Data Management & Warehousing




                                                              WHITE PAPER


                                   Data Warehouse
                               Project Management
                                                      DAVID M WALKER
                                                                           Version: 1.0
                                                                      Date: 14/10/2008




                      Data Management & Warehousing

   138 Finchampstead Road, Wokingham, Berkshire, RG41 2NU, United Kingdom

                          http://www.datamgmt.com
White Paper - Data Warehouse Project Management




Table of Contents

Table of Contents ...................................................................................................................... 2!
Synopsis .................................................................................................................................... 3!
Intended Audience .................................................................................................................... 3!
About Data Management & Warehousing ................................................................................. 3!
Introduction................................................................................................................................ 4!
Common Problems.................................................................................................................... 5!
   Setting the wrong expectations ............................................................................................. 5!
   Managing the Technical Architecture.................................................................................... 7!
   Resource Turnover ............................................................................................................... 8!
The building blocks of a project control ..................................................................................... 9!
   Phases .................................................................................................................................. 9!
   Milestones ........................................................................................................................... 10!
   Activities .............................................................................................................................. 10!
   Tasks................................................................................................................................... 10!
   Issues.................................................................................................................................. 11!
   Enhancements .................................................................................................................... 11!
   Test cases........................................................................................................................... 12!
   Defects ................................................................................................................................ 12!
   Risks ................................................................................................................................... 12!
The Event Horizon................................................................................................................... 14!
   Short Term .......................................................................................................................... 14!
   Medium Term ...................................................................................................................... 14!
   Long Term........................................................................................................................... 14!
Tools and Technology ............................................................................................................. 15!
   Project Management Software............................................................................................ 15!
   Ticketing.............................................................................................................................. 15!
   Version Control ................................................................................................................... 16!
   Wiki ..................................................................................................................................... 17!
Methodologies ......................................................................................................................... 18!
Project Leadership .................................................................................................................. 19!
   The Executive Sponsor ....................................................................................................... 19!
   Project Sponsor................................................................................................................... 19!
   Project Manager.................................................................................................................. 20!
   Technical Architect.............................................................................................................. 20!
   Senior Business Analyst ..................................................................................................... 21!
   Leadership Style ................................................................................................................. 21!
   Organisational Learning ...................................................................................................... 22!
   Team Rotation..................................................................................................................... 23!
Estimating and Effort ............................................................................................................... 24!
Tips and Tricks ........................................................................................................................ 26!
Summary ................................................................................................................................. 28!
Appendix 1 – Governance Procedures ................................................................................... 29!
   Change Management Processes........................................................................................ 29!
   Data Warehouse Processes ............................................................................................... 30!
   Data Management Processes............................................................................................. 31!
Appendix 2 – Project Services ................................................................................................ 32!
Copyright ................................................................................................................................. 32!




         © 2008 Data Management & Warehousing                                                                                          Page 2
White Paper - Data Warehouse Project Management




Synopsis
Data warehouse projects pose a specific set of challenges for the project manager. Whilst
most IT projects are a development to support a well defined pattern of work a data
warehouse is, by design, there to support users asking ad hoc questions of the data available
to the business. It is also a project that will have more interfaces and more change than any
other system within the organisation.

Projects often have poorly set expectations in terms of timescales; the likely return on
investment, the vendors’ promises for tools or the expectations set between the business and
IT within an organisation. They also have large technical architectures and resourcing issues
that need to be handled.

This document will outline the building blocks of good project control including the definition of
phases, milestones, activities, tasks, issues, enhancements, test cases, defects and risks and
will discuss how they can be managed, and when, using an event horizon, the project
manager can expect to get information.

To help manage these building blocks this paper will look at the types of tools and technology
that are available and how they can be used to assist the project manager. It also looks at
how these tools fit into methodologies.

The final section of the paper has looked at how effective project leadership and estimating
can improve the chances of success for a project. This includes understanding the roles of
the executive sponsor, project manager, technical architect and senior business analyst along
with the use of different leadership styles, organisational learning and team rotation.



Intended Audience
Reader                                            Recommended Reading
Executive                                         Entire Document
Business Users                                    Synopsis
IT Management                                     Entire Document
IT Strategy                                       Synopsis
IT Project Management                             Entire Document
IT Developers                                     Synopsis




About Data Management & Warehousing
Data Management & Warehousing is a specialist consultancy in data warehousing, based in
Wokingham, Berkshire in the United Kingdom. Founded in 1995 by David M Walker, our
consultants have worked for major corporations around the world including the US, Europe,
Africa and the Middle East. Our clients are invariably large organisations with a pressing need
for business intelligence. We have worked in many industry sectors but have specialists in
Telco’s, manufacturing, retail, financial and transport as well as technical expertise in many of
the leading technologies.

For further information visit our website at: http://www.datamgmt.com




      © 2008 Data Management & Warehousing                                                  Page 3
White Paper - Data Warehouse Project Management




Introduction
Data warehousing projects are notorious for both being delivered late and over budget. Why
is this and what can be done to prevent it?

The common problems that affect the data warehouse can be grouped by the expectations
that are set, the technology used and the management of resources. There is also a need to
define the components of project control and to develop understanding of the level to which
these can be planned and forecast.

With this understanding it is possible to look at tools, technologies and methodologies that
can assist the project manager to control, support and deliver a solution.

Finally this paper looks at the impact of project leadership techniques and the effect that good
estimate efforts can have on the delivery of a project.

This paper does not set out to be an exhaustive manual for the management of a data
warehouse project, rather a guide to help project managers understand the difference
between data warehousing projects and others that they may have been responsible. It also
suggests some things that should be considered when managing such projects.




      © 2008 Data Management & Warehousing                                                Page 4
White Paper - Data Warehouse Project Management




Common Problems
Data warehouse projects often suffer from poorly set expectations, problems with the
technical architecture and resource turnover. These common categories have multiple and
varied underlying causes:

     Setting the wrong expectations
     The failure to set the right expectations of a data warehouse is part of every project and
     the reason that they are often perceived not to deliver. This failure to set expectations
     occurs at many levels:

         •   Timescales

             For most large organisations a data warehouse project will have many phases,
             take years to build and have to be supported for many more years afterwards.
             Development and production phases will overlap and once in production the
             environment will be subject to massive amounts of change. When a Data
             Warehouse project is conceived it will not be discussed in these terms but as
             just another project with a finite timescale and a simple set of phases.

         •   Return on Investment

             The business case generated to justify a data warehouse project will always
             make a number of promises about return on investment, which are deemed
             necessary to get the budget. However, the real benefit will either come from an
             unexpected quarter (e.g. a fraud being discovered or the ability to drop a costly
             product range) or be from intangible benefits (e.g. business analysts that stop
             creating their own small database and spreadsheet applications and start
             analysing the business and delivering indirect business benefit). Business
             cases should be looked upon as a reason for starting rather than a defined
             return on investment. The deliverable, and therefore the return on investment
             should be measured in terms of what benefit was derived rather than against
             some planned benefit. Some phases will deliver more, and some less than
             expected.

         •   Vendor set expectations of tools

             Data Warehousing and Business Intelligence tool are purchased with an
             expectation of productivity gains and reduced total cost of ownership however
             the reality is often more complex:

                  o   One reporting tool will not be sufficient for all your reporting needs.

                  o   An ETL tool provides a well-defined development environment but
                      often does not provide the productivity benefits promised and requires
                      more expensive, specialist resources.

                  o   It is often difficult to integrate the tools in the advertised way.

                  o   Changing from one tool to another often does not fix the underlying
                      issue, or does so only at significant cost.

                  o   Technology sets leapfrog one another; a unique feature in one tool will
                      often be in another with the next release.




     © 2008 Data Management & Warehousing                                                   Page 5
White Paper - Data Warehouse Project Management




    •   IT set expectations to the business

        IT are often guilty of being over-optimistic about the point at which the benefit
        will occur:

             o   The initial phases of a project are about understanding and
                 infrastructure. It is only when these are in place that the business
                 facing solution can be deployed.

             o   Quick-win solutions, whilst valuable in the short-term, have a long-term
                 cost that has to be accounted for. This is because there is both an on-
                 going management cost and a de-commissioning cost that the
                 business will have to pay later. Quick-win solutions often also
                 compromise data quality that in turn damages user confidence in the
                 system

             o   The final solution can never be reconciled exactly against the current
                 solution, this is because there will be unknown bugs in the currently
                 delivered solution, new sources of data and different treatments of that
                 data. It should, however, be possible to explain all the differences.

             o   The testing and issue resolution of a system will take longer than
                 expected.

    •   Business set expectations to IT

        The business will often point to IT for its failings but it too will fail to manage
        expectations. Commonly:

             o   The business will not invest the time required to deliver requirements
                 and analysis.

             o   The data quality will be much worse than the business is prepared to
                 acknowledge and the business will be slow to respond to the need to
                 change working practices to improve the data quality.

             o   The business will not spend enough time or dedicate enough resource
                 to testing.

             o   The business will not spend enough time or dedicate enough resource
                 to training.

             o   There will be phases of the project where they lose focus as other
                 business critical events take place.

             o   When the time comes to de-commission existing solutions and tactical
                 solutions built along the way the business will be unwilling or unable to
                 do so, often fearing that some piece of data has been overlooked.




© 2008 Data Management & Warehousing                                                     Page 6
White Paper - Data Warehouse Project Management




        Managing the Technical Architecture
        The technical architecture of a data warehouse is the framework on which the solution
        is delivered. Data Warehouses are often described as ‘complex’ without further
        explanation. It is not that the process itself is difficult (copy data from the source
        systems, format it and write a report on it), nor does it need unusually complex
        technology to deliver. Instead the complexity comes from the scale of the solution. A
        reasonable sized data warehouse will have thousands of individual ETL mappings and
        hundreds of reports all serving a large community of users quickly.

