SlideShare ist ein Scribd-Unternehmen logo
1 von 35
6 - Project Time Management
Project Management Training
Created by ejlp12@gmail.com, June 2010
Project Time Management
Knowledge
Area
Process
Initiating Planning Executing
Monitoring &
Control
Closing
Time
Activity Definition
Activity Sequencing
Activity Resource Estimating
Activity Duration Estimating
Schedule Development
Schedule Control
Enter phase/
Start project
Exit phase/
End project
Initiating
Processes
Closing
Processes
Planning
Processes
Executing
Processes
Monitoring &
Controlling Processes
Project Time Management
• The process required to manage timely completion of the project
• Project time management start with planning by the project
management team (not shown as a discrete process)
• In small project, defining & sequencing activities, estimating activity
resource & duration, developing schedule are viewed as a single
process.
6.1 Define Activities
• The process of identifying the specific actions to be performed produce the
project deliverables.
• Work package decomposed into activities (schedule activities)
Inputs
1. Scope baseline
2. Enterprise
environmental factors
3. Organizational process
assets
Tools &
Techniques
1. Decompositions
2. Rolling wave planning
3. Templates
4. Expert judgment
Outputs
1. Activity list
2. Activity attributes
3. Milestone list
In the real word sometime we skip define activities since we take WBS down to the activity level.
This is not a wrong practice but not a PMBOK practice.
Define Activities (Tools & Techniques)
• Rolling Wave Planning: progressive elaboration planning where you do not to plan
activities until you start the project management process for that phase is in the project life
cycle
• Activity Attributes:
– Use for schedule development, selecting, ordering, sorting the planned schedule
activities
– Used to identify e.g. responsible person, place, level of effort (LOE), apportioned effort
(AE)
• Milestone: a significant point or event in the project.
– Not a work activity
– Checkpoint to help control the project
– Additional milestone can be add in Sequence Activities & Develop Schedule process
– The list can indicates the level of milestone (mandatory, optional, etc)
6.2 Sequence Activities
• Process of identifying and documenting relationship among the project
activities
Inputs
1. Activity list
2. Activity attributes
3. Milestone list
4. Project scope statement
5. Organizational process
assets
Tools &
Techniques
1. Precedence
diagramming method
(PDM)
2. Dependency
determination
3. Applying leads and lags
4. Schedule network
templates
Outputs
1. Project schedule
network diagram
2. Project document
updates
Precedence Diagramming Method (PDM)
• Precedence Diagramming Method (PDM) or Activity-on-Node (AON)
– Method used in Critical Path Methodology(CPM)
– No dummy activities
– Logical relationship:
• Finish-to-Start (FS)
• Finish-to-Finish (FF)
• Start-to-Start (SS)
• Start-to-Finish (SF)
Applying Leads & Lags
• Use leads and lags to support realistic and achievable project schedule.
• Each activity is connected at least to one predecessor and one successor except
the start and the end.
• Leads.
– May be added to start an activity before the predecessor activity is complete.
• Lags
– Inserted waiting time between activities
A B C
predecessor Successor
A
B
A
B
Precedence Diagramming Method (PDM)
• Example of PDM which showing logical relationship and leads or lags
• Other method to draw network diagram:
– Arrow Diagramming Method (ADM)
– GERT: allows loops between activities
Dependency Determination
To define sequence among activity, these type of dependency are used:
1. Mandatory (hard logic)
– Inherent in the nature of work being done or required by the contract
– E.g. You must design before you can develop
2. Discretionary (preferred, preferential, or soft logic)
– Define base on knowledge
– Can be changed if needed
– Important when how to shorten or re-sequence the project
3. External
– Based on the need t of the party outside the project
Network diagram
• ≠ PERT chart
• Shows just dependencies (logical relationship)
• Could show the critical path if activity duration estimates added
PERT Âť
PMD
EF = ES + D -1
LS = LF – D +1
Float (F) = LS – ES = LF – EF
ES = Early Start
LS = Latest Start
EF = Early Finish
LF = Late Finish
6.3 Estimate Activity Resources
• Process of estimating the type and quantities of material, people, equipment
or supplies required to perform each activity.
Inputs
1. Activity list
2. Activity attributes
3. Resource Calendars
4. Enterprise
environmental factors
5. Organizational process
assets
Tools &
Techniques
1. Expert judgment
2. Alternatives analysis
3. Published estimating
data
4. Bottom-up estimating
5. Project management
software
Outputs
1. Activity resource
requirements
2. Resource breakdown
structure
3. Project document
updates
Estimate Activity Resource (Tools & Techniques)
• Resource Calendar:
– Information (skill, location, etc) in which resource (people, equipment, material,
etc) are potentially available.
• Published estimating data:
– Use company’s rates
• Bottom up estimating:
– Activity is decomposed to be more confidence in estimating
6.4 Estimate Activity Durations
• Process of approximating the number of work periods to complete
individual activities with estimated resources.
• Schedule shall be as believable and realistic as possible (do not allow padding)
Inputs
1. Activity list
2. Activity attributes
3. Activity resource
requirements
4. Resource Calendars
5. Project scope statement
6. Enterprise
environmental factors
7. Organizational process
assets
Tools &
Techniques
1. Expert judgment
2. Analogous estimating
3. Parametric estimating
4. Three-point estimates
5. Reserve analysis
Outputs
1. Activity duration
estimates
2. Project document
updates
Estimate Activity Durations (Tools & Techniques)
• Analogous Estimating (Top down):
– use actual duration of previous activity (historical) that has similarity
• Parametric Estimating:
– use statistical relationship between historical data and other variables (e.g.
learning curve)
– The result can become heuristics (experience based technique/rule of thumb)
• Reserve analysis (buffer): includes contingency reserves
“A Buffer Isn’t Padding. Padding is extra time added to a schedule that you
don’t really think you need but that you add just to feel confident in the estimate.
Padding is when I take a conventional approach to building a Gantt chart, come
up with three months, but tell my boss four months.”
Mike Cohn – Agile Software Development
• Also called Program Evaluation and Review technique (PERT)
• Use for time and cost estimation
• Expected calculated from Most-likely, Optimistic, Pessimistic
• Range of estimate = EAD (Expected Activity Duration) +/- SD (Standard Deviation)
• Standard deviation cannot be sum.
• Variance used to calculate total SD of the project
3-Points Estimate (PERT)
Expected
6
Ο4ΜP 
Standard
Deviation
6
ΟP
Variance





