four Contract Conditions can be applied to nearly
every kind of project, expect for that of managing contracting or simply
consulting or designing
FIDIC
The first edition of FIDIC Conditions of Contract for
Works of Civil Engineering Construction (use “Red
Book” in the following) was compiled in 1957,and
later its second, third, and fourth edition were issued
in 1963, 1977, and 1987 respectively.
FIDIC
With the investigation of the governments,
employers, contractors and consulting engineers all
over the world about their application of the “Red
Book”, 204 findings reports were returned.
According to the findings, the FIDIC Contract
Committee organized a group of experts to compile
the new Contract Condition models to be applied in
the 21stcentury.
High-quality Provisions and Logical Clause
Sequencing:
 Compared with the original “Red Book”, the “New
Red Book” has163 clauses, nearly 40% being
freshly compiled. An additional 40% were modified
and given supplements. Only 20% were kept intact.
The old edition adopted ICE’s disorderly style bit
in the clause sequence, while in the new edition,
the related sub-clauses are put into one clause
when possible, and convenient to the users.
Green Book -
Low value,
simple works
100%0%
Amount of design by Contractor
•RisktransfertoContractor
•Certaintyofoutturnprice
Red
Yellow
Silver
OLD NEW
Civil
‘Red Book’
4th Edition
1987,1992
Construction
(mainly)
Employer-
Design
1999
Typical Sequence of dispute Events Envisaged in
Clause 20
20.2 Parties
appoint
the DAB
20.4 A Party
refers a dispute
to the DAB
Parties present
submissions to the DAB
20.4 A Party may
issue a “notice of
dissatisfaction”
DAB gives its decision
< 28d < 84d < 28d < 56d
Amicable Settlement
The Parties in a FIDIC Contract
The Current (1999) Red Book – Basic Features
The Current (1999) Red Book – Basic Features
1. Suitable for all civil works projects where main responsibility for
design lies with Employer (or his Engineer).
2. Some design may, of course, be carried out by Contractor.
3. Administration of Contract and supervision by Engineer.
4. Approval of work, payment and claims certified by Engineer.
5. Work done is measured, payment according to Bill of Quantities.
6. Option for payment on lump sum basis.
7. Balanced / fair risk-sharing.
More specific provisions concerning the rights &
obligations of the contracting parties
Taking the clause of Employer’s default as an example,
there are 3 points added to the new red book: two of them
are concerned with payments. This shows the strict
requirement for the employer. However the contractor
should institute a quality assurance system and submit to
the engineer to audit any aspect of the system before
execution.
Monthly progress report shall be prepared by contractor to
submit to engineer every month, otherwise, payment won’t
be given.
Any kind of Bribe can result in contractors default.
All of the above are high requirements from the contractor.
To solve the problem of Back payment using
world wide reference
Since the problem of Employers financial vacancy or
contractor financing are originating world wide, the relative
clause and regulations are added into FIDIC condition of
contract
The employers shall submit within 28 days, after receiving
any request from contractor reasonable agreement that
financial agreement has been made.
If the employer intends to make any significant change to
his financial agreement, he shall give notice to contractor
with detailed particulars.
To Solve the Problem of Back Payment using
World Wide Experience for Reference:
It is reported that the back payment and debt
between the engineering units in China have added
up to 280 billion (RMB), which is mostly
Employer’s (government included) default to the
Contractor. The problem has greatly influenced the
construction corporations that their economic
strength were weakened. The market needs a legal
system to provide a guarantee for free and fair
competition.
 Since the problems of the Employer’s financial vacancy or
Contractor financing are originating worldwide, the relative clauses
and regulations are added into FIDIC Conditions of Contract:
 Employer’s financial arrangement. The Employer shall submit
within 28 days after receiving any request from the Contractor
reasonable evidence that financial arrangement has been made. If
the Employer intends to make any material change to his financial
arrangement, he shall give notice to the Contractor with detailed
particulars.
 If the Employer fails to execute in accordance with this clause, the
Contractor may, after giving a 21 days’ notice to the Employer,
suspend the work or reduce production output as a kind of warning;
if the Contractor does not receive any reasonable financial
arrangement certificate within 42 days after giving the warning, he
shall be entitled to terminate the Contract, for it is the Employer’s
default. Also the Contractor can get all the compensation earned on
the condition of Employer’s default.
 Contractor Financed Project’s execution. It is specially set up in the
Particular Conditions an Example Provisions for Contractor
Finance, which defines that if it is Contractor financing and he has
committed to the project, the Employer shall deliver a bank
payment guarantee to the Contractor within 28 days after both
parties have entered into the Contract Agreement. If the Contractor
does not receive the guarantee, the Engineer shall not issue the
notice to commence. It is defined in the guarantee that if the
Employer fails to make payment in full by the date 14 days after the
expiry of the period specified in the contract as that within which
such payment should have been made, the Contractor shall been
entitled to demand for payment from the bank with a certificate,
Contractor’s signatures which must be authenticated by his bankers
or by a notary public.