        In order to do this it is important to observe the following principle:

                                           Keep the architecture simple

        Whilst this may seem obvious, simplicity is hard to do and has to be regularly worked
        on. Keeping things simple requires a conscientious decision. Some common examples
        include:

               o    Small is beautiful.
                    Creating more simple ETL mappings rather than large single blocks of code
                    makes change and maintenance easier.
                    Have a larger number of smaller data marts rather than one single ‘super-
                    mart’ which results in complex change management.
                    Have multiple reports for different people instead of one that tries to satisfy
                    everyone. A change to meet a requirement from one user will undoubtedly
                    leave another user unhappy.

               o    Have discreet ‘componentised’ functionality.
                    Use the right tool for the job. For example don’t store data in the ETL tool,
                    don’t use a reporting tool to perform ETL, extract data for downstream
                    sources in a consistent way, etc.

               o    Ensure that the data load process is complete and auditable.
                    It is common for data warehouses to allow direct updates to the database by
                    DBAs etc to maintain reference data. This should be prohibited and an
                                                                                                 1
                    application provided to the business for them to perform this functionality.

               o    Minimise components.
                    There is often a temptation to make tweaks to the technical architecture to
                    have a larger number of ‘best of breed’ tools to accommodate certain
                    requirements. In practice this increases the maintenance costs and support
                    skills required whereas the existing toolset can often provide a sufficient
                    solution.

               o    Keep it clean.
                    A data warehouse whose data is not clean quickly falls into disrepute and
                    becomes unused. The technical architecture has to support data quality
                    monitoring and data cleansing and there must also be processes to deliver
                    change in the source system.



1
  This may seem counter-intuitive, how can writing a whole separate application to maintain data be simpler than just
writing the SQL? The reason for this requirement is that there is no audit trail and therefore no way of knowing what
updates have been done. If instead a business user has to maintain the data via an application and this is loaded into
the data warehouse via ETL then the business takes responsibility for maintaining the data and there is an audit trail
of where the data change came from. Writing SQL also creates a large number of small, ad-hoc SQL jobs. This
takes time and sooner or later someone will make a mistake with the SQL that may take a lot of work to correct.



       © 2008 Data Management & Warehousing                                                                   Page 7
White Paper - Data Warehouse Project Management



             o    Tactical Solutions.
                  Every project has them and there is often a very good case for them but they
                  always cost more to remove than to create and often de-rail the ‘keep it
                  simple’ principle. If tactical solutions become necessary then they should
                  have an implementation, an expected lifetime, maintenance cost for the
                  lifetime, a lifetime-overrun cost and a decommissioning cost. When presented
                  with these costs tactical solutions often look a lot less appealing.

             o    Have an active de-commissioning policy.
                  Data Warehouses have a lot of code that needs to be maintained and takes
                  time to run. If database entities are no longer used then de-commission them
                  and the ETL that feeds them. The same is true for a report that has been
                  replaced or just fallen into disuse.


       Resource Turnover
       Data Warehouses are long-term projects and are likely to engage internal and external
       staff for several years. For a variety of reasons staff will come and go during that time.
       It is also possible for the new arrivals to bring new ideas and ways to improve what is
       being done. Whilst this is to be welcomed it also presents a very specific and potentially
       expensive risk. This often manifests itself when new members of staff come in and say
       ‘I wouldn’t have done it this way – let’s start doing it another way’ For whatever reason
       a significant change in direction most often results in one of two outcomes; expensive
       re-work to keep a consistent architecture or a complex architecture that requires more
                                                                                        2
       support and documenting the route to the current point can avoid such re-work.

       In addition ensure that there is sufficient briefing material available so that new starters
       can get up to speed quickly and before launching into the ‘I wouldn’t have done it this
       way’ discussions.




2
 Key Design Decisions – a template for documenting critical decisions in the design process. See the ‘Data
Warehouse Documentation Roadmap’ white paper from Data Management & Warehousing



       © 2008 Data Management & Warehousing                                                        Page 8
White Paper - Data Warehouse Project Management




The building blocks of a project control
The following section offers a description of the components of the project control (the project
plan in conjunction with project risks, issues and defects). Whilst all the terms will be familiar
to readers they are described here to ensure consistent use and discuss the interaction
between them.

       Phases
       The phase of the program is a set of work with a defined outcome that delivers benefit
       to the project as a whole. Note that there should be phases of the project that do not
       deliver direct business benefit but are required for the project to succeed. It would be
       common for a data warehouse project to have the following initial phases:

             •    Phase 1: Mobilisation (2 weeks).
                  This short phase at the start of a project aims to get everything ready for the
                  team to begin. It includes getting building passes, office space, network
                  access, systems permissions and other basic structures in place. Too often
                                                                      3
                  there is a perceived need to see everyone on site and working on day one. In
                  reality this normally wastes a significant amount of resource that will be
                  required in the later phases of the project.

             •    Phase 2: Technical Architecture & Initial Business Requirements (4-8 weeks).
                  This second phase is about putting a sound basic infrastructure in place. The
                  technical architecture provides a solid platform on which to build whilst the
                  initial business requirements are used to develop a list of priorities for
                  development. These also provide the basis for developing the initial resourcing
                  plans for enlarging the team.

             •    Phase 3: Data Warehouse Infrastructure Deployment (4-8 weeks).
                  With this phase sufficient hardware and software is deployed and the initial
                  data warehouse logical data model created and a plan for the subsequent
                  phases of data mart deployment is developed.

             •    Subsequent Phases: Data Mart Delivery (3-6 months each).
                  From this point on the iterative development of data marts and reporting
                  solutions can begin. Each phase represents a deliverable of direct business
                  benefit.

       Phases can overlap but only in a controlled way such as not to cause resourcing or
       technical conflict between phases. The above outline means that whilst the speed of
       delivery gets faster later in the project the initial delivery will be six to nine months from
       inception.
                                                                                       4
       Phases are often driven by an enhancement packaging process that groups together a
       series of requirements and enhancements into a phase scope definition.




3
  This is particularly common in system integrator run projects where the client often says “How big is your team and
when will they arrive?” because the client want to see movement on the project.
4
  See Appendix 1 for a description of governance processes for a data warehouse environment



       © 2008 Data Management & Warehousing                                                                  Page 9
White Paper - Data Warehouse Project Management




Milestones
Milestones are the checkpoints within a phase of the project. For example each data
mart phase may have milestones that indicate the completion of Requirements
Gathering, Analysis, Design, Build, Test, Deployment, Training, etc.

Activities
Activities describe what needs to be done to complete a specific milestone. Therefore
the milestone ‘Analysis Complete’ may have activities such as ‘Identify Potential
Source Systems’, ‘Perform Data Quality Analysis’, ‘Perform Source System Analysis’,
etc. These are normally carried out by a team or group of people and normally have
estimated elapsed durations associated with them. Whilst some activities are
dependent on others many will have dependencies at a lower level. For example whilst
the activity ‘Indentify Potential Source Systems’ is going on there may be no reason
why the ‘Perform Data Quality Analysis’ for the first identified system cannot start.

It is often difficult to represent this in a project management tool and common for
project managers to reflect the situation as a number of activities of fixed duration that
are dependent on the completion of one before the next starts, or not to have any
dependencies between activities. Both methods cause the plan to slip.

Tasks
Tasks are the specific items of work to be carried out by an individual. It is important
that a named individual is responsible for the task, not a group or a team. Where a task
is not yet assigned to an individual it should be assigned to the team leader so that they
are aware that they have to (re-)assign it on to someone to actually do the work.

It should also be noted that tasks can have sub-tasks, for example the task ‘Document
Technical Architecture’ may require sub-tasks of ‘Document Database Architecture’
and ‘Document Hardware Architecture’. All three of these tasks should also have an
individual owner who may or may not be the same person as the person responsible
for bringing the whole document together.

Tasks also have real dependencies on other tasks being completed. Individuals can
work very effectively if they have a bank of outstanding tasks, each with a priority and if
they cannot work on one task can move to the next one quickly and easily. Issues may
hold up tasks.




© 2008 Data Management & Warehousing                                                Page 10
White Paper - Data Warehouse Project Management




          Issues
          An issue is something that affects the progress of the project. Issues can occur at a
          project level or affecting an individual task. For example:

               •    A team member going off unexpectedly on long-term sick leave is a project
                    level issue that needs to be resolved.
               •    The inability to get a username and password for an individual system that
                    prevents someone completing a source systems analysis is a task level issue.

          Issues introduce delays in the project and so it is important to see the impact of issues
          as soon as possible.

               •   Project level issues should be driven down to task level as quickly as possible.
                   Using the example above of long term sickness the process of driving it down
                   to task level would be to re-assign tasks that belonged to that individual to
                   others.
               •   Task level issues often mean that the person responsible moves onto the next
                   task in the task bank and can come back to the other task when the issue is
                   resolved.

          Mistakes and consequently issues are inevitable on a project. As such active
          management and an environment where mistakes are accepted, learnt from and
          documented is to be favoured over one in which people try to hide their mistakes. An
          understanding of the types of issues over the lifecycle of the project is the first step
          towards improving both the quality and speed of delivery. An Issue Management
                                        5
          Process should manage issues

          Enhancements
          An enhancement is a change to the system with the aim of improving it. In a
          development such as a data warehouse where new requirements are continuously
          being developed it usual that an enhancement is captured, considered and if
          appropriate worked into the requirements documentation for inclusion in a subsequent
          phase via the enhancement packaging process.

          Not all enhancements need to go through the requirements process. Some, such as an
          improved navigation paradigm for the user interface, may be considered and passed
          directly as a task to the person who can affect the change. This rapid response process
          is very useful if there are separate teams responsible for issues and maintenance as
          well as the main development teams.




5
    See Appendix 1 for a description of governance processes for a data warehouse environment



          © 2008 Data Management & Warehousing                                                  Page 11
White Paper - Data Warehouse Project Management




          Test cases
          Test cases are a special type of task associated with testing.

          A test case is a set of tasks supported by scripts and routines that help automate and
          manage the testing of software. Every piece of code developed should have an
          associated test case. Where an issue is found with the code it becomes a defect that
          has to be rectified. A test case may reveal many defects, or none and test cases may
          have to be repeated a number of times until the code is defect free.

          In some environments it is useful to consider not only code but also the review of
          documents as test cases and the issues raised from the review as defects. This allows
          a separation in the reporting between tasks originally associated with the plan and work
          carried out because of the incompleteness of the deliverable (i.e. defects). The test
          case for a document would simply be to review it.

          As with issues above, mistakes are inevitable in the development process and
          therefore should be accepted and documented as part of improving the process rather
          than being hidden away.

          Defects
          Defects are a special type of issue associated with testing.

          A defect is a material error with a deliverable. In the case of code this may be as a
          result of an undelivered but promised requirement, a misinterpretation of the
          requirements, unexpected results (common when testing boundary conditions and
          exceptional usage) etc. A defect should be resolved before the code is deployed (even
          if the resolution is to say that the functionality will be delivered in a subsequent phase).