 
6
ΟP 2
 varianceSD
Exercise: Tree-point estimates (PERT)
Activity
Duration Expected
Duration
(PERT)
Activity
Standard
Deviation
Variance
range
Range of
the estimate
P M O
A 3 5 1
B 8 4 2
C 15 8 5
D 20 10 5
Project (Total) -
Exercise: PERT - Most tricky question
• Together with your team, you applied three-point estimation on a Critical path
which consists of two activities.
The following duration uncertainties are all calculated assuming a Âą3 sigma
Confidence interval.
The duration uncertainty—defined as pessimistic minus optimistic estimate—of the
first activity is 18 days; the second estimate has an uncertainty of 24 days.
Applying the PERT formula for paths, what is the duration uncertainty of the entire
path?
A. 21 days
B. 30 days
C. 42 days
D. No statement is possible from the information given.
Exercise: PERT - Most tricky question (Answer)
• See that the question says that Duration Uncertainty is Pessimistic minus Optimistic in other
words P-O. We know that SD is (P-O ) / 6 , thus SD is "duration Certainty " / 6
Thus
For Path 1 : SD = 18/6 = 3
Variance = 3*3 = 9
For path 2 : SD = 24 /6 = 4
Variance = 4*4 = 16
Total Path Variance = 16 + 9 = 25
Sqrt (25) = 5
Meaning (P-O) / 6 = 5
(p-O) = 5 * 6
DURATION UNCERTAINTY = 30
6.5 Develop Schedule
• Process of analyzing activity sequences, durations, resource requirements,
and schedule constraints to create the project schedule.
Inputs
1. Activity list
2. Activity attributes
3. Project schedule
network diagram
4. Activity resource
requirements
5. Resource Calendars
6. Activity duration
estimates
7. Project scope statement
8. Enterprise
environmental factors
9. Organizational process
assets
Tools &
Techniques
1. Schedule network
analysis
2. Critical path method
3. Critical chain method
4. Resource leveling
5. What-if scenario
analysis
6. Applying leads and lags
7. Schedule compression
8. Scheduling tool
Outputs
1. Project schedule
2. Schedule baseline
3. Schedule data
4. Project document
updates
Critical Path
• Critical Path is the longest duration path
• Identify the shortest time needed to complete a project
• There can be more than one critical path
• We don’t want critical path, it increase risk
• Don’t leave a project with a negative float, you would compress the schedule
• Near-critical path is the path that has close in duration to critical path
• Float (Slack)
– Total float: the amount of time an activity can be delayed without delaying the
project end date or intermediary milestone.
– Free float: the amount of time an activity can be delayed without delaying the
early start date of its successor(s).
– Project float: the amount of time an activity can be delayed without delaying the
externally imposed project completion date required by customer/management.
Critical Path Method Basic
Activity Precedence Duration
A 2
B 3
C A 1
D B 4
E B 2
F C 1
G D,F 5
H E 2
I H 2
J G,I 0
K
• Dummy activity = 0 resource & 0 duration
• Critical activities
- all activities in the critical path
- Delay in the completion of these activities will lengthen the project
timescale
- Has float = 0
Critical Path using PDM
Calculation
• Forward Pass:
• ES + D = ES(successor)
• use highest value on join
• Backward Pass:
• LS – D (predecessor) = LS (predecessor)
• Use lowest value on join
Forward Pass
Backward Pass
Exercise
Questions:
• What is the critical path?
• What is critical path duration?
• What is float (slack) duration of activity A30?
Answers:
• -
• -
• -
• The longest duration path through the project considering both activity
dependencies and resource constraints.
• Network diagram and critical path are identified first
• Type of buffers
– Project buffer
– Feeding buffer
– Resource buffer
Critical Chain (Buffer Management) Method
• Analysis on effect of changes on a particular thing (assumption) on the
project which make activity duration change.
• Monte Carlo Simulation
Used when there is possibility that the critical path will be different
for a given set of project conditions.
– Using probability distribution for each activity or group of activities
– Using computer software
– Using three-point estimates and network diagram
– Help deal with “path convergence”
• Multiple paths converge into one or more activities (but adding risk)
What-if Scenario Analysis
• Fast Tracking
– Performing critical path activities in parallel.
– Usually increase risk and requires more attention to communication.
– May need a rework.
– E.g. Design is half finished and start coding.
• Crashing
– Analyze cost and schedule trade-offs.
– Determine most compression for least cost.
– Crash the tasks that cost the least first, focusing on minimizing project cost.
– Always results in increased cost.
Schedule Compression
Project Schedule
• Schedule can be shown with or without dependencies (logical
relationship).
• Presented as
– Summary form e.g. Master Schedule, Milestone schedule
– Detailed form
• Format:
– Network diagram
– Milestone chart
– Bar chart (Gantt chart)
Schedule Data
• Includes at least:
– Schedule milestone
– Schedule activities
– Activity attributes
– Assumptions & Constraints
• Additional information can be added, such as
– Resource histograms
– Cash-flow projections
– Order & delivery schedules
– Alternative schedules
6.6 Control Schedule
• Process of analyzing activity sequences, durations, resource requirements,
and schedule constraints to create the project schedule.
Inputs
1. Project Management
Plan
2. Project Schedule
3. Work performance
information
4. Organizational process
assets
Tools &
Techniques
1. Performance reviews
2. Variance Analysis
3. Project Management
Software
4. Resource leveling
5. What-if scenario
analysis
6. Adjusting leads & lags
7. Schedule compression
8. Schedule tooling
Outputs
1. Work performance
measurements
2. Organizational process
assets updates
3. Change requests
4. Project management
plan updates
5. Project document
updates
Thank You
Next topic:
Project Cost Management

Weitere ähnliche Inhalte

Was ist angesagt?