Weitere ähnliche Inhalte

Was ist angesagt?

Training fidic moustafa ismail 2017 _ lec 4
Training fidic moustafa ismail  2017 _  lec 4Training fidic moustafa ismail  2017 _  lec 4
Training fidic moustafa ismail 2017 _ lec 4Moustafa Ismail Abu Dief
 
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias TanFIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias TanAdrias TAN
 
time bar clauses
time bar clausestime bar clauses
time bar clausesAMILA GAYAN
 
Ss 5 training fidic Dr. Moustafa Ismail 2017 _ lec 5
Ss 5 training fidic Dr. Moustafa Ismail  2017 _ lec 5Ss 5 training fidic Dr. Moustafa Ismail  2017 _ lec 5
Ss 5 training fidic Dr. Moustafa Ismail 2017 _ lec 5Moustafa Ismail Abu Dief
 
Claims & disputes management
Claims & disputes managementClaims & disputes management
Claims & disputes managementMohammed Tanbouz
 
Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)mohamed Ismail
 
Construction Claims Explained
Construction Claims ExplainedConstruction Claims Explained
Construction Claims Explainedclaimsconsultancy
 
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdfFIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdfBayuDarma4
 
Dispute resolution technique
Dispute resolution techniqueDispute resolution technique
Dispute resolution techniqueSaad Ullah
 
Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)Fakhar-un -Nisa
 
Fidic contract
Fidic contract Fidic contract
Fidic contract Yash Patel
 
Update Delay Analysis
Update Delay AnalysisUpdate Delay Analysis
Update Delay AnalysisChris Carson
 
Contract payment and variation
Contract payment and variationContract payment and variation
Contract payment and variationVj NiroSh
 
Conditions Of Contract
Conditions Of ContractConditions Of Contract
Conditions Of Contractguestdb5e498
 

Was ist angesagt? (20)

Training fidic moustafa ismail 2017 _ lec 4
Training fidic moustafa ismail  2017 _  lec 4Training fidic moustafa ismail  2017 _  lec 4
Training fidic moustafa ismail 2017 _ lec 4
 
FIDIC 2017 Yellow and Silver in EPC and PPP Contracts
FIDIC 2017 Yellow and Silver in EPC and PPP ContractsFIDIC 2017 Yellow and Silver in EPC and PPP Contracts
FIDIC 2017 Yellow and Silver in EPC and PPP Contracts
 
Cl presentation
Cl presentationCl presentation
Cl presentation
 
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias TanFIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
 
time bar clauses
time bar clausestime bar clauses
time bar clauses
 
Ss 5 training fidic Dr. Moustafa Ismail 2017 _ lec 5
Ss 5 training fidic Dr. Moustafa Ismail  2017 _ lec 5Ss 5 training fidic Dr. Moustafa Ismail  2017 _ lec 5
Ss 5 training fidic Dr. Moustafa Ismail 2017 _ lec 5
 
Claims & disputes management
Claims & disputes managementClaims & disputes management
Claims & disputes management
 
Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)
 
Construction Claims Explained
Construction Claims ExplainedConstruction Claims Explained
Construction Claims Explained
 
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdfFIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
 
Dispute resolution technique
Dispute resolution techniqueDispute resolution technique
Dispute resolution technique
 
claims management framework
 claims management framework claims management framework
claims management framework
 
Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)
 
Fidic contract
Fidic contract Fidic contract
Fidic contract
 
Claims
ClaimsClaims
Claims
 
Update Delay Analysis
Update Delay AnalysisUpdate Delay Analysis
Update Delay Analysis
 