          This can also be applied to review comments for documentation that are, in effect,
          defects in the deliverable. Each defect should be reviewed and changes applied where
          appropriate before the defect is closed.

          Risks
          There may be external circumstances or events that cannot occur for the project to be
          successful. If you believe such an event is likely to happen, then it would be a risk.
          Identifying something as a risk increases its visibility, and allows a proactive risk
                                                6
          management plan to be put into place.

          If an event is within control of the project team, such as having testing complete by a
          certain date, then it is not a risk. If an event has a one hundred percent chance of
          occurring, then it is not a risk, since there is no "likelihood" or risk involved but it is an
          issue.

          Examples of risks might be a "Re-organization may result in key people being
          reassigned," or "The new hardware may not be able handle the expected volume."

          Risks are managed by developing mitigations or ways in which to avoid the risk or
          prevent it from becoming a reality.




6
    http://www.mariosalexandrou.com/definition/risk.asp



          © 2008 Data Management & Warehousing                                                  Page 12
White Paper - Data Warehouse Project Management



      A risk can be quantified in two dimensions:

          •   The first is the probability of it happening which is a measure of how likely it is
              that a risk will become an issue.

          •   The second is the impact that is a measure of the impact in terms of resource,
              time or scope.

      Projects usually measure
      both of these dimensions
      on a High/Med/Low type
      scale. This can produce a
      grid as illustrated.

      The grid can then be used
      to assess the level of
      mitigation (or actions to
      prevent the risk from
      becoming an issue) that
      should be associated with
      each of the risks.

      Obviously the ‘hotter’ the
      risk the more attention that
      should     be    paid     to
      developing mitigation for
      that risk.

This can all be summarised in the
diagram below:




Figure 1 - Project Control



      © 2008 Data Management & Warehousing                                                Page 13
White Paper - Data Warehouse Project Management




The Event Horizon
Projects are often expected to have detailed plans from start to finish; in practice this is both
unrealistic and impossible to maintain for data warehouse projects. Instead projects should
aim to deal with the plan depending on when events are likely to happen.

      Short Term
      Current or near term phases need to be tracking every aspect of the work from the
      scope (enhancements) through milestones, activities, risks, tasks, test cases and for
      the current and next phase issues and defects. It is the issues and defects that will
      cause the current phase to be delayed or have other resource impact. The financial
      implications in the short term are over-spending or use of contingency because there is
      no space in which to manoeuvre.

      Medium Term
      Phases further out need to have the scope, milestones, activities, risks and where
      possible tasks planned out. These plans, their timescales and the budget for these
      phases should be adjusted in the light of experience gained on current and previous
      phases should influence the work being defined for these phases.

      Long Term
      Long-term plans are normally limited to rough scopes of work and timescales (for
      example we hope to add market segmentation to the data warehouse and expect it to
      take 5 people 3 months). This allows estimated budget requirements to be calculated
      but is highly dependent on the timescales and successful delivery of the previous
      phases. Learning from current work will improve the estimating over time.

Using the above definitions it is possible to indicate what information a project manager
should ideally have available in the following graphical way:




Figure 2 - Information available to a project manager

In practice managers normally have even less information available (indicated by the red
line). This means that both the short-term and medium-term horizons each cover two phases
rather than the three phases of the ideal situation. The long-term view is then restricted to
knowing what enhancements are needed.




      © 2008 Data Management & Warehousing                                                Page 14
White Paper - Data Warehouse Project Management




Tools and Technology

In order to manage such a large-scale project it is important to use a number of tools to help
keep track of all the aspects of the project.
                                                   7
There are six major groups of software that are needed for corporate programme/project
management:
                                               8
    •    Project Management Software
                                9
    •    Collaborative Software
                                  10
    •    Ticket Tracking Systems
                                      11
    •    Project Portfolio Management
                                 12
    •    Resource Management
                           13
    •    Revision Control

For a data warehouse it would be common to use the following tools in the following way:

        Project Management Software
        Most organisations either have a large centralised project management system such as
        Primavera P3 or desktop project management systems such as Microsoft Project.
        These provide the high-level Gantt charts and resource management. In the
        components outlined above it is most common to put the phases, milestones and
        activities into this type of tool. The detailed and changing nature of the tasks makes
        most of the tools unsuitable for the level of detail required. Also the tools tend to be
        inaccessible to those doing the work for a number of reasons:

            •    Organisations are unwilling to invest in licences for every team member.
            •    Applications require a desktop/laptop install.
            •    Developers are unwilling to engage in using a project management tool.
            •    Project managers don’t share the plan with developers for fear of contradiction
                 about the proposed timescales

        As a result these tools are useful for holding the phase, milestone and activity level
        information but are rarely useful for task level information in data warehouse projects
        due to the large number of interlinking tasks required to manage the environment.

        Ticketing
        Ticketing systems are often used to track issues with software but their use can be
        much broader. Most ticketing systems allow the classification of tickets as well as
        dependencies between tickets and a workflow element that allows tickets to be
        assigned to others. A well-configured system is therefore the ideal tool for managing
        tasks, issues, risks, test cases, defects and individual enhancement requests.

        Tasks are initially raised; as the team member works on the task they may create
        dependant or sub-tasks (often as simple reminders to themselves or others). When
        issues arise they are captured against the task that is being affected allowing project

7
  http://en.wikipedia.org/wiki/List_of_project_management_software
8
  http://en.wikipedia.org/wiki/Project_management_software
9
  http://en.wikipedia.org/wiki/Collaborative_software
10
   http://en.wikipedia.org/wiki/Issue_tracking_system
11
   http://en.wikipedia.org/wiki/Project_Portfolio_Management
12
   http://en.wikipedia.org/wiki/Resource_Management
13
   http://en.wikipedia.org/wiki/Revision_control



        © 2008 Data Management & Warehousing                                             Page 15
White Paper - Data Warehouse Project Management



       managers to see what is impacting the project timelines. The same is true for the other
       ticket types (enhancement, risk, test case and defect).
       Deploying a ticketing system, and opening it to everyone involved in the project from
       business user to developer, allowing everyone to see everything, can have dramatic
       effects on the speed and quality of development.

       It is important that the culture around the system is one of mutual trust and respect. It is
       easy for a poor manager to go and count the number of defects in an individual
       developer’s code as a KPI of that developer’s performance. This is very naïve for two
       reasons: it discourages honesty and it does not measure performance at all.
       Discouraging honesty is a disaster, because the manager will never know the true state
       of the project again. The number of defects against one developer may be high
       because that person is the most skilled developer and therefore gets the most difficult
       work to do, because the specification was wrong, because the source system has
       changed, or because the requirements changed when the users saw the initial
                14
       results.

       An effective ticketing system will also highlight delays and bottlenecks in the process
       where, for example, critical blocking tasks go unanswered. Careful review of this
       information allows risks and issues to be addressed early, thus reducing impact and for
       an understanding of the root cause of delays to be gained which can be used to speed
       up subsequent phases.

       It also removes the process whereby the project manager each week goes around and
       disturbs everyone else on the project to get an update on the status of each task, which
       wastes huge amounts of time for those disturbed. A project manager can get the status
       from the system and then talk to those individuals whose tasks and issues have a
       material effect on the status of the project. This is management by exception rather
       than micro-management of the process.

       Version Control
       A version control system is vital to the development of a data warehouse, not just for
       the code developed but every document used throughout the life of the project and
       subsequent maintenance. Whilst there are products especially built for document rather
       than code version control it is often sufficient just to use the same piece of software.

       The advantages of source code control have long been established but documentation
       control is often not addressed. If there is a requirements document on a shared drive
       that is updated when a new requirement emerges and (if the author remembers) the
       version number on the front page or in the file name is updated this does not mean that
       everyone working on the project has the same document.

       If someone copies it to their laptop to work on it at home over the weekend and on their
       return copies back to the shared drive all would appear well. The issue arises if two
       people have had the same idea, when the second person copies their work back to the
       shared drive the first person’s work is simply overwritten.




14
   This is a failing in the requirements capture process that should be picked up by the project manager from these
tickets and corrected



       © 2008 Data Management & Warehousing                                                               Page 16
White Paper - Data Warehouse Project Management




Using      a      version
control system also
means        that     the
development         team
can work against a
fixed     version       of
requirements for a
period of time, even if
others        in      the
organisation are still
updating              the
requirements.        This
stability allows the
development process
to be smoother and a
gap analysis performed at a later stage to understand what has changes allows the
developers to catch up with the requirement (normally in another phase).


Finally the repository provides an auditable trail of the changes in all aspects of the
project documentation that again can help with improving future phases.

Wiki
The introduction to this section described collaborative software that covers a broad
swathe of technology. In practice the most useful software that one can use is a wiki.
This provides a number of web pages that any user can update with a syntax that is
simpler than standard HTML. The pages that get created are often part of the informal
structure that helps the programme move along.

Wikis can be used for frequently asked questions, staff lists, announcements, social
events, guides to using other parts of the project, etc. Since they are a shared
resource, editable by all they can provide a productive communication tool that is far
more effective than email for encouraging collaboration.

Wikis are more common than most people realise with websites such as Wikipedia
using the same quick, cheap, easy software to build an encyclopaedia that can be
deployed as the team’s main source of information for the project. It can also have the
‘water-cooler’ effect where people from IT and the business collect to share information
in an informal manner rather than through formal documentation or review processes.




© 2008 Data Management & Warehousing                                             Page 17
White Paper - Data Warehouse Project Management




Methodologies
Most organisations will have a preferred IT development methodology. It is likely that the
                                                                                15
larger the organization the more structured the methodology (for example PRINCE2 or other
                                                                                         16
waterfall approaches). These processes are often assessed by mechanisms such as CMMI.
                                                      17
Few large organisations are willing to adopt agile approaches despite both the business
side saying that IT should deliver faster and meet requirements more completely and the IT
side saying that they are trying to be flexible and meet that demand.

As a result the organisations’ methodologies will not be well suited for the development of a
data warehouse. This is because most methodologies have a fixed scope and a clear
objective. The deployment of a new financial package covers certain well-defined business
processes, has well understood inputs and outputs and bears scrutiny by use cases to
examine the steps.