PMP Training - 10 project communication management
PMP Training - 10 project communication managementPMP Training - 10 project communication management
PMP Training - 10 project communication managementejlp12
 
PMP Training - 06 project time management2
PMP Training - 06 project time management2PMP Training - 06 project time management2
PMP Training - 06 project time management2ejlp12
 
Project Management Presentation material
Project Management Presentation material Project Management Presentation material
Project Management Presentation material Abdel Rahman okasha
 
5. project activity and risk planning
5. project activity and risk planning5. project activity and risk planning
5. project activity and risk planningJeanette C. Patindol
 
The Project Management Process - Week 9 Performance Management
The Project Management Process - Week 9   Performance ManagementThe Project Management Process - Week 9   Performance Management
The Project Management Process - Week 9 Performance ManagementCraig Brown
 
Project Schedule Management - Sequence Activities - PMP Workgroup
Project Schedule Management - Sequence Activities - PMP WorkgroupProject Schedule Management - Sequence Activities - PMP Workgroup
Project Schedule Management - Sequence Activities - PMP WorkgroupTÚng Trần Thanh
 
project planning-estimation
project planning-estimationproject planning-estimation
project planning-estimationReetesh Gupta
 
Project Planning And Controlling
Project Planning And ControllingProject Planning And Controlling
Project Planning And ControllingGiancarlo Berner
 
Project management master class karin rheeder
Project management master class   karin rheederProject management master class   karin rheeder
Project management master class karin rheederKarin Rheeder
 
Project Resource Management - PMBOK6
Project Resource Management - PMBOK6Project Resource Management - PMBOK6
Project Resource Management - PMBOK6Agus Suhanto
 
Project management
Project managementProject management
Project managementtwilight89
 
Triple Constraints of Projects: Scope, Cost & Schedule
Triple Constraints of Projects: Scope, Cost & ScheduleTriple Constraints of Projects: Scope, Cost & Schedule
Triple Constraints of Projects: Scope, Cost & Scheduleshofiulalom
 
Selecting the Right Project Management Software
Selecting the Right Project Management SoftwareSelecting the Right Project Management Software
Selecting the Right Project Management SoftwareMohammad Ashraf Khan, PMP
 

Was ist angesagt? (20)

PMP Training - 10 project communication management
PMP Training - 10 project communication managementPMP Training - 10 project communication management
PMP Training - 10 project communication management
 
5. PMP Training - Time management
5. PMP Training - Time management5. PMP Training - Time management
5. PMP Training - Time management
 
PMP Training - 06 project time management2
PMP Training - 06 project time management2PMP Training - 06 project time management2
PMP Training - 06 project time management2
 
Project Management Presentation material
Project Management Presentation material Project Management Presentation material
Project Management Presentation material
 
04 project integration management
04 project integration management04 project integration management
04 project integration management
 
Pmp time chapter 6
Pmp time chapter 6Pmp time chapter 6
Pmp time chapter 6
 
5. project activity and risk planning
5. project activity and risk planning5. project activity and risk planning
5. project activity and risk planning
 
Introduction to schedule management
Introduction to schedule managementIntroduction to schedule management
Introduction to schedule management
 
The Project Management Process - Week 9 Performance Management
The Project Management Process - Week 9   Performance ManagementThe Project Management Process - Week 9   Performance Management
The Project Management Process - Week 9 Performance Management
 
PMBoK6Ed.lect1.introduction
PMBoK6Ed.lect1.introductionPMBoK6Ed.lect1.introduction
PMBoK6Ed.lect1.introduction
 
Project Schedule Management - Sequence Activities - PMP Workgroup
Project Schedule Management - Sequence Activities - PMP WorkgroupProject Schedule Management - Sequence Activities - PMP Workgroup
Project Schedule Management - Sequence Activities - PMP Workgroup
 
project planning-estimation
project planning-estimationproject planning-estimation
project planning-estimation
 
Project Planning And Controlling
Project Planning And ControllingProject Planning And Controlling
Project Planning And Controlling
 
Project management master class karin rheeder
Project management master class   karin rheederProject management master class   karin rheeder
Project management master class karin rheeder
 
Project Resource Management - PMBOK6
Project Resource Management - PMBOK6Project Resource Management - PMBOK6
Project Resource Management - PMBOK6
 
Project planning and control
Project planning and controlProject planning and control
Project planning and control
 
Project management
Project managementProject management
Project management
 
Triple Constraints of Projects: Scope, Cost & Schedule
Triple Constraints of Projects: Scope, Cost & ScheduleTriple Constraints of Projects: Scope, Cost & Schedule
Triple Constraints of Projects: Scope, Cost & Schedule
 
Selecting the Right Project Management Software
Selecting the Right Project Management SoftwareSelecting the Right Project Management Software
Selecting the Right Project Management Software
 
06 project time management m
06 project time management m06 project time management m
06 project time management m
 