Contract payment and variation
Contract payment and variationContract payment and variation
Contract payment and variation
 
Delay Analysis and Concurrent Delay
Delay Analysis and Concurrent DelayDelay Analysis and Concurrent Delay
Delay Analysis and Concurrent Delay
 
Fundamentals of Construction Contracts - English, ver. 2021
Fundamentals of Construction Contracts - English, ver. 2021Fundamentals of Construction Contracts - English, ver. 2021
Fundamentals of Construction Contracts - English, ver. 2021
 
Conditions Of Contract
Conditions Of ContractConditions Of Contract
Conditions Of Contract
 

Andere mochten auch

Fidic flow charts final
Fidic flow charts finalFidic flow charts final
Fidic flow charts finalFitBlar Mit
 
Fidic yellow vs silver
Fidic yellow vs silverFidic yellow vs silver
Fidic yellow vs silverWeero Koster
 
FIDIC SIlver Book in Power Projects
FIDIC SIlver Book in Power ProjectsFIDIC SIlver Book in Power Projects
FIDIC SIlver Book in Power ProjectsFrancis Ho
 
EPC v EPCM Contracting- A Comparison
EPC v EPCM Contracting- A ComparisonEPC v EPCM Contracting- A Comparison
EPC v EPCM Contracting- A Comparisonhelensuni
 
Risk Assessment, Mitigation And Management In Epc Projects With Case Study By...
Risk Assessment, Mitigation And Management In Epc Projects With Case Study By...Risk Assessment, Mitigation And Management In Epc Projects With Case Study By...
Risk Assessment, Mitigation And Management In Epc Projects With Case Study By...HIMADRI BANERJI
 
Strategic Planning : the best way to manage EPC Contract Risks
Strategic Planning : the best way to manage EPC Contract RisksStrategic Planning : the best way to manage EPC Contract Risks
Strategic Planning : the best way to manage EPC Contract RisksPankaj K Sinha
 
Conciliation & Mediation
Conciliation & MediationConciliation & Mediation
Conciliation & MediationTuhin Sarkar
 
Fidic conditions of subcontract agreement
Fidic conditions of subcontract agreementFidic conditions of subcontract agreement
Fidic conditions of subcontract agreementabdmuhaiminyunus
 
Hasselbalch costablecken examining the relationship between barriers and curr...
Hasselbalch costablecken examining the relationship between barriers and curr...Hasselbalch costablecken examining the relationship between barriers and curr...
Hasselbalch costablecken examining the relationship between barriers and curr...Dr. Paul Davis
 
Delay, dispute (1st annual conf. of planning in cairo 23-8-2014) engr. m maged
Delay, dispute  (1st annual conf. of planning in cairo 23-8-2014) engr. m magedDelay, dispute  (1st annual conf. of planning in cairo 23-8-2014) engr. m maged
Delay, dispute (1st annual conf. of planning in cairo 23-8-2014) engr. m magedM Maged Hegazy, LLM, MBA, CCP, P3O
 
A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006Melvin Lim
 
Conciliation
ConciliationConciliation
ConciliationDolly03
 

Andere mochten auch (17)

Fidic flow charts final
Fidic flow charts finalFidic flow charts final
Fidic flow charts final
 
Fidic yellow vs silver
Fidic yellow vs silverFidic yellow vs silver
Fidic yellow vs silver
 
FIDIC SIlver Book in Power Projects
FIDIC SIlver Book in Power ProjectsFIDIC SIlver Book in Power Projects
FIDIC SIlver Book in Power Projects
 
EPC v EPCM Contracting- A Comparison
EPC v EPCM Contracting- A ComparisonEPC v EPCM Contracting- A Comparison
EPC v EPCM Contracting- A Comparison
 
Construction Claims
Construction ClaimsConstruction Claims
Construction Claims
 
Risk Assessment, Mitigation And Management In Epc Projects With Case Study By...
Risk Assessment, Mitigation And Management In Epc Projects With Case Study By...Risk Assessment, Mitigation And Management In Epc Projects With Case Study By...
Risk Assessment, Mitigation And Management In Epc Projects With Case Study By...
 