A data warehouse is a system that will have a number of fixed outputs but also the intangible
‘just load up the data and I will know what I need when I see it‘ type requirement. It has a
                                                        18
huge number of changing inputs from the source systems and often has large parts that will
be in production whilst others are under development causing a crossover between the
deployment and maintenance phases.

Data warehouses are therefore inherently risky ventures and yet assessments such as CMMI
                                                        19
set out to avoid projects that carry risk. In Peopleware it suggests of CMMI assessments:

                     The projects most worth doing are the ones that will
                     move you DOWN one full level on your process scale

Trying to deploy large-scale data warehouses in large organisations is what has lead to the
concepts described in this document, whereby phases, milestones and activities can be
managed within the organisation’s standard structures but allowing more agile development
methods at the task level as well as detailed tracking of the relationship between issues and
tasks which improves time and resource management.

Remember that it is the deliverable and not the methodology used to get there that is
important. It is all too easy to get trapped in trying to complete a methodology rather than the
deliverable.




15
   http://en.wikipedia.org/wiki/Prince2
16
   http://en.wikipedia.org/wiki/CMMI
17
   http://en.wikipedia.org/wiki/Agile_software_development
18
   Imagine an organisation that has 25 source systems and two software upgrades/patches a year to each of them.
This means that there are 50 changes a year or one a week to be analysed, designed, build and tested as well as
managing maintenance and other issues that arise.
19
   Peopleware – Productive Projects and Team: Tom DeMarco and Timothy Lister, Dorset House Publishing, Second
Edition 1999, Chapter 29: Process Improvement Programmes



       © 2008 Data Management & Warehousing                                                            Page 18
White Paper - Data Warehouse Project Management




Project Leadership
The single biggest impact on any project comes from the leadership it receives. Since a data
warehouse is such a long-term commitment the leadership staff should understand that they
are entering into a project that they may be engaged in for several years. A revolving door
policy of leaders will only slow the project down.

The project leadership comes in two parts:

     •    The sponsors: An executive sponsor and his delegate, the project sponsor, who
          commission the project and will ultimately, control its use.

     •    The project team: Leadership within the team normally consists of three individuals, a
          project manager, a senior technical architect and a senior business analyst who must
          work together to deliver, each taking responsibility for their own area but deferring to
          the others for their respective areas of responsibility.

The roles are outlined in more detail below:

         The Executive Sponsor
         The Executive Sponsor is a senior manager or executive with demonstrable interest in
         the outcome of the project, who is ultimately responsible for securing spending
         authority and resources for the project. Ideally, the Executive Sponsor should be the
         highest-ranking manager possible, in proportion to the project size and scope.

         The Executive Sponsor acts as a vocal and visible champion, legitimizes the project’s
         goals and objectives, keeps abreast of major project activities, and is the ultimate
         decision-maker for the project. The Executive Sponsor provides support for the Project
         Sponsor and the Project Manager. They have final approval of all scope changes, and
         signs off on approvals to proceed to each succeeding project phase. The Executive
         Sponsor may elect to delegate some of the above responsibilities to the Project
         Sponsor (sometimes known as the Executive Sponsor’s Agent).

         Project Sponsor
                                20
         The Project Sponsor is someone who strongly supports the objectives of the project
         and is willing to act as a champion and advocate on behalf of the project. To this end
         they are the primary source of business input and take ownership from a business and
         governance perspective.

         This can be broken down into six main responsibilities:

             •   Accountability
                 The project sponsor is responsible for holding the project manager to account
                 and consequently keeping the project on track. The project sponsors must also
                 make themselves available to provide support and address risks and issues.




20
   Adapted from:
http://www.stanford.edu/dept/its/projects/PMO/files/linked_files/guidelines_sponsors.pdf
http://ithelp.lincoln.ac.nz/site/story_images/3021_project_sponsor_s8869.pdf
http://www.cit.cornell.edu/computer/robohelp/cpmm/Project_Roles_and_Responsibilities.htm




         © 2008 Data Management & Warehousing                                              Page 19
White Paper - Data Warehouse Project Management



    •   Strategic Fit
        Assure that the project is aligned with the organization’s strategic goals.

    •   Resources
        Provide or locate resources for the project especially where these are outside
        the control of the project manager and protect resources from being pulled
        away.

    •   Project Finances
        Provide or locate funding for the project and track the budget in conjunction
        with the project manager.

    •   Lead Political Charge
        Help the project manager navigate the organization’s political environment.

    •   Own the Final Product
        Be clear on what is expected in the end and help celebrate & transition.

Project Manager
The Project Manager is the person responsible for ensuring that the Project Team
completes the project. The Project Manager develops the project plan with the team
and manages the team’s performance of project activities. It is also the responsibility of
the Project Manager to secure acceptance and approval of deliverables from the
Project Sponsor and other stakeholders. The Project Manager is responsible for
communication, including status reporting, risk management, escalation of issues that
cannot be resolved in the team, and, in general, making sure the project is delivered in
budget, on schedule, and within scope.

Technical Architect
The Technical Architect is the single point of responsibility for the technical solution
from an application and system perspective.

The main responsibilities of the Technical Architect are to:

    •   Define the technical architecture
    •   Solve technical issues
    •   Ensure that all components of the technical architecture are properly integrated
        and implemented
    •   Define the development tools and environment
    •   Coach the technical team in the development of the technical architecture
    •   Provide technical support and technical quality control throughout all stages of
        the project
    •   Co-ordinate vendor services related to technology selection and
        implementation
    •   Work with the Senior Business Analyst to determine how the technology can
        be applied to meet the business needs
    •   Work with the Project Manager to ensure the smooth running of the project
    •   Evangelise the technical solution to the rest of the IT community and the
        business




© 2008 Data Management & Warehousing                                                  Page 20
White Paper - Data Warehouse Project Management




       Senior Business Analyst
       The Senior Business Analyst is responsible for:

            •       Analysing and Defining the business requirements and solution
            •       Quickly and clearly understanding the business issues and data challenges
            •       Identifying the organization's strengths and weaknesses and suggesting areas
                    of improvement.
            •       Reviewing and editing requirements, specifications, business processes and
                    recommendations related to proposed solution.
            •       Leading the testing efforts
            •       Working with the business to identify required changes
            •       Communicating the required changes to the development team
            •       Work with the Technical Architect to determine how the business need will be
                    met by the technology
            •       Work with the Project Manager to ensure the smooth running of the project
            •       Evangelise the business solution to the rest of the IT community and the
                    business

       Leadership Style
       Managing a small team to develop a large complex environment requires a degree of
       skill and the ability to adjust the style of leadership to match the situation. This type of
       flexibility is known as situational leadership and is a necessary quality in a data
       warehouse project.
                                                                                              21
                                                               Kenneth Blanchard wrote “... managers
                                                               should work for their people, ... and not
                          Supporting          Coaching         the reverse. ... If you think that your
                                                               people are responsible and that your job
           Supportive
           Behaviour




                                                               is to be responsive, you really work hard
                                                               to provide them with the resources and
                                                               working conditions they need to
                          Delegating          Directing        accomplish the goals you've agreed to.
                                                               You realize your job is not to do all the
                                                               work yourself or sit back and wait to
                                                               'catch them doing something wrong', but
                                                               to roll up your sleeves and help them
                            Directive Behaviour                win. If they win, you win.”


       As staff develop on a data warehouse project it is typical for a good leadership team to
       move from a directive style through the coaching style and supporting style and
       ultimately reaching the delegating style. For example the technical architect may start
       with ‘Build the data warehouse this way’ moving through ‘We build the data warehouse
       this way because …’ and ‘I like what you have done but have you considered …’ and
       ending with ‘Thanks, that’s just what I envisioned’.

       To this end a strong relationship and shared vision between project manager, technical
       architect and senior business analyst is essential.




21
   "Leadership and the One-Minute Manager", Kenneth Blanchard, Patricia Zigarmi, and Drea Zigarmi, p18. This is a
refinement of Path-Goal Theory developed by Robert House in 1971



       © 2008 Data Management & Warehousing                                                             Page 21
White Paper - Data Warehouse Project Management




          Organisational Learning
          Most people working on a project will learn in some way, but this knowledge, locked
          away in an individual, is of little value to the business as a whole. The team have to
          become a learning organisation that actively creates, captures, transfers and mobilizes
                                                                       22
          knowledge to enable it to adapt to a changing environment.
                                                                                              23
                    “Knowledge is not knowledge until someone else knows that one knows.”

          For a data warehouse project organisational learning is critical, as, not only is the
          environment rapidly changing but the number of places from which information is
          sourced is larger than any other IT project the business is likely to engage in. In this
          context information is more than data being transferred inside systems, it also includes
          information about how business processes work, key contacts both inside and outside
          the organisation, critical business requirements, data quality issues, etc.

          Organisational learning is a cultural phenomenon that requires team members to
          actively participate in developing knowledge. To this end a ticketing system, wiki and
          document versioning system provide tools but it is the people who have to engage in
          the concept and as a result be willing to:

                •    Share information in a timely fashion
                •    Capture even the most incidental information
                •    Provide access to work in progress
                •    Be open about issues and mistakes
                •    Submit everything to a rapid peer review processes
                •    Re-use rather than re-invent
                •    Research and capture research for others to use
                •    Have largely unrestricted access to the entire project knowledge repository
                •    Accept change as inevitable and be prepared to adapt

          A team that has a culture capable of organisational learning will be:

                •    More productive because they have the information to do the job
                •    Happier because they are learning and their contribution is recognised
                •    Less prone to expensive re-work as issues are addressed earlier

          All of this leads to faster, more successful projects.




22
     http://en.wikipedia.org/wiki/Organizational_learning
23
     Gaius Lucilius c180Bc-103BC



          © 2008 Data Management & Warehousing                                                 Page 22
White Paper - Data Warehouse Project Management




Team Rotation
It is common practice for the most experienced
developers to be put in change of major
enhancements and then in a sliding scale of
experience to assign people to maintenance work
and issue resolution. This has initial benefits of
getting the best developers to do the largest
chunk of work but projects can also benefit from
rotating people so that after the enhancement is
developed those resources move to the issue
handling and other developers move up to
maintenance from issues and to enhancements
from maintenance.

This has a number of very positive aspects. Firstly
the most skilled developers have done the first
development, and have therefore laid down the principles and standards for future
development that the others will follow. By moving these people into issue handling
they also become aware of the consequences of their work and any quality or design
issues that have been introduced.