Andere mochten auch

04 projectintegrationmanagement
04 projectintegrationmanagement04 projectintegrationmanagement
04 projectintegrationmanagementDhamo daran
 
PMP Exam Preparation Course: 05 Project Time Management
PMP Exam Preparation Course: 05 Project Time ManagementPMP Exam Preparation Course: 05 Project Time Management
PMP Exam Preparation Course: 05 Project Time ManagementB M Shahrier Majumder, PMP, CSM
 
PMP Exam Preparation Course: 01 Project Management Framework
PMP Exam Preparation Course: 01 Project Management FrameworkPMP Exam Preparation Course: 01 Project Management Framework
PMP Exam Preparation Course: 01 Project Management FrameworkB M Shahrier Majumder, PMP, CSM
 
09 projecthumanresourcemanagement
09 projecthumanresourcemanagement09 projecthumanresourcemanagement
09 projecthumanresourcemanagementDhamo daran
 
12 projectprocurementmanagement
12 projectprocurementmanagement12 projectprocurementmanagement
12 projectprocurementmanagementDhamo daran
 
PMP Preparation 1 - Framework
PMP Preparation 1 - FrameworkPMP Preparation 1 - Framework
PMP Preparation 1 - FrameworkAndrew Mikityuk
 
13 project control & closing management
13 project control & closing management13 project control & closing management
13 project control & closing managementDhamo daran
 
04 projectintegrationmanagement
04 projectintegrationmanagement04 projectintegrationmanagement
04 projectintegrationmanagementDhamo daran
 
10 projectcommunicationmanagement
10 projectcommunicationmanagement10 projectcommunicationmanagement
10 projectcommunicationmanagementDhamo daran
 
Projectriskmanagement pmbok5
Projectriskmanagement pmbok5Projectriskmanagement pmbok5
Projectriskmanagement pmbok5Dhamo daran
 
Project initiating and planning
Project initiating and planningProject initiating and planning
Project initiating and planningSaad Al Jabri
 
Project Procurment Management
Project Procurment ManagementProject Procurment Management
Project Procurment ManagementSaad Al Jabri
 
01 introductiontoframework
01 introductiontoframework01 introductiontoframework
01 introductiontoframeworkDhamo daran
 
Project communication management
Project communication managementProject communication management
Project communication managementSaad Al Jabri
 
PMP Prep 3 - Project Integration Management
PMP Prep 3 - Project Integration ManagementPMP Prep 3 - Project Integration Management
PMP Prep 3 - Project Integration ManagementAndrew Mikityuk
 
Online PMP Training Material for PMP Exam - Quality Management Knowledge Area
Online PMP Training Material for PMP Exam - Quality Management Knowledge AreaOnline PMP Training Material for PMP Exam - Quality Management Knowledge Area
Online PMP Training Material for PMP Exam - Quality Management Knowledge AreaGlobalSkillup
 

Andere mochten auch (20)

04 projectintegrationmanagement
04 projectintegrationmanagement04 projectintegrationmanagement
04 projectintegrationmanagement
 
PMP Exam Preparation Course: 05 Project Time Management
PMP Exam Preparation Course: 05 Project Time ManagementPMP Exam Preparation Course: 05 Project Time Management
PMP Exam Preparation Course: 05 Project Time Management
 
PMP Exam Preparation Course: 01 Project Management Framework
PMP Exam Preparation Course: 01 Project Management FrameworkPMP Exam Preparation Course: 01 Project Management Framework
PMP Exam Preparation Course: 01 Project Management Framework
 
09 projecthumanresourcemanagement
09 projecthumanresourcemanagement09 projecthumanresourcemanagement
09 projecthumanresourcemanagement
 
12 projectprocurementmanagement
12 projectprocurementmanagement12 projectprocurementmanagement
12 projectprocurementmanagement
 
PMP Preparation 1 - Framework
PMP Preparation 1 - FrameworkPMP Preparation 1 - Framework
PMP Preparation 1 - Framework
 
13 project control & closing management
13 project control & closing management13 project control & closing management
13 project control & closing management
 
04 projectintegrationmanagement
04 projectintegrationmanagement04 projectintegrationmanagement
04 projectintegrationmanagement
 
10 projectcommunicationmanagement
10 projectcommunicationmanagement10 projectcommunicationmanagement
10 projectcommunicationmanagement
 
Project time management 1 final
Project time management 1 finalProject time management 1 final
Project time management 1 final
 
Chap013
Chap013Chap013
Chap013
 
Projectriskmanagement pmbok5
Projectriskmanagement pmbok5Projectriskmanagement pmbok5
Projectriskmanagement pmbok5
 
Project initiating and planning
Project initiating and planningProject initiating and planning
Project initiating and planning
 
Project Procurment Management
Project Procurment ManagementProject Procurment Management
Project Procurment Management
 
01 introductiontoframework
01 introductiontoframework01 introductiontoframework
01 introductiontoframework
 
Project communication management
Project communication managementProject communication management
Project communication management
 
Project cost management
Project cost managementProject cost management
Project cost management
 
PMP Prep 3 - Project Integration Management
PMP Prep 3 - Project Integration ManagementPMP Prep 3 - Project Integration Management
PMP Prep 3 - Project Integration Management
 
Online PMP Training Material for PMP Exam - Quality Management Knowledge Area
Online PMP Training Material for PMP Exam - Quality Management Knowledge AreaOnline PMP Training Material for PMP Exam - Quality Management Knowledge Area
Online PMP Training Material for PMP Exam - Quality Management Knowledge Area
 
07 project cost management
07 project cost management07 project cost management
07 project cost management
 