Strategic Planning : the best way to manage EPC Contract Risks
Strategic Planning : the best way to manage EPC Contract RisksStrategic Planning : the best way to manage EPC Contract Risks
Strategic Planning : the best way to manage EPC Contract Risks
 
Conciliation & Mediation
Conciliation & MediationConciliation & Mediation
Conciliation & Mediation
 
Epc Vs Epcm
Epc Vs EpcmEpc Vs Epcm
Epc Vs Epcm
 
fidic-contracts
fidic-contractsfidic-contracts
fidic-contracts
 
Fidic conditions of subcontract agreement
Fidic conditions of subcontract agreementFidic conditions of subcontract agreement
Fidic conditions of subcontract agreement
 
Ippc6 bpp
Ippc6 bppIppc6 bpp
Ippc6 bpp
 
Hasselbalch costablecken examining the relationship between barriers and curr...
Hasselbalch costablecken examining the relationship between barriers and curr...Hasselbalch costablecken examining the relationship between barriers and curr...
Hasselbalch costablecken examining the relationship between barriers and curr...
 
Ippc 6 presentation
Ippc 6 presentationIppc 6 presentation
Ippc 6 presentation
 
Delay, dispute (1st annual conf. of planning in cairo 23-8-2014) engr. m maged
Delay, dispute  (1st annual conf. of planning in cairo 23-8-2014) engr. m magedDelay, dispute  (1st annual conf. of planning in cairo 23-8-2014) engr. m maged
Delay, dispute (1st annual conf. of planning in cairo 23-8-2014) engr. m maged
 
A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006
 
Conciliation
ConciliationConciliation
Conciliation
 

Ähnlich wie Fidic law1

dokumen.tips_fidic-power-point-presentation.pdf
dokumen.tips_fidic-power-point-presentation.pdfdokumen.tips_fidic-power-point-presentation.pdf
dokumen.tips_fidic-power-point-presentation.pdfafadlalla
 
FIDIC Red Book (PEC 2019).pdf
FIDIC Red Book (PEC 2019).pdfFIDIC Red Book (PEC 2019).pdf
FIDIC Red Book (PEC 2019).pdfsajidkhan82714
 
FIDIC Presentation-2016.pdf
FIDIC Presentation-2016.pdfFIDIC Presentation-2016.pdf
FIDIC Presentation-2016.pdfPachyCarmona1
 
Contracts PPT.pptx
Contracts PPT.pptxContracts PPT.pptx
Contracts PPT.pptxAditya Mane
 
07 cl-assignment-syafiq-qy-macy-huiyong-deric
07 cl-assignment-syafiq-qy-macy-huiyong-deric07 cl-assignment-syafiq-qy-macy-huiyong-deric
07 cl-assignment-syafiq-qy-macy-huiyong-dericSyafiq Zariful
 
Mode of Tendering.pptx
 Mode of Tendering.pptx Mode of Tendering.pptx
Mode of Tendering.pptxssuser4ae21a
 
05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITIONByishimoBTCChef
 
FIDIC.RICS CPD Event Singapore 2012.ppt
FIDIC.RICS CPD Event Singapore 2012.pptFIDIC.RICS CPD Event Singapore 2012.ppt
FIDIC.RICS CPD Event Singapore 2012.pptDonaAlisyahSiregar
 
2017 Tunnel Journal on Emerald Book and GBR
2017 Tunnel Journal on Emerald Book and GBR2017 Tunnel Journal on Emerald Book and GBR
2017 Tunnel Journal on Emerald Book and GBRandrewng540722
 
FIDIC-ACEG European Regional Infrastructure Conference, 6-7 March 2018, Tbili...
FIDIC-ACEG European Regional Infrastructure Conference, 6-7 March 2018, Tbili...FIDIC-ACEG European Regional Infrastructure Conference, 6-7 March 2018, Tbili...
FIDIC-ACEG European Regional Infrastructure Conference, 6-7 March 2018, Tbili...Cerasela Angelescu
 

Ähnlich wie Fidic law1 (20)

dokumen.tips_fidic-power-point-presentation.pdf
dokumen.tips_fidic-power-point-presentation.pdfdokumen.tips_fidic-power-point-presentation.pdf
dokumen.tips_fidic-power-point-presentation.pdf
 
12953021.ppt
12953021.ppt12953021.ppt
12953021.ppt
 
FIDIC Red Book (PEC 2019).pdf
FIDIC Red Book (PEC 2019).pdfFIDIC Red Book (PEC 2019).pdf
FIDIC Red Book (PEC 2019).pdf
 