For the other less experienced teams they see career development as they can learn
new skills and have an opportunity to show that they can move up to the next level. If
problems occur they can still be supported by more senior developers but it is better to
allow people learn early.

This practice is also helpful in staff retention because it creates varied work and an
opportunity to learn. It also means that people will work across subject areas and
therefore have a greater understanding of the whole. This in turn makes it easier when
individuals do leave as combined with the organisational learning discussed above the
team is greater than the sum of its parts.




© 2008 Data Management & Warehousing                                             Page 23
White Paper - Data Warehouse Project Management




Estimating and Effort
Initial estimating on a data warehouse project will always be very subjective and therefore
wrong. Plans will often start with what the developer feels is required (and therefore very high)
and then adjusted down to meet what the project manager feels is acceptable (and therefore
very low). The final value will be somewhere between the two.

It is important that everyone understands that the timescales will change in light of
experience. Subsequent re-assessments of effort will become more accurate if the
organisation is willing to learn. This is often done by the organisational learning process
described above, combined with end of milestone or phase reviews and detailed reviews of
the ticketing system – what issues arose, will similar issues arise in the next development and
how to allow or compensate for them.

Tasks are also non-uniform, some tasks will take a short amount of time – often those at the
start and the end of a phase, others will take a longer period – often those in the middle of the
        24
phase. Project monitoring systems that determine completeness by the number of tasks
complete as a percentage of the total number of tasks will see the project initially getting
‘ahead of schedule’ before ‘falling massively behind schedule’ and finally ‘recovering some of
the lost time’. This is exacerbated by the fact that if a ticketing system is used additional tasks
will be created and therefore the percentage complete will appear to drop at some points in
the project. Better measures are around the ratio of tasks to issues and the completion of
activities to planned activity duration.

Agile and other similar methodologies provide several techniques for improving the
estimation.
                                25
The first of these is velocity (or sometimes better known as load factor). This is the ratio
between the developers’ estimate and what is actually achieved. So if a task is estimated as
taking 4 days and then takes 10 days the “velocity” is 10/4 or 2.5. For the next phase the
developers’ estimates are taken and multiplied by 2.5 to determine the likely timescale. The
velocity is measured for each estimate and whilst initially it will oscillate widely after a few
iterations it will settle to a factor that can regularly be used calculate elapsed time.

The accuracy comes from allowing for two factors. The first factor is the developers own
tendency to over or under estimate the effort required to do any given piece of work. The
second factor is the distraction that the work environment provides with telephone calls, e-
mails and meetings, etc. These work distractions usually have an organisation specific pattern
that is not normally factored in by developers but needs to be consistently applied to plans

Over a period of time developers will come to understand their own estimating and their
velocity will tend to a constant. The consistency of this number is what allows project
managers to be able to estimate accurately.
                                                                                        26
Agile development processes also introduce the concept of technical debt . This is the
obligation that an organization incurs when it chooses a design or construction approach that
is expedient in the short term but that increases complexity and is more costly in the long
term.




24
   See the Data Management & warehousing white paper “How Data Works” for a discussion of volume vs.
complexity in data and how this affects the timescales in a data warehouse project.
25
   Version One discussion of Velocity: http://www.versionone.com/Resources/Velocity.asp
26
   First proposed by Ward Cunningham in 1992 at the OOPSLA92 conference (http://c2.com/doc/oopsla92.html)



       © 2008 Data Management & Warehousing                                                      Page 24
White Paper - Data Warehouse Project Management



Technical debt can occur accidentally (when a mistake is made) or deliberately (when a
conscience decision is made to put something off). The secret to a successful implementation
is to continually work to manage and reduce the debt, just like debt in real life. It is technical
debt, so often unaccounted for, that often derails large projects as they run out of resource
and don’t understand where it has gone.

Debt can be classified just as in real life financial situations:

     •    Debt incurred un-intentionally
             o Usually due to low quality work (the uninsured loss)
     •    Debt incurred intentionally
             o Short-term debt, usually incurred reactively, for tactical reasons such as
                  numerous tiny shortcuts (credit card expenditure)
             o Medium-term debt incurred by individually identifiable shortcuts such as the
                  creation of a tactical data mart (the car loan)
             o Long-term debt, usually incurred proactively, for strategic reasons such as
                  the delay in purchasing significant technical infrastructure (the mortgage)
     •    Non Debt
             o Some things are not technical debt such as feature backlog, deferred
                  features, cut features, etc. Not all incomplete work is debt. These aren't debt,
                  because they don't require resource to correct them (the interest payment).

Debt requires re-payment with interest, i.e. whatever has been done has cost something (the
debt) and correcting it requires additional resource (the interest) to put it to how it should be.
                                                                                          27
As in financial circumstances delaying repayment always costs more in the long term.

It should be noted that a well-defined technical architecture as discussed above is needed in
order to identify technical debt. This is because there must be a blueprint and baseline
against which to draw comparisons against. This also re-enforces the need for a simple
architecture as measurement is more difficult against complex architectures.

It is often thought that time-boxing project phases either cannot be done for data warehouse
projects or will force developers to deliver something. Neither is true. A time-boxed project will
deliver something but can incur technical debt for those things that get omitted or
compromised. The delivered solution may be of little value if the time allowed is insufficient. If
the techniques described above are employed then early phases should be run as scope or
benefit driven rather than relying on time boxing. As velocity and technical debt are better
understood in the environment the project can switch to time-boxed activities to allow the
business to see tangible time-scaled development and deployment roadmap.

Finally the project manager must understand the cost of their actions. By putting good
communication, processes and systems in place the project manager can effectively monitor
and manage a project by exception, allowing the senior business analyst to handle the
business aspects and the technical architect to manage the technology and together progress
the delivery. If a team of eight people is brought together once a week for a two-hour status
meeting with the project manager, then two working days out of the forty working days (eight
people for five days a week assuming eight hour days) available in the week are lost. That
weekly status meeting reflects 5% of all the available resource!
                                                                                                 28
                     The ultimate management sin is wasting people’s time




27
   Note: The original draft of this paper was written before the 2008 financial crisis. The failure to manage debt in the
real world caused significant institutional melt down. This is mirrored by the meltdown of large data warehouse
projects within large organisations that have failed to manage technical debt.
28
   Peopleware – Productive Projects and Team: Tom DeMarco and Timothy Lister, Dorset House Publishing, Second
Edition 1999, Chapter 33



         © 2008 Data Management & Warehousing                                                                   Page 25
White Paper - Data Warehouse Project Management




Tips and Tricks
The following section lists some items that are useful for a project manager to remember. It is
not exhaustive but provides some high level reminders:

    •    Phase 1: Mobilisation
         Setting up a project has a cost, having a Mobilisation phase allows time and resource
         to be allocated to the setup. If there is no allowance for it then at the end of the first
         phase the cost of setup will be at least equal to the delay in the delivery of the phase.

    •    Team Members Wiki Page
         If the project has a wiki (which it should) take photographs of everyone and add them
         to a page that has everyone on it, order it alphabetically by first name rather than in
         any organisational structure, include their contact details. This is again something that
         makes people feel involved and is a useful resource when someone remote to the
         core team or a new starter wants to contact another member of the team.

    •    Develop a no blame culture
         Mistakes happen – they come from a lack of understanding or knowledge or poor
         communication and everyone on the team will make them at different times. It is
         therefore important that people are willing to admit to their mistakes and learn from
         them and that the project manager understands why mistakes are occurring and then
         take corrective action (e.g. training, improved communication channels, etc.) Where
         mistakes are hidden there is a build up of issues and technical debt that appear,
         inevitably, at critical points in the project.

    •    Large Teams & Parallel Streams
         Avoid large teams and large numbers of parallel streams of work. Data warehouses
         are complex intertwined systems and the impact of a large number of teams trying to
         work simultaneously across the system will out-weigh any benefit from parallel
         working. Parallel teams work where there are discreet non-interacting areas,
         otherwise the contention between components and resources becomes too much of
         an overhead. Also as a team gets larger the degree of effective communication within
         the team drops. The balance is to have sufficient people to do the work and yet few
         enough to ensure effective communication between them.

    •    Transparency
         By default let everyone involved with the project see everything. Exceptionally restrict
         access to sensitive documents. Always challenge any request to categorise a
         document as “sensitive”. This helps for many reasons; delays are not a sudden
         surprise to users, others on the project often volunteer help or expertise about issues
         in unexpected areas, it develops an inclusive aspect to the team dynamic, it provides
         an opportunity for people to learn from the work of others, etc.

    •    Document and version everything
         As this document has discussed, having a ticketing and version control system in
         place makes management of a rapidly changing environment possible. No individual
         or group of individuals can effectively manage all the tasks, risks, issues, changes
         and documents of a large project with manual systems and if the system is easy to
         use then documenting everything is preferable to trying to decide what might be
         needed in the future.




        © 2008 Data Management & Warehousing                                               Page 26
White Paper - Data Warehouse Project Management




     •    Use Storyboards but avoid Use Cases
                                                                             29
          Many formal methodologies for OLTP systems have use-cases that describe how a
          user must get through a system. This is fine for such solutions where a pre-defined
          path is essential. For a data warehouse the individual use case is irrelevant as the
          user is unlikely to follow the same route regularly. Instead a story is required that talks
          of a user being asked to produce a specific report and then having to do analysis of
          another set of data and incorporate it in the results, etc. The storyboard should
          describe the process of moving around the system but not prescribe specific routes
          for users to take, instead focusing on how to transition between aspects of the
          system.

     •    Key Design Decisions
          Whilst the idea of documenting everything has already been described it is
          particularly important to document key design decisions such that when a problem
          occurs it is easy to follow the intended route rather than revert to a re-evaluation of
          possible solutions.

     •    Manage Technical Debt
          Ensure that everyone can quantify the cost implications of the decisions they make
          and document them in such a way that the project can assess the technical debt they
          are accruing and schedule the debt reduction appropriately.




29
  “UML Distilled” Martin Fowler “The more I see of use cases, the less valuable the use case
diagram seems to be. With use cases, concentrate your energy on their text rather than on
the diagram. Despite the fact that the UML has nothing to say about the use case text, it is
the text that contains all the value in the technique.”



         © 2008 Data Management & Warehousing                                                Page 27
White Paper - Data Warehouse Project Management




Summary
Data warehouse projects pose a specific set of challenges for the project manager. Projects
often have poorly set expectations in terms of timescales, the likely return on investment, the
vendors’ promises for tools or the expectations set between the business and IT within an
organisation. They also have large technical architectures and resourcing issues that need to
be handled.