Ähnlich wie 06 projecttimemanagement

Topic 11 - Project Schedule Management.pdf
Topic 11 - Project Schedule Management.pdfTopic 11 - Project Schedule Management.pdf
Topic 11 - Project Schedule Management.pdfHuyNguyen657394
 
TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5Hisham Ali,PMP
 
Project Management: Project Schedule Management Knowledge Area
Project Management: Project Schedule Management Knowledge AreaProject Management: Project Schedule Management Knowledge Area
Project Management: Project Schedule Management Knowledge AreaJoshua Render
 
Day 3 Schedule -walaa (3).pptx
Day 3 Schedule -walaa (3).pptxDay 3 Schedule -walaa (3).pptx
Day 3 Schedule -walaa (3).pptxMohanadRabea1
 
PMP Muzette Charles_Spring2019_Week3_Chapter6
PMP Muzette Charles_Spring2019_Week3_Chapter6PMP Muzette Charles_Spring2019_Week3_Chapter6
PMP Muzette Charles_Spring2019_Week3_Chapter6Muzette Charles, PMP
 
ABCs Of Project Time Management Planning Slides
ABCs Of Project Time Management Planning SlidesABCs Of Project Time Management Planning Slides
ABCs Of Project Time Management Planning SlidesYousef Abugosh, PMP, MA
 
Project-Time-Line.pdf
Project-Time-Line.pdfProject-Time-Line.pdf
Project-Time-Line.pdfNabeel Ahmad
 
AWIN presentation it's only logical-a scheduling overview
AWIN presentation it's only logical-a scheduling overviewAWIN presentation it's only logical-a scheduling overview
AWIN presentation it's only logical-a scheduling overviewDanielle Murphy
 
Software Engineering (Project Scheduling)
Software Engineering (Project Scheduling)Software Engineering (Project Scheduling)
Software Engineering (Project Scheduling)ShudipPal
 
A brief on project time management
A brief on project time managementA brief on project time management
A brief on project time managementImran Jamil
 
Time management pressent
Time management pressentTime management pressent
Time management pressentiklil fairuz
 
Time --updated 60b084af4f5af-
Time --updated 60b084af4f5af-Time --updated 60b084af4f5af-
Time --updated 60b084af4f5af-seminiMaya
 
Managing the information system project
Managing the information system projectManaging the information system project
Managing the information system projectalpha1unity
 
Managing the information system project
Managing the information system projectManaging the information system project
Managing the information system projecta23ccb
 
Time Management within IT Project Management
Time Management within IT Project ManagementTime Management within IT Project Management
Time Management within IT Project Managementrielaantonio
 

Ähnlich wie 06 projecttimemanagement (20)

Topic 11 - Project Schedule Management.pdf
Topic 11 - Project Schedule Management.pdfTopic 11 - Project Schedule Management.pdf
Topic 11 - Project Schedule Management.pdf
 
TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5
 
Time management
Time managementTime management
Time management
 
Session 8 4th edition PMP
Session 8 4th edition PMPSession 8 4th edition PMP
Session 8 4th edition PMP
 
CAPM Week 2 Chapter 6
CAPM Week 2 Chapter 6CAPM Week 2 Chapter 6
CAPM Week 2 Chapter 6
 
Project Management: Project Schedule Management Knowledge Area
Project Management: Project Schedule Management Knowledge AreaProject Management: Project Schedule Management Knowledge Area
Project Management: Project Schedule Management Knowledge Area
 
Day 3 Schedule -walaa (3).pptx
Day 3 Schedule -walaa (3).pptxDay 3 Schedule -walaa (3).pptx
Day 3 Schedule -walaa (3).pptx
 
PMP Muzette Charles_Spring2019_Week3_Chapter6
PMP Muzette Charles_Spring2019_Week3_Chapter6PMP Muzette Charles_Spring2019_Week3_Chapter6
PMP Muzette Charles_Spring2019_Week3_Chapter6
 
ABCs Of Project Time Management Planning Slides
ABCs Of Project Time Management Planning SlidesABCs Of Project Time Management Planning Slides
ABCs Of Project Time Management Planning Slides
 
4) PTM & PCM .pptx
4) PTM & PCM .pptx4) PTM & PCM .pptx
4) PTM & PCM .pptx
 
Project-Time-Line.pdf
Project-Time-Line.pdfProject-Time-Line.pdf
Project-Time-Line.pdf
 
AWIN presentation it's only logical-a scheduling overview
AWIN presentation it's only logical-a scheduling overviewAWIN presentation it's only logical-a scheduling overview
AWIN presentation it's only logical-a scheduling overview
 
Software Engineering (Project Scheduling)
Software Engineering (Project Scheduling)Software Engineering (Project Scheduling)
Software Engineering (Project Scheduling)
 
A brief on project time management
A brief on project time managementA brief on project time management
A brief on project time management
 
Session 5 4th edition PMP
Session 5 4th edition PMPSession 5 4th edition PMP
Session 5 4th edition PMP
 
Time management pressent
Time management pressentTime management pressent
Time management pressent
 
Time --updated 60b084af4f5af-
Time --updated 60b084af4f5af-Time --updated 60b084af4f5af-
Time --updated 60b084af4f5af-
 
Managing the information system project
Managing the information system projectManaging the information system project
Managing the information system project
 
Managing the information system project
Managing the information system projectManaging the information system project
Managing the information system project
 
Time Management within IT Project Management
Time Management within IT Project ManagementTime Management within IT Project Management
Time Management within IT Project Management
 

Mehr von Dhamo daran

Mehr von Dhamo daran (19)