FIDIC Presentation-2016.pdf
FIDIC Presentation-2016.pdfFIDIC Presentation-2016.pdf
FIDIC Presentation-2016.pdf
 
Contracts PPT.pptx
Contracts PPT.pptxContracts PPT.pptx
Contracts PPT.pptx
 
17 10 16
17 10 1617 10 16
17 10 16
 
07 cl-assignment-syafiq-qy-macy-huiyong-deric
07 cl-assignment-syafiq-qy-macy-huiyong-deric07 cl-assignment-syafiq-qy-macy-huiyong-deric
07 cl-assignment-syafiq-qy-macy-huiyong-deric
 
FIDIC 2019
FIDIC 2019FIDIC 2019
FIDIC 2019
 
Mode of Tendering.pptx
 Mode of Tendering.pptx Mode of Tendering.pptx
Mode of Tendering.pptx
 
Ak contract management
Ak contract managementAk contract management
Ak contract management
 
05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION
 
Fidic.pptx
Fidic.pptxFidic.pptx
Fidic.pptx
 
Chapter two.pptx
Chapter two.pptxChapter two.pptx
Chapter two.pptx
 
Business Excellence and Enhancement of ROI by Dr Punit Sethi
Business Excellence and Enhancement of ROI by Dr Punit SethiBusiness Excellence and Enhancement of ROI by Dr Punit Sethi
Business Excellence and Enhancement of ROI by Dr Punit Sethi
 
FIDIC.RICS CPD Event Singapore 2012.ppt
FIDIC.RICS CPD Event Singapore 2012.pptFIDIC.RICS CPD Event Singapore 2012.ppt
FIDIC.RICS CPD Event Singapore 2012.ppt
 
2017 Tunnel Journal on Emerald Book and GBR
2017 Tunnel Journal on Emerald Book and GBR2017 Tunnel Journal on Emerald Book and GBR
2017 Tunnel Journal on Emerald Book and GBR
 
FIDIC-ACEG European Regional Infrastructure Conference, 6-7 March 2018, Tbili...
FIDIC-ACEG European Regional Infrastructure Conference, 6-7 March 2018, Tbili...FIDIC-ACEG European Regional Infrastructure Conference, 6-7 March 2018, Tbili...
FIDIC-ACEG European Regional Infrastructure Conference, 6-7 March 2018, Tbili...
 
Kandil_Sameh_AR50123
Kandil_Sameh_AR50123Kandil_Sameh_AR50123
Kandil_Sameh_AR50123
 
FIDIC intro author eng. mohammed fadlalla
FIDIC intro  author eng. mohammed fadlallaFIDIC intro  author eng. mohammed fadlalla
FIDIC intro author eng. mohammed fadlalla
 
Fidic db-yellow-book
Fidic db-yellow-bookFidic db-yellow-book
Fidic db-yellow-book
 

Mehr von dhiraj.gaur

Presentation cvp analysis 140908
Presentation cvp analysis 140908Presentation cvp analysis 140908
Presentation cvp analysis 140908dhiraj.gaur
 
O.b.airtel final
O.b.airtel finalO.b.airtel final
O.b.airtel finaldhiraj.gaur
 
Nirma case study_abhishek
Nirma case study_abhishekNirma case study_abhishek
Nirma case study_abhishekdhiraj.gaur
 
Investment management
Investment managementInvestment management
Investment managementdhiraj.gaur
 
Enterprise business systems1
Enterprise business systems1Enterprise business systems1
Enterprise business systems1dhiraj.gaur
 
final presentation
final presentationfinal presentation
final presentationdhiraj.gaur
 
integrative negotiation
integrative negotiationintegrative negotiation
integrative negotiationdhiraj.gaur
 
Hid security analysisproject_201209_final
Hid security analysisproject_201209_finalHid security analysisproject_201209_final
Hid security analysisproject_201209_finaldhiraj.gaur
 
Hid finalfinal project
Hid finalfinal projectHid finalfinal project
Hid finalfinal projectdhiraj.gaur
 
Hid fiscal policy
Hid fiscal policyHid fiscal policy
Hid fiscal policydhiraj.gaur
 
Hid penalties and prosecution
Hid penalties and prosecutionHid penalties and prosecution
Hid penalties and prosecutiondhiraj.gaur
 