This document has outlined the building blocks of good project control including the definition
of phases, milestones, activities, tasks, issues, enhancements, test cases, defects and risks
and discussed how they can be managed, and when, using an event horizon the project
manager can expect to get information.

To help manage these building blocks this paper has looked at the types of tools and
technology and how they can be used to assist the project manager. These tools include
project management software, ticketing systems, version control and wikis. It has also looked
at how these tools fit into methodologies.

The final section of the paper has looked at how effective project leadership and estimating
can improve the chances of success for a project. This has included understanding the roles
of the executive sponsor, project manager, technical architect and senior business analyst
along with the use of different leadership styles, organisational learning and team rotation.




      © 2008 Data Management & Warehousing                                              Page 28
White Paper - Data Warehouse Project Management




Appendix 1 – Governance Procedures
Each organisation will create its own processes for the governance of the data warehouse
project. Data Management & Warehousing have defined and used processes in three major
groups:

    •    Change Management Processes
         Identifying and controlling enhancements, maintenance and issues with the system

    •    Data Warehouse Processes
         The processes associated with the build and deployment of the data warehouse itself

    •    Data Management Processes
         The processes associated with the management of the data held within the data
         warehouse

Outlined below are the major components of each of the processes. These are given as
examples only and are shown only with the high level summary diagrams and short
descriptions as indicators to what should be developed by an organisation to service its
environment


        Change Management Processes
                                                Enhancements and maintenance processes are
                                                required to ensure the communication of the
                                                organisation’s  requirements    of   the   data
                                                warehouse and to ensure that those requirements
                                                are costed and prioritised in such a way as to
                                                deliver maximum benefit.




                                                The issue management process is required to
                                                ensure that all issues found with business
                                                intelligence outputs are captured and resolved
                                                consistently, allowing for KPI capture and process
                                                visibility for active management.




        © 2008 Data Management & Warehousing                                              Page 29
White Paper - Data Warehouse Project Management




Data Warehouse Processes
                                        The requirements process is required to ensure
                                        that the user requirements are met effectively by
                                        creating a statement of what is required and a
                                        process for changing the definition of what is
                                        required




                                        The enhancement request packaging process is
                                        required to ensure that the scope is limited to user
                                        requirements that deliver benefit at reasonable
                                        cost and project timescales are predictable.




                                        The ETL design & build process is required to
                                        ensure that a reliable, robust, accurate and
                                        performant data loading process is designed and
                                        build.




                                        The report design and build process is required to
                                        ensure that a reliable, robust, accurate and easy
                                        to use reporting solution is designed and build.



                                        The testing process is required to ensure that the
                                        solution is a robust and accurate reflection of the
                                        requirements; that changes and issues are
                                        handled promptly, and performance is adequate.




© 2008 Data Management & Warehousing                                                Page 30
White Paper - Data Warehouse Project Management




Data Management Processes
                                        The data quality process is required to measure,
                                        control and improve the quality of data held in the
                                        data warehouse, reacting to new issues quickly
                                        and ensuring source systems are responsible for
                                        the data they provide.




                                        The data model process is required to develop
                                        and maintain both the logical and physical data
                                        models against set standards, and aligned with
                                        metadata.




                                        The data lifecycle process is required to give
                                        structure to the adding and removing of data from
                                        the data warehouse, and maintaining a balance
                                        between business, hardware, cost and compliance
                                        considerations.



                                        The data security process is required to ensure
                                        that the organization complies with legal
                                        requirements related to data protection, and that
                                        the data warehouse complies with all the
                                        organizations' internal data policies.



                                        The metadata process is required to ensure that
                                        metadata is captured consistently as part of the
                                        data warehouse development, such that it can be
                                        effectively used in applications including data
                                        quality checking, data profiling and data security.




© 2008 Data Management & Warehousing                                               Page 31
White Paper - Data Warehouse Project Management




Appendix 2 – Project Services
Data Management & Warehousing have a web based project management service configured
for the development and management of data warehouses.

The solution provides a complete environment including version control, ticketing, wiki and
many other features using free, widely available, open source software.




A full description of the service can be found at:

        http://projects.datamgmt.com

A demonstration system can be found at:

        http://projects.datamgmt.com/demo

The Data Management & Warehousing internal project management (screenshot above) can
be found at:

        http://projects.datamgmt.com/datamgmt

A description of how to build the system on your own server can be found at:

        http://projects.datamgmt.com/howto

The company also hosts the service for clients who require a fast start on their projects.



Copyright
© 2008 Data Management & Warehousing. All rights reserved. Reproduction not permitted
without written authorisation. References to other companies and their products use
trademarks owned by the respective companies and are for reference purposes only.

Some terms and definitions taken from Wikipedia




      © 2008 Data Management & Warehousing                                               Page 32

Weitere ähnliche Inhalte

Was ist angesagt?

Wallchart - Data Warehouse Documentation Roadmap
Wallchart - Data Warehouse Documentation RoadmapWallchart - Data Warehouse Documentation Roadmap
Wallchart - Data Warehouse Documentation Roadmap
David Walker
 

Was ist angesagt? (20)

Data Warehouse or Data Lake, Which Do I Choose?
Data Warehouse or Data Lake, Which Do I Choose?Data Warehouse or Data Lake, Which Do I Choose?
Data Warehouse or Data Lake, Which Do I Choose?
 
Capturing Data Requirements
Capturing Data RequirementsCapturing Data Requirements
Capturing Data Requirements
 
Emerging Trends in Data Architecture – What’s the Next Big Thing?
Emerging Trends in Data Architecture – What’s the Next Big Thing?Emerging Trends in Data Architecture – What’s the Next Big Thing?
Emerging Trends in Data Architecture – What’s the Next Big Thing?
 
Microsoft Data Warehouse Business Intelligence Lifecycle - The Kimball Approach
Microsoft Data Warehouse Business Intelligence Lifecycle - The Kimball ApproachMicrosoft Data Warehouse Business Intelligence Lifecycle - The Kimball Approach
Microsoft Data Warehouse Business Intelligence Lifecycle - The Kimball Approach
 
Wallchart - Data Warehouse Documentation Roadmap
Wallchart - Data Warehouse Documentation RoadmapWallchart - Data Warehouse Documentation Roadmap
Wallchart - Data Warehouse Documentation Roadmap
 
Activate Data Governance Using the Data Catalog
Activate Data Governance Using the Data CatalogActivate Data Governance Using the Data Catalog
Activate Data Governance Using the Data Catalog
 
Introduction to Data Governance
Introduction to Data GovernanceIntroduction to Data Governance
Introduction to Data Governance
 
Data Architecture, Solution Architecture, Platform Architecture — What’s the ...
Data Architecture, Solution Architecture, Platform Architecture — What’s the ...Data Architecture, Solution Architecture, Platform Architecture — What’s the ...
Data Architecture, Solution Architecture, Platform Architecture — What’s the ...
 
Operational Data Vault
Operational Data VaultOperational Data Vault
Operational Data Vault
 
Data modelling 101
Data modelling 101Data modelling 101
Data modelling 101
 
Data warehouse presentaion
Data warehouse presentaionData warehouse presentaion
Data warehouse presentaion
 
Lessons in Data Modeling: Why a Data Model is an Important Part of Your Data ...
Lessons in Data Modeling: Why a Data Model is an Important Part of Your Data ...Lessons in Data Modeling: Why a Data Model is an Important Part of Your Data ...
Lessons in Data Modeling: Why a Data Model is an Important Part of Your Data ...
 
Webinar: Decoding the Mystery - How to Know if You Need a Data Catalog, a Dat...
Webinar: Decoding the Mystery - How to Know if You Need a Data Catalog, a Dat...Webinar: Decoding the Mystery - How to Know if You Need a Data Catalog, a Dat...
Webinar: Decoding the Mystery - How to Know if You Need a Data Catalog, a Dat...
 
Business requirements gathering for bi
Business requirements gathering for biBusiness requirements gathering for bi
Business requirements gathering for bi
 
Business Intelligence - Intro
Business Intelligence - IntroBusiness Intelligence - Intro
Business Intelligence - Intro
 
Introduction To Data Warehousing
Introduction To Data WarehousingIntroduction To Data Warehousing
Introduction To Data Warehousing
 
Planning Data Warehouse
Planning Data WarehousePlanning Data Warehouse
Planning Data Warehouse
 
Capturing Business Requirements For Scorecards, Dashboards And Reports
Capturing Business Requirements For Scorecards, Dashboards And ReportsCapturing Business Requirements For Scorecards, Dashboards And Reports
Capturing Business Requirements For Scorecards, Dashboards And Reports
 
Essential Metadata Strategies
Essential Metadata StrategiesEssential Metadata Strategies
Essential Metadata Strategies
 
Data Governance
Data GovernanceData Governance
Data Governance
 

Andere mochten auch

What is a Data Warehouse and How Do I Test It?
What is a Data Warehouse and How Do I Test It?What is a Data Warehouse and How Do I Test It?
What is a Data Warehouse and How Do I Test It?
RTTS
 
Data Warehouse Modeling
Data Warehouse ModelingData Warehouse Modeling
Data Warehouse Modeling
vivekjv
 
Energy Strategy Group_Report 2012 efficienza energetica
Energy Strategy Group_Report 2012 efficienza energeticaEnergy Strategy Group_Report 2012 efficienza energetica
Energy Strategy Group_Report 2012 efficienza energetica
Eugenio Bacile di Castiglione
 

Andere mochten auch (18)

planning & project management for DWH
planning & project management for DWHplanning & project management for DWH
planning & project management for DWH
 
Building an Effective Data Warehouse Architecture
Building an Effective Data Warehouse ArchitectureBuilding an Effective Data Warehouse Architecture
Building an Effective Data Warehouse Architecture
 
What is a Data Warehouse and How Do I Test It?
What is a Data Warehouse and How Do I Test It?What is a Data Warehouse and How Do I Test It?
What is a Data Warehouse and How Do I Test It?
 