Chap021
Chap021Chap021
Chap021
 
Chap020
Chap020Chap020
Chap020
 
Chap019
Chap019Chap019
Chap019
 
Chap018
Chap018Chap018
Chap018
 
Chap017
Chap017Chap017
Chap017
 
Chap016
Chap016Chap016
Chap016
 
Chap015
Chap015Chap015
Chap015
 
Chap014
Chap014Chap014
Chap014
 
Chap012
Chap012Chap012
Chap012
 
Chap011
Chap011Chap011
Chap011
 
Chap010
Chap010Chap010
Chap010
 
Chap009
Chap009Chap009
Chap009
 
Chap008
Chap008Chap008
Chap008
 
Chap007
Chap007Chap007
Chap007
 
Chap006
Chap006Chap006
Chap006
 
Chap005
Chap005Chap005
Chap005
 
Chap004
Chap004Chap004
Chap004
 
Chap003
Chap003Chap003
Chap003
 
Chap002
Chap002Chap002
Chap002
 

KĂźrzlich hochgeladen

ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITYISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITYKayeClaireEstoconing
 
FILIPINO PSYCHology sikolohiyang pilipino
FILIPINO PSYCHology sikolohiyang pilipinoFILIPINO PSYCHology sikolohiyang pilipino
FILIPINO PSYCHology sikolohiyang pilipinojohnmickonozaleda
 
Proudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxProudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxthorishapillay1
 
Choosing the Right CBSE School A Comprehensive Guide for Parents
Choosing the Right CBSE School A Comprehensive Guide for ParentsChoosing the Right CBSE School A Comprehensive Guide for Parents
Choosing the Right CBSE School A Comprehensive Guide for Parentsnavabharathschool99
 
AUDIENCE THEORY -CULTIVATION THEORY - GERBNER.pptx
AUDIENCE THEORY -CULTIVATION THEORY -  GERBNER.pptxAUDIENCE THEORY -CULTIVATION THEORY -  GERBNER.pptx
AUDIENCE THEORY -CULTIVATION THEORY - GERBNER.pptxiammrhaywood
 
How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17Celine George
 
Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17Celine George
 
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTSGRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTSJoshuaGantuangco2
 
4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptx4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptxmary850239
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Transaction Management in Database Management System
Transaction Management in Database Management SystemTransaction Management in Database Management System
Transaction Management in Database Management SystemChristalin Nelson
 
Karra SKD Conference Presentation Revised.pptx
Karra SKD Conference Presentation Revised.pptxKarra SKD Conference Presentation Revised.pptx
Karra SKD Conference Presentation Revised.pptxAshokKarra1
 
Concurrency Control in Database Management system
Concurrency Control in Database Management systemConcurrency Control in Database Management system
Concurrency Control in Database Management systemChristalin Nelson
 
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...Nguyen Thanh Tu Collection
 
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdfInclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdfTechSoup
 
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATIONTHEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATIONHumphrey A BeĂąa
 
Student Profile Sample - We help schools to connect the data they have, with ...
Student Profile Sample - We help schools to connect the data they have, with ...Student Profile Sample - We help schools to connect the data they have, with ...
Student Profile Sample - We help schools to connect the data they have, with ...SeĂĄn Kennedy
 
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptxINTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptxHumphrey A BeĂąa
 
What is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPWhat is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPCeline George
 

KĂźrzlich hochgeladen (20)

ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITYISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
 
FILIPINO PSYCHology sikolohiyang pilipino
FILIPINO PSYCHology sikolohiyang pilipinoFILIPINO PSYCHology sikolohiyang pilipino
FILIPINO PSYCHology sikolohiyang pilipino
 
Proudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxProudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptx
 
Choosing the Right CBSE School A Comprehensive Guide for Parents
Choosing the Right CBSE School A Comprehensive Guide for ParentsChoosing the Right CBSE School A Comprehensive Guide for Parents
Choosing the Right CBSE School A Comprehensive Guide for Parents
 
AUDIENCE THEORY -CULTIVATION THEORY - GERBNER.pptx
AUDIENCE THEORY -CULTIVATION THEORY -  GERBNER.pptxAUDIENCE THEORY -CULTIVATION THEORY -  GERBNER.pptx
AUDIENCE THEORY -CULTIVATION THEORY - GERBNER.pptx
 
How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17
 
Raw materials used in Herbal Cosmetics.pptx
Raw materials used in Herbal Cosmetics.pptxRaw materials used in Herbal Cosmetics.pptx
Raw materials used in Herbal Cosmetics.pptx
 
Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17
 
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTSGRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
 
4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptx4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptx
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
 
Transaction Management in Database Management System
Transaction Management in Database Management SystemTransaction Management in Database Management System
Transaction Management in Database Management System
 
Karra SKD Conference Presentation Revised.pptx
Karra SKD Conference Presentation Revised.pptxKarra SKD Conference Presentation Revised.pptx
Karra SKD Conference Presentation Revised.pptx
 
Concurrency Control in Database Management system
Concurrency Control in Database Management systemConcurrency Control in Database Management system
Concurrency Control in Database Management system
 
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
 
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdfInclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
 
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATIONTHEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
 
Student Profile Sample - We help schools to connect the data they have, with ...
Student Profile Sample - We help schools to connect the data they have, with ...Student Profile Sample - We help schools to connect the data they have, with ...
Student Profile Sample - We help schools to connect the data they have, with ...
 