Hid operations strategy
Hid operations strategyHid operations strategy
Hid operations strategydhiraj.gaur
 

Mehr von dhiraj.gaur (20)

Presentation cvp analysis 140908
Presentation cvp analysis 140908Presentation cvp analysis 140908
Presentation cvp analysis 140908
 
China culture
China  cultureChina  culture
China culture
 
Rm tutorial
Rm tutorialRm tutorial
Rm tutorial
 
O.b.airtel final
O.b.airtel finalO.b.airtel final
O.b.airtel final
 
Nirma case study_abhishek
Nirma case study_abhishekNirma case study_abhishek
Nirma case study_abhishek
 
Upi case study
Upi   case studyUpi   case study
Upi case study
 
Tata
TataTata
Tata
 
Investment management
Investment managementInvestment management
Investment management
 
Enterprise business systems1
Enterprise business systems1Enterprise business systems1
Enterprise business systems1
 
final presentation
final presentationfinal presentation
final presentation
 
group 2
group 2group 2
group 2
 
integrative negotiation
integrative negotiationintegrative negotiation
integrative negotiation
 
som project
som projectsom project
som project
 
Hid fin project
Hid fin projectHid fin project
Hid fin project
 
Hid security analysisproject_201209_final
Hid security analysisproject_201209_finalHid security analysisproject_201209_final
Hid security analysisproject_201209_final
 
Hid finalfinal project
Hid finalfinal projectHid finalfinal project
Hid finalfinal project
 
Hid fiscal policy
Hid fiscal policyHid fiscal policy
Hid fiscal policy
 
Hid penalties and prosecution
Hid penalties and prosecutionHid penalties and prosecution
Hid penalties and prosecution
 
Hid operations strategy
Hid operations strategyHid operations strategy
Hid operations strategy
 
Hid mgcg
Hid mgcgHid mgcg
Hid mgcg
 

Kürzlich hochgeladen

Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...amitlee9823
 
Falcon Invoice Discounting: Empowering Your Business Growth
Falcon Invoice Discounting: Empowering Your Business GrowthFalcon Invoice Discounting: Empowering Your Business Growth
Falcon Invoice Discounting: Empowering Your Business GrowthFalcon investment
 
Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...
Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...
Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...lizamodels9
 
Call Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service NoidaCall Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service Noidadlhescort
 
PHX May 2024 Corporate Presentation Final
PHX May 2024 Corporate Presentation FinalPHX May 2024 Corporate Presentation Final
PHX May 2024 Corporate Presentation FinalPanhandleOilandGas
 
Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...
Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...
Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...Sheetaleventcompany
 
Eluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort Service
Eluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort ServiceEluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort Service
Eluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort ServiceDamini Dixit
 
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)Lundin Gold - Q1 2024 Conference Call Presentation (Revised)
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)Adnet Communications
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...amitlee9823
 
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...rajveerescorts2022
 
Call Girls From Raj Nagar Extension Ghaziabad❤️8448577510 ⊹Best Escorts Servi...
Call Girls From Raj Nagar Extension Ghaziabad❤️8448577510 ⊹Best Escorts Servi...Call Girls From Raj Nagar Extension Ghaziabad❤️8448577510 ⊹Best Escorts Servi...
Call Girls From Raj Nagar Extension Ghaziabad❤️8448577510 ⊹Best Escorts Servi...lizamodels9
 
Falcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investorsFalcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investorsFalcon Invoice Discounting
 
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60% in 6 Months
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60%  in 6 MonthsSEO Case Study: How I Increased SEO Traffic & Ranking by 50-60%  in 6 Months
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60% in 6 MonthsIndeedSEO
 
Business Model Canvas (BMC)- A new venture concept
Business Model Canvas (BMC)-  A new venture conceptBusiness Model Canvas (BMC)-  A new venture concept
Business Model Canvas (BMC)- A new venture conceptP&CO
 
Whitefield CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
Whitefield CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRLWhitefield CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
Whitefield CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRLkapoorjyoti4444
 
Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxWorkforce Group
 
Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st CenturyFamous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Centuryrwgiffor
 
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai KuwaitThe Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwaitdaisycvs
 

Kürzlich hochgeladen (20)

Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
 
Falcon Invoice Discounting: Empowering Your Business Growth
Falcon Invoice Discounting: Empowering Your Business GrowthFalcon Invoice Discounting: Empowering Your Business Growth
Falcon Invoice Discounting: Empowering Your Business Growth
 
Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...
Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...
Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...
 