Data Warehouse Modeling
Data Warehouse ModelingData Warehouse Modeling
Data Warehouse Modeling
 
DATA WAREHOUSING
DATA WAREHOUSINGDATA WAREHOUSING
DATA WAREHOUSING
 
Enterprise Data Architecture Deliverables
Enterprise Data Architecture DeliverablesEnterprise Data Architecture Deliverables
Enterprise Data Architecture Deliverables
 
Metadata in data warehouse
Metadata in data warehouseMetadata in data warehouse
Metadata in data warehouse
 
Business Analysis Fundamentals
Business Analysis FundamentalsBusiness Analysis Fundamentals
Business Analysis Fundamentals
 
Data Warehouse Design and Best Practices
Data Warehouse Design and Best PracticesData Warehouse Design and Best Practices
Data Warehouse Design and Best Practices
 
Information från Läkemedelsverket #5 2013
Information från Läkemedelsverket #5 2013Information från Läkemedelsverket #5 2013
Information från Läkemedelsverket #5 2013
 
Secure PIN Management How to Issue and Change PINs Securely over the Web
Secure PIN Management How to Issue and Change PINs Securely over the WebSecure PIN Management How to Issue and Change PINs Securely over the Web
Secure PIN Management How to Issue and Change PINs Securely over the Web
 
"15 Business Story Ideas to Jump on Now"
"15 Business Story Ideas to Jump on Now""15 Business Story Ideas to Jump on Now"
"15 Business Story Ideas to Jump on Now"
 
Nt1310 project
Nt1310 projectNt1310 project
Nt1310 project
 
cathy resume
cathy resumecathy resume
cathy resume
 
Credit cards
Credit cardsCredit cards
Credit cards
 
Energy Strategy Group_Report 2012 efficienza energetica
Energy Strategy Group_Report 2012 efficienza energeticaEnergy Strategy Group_Report 2012 efficienza energetica
Energy Strategy Group_Report 2012 efficienza energetica
 
Context Based Authentication
Context Based AuthenticationContext Based Authentication
Context Based Authentication
 
Basics of Coding in Pediatrics Medical Billing
Basics of Coding in Pediatrics Medical BillingBasics of Coding in Pediatrics Medical Billing
Basics of Coding in Pediatrics Medical Billing
 

Ähnlich wie White Paper - Data Warehouse Project Management

White Paper - Data Warehouse Governance
White Paper -  Data Warehouse GovernanceWhite Paper -  Data Warehouse Governance
White Paper - Data Warehouse Governance
David Walker
 
Data warehouse-dimensional-modeling-and-design
Data warehouse-dimensional-modeling-and-designData warehouse-dimensional-modeling-and-design
Data warehouse-dimensional-modeling-and-design
Sarita Kataria
 
Project Management Methodology Guidelines
Project Management Methodology GuidelinesProject Management Methodology Guidelines
Project Management Methodology Guidelines
boetabrad
 
E-Commerce
E-CommerceE-Commerce
E-Commerce
concoff
 
Scorecard & Dashboards
Scorecard & DashboardsScorecard & Dashboards
Scorecard & Dashboards
Sunam Pal
 
PROJECT FAST INVENTORY Delivere.docx
PROJECT FAST INVENTORY  Delivere.docxPROJECT FAST INVENTORY  Delivere.docx
PROJECT FAST INVENTORY Delivere.docx
woodruffeloisa
 
Big data-comes-of-age ema-9sight
Big data-comes-of-age ema-9sightBig data-comes-of-age ema-9sight
Big data-comes-of-age ema-9sight
Jyrki Määttä
 
GenRays Project Scope Document
GenRays Project Scope DocumentGenRays Project Scope Document
GenRays Project Scope Document
April Drake
 
Dw hk-white paper
Dw hk-white paperDw hk-white paper
Dw hk-white paper
july12jana
 
EA for MA - London June 15 - FINAL v1.1
EA for MA - London June 15 - FINAL v1.1EA for MA - London June 15 - FINAL v1.1
EA for MA - London June 15 - FINAL v1.1
Andrew Swindell
 
3rd Year Final Project
3rd Year Final Project3rd Year Final Project
3rd Year Final Project
Conrad Ryan
 

Ähnlich wie White Paper - Data Warehouse Project Management (20)

White Paper - Data Warehouse Governance
White Paper -  Data Warehouse GovernanceWhite Paper -  Data Warehouse Governance
White Paper - Data Warehouse Governance
 
White Paper - Overview Architecture For Enterprise Data Warehouses
White Paper -  Overview Architecture For Enterprise Data WarehousesWhite Paper -  Overview Architecture For Enterprise Data Warehouses
White Paper - Overview Architecture For Enterprise Data Warehouses
 
White Paper - The Business Case For Business Intelligence
White Paper -  The Business Case For Business IntelligenceWhite Paper -  The Business Case For Business Intelligence
White Paper - The Business Case For Business Intelligence
 
White Paper - How Data Works
White Paper - How Data WorksWhite Paper - How Data Works
White Paper - How Data Works
 
Data warehouse-dimensional-modeling-and-design
Data warehouse-dimensional-modeling-and-designData warehouse-dimensional-modeling-and-design
Data warehouse-dimensional-modeling-and-design
 
Project Management Methodology Guidelines
Project Management Methodology GuidelinesProject Management Methodology Guidelines
Project Management Methodology Guidelines
 
A Study Of Agile Project Management Methods Used For IT Implementation Projec...
A Study Of Agile Project Management Methods Used For IT Implementation Projec...A Study Of Agile Project Management Methods Used For IT Implementation Projec...
A Study Of Agile Project Management Methods Used For IT Implementation Projec...
 
Why you need excellent documents and how to produce them… with Enterprise Arc...
Why you need excellent documents and how to produce them… with Enterprise Arc...Why you need excellent documents and how to produce them… with Enterprise Arc...
Why you need excellent documents and how to produce them… with Enterprise Arc...
 
Project Management Methodology Guidelines
Project Management Methodology GuidelinesProject Management Methodology Guidelines
Project Management Methodology Guidelines
 
E-Commerce
E-CommerceE-Commerce
E-Commerce
 
Scorecard & Dashboards
Scorecard & DashboardsScorecard & Dashboards
Scorecard & Dashboards
 
PROJECT FAST INVENTORY Delivere.docx
PROJECT FAST INVENTORY  Delivere.docxPROJECT FAST INVENTORY  Delivere.docx
PROJECT FAST INVENTORY Delivere.docx
 
Big data-comes-of-age ema-9sight
Big data-comes-of-age ema-9sightBig data-comes-of-age ema-9sight
Big data-comes-of-age ema-9sight
 
The Road to IT Governance Excellence
The Road to IT Governance ExcellenceThe Road to IT Governance Excellence
The Road to IT Governance Excellence
 
Using ADO.NET Entity Framework in Domain Driven Design: A Pattern Approach
Using ADO.NET Entity Framework in Domain Driven Design: A Pattern ApproachUsing ADO.NET Entity Framework in Domain Driven Design: A Pattern Approach
Using ADO.NET Entity Framework in Domain Driven Design: A Pattern Approach
 
GenRays Project Scope Document
GenRays Project Scope DocumentGenRays Project Scope Document
GenRays Project Scope Document
 
Dw hk-white paper
Dw hk-white paperDw hk-white paper
Dw hk-white paper
 
sada_shopping
sada_shoppingsada_shopping
sada_shopping
 
EA for MA - London June 15 - FINAL v1.1
EA for MA - London June 15 - FINAL v1.1EA for MA - London June 15 - FINAL v1.1
EA for MA - London June 15 - FINAL v1.1
 
3rd Year Final Project
3rd Year Final Project3rd Year Final Project
3rd Year Final Project
 

Mehr von David Walker

Data warehousing change in a challenging environment
Data warehousing change in a challenging environmentData warehousing change in a challenging environment
Data warehousing change in a challenging environment
David Walker
 
Building a data warehouse of call data records
Building a data warehouse of call data recordsBuilding a data warehouse of call data records
Building a data warehouse of call data records
David Walker
 
Struggling with data management
Struggling with data managementStruggling with data management
Struggling with data management
David Walker
 
A linux mac os x command line interface
A linux mac os x command line interfaceA linux mac os x command line interface
A linux mac os x command line interface
David Walker
 
Connections a life in the day of - david walker
Connections   a life in the day of - david walkerConnections   a life in the day of - david walker
Connections a life in the day of - david walker
David Walker
 
Conspectus data warehousing appliances – fad or future
Conspectus   data warehousing appliances – fad or futureConspectus   data warehousing appliances – fad or future
Conspectus data warehousing appliances – fad or future
David Walker
 
Implementing Netezza Spatial
Implementing Netezza SpatialImplementing Netezza Spatial
Implementing Netezza Spatial
David Walker
 
Storage Characteristics Of Call Data Records In Column Store Databases
Storage Characteristics Of Call Data Records In Column Store DatabasesStorage Characteristics Of Call Data Records In Column Store Databases
Storage Characteristics Of Call Data Records In Column Store Databases
David Walker
 

Mehr von David Walker (20)

Moving To MicroServices
Moving To MicroServicesMoving To MicroServices
Moving To MicroServices
 
Big Data Week 2016 - Worldpay - Deploying Secure Clusters
Big Data Week 2016  - Worldpay - Deploying Secure ClustersBig Data Week 2016  - Worldpay - Deploying Secure Clusters
Big Data Week 2016 - Worldpay - Deploying Secure Clusters
 
Data Works Berlin 2018 - Worldpay - PCI Compliance
Data Works Berlin 2018 - Worldpay - PCI ComplianceData Works Berlin 2018 - Worldpay - PCI Compliance
Data Works Berlin 2018 - Worldpay - PCI Compliance
 
Data Works Summit Munich 2017 - Worldpay - Multi Tenancy Clusters
Data Works Summit Munich 2017 - Worldpay - Multi Tenancy ClustersData Works Summit Munich 2017 - Worldpay - Multi Tenancy Clusters
Data Works Summit Munich 2017 - Worldpay - Multi Tenancy Clusters
 
Big Data Analytics 2017 - Worldpay - Empowering Payments
Big Data Analytics 2017  - Worldpay - Empowering PaymentsBig Data Analytics 2017  - Worldpay - Empowering Payments
Big Data Analytics 2017 - Worldpay - Empowering Payments
 
Data Driven Insurance Underwriting
Data Driven Insurance UnderwritingData Driven Insurance Underwriting
Data Driven Insurance Underwriting
 
Data Driven Insurance Underwriting (Dutch Language Version)
Data Driven Insurance Underwriting (Dutch Language Version)Data Driven Insurance Underwriting (Dutch Language Version)
Data Driven Insurance Underwriting (Dutch Language Version)
 