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptxINTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
 
What is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPWhat is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERP
 

06 projecttimemanagement

  • 1. 6 - Project Time Management Project Management Training Created by ejlp12@gmail.com, June 2010
  • 2. Project Time Management Knowledge Area Process Initiating Planning Executing Monitoring & Control Closing Time Activity Definition Activity Sequencing Activity Resource Estimating Activity Duration Estimating Schedule Development Schedule Control Enter phase/ Start project Exit phase/ End project Initiating Processes Closing Processes Planning Processes Executing Processes Monitoring & Controlling Processes
  • 3. Project Time Management • The process required to manage timely completion of the project • Project time management start with planning by the project management team (not shown as a discrete process) • In small project, defining & sequencing activities, estimating activity resource & duration, developing schedule are viewed as a single process.
  • 4. 6.1 Define Activities • The process of identifying the specific actions to be performed produce the project deliverables. • Work package decomposed into activities (schedule activities) Inputs 1. Scope baseline 2. Enterprise environmental factors 3. Organizational process assets Tools & Techniques 1. Decompositions 2. Rolling wave planning 3. Templates 4. Expert judgment Outputs 1. Activity list 2. Activity attributes 3. Milestone list In the real word sometime we skip define activities since we take WBS down to the activity level. This is not a wrong practice but not a PMBOK practice.
  • 5. Define Activities (Tools & Techniques) • Rolling Wave Planning: progressive elaboration planning where you do not to plan activities until you start the project management process for that phase is in the project life cycle • Activity Attributes: – Use for schedule development, selecting, ordering, sorting the planned schedule activities – Used to identify e.g. responsible person, place, level of effort (LOE), apportioned effort (AE) • Milestone: a significant point or event in the project. – Not a work activity – Checkpoint to help control the project – Additional milestone can be add in Sequence Activities & Develop Schedule process – The list can indicates the level of milestone (mandatory, optional, etc)
  • 6. 6.2 Sequence Activities • Process of identifying and documenting relationship among the project activities Inputs 1. Activity list 2. Activity attributes 3. Milestone list 4. Project scope statement 5. Organizational process assets Tools & Techniques 1. Precedence diagramming method (PDM) 2. Dependency determination 3. Applying leads and lags 4. Schedule network templates Outputs 1. Project schedule network diagram 2. Project document updates
  • 7. Precedence Diagramming Method (PDM) • Precedence Diagramming Method (PDM) or Activity-on-Node (AON) – Method used in Critical Path Methodology(CPM) – No dummy activities – Logical relationship: • Finish-to-Start (FS) • Finish-to-Finish (FF) • Start-to-Start (SS) • Start-to-Finish (SF)
  • 8. Applying Leads & Lags • Use leads and lags to support realistic and achievable project schedule. • Each activity is connected at least to one predecessor and one successor except the start and the end. • Leads. – May be added to start an activity before the predecessor activity is complete. • Lags – Inserted waiting time between activities A B C predecessor Successor A B A B
  • 9. Precedence Diagramming Method (PDM) • Example of PDM which showing logical relationship and leads or lags • Other method to draw network diagram: – Arrow Diagramming Method (ADM) – GERT: allows loops between activities
  • 10. Dependency Determination To define sequence among activity, these type of dependency are used: 1. Mandatory (hard logic) – Inherent in the nature of work being done or required by the contract – E.g. You must design before you can develop 2. Discretionary (preferred, preferential, or soft logic) – Define base on knowledge – Can be changed if needed – Important when how to shorten or re-sequence the project 3. External – Based on the need t of the party outside the project Network diagram • ≠ PERT chart • Shows just dependencies (logical relationship) • Could show the critical path if activity duration estimates added PERT Âť
  • 11. PMD EF = ES + D -1 LS = LF – D +1 Float (F) = LS – ES = LF – EF ES = Early Start LS = Latest Start EF = Early Finish LF = Late Finish
  • 12. 6.3 Estimate Activity Resources • Process of estimating the type and quantities of material, people, equipment or supplies required to perform each activity. Inputs 1. Activity list 2. Activity attributes 3. Resource Calendars 4. Enterprise environmental factors 5. Organizational process assets Tools & Techniques 1. Expert judgment 2. Alternatives analysis 3. Published estimating data 4. Bottom-up estimating 5. Project management software Outputs 1. Activity resource requirements 2. Resource breakdown structure 3. Project document updates
  • 13. Estimate Activity Resource (Tools & Techniques) • Resource Calendar: – Information (skill, location, etc) in which resource (people, equipment, material, etc) are potentially available. • Published estimating data: – Use company’s rates • Bottom up estimating: – Activity is decomposed to be more confidence in estimating
  • 14. 6.4 Estimate Activity Durations • Process of approximating the number of work periods to complete individual activities with estimated resources. • Schedule shall be as believable and realistic as possible (do not allow padding) Inputs 1. Activity list 2. Activity attributes 3. Activity resource requirements 4. Resource Calendars 5. Project scope statement 6. Enterprise environmental factors 7. Organizational process assets Tools & Techniques 1. Expert judgment 2. Analogous estimating 3. Parametric estimating 4. Three-point estimates 5. Reserve analysis Outputs 1. Activity duration estimates 2. Project document updates
  • 15. Estimate Activity Durations (Tools & Techniques) • Analogous Estimating (Top down): – use actual duration of previous activity (historical) that has similarity • Parametric Estimating: – use statistical relationship between historical data and other variables (e.g. learning curve) – The result can become heuristics (experience based technique/rule of thumb) • Reserve analysis (buffer): includes contingency reserves “A Buffer Isn’t Padding. Padding is extra time added to a schedule that you don’t really think you need but that you add just to feel confident in the estimate. Padding is when I take a conventional approach to building a Gantt chart, come up with three months, but tell my boss four months.” Mike Cohn – Agile Software Development