Call Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service NoidaCall Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service Noida
 
PHX May 2024 Corporate Presentation Final
PHX May 2024 Corporate Presentation FinalPHX May 2024 Corporate Presentation Final
PHX May 2024 Corporate Presentation Final
 
Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...
Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...
Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...
 
Eluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort Service
Eluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort ServiceEluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort Service
Eluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort Service
 
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)Lundin Gold - Q1 2024 Conference Call Presentation (Revised)
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
 
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
 
Call Girls From Raj Nagar Extension Ghaziabad❤️8448577510 ⊹Best Escorts Servi...
Call Girls From Raj Nagar Extension Ghaziabad❤️8448577510 ⊹Best Escorts Servi...Call Girls From Raj Nagar Extension Ghaziabad❤️8448577510 ⊹Best Escorts Servi...
Call Girls From Raj Nagar Extension Ghaziabad❤️8448577510 ⊹Best Escorts Servi...
 
Falcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investorsFalcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investors
 
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60% in 6 Months
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60%  in 6 MonthsSEO Case Study: How I Increased SEO Traffic & Ranking by 50-60%  in 6 Months
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60% in 6 Months
 
Business Model Canvas (BMC)- A new venture concept
Business Model Canvas (BMC)-  A new venture conceptBusiness Model Canvas (BMC)-  A new venture concept
Business Model Canvas (BMC)- A new venture concept
 
Falcon Invoice Discounting platform in india
Falcon Invoice Discounting platform in indiaFalcon Invoice Discounting platform in india
Falcon Invoice Discounting platform in india
 
Whitefield CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
Whitefield CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRLWhitefield CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
Whitefield CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
 
Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptx
 
Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st CenturyFamous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Century
 
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabiunwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
 
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai KuwaitThe Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
 

