You manage a team of 4 employees. The entire team is responsible for completing 4 projects on time. The time to complete the task is 4 weeks, and this is the time needed and is based on a 56-hour work week for each team member. Each team member will work 7 days a week, since this is a priority project and, must be completed on time. The names of the 4 team members are A, B, C, and D. Based on historical data, at least 1 of the 4 team members calls in sick at least (and only) 1 time per week. Based on this information, what is the probability that the project will be completed on time? .