  • 16. • Also called Program Evaluation and Review technique (PERT) • Use for time and cost estimation • Expected calculated from Most-likely, Optimistic, Pessimistic • Range of estimate = EAD (Expected Activity Duration) +/- SD (Standard Deviation) • Standard deviation cannot be sum. • Variance used to calculate total SD of the project 3-Points Estimate (PERT) Expected 6 Ο4ΜP  Standard Deviation 6 ΟP Variance        6 ΟP 2  varianceSD
  • 17. Exercise: Tree-point estimates (PERT) Activity Duration Expected Duration (PERT) Activity Standard Deviation Variance range Range of the estimate P M O A 3 5 1 B 8 4 2 C 15 8 5 D 20 10 5 Project (Total) -
  • 18. Exercise: PERT - Most tricky question • Together with your team, you applied three-point estimation on a Critical path which consists of two activities. The following duration uncertainties are all calculated assuming a Âą3 sigma Confidence interval. The duration uncertainty—defined as pessimistic minus optimistic estimate—of the first activity is 18 days; the second estimate has an uncertainty of 24 days. Applying the PERT formula for paths, what is the duration uncertainty of the entire path? A. 21 days B. 30 days C. 42 days D. No statement is possible from the information given.
  • 19. Exercise: PERT - Most tricky question (Answer) • See that the question says that Duration Uncertainty is Pessimistic minus Optimistic in other words P-O. We know that SD is (P-O ) / 6 , thus SD is "duration Certainty " / 6 Thus For Path 1 : SD = 18/6 = 3 Variance = 3*3 = 9 For path 2 : SD = 24 /6 = 4 Variance = 4*4 = 16 Total Path Variance = 16 + 9 = 25 Sqrt (25) = 5 Meaning (P-O) / 6 = 5 (p-O) = 5 * 6 DURATION UNCERTAINTY = 30
  • 20. 6.5 Develop Schedule • Process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule. Inputs 1. Activity list 2. Activity attributes 3. Project schedule network diagram 4. Activity resource requirements 5. Resource Calendars 6. Activity duration estimates 7. Project scope statement 8. Enterprise environmental factors 9. Organizational process assets Tools & Techniques 1. Schedule network analysis 2. Critical path method 3. Critical chain method 4. Resource leveling 5. What-if scenario analysis 6. Applying leads and lags 7. Schedule compression 8. Scheduling tool Outputs 1. Project schedule 2. Schedule baseline 3. Schedule data 4. Project document updates
  • 21. Critical Path • Critical Path is the longest duration path • Identify the shortest time needed to complete a project • There can be more than one critical path • We don’t want critical path, it increase risk • Don’t leave a project with a negative float, you would compress the schedule • Near-critical path is the path that has close in duration to critical path • Float (Slack) – Total float: the amount of time an activity can be delayed without delaying the project end date or intermediary milestone. – Free float: the amount of time an activity can be delayed without delaying the early start date of its successor(s). – Project float: the amount of time an activity can be delayed without delaying the externally imposed project completion date required by customer/management.
  • 22. Critical Path Method Basic Activity Precedence Duration A 2 B 3 C A 1 D B 4 E B 2 F C 1 G D,F 5 H E 2 I H 2 J G,I 0 K • Dummy activity = 0 resource & 0 duration • Critical activities - all activities in the critical path - Delay in the completion of these activities will lengthen the project timescale - Has float = 0
  • 23. Critical Path using PDM Calculation • Forward Pass: • ES + D = ES(successor) • use highest value on join • Backward Pass: • LS – D (predecessor) = LS (predecessor) • Use lowest value on join Forward Pass Backward Pass
  • 24. Exercise Questions: • What is the critical path? • What is critical path duration? • What is float (slack) duration of activity A30? Answers: • - • - • -
  • 25. • The longest duration path through the project considering both activity dependencies and resource constraints. • Network diagram and critical path are identified first • Type of buffers – Project buffer – Feeding buffer – Resource buffer Critical Chain (Buffer Management) Method
  • 26.
  • 27.
  • 28.
  • 29.
  • 30. • Analysis on effect of changes on a particular thing (assumption) on the project which make activity duration change. • Monte Carlo Simulation Used when there is possibility that the critical path will be different for a given set of project conditions. – Using probability distribution for each activity or group of activities – Using computer software – Using three-point estimates and network diagram – Help deal with “path convergence” • Multiple paths converge into one or more activities (but adding risk) What-if Scenario Analysis
  • 31. • Fast Tracking – Performing critical path activities in parallel. – Usually increase risk and requires more attention to communication. – May need a rework. – E.g. Design is half finished and start coding. • Crashing – Analyze cost and schedule trade-offs. – Determine most compression for least cost. – Crash the tasks that cost the least first, focusing on minimizing project cost. – Always results in increased cost. Schedule Compression
  • 32. Project Schedule • Schedule can be shown with or without dependencies (logical relationship). • Presented as – Summary form e.g. Master Schedule, Milestone schedule – Detailed form • Format: – Network diagram – Milestone chart – Bar chart (Gantt chart)
  • 33. Schedule Data • Includes at least: – Schedule milestone – Schedule activities – Activity attributes – Assumptions & Constraints • Additional information can be added, such as – Resource histograms – Cash-flow projections – Order & delivery schedules – Alternative schedules
  • 34. 6.6 Control Schedule • Process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule. Inputs 1. Project Management Plan 2. Project Schedule 3. Work performance information 4. Organizational process assets Tools & Techniques 1. Performance reviews 2. Variance Analysis 3. Project Management Software 4. Resource leveling 5. What-if scenario analysis 6. Adjusting leads & lags 7. Schedule compression 8. Schedule tooling Outputs 1. Work performance measurements 2. Organizational process assets updates 3. Change requests 4. Project management plan updates 5. Project document updates
  • 35. Thank You Next topic: Project Cost Management

Hinweis der Redaktion

  1. Revise this slide!
  2. Revise this slide!
  3. Revise this slide!