Fidic law1

  • 1. SUBMITTED BY: ANIL YADAV ASHOK PERSHAD DHIRAJ GAUR MANOJ MUKUL VERMA FIDIC
  • 2. Fédération Internationale Des Ingénieurs-Conseils - FIDIC FIDIC is the French acronym for the International Federation of Consulting Engineers. FIDIC was founded in 1913 to promote the professional interests of the member associations and to disseminate information of interest to members of its component national associations Today FIDIC membership numbers more than 60 countries and represents most of the private practice consulting engineers in the world. Only associations of consulting engineers are eligible for FIDIC membership. During the past half century, the International Federation of Consulting Engineers (FIDIC) has devoted itself to the compilation of management documents for all kinds of projects, among which the FIDIC Conditions of Contract are of the highest influence and are the most popular application.
  • 3. New Edition FIDIC The new models include : FIDIC Conditions of Contract for Construction, the (New Red Book) FIDIC Conditions of Contract for Plant and Design/Build, the (New Yellow Book) FIDIC Conditions of Contract for EPC Turnkey Projects, the (Silver Book) FIDIC Short Form of Contract, the (Green Book) FIDIC Conditions of Contract (new edition) raised a higher requirement to the Parties concerned in the area of contract management 12
  • 4. APPLICATION Applicability under Various Project Delivery and Contracting System:  1. The “New Red Book” can be used in any kind of Engineering Construction Contract.  2. The “New Yellow Book” applies to the lump sum contract project where the Contractor takes participation in the design work.  3. The “Silver Book” applies to the turnkey projects of infrastructures or large-scale factories, where the Contractor takes on more work and risk while the Employer’s participation is small (private financing or government financing), but it is strictly defined upon the investment and construction period.  4. The “Green Book” can be used in all kinds of small-scale projects.  5. Altogether, these four Contract Conditions can be applied to nearly every kind of project, expect for that of managing contracting or simply consulting or designing
  • 5. FIDIC The first edition of FIDIC Conditions of Contract for Works of Civil Engineering Construction (use “Red Book” in the following) was compiled in 1957,and later its second, third, and fourth edition were issued in 1963, 1977, and 1987 respectively.
  • 6. FIDIC With the investigation of the governments, employers, contractors and consulting engineers all over the world about their application of the “Red Book”, 204 findings reports were returned. According to the findings, the FIDIC Contract Committee organized a group of experts to compile the new Contract Condition models to be applied in the 21stcentury.
  • 7. High-quality Provisions and Logical Clause Sequencing:  Compared with the original “Red Book”, the “New Red Book” has163 clauses, nearly 40% being freshly compiled. An additional 40% were modified and given supplements. Only 20% were kept intact. The old edition adopted ICE’s disorderly style bit in the clause sequence, while in the new edition, the related sub-clauses are put into one clause when possible, and convenient to the users.
  • 8. Green Book - Low value, simple works 100%0% Amount of design by Contractor •RisktransfertoContractor •Certaintyofoutturnprice Red Yellow Silver
  • 9. OLD NEW Civil ‘Red Book’ 4th Edition 1987,1992 Construction (mainly) Employer- Design 1999
  • 10. Typical Sequence of dispute Events Envisaged in Clause 20 20.2 Parties appoint the DAB 20.4 A Party refers a dispute to the DAB Parties present submissions to the DAB 20.4 A Party may issue a “notice of dissatisfaction” DAB gives its decision < 28d < 84d < 28d < 56d Amicable Settlement
  • 11. The Parties in a FIDIC Contract
  • 12. The Current (1999) Red Book – Basic Features The Current (1999) Red Book – Basic Features 1. Suitable for all civil works projects where main responsibility for design lies with Employer (or his Engineer). 2. Some design may, of course, be carried out by Contractor. 3. Administration of Contract and supervision by Engineer. 4. Approval of work, payment and claims certified by Engineer. 5. Work done is measured, payment according to Bill of Quantities. 6. Option for payment on lump sum basis. 7. Balanced / fair risk-sharing.
  • 13. More specific provisions concerning the rights & obligations of the contracting parties Taking the clause of Employer’s default as an example, there are 3 points added to the new red book: two of them are concerned with payments. This shows the strict requirement for the employer. However the contractor should institute a quality assurance system and submit to the engineer to audit any aspect of the system before execution. Monthly progress report shall be prepared by contractor to submit to engineer every month, otherwise, payment won’t be given. Any kind of Bribe can result in contractors default. All of the above are high requirements from the contractor.
  • 14. To solve the problem of Back payment using world wide reference Since the problem of Employers financial vacancy or contractor financing are originating world wide, the relative clause and regulations are added into FIDIC condition of contract The employers shall submit within 28 days, after receiving any request from contractor reasonable agreement that financial agreement has been made. If the employer intends to make any significant change to his financial agreement, he shall give notice to contractor with detailed particulars.
  • 15. To Solve the Problem of Back Payment using World Wide Experience for Reference: It is reported that the back payment and debt between the engineering units in China have added up to 280 billion (RMB), which is mostly Employer’s (government included) default to the Contractor. The problem has greatly influenced the construction corporations that their economic strength were weakened. The market needs a legal system to provide a guarantee for free and fair competition.
  • 16.  Since the problems of the Employer’s financial vacancy or Contractor financing are originating worldwide, the relative clauses and regulations are added into FIDIC Conditions of Contract:  Employer’s financial arrangement. The Employer shall submit within 28 days after receiving any request from the Contractor reasonable evidence that financial arrangement has been made. If the Employer intends to make any material change to his financial arrangement, he shall give notice to the Contractor with detailed particulars.  If the Employer fails to execute in accordance with this clause, the Contractor may, after giving a 21 days’ notice to the Employer, suspend the work or reduce production output as a kind of warning; if the Contractor does not receive any reasonable financial arrangement certificate within 42 days after giving the warning, he shall be entitled to terminate the Contract, for it is the Employer’s default. Also the Contractor can get all the compensation earned on the condition of Employer’s default.
  • 17.  Contractor Financed Project’s execution. It is specially set up in the Particular Conditions an Example Provisions for Contractor Finance, which defines that if it is Contractor financing and he has committed to the project, the Employer shall deliver a bank payment guarantee to the Contractor within 28 days after both parties have entered into the Contract Agreement. If the Contractor does not receive the guarantee, the Engineer shall not issue the notice to commence. It is defined in the guarantee that if the Employer fails to make payment in full by the date 14 days after the expiry of the period specified in the contract as that within which such payment should have been made, the Contractor shall been entitled to demand for payment from the bank with a certificate, Contractor’s signatures which must be authenticated by his bankers or by a notary public.