An introduction to data virtualization in business intelligence
An introduction to data virtualization in business intelligenceAn introduction to data virtualization in business intelligence
An introduction to data virtualization in business intelligence
 
BI SaaS & Cloud Strategies for Telcos
BI SaaS & Cloud Strategies for TelcosBI SaaS & Cloud Strategies for Telcos
BI SaaS & Cloud Strategies for Telcos
 
Building an analytical platform
Building an analytical platformBuilding an analytical platform
Building an analytical platform
 
Data warehousing change in a challenging environment
Data warehousing change in a challenging environmentData warehousing change in a challenging environment
Data warehousing change in a challenging environment
 
Building a data warehouse of call data records
Building a data warehouse of call data recordsBuilding a data warehouse of call data records
Building a data warehouse of call data records
 
Struggling with data management
Struggling with data managementStruggling with data management
Struggling with data management
 
A linux mac os x command line interface
A linux mac os x command line interfaceA linux mac os x command line interface
A linux mac os x command line interface
 
Connections a life in the day of - david walker
Connections   a life in the day of - david walkerConnections   a life in the day of - david walker
Connections a life in the day of - david walker
 
Conspectus data warehousing appliances – fad or future
Conspectus   data warehousing appliances – fad or futureConspectus   data warehousing appliances – fad or future
Conspectus data warehousing appliances – fad or future
 
An introduction to social network data
An introduction to social network dataAn introduction to social network data
An introduction to social network data
 
Using the right data model in a data mart
Using the right data model in a data martUsing the right data model in a data mart
Using the right data model in a data mart
 
Implementing Netezza Spatial
Implementing Netezza SpatialImplementing Netezza Spatial
Implementing Netezza Spatial
 
Storage Characteristics Of Call Data Records In Column Store Databases
Storage Characteristics Of Call Data Records In Column Store DatabasesStorage Characteristics Of Call Data Records In Column Store Databases
Storage Characteristics Of Call Data Records In Column Store Databases
 

Kürzlich hochgeladen

Architecting Cloud Native Applications
Architecting Cloud Native ApplicationsArchitecting Cloud Native Applications
Architecting Cloud Native Applications
WSO2
 
Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024
Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024
Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024
Victor Rentea
 
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers:  A Deep Dive into Serverless Spatial Data and FMECloud Frontiers:  A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Safe Software
 
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
?#DUbAI#??##{{(☎️+971_581248768%)**%*]'#abortion pills for sale in dubai@
 
Why Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire businessWhy Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire business
panagenda
 

Kürzlich hochgeladen (20)

Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost SavingRepurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
 
Architecting Cloud Native Applications
Architecting Cloud Native ApplicationsArchitecting Cloud Native Applications
Architecting Cloud Native Applications
 
Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024
Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024
Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024
 
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers:  A Deep Dive into Serverless Spatial Data and FMECloud Frontiers:  A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
 
MINDCTI Revenue Release Quarter One 2024
MINDCTI Revenue Release Quarter One 2024MINDCTI Revenue Release Quarter One 2024
MINDCTI Revenue Release Quarter One 2024
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected Worker
 
Spring Boot vs Quarkus the ultimate battle - DevoxxUK
Spring Boot vs Quarkus the ultimate battle - DevoxxUKSpring Boot vs Quarkus the ultimate battle - DevoxxUK
Spring Boot vs Quarkus the ultimate battle - DevoxxUK
 
Strategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a FresherStrategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a Fresher
 
JohnPollard-hybrid-app-RailsConf2024.pptx
JohnPollard-hybrid-app-RailsConf2024.pptxJohnPollard-hybrid-app-RailsConf2024.pptx
JohnPollard-hybrid-app-RailsConf2024.pptx
 
ICT role in 21st century education and its challenges
ICT role in 21st century education and its challengesICT role in 21st century education and its challenges
ICT role in 21st century education and its challenges
 
AI+A11Y 11MAY2024 HYDERBAD GAAD 2024 - HelloA11Y (11 May 2024)
AI+A11Y 11MAY2024 HYDERBAD GAAD 2024 - HelloA11Y (11 May 2024)AI+A11Y 11MAY2024 HYDERBAD GAAD 2024 - HelloA11Y (11 May 2024)
AI+A11Y 11MAY2024 HYDERBAD GAAD 2024 - HelloA11Y (11 May 2024)
 
WSO2's API Vision: Unifying Control, Empowering Developers
WSO2's API Vision: Unifying Control, Empowering DevelopersWSO2's API Vision: Unifying Control, Empowering Developers
WSO2's API Vision: Unifying Control, Empowering Developers
 
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
 
Why Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire businessWhy Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire business
 
Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...
Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...
Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...
 
Exploring Multimodal Embeddings with Milvus
Exploring Multimodal Embeddings with MilvusExploring Multimodal Embeddings with Milvus
Exploring Multimodal Embeddings with Milvus
 
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...
 
AWS Community Day CPH - Three problems of Terraform
AWS Community Day CPH - Three problems of TerraformAWS Community Day CPH - Three problems of Terraform
AWS Community Day CPH - Three problems of Terraform
 
Apidays New York 2024 - The value of a flexible API Management solution for O...
Apidays New York 2024 - The value of a flexible API Management solution for O...Apidays New York 2024 - The value of a flexible API Management solution for O...
Apidays New York 2024 - The value of a flexible API Management solution for O...
 
Six Myths about Ontologies: The Basics of Formal Ontology
Six Myths about Ontologies: The Basics of Formal OntologySix Myths about Ontologies: The Basics of Formal Ontology
Six Myths about Ontologies: The Basics of Formal Ontology
 

White Paper - Data Warehouse Project Management

  • 1. Data Management & Warehousing WHITE PAPER Data Warehouse Project Management DAVID M WALKER Version: 1.0 Date: 14/10/2008 Data Management & Warehousing 138 Finchampstead Road, Wokingham, Berkshire, RG41 2NU, United Kingdom http://www.datamgmt.com
  • 2. White Paper - Data Warehouse Project Management Table of Contents Table of Contents ...................................................................................................................... 2! Synopsis .................................................................................................................................... 3! Intended Audience .................................................................................................................... 3! About Data Management & Warehousing ................................................................................. 3! Introduction................................................................................................................................ 4! Common Problems.................................................................................................................... 5! Setting the wrong expectations ............................................................................................. 5! Managing the Technical Architecture.................................................................................... 7! Resource Turnover ............................................................................................................... 8! The building blocks of a project control ..................................................................................... 9! Phases .................................................................................................................................. 9! Milestones ........................................................................................................................... 10! Activities .............................................................................................................................. 10! Tasks................................................................................................................................... 10! Issues.................................................................................................................................. 11! Enhancements .................................................................................................................... 11! Test cases........................................................................................................................... 12! Defects ................................................................................................................................ 12! Risks ................................................................................................................................... 12! The Event Horizon................................................................................................................... 14! Short Term .......................................................................................................................... 14! Medium Term ...................................................................................................................... 14! Long Term........................................................................................................................... 14! Tools and Technology ............................................................................................................. 15! Project Management Software............................................................................................ 15! Ticketing.............................................................................................................................. 15! Version Control ................................................................................................................... 16! Wiki ..................................................................................................................................... 17! Methodologies ......................................................................................................................... 18! Project Leadership .................................................................................................................. 19! The Executive Sponsor ....................................................................................................... 19! Project Sponsor................................................................................................................... 19! Project Manager.................................................................................................................. 20! Technical Architect.............................................................................................................. 20! Senior Business Analyst ..................................................................................................... 21! Leadership Style ................................................................................................................. 21! Organisational Learning ...................................................................................................... 22! Team Rotation..................................................................................................................... 23! Estimating and Effort ............................................................................................................... 24! Tips and Tricks ........................................................................................................................ 26! Summary ................................................................................................................................. 28! Appendix 1 – Governance Procedures ................................................................................... 29! Change Management Processes........................................................................................ 29! Data Warehouse Processes ............................................................................................... 30! Data Management Processes............................................................................................. 31! Appendix 2 – Project Services ................................................................................................ 32! Copyright ................................................................................................................................. 32! © 2008 Data Management & Warehousing Page 2
  • 3. White Paper - Data Warehouse Project Management Synopsis Data warehouse projects pose a specific set of challenges for the project manager. Whilst most IT projects are a development to support a well defined pattern of work a data warehouse is, by design, there to support users asking ad hoc questions of the data available to the business. It is also a project that will have more interfaces and more change than any other system within the organisation. Projects often have poorly set expectations in terms of timescales; the likely return on investment, the vendors’ promises for tools or the expectations set between the business and IT within an organisation. They also have large technical architectures and resourcing issues that need to be handled. This document will outline the building blocks of good project control including the definition of phases, milestones, activities, tasks, issues, enhancements, test cases, defects and risks and will discuss how they can be managed, and when, using an event horizon, the project manager can expect to get information. To help manage these building blocks this paper will look at the types of tools and technology that are available and how they can be used to assist the project manager. It also looks at how these tools fit into methodologies. The final section of the paper has looked at how effective project leadership and estimating can improve the chances of success for a project. This includes understanding the roles of the executive sponsor, project manager, technical architect and senior business analyst along with the use of different leadership styles, organisational learning and team rotation. Intended Audience Reader Recommended Reading Executive Entire Document Business Users Synopsis IT Management Entire Document IT Strategy Synopsis IT Project Management Entire Document IT Developers Synopsis About Data Management & Warehousing Data Management & Warehousing is a specialist consultancy in data warehousing, based in Wokingham, Berkshire in the United Kingdom. Founded in 1995 by David M Walker, our consultants have worked for major corporations around the world including the US, Europe, Africa and the Middle East. Our clients are invariably large organisations with a pressing need for business intelligence. We have worked in many industry sectors but have specialists in Telco’s, manufacturing, retail, financial and transport as well as technical expertise in many of the leading technologies. For further information visit our website at: http://www.datamgmt.com © 2008 Data Management & Warehousing Page 3
  • 4. White Paper - Data Warehouse Project Management Introduction Data warehousing projects are notorious for both being delivered late and over budget. Why is this and what can be done to prevent it? The common problems that affect the data warehouse can be grouped by the expectations that are set, the technology used and the management of resources. There is also a need to define the components of project control and to develop understanding of the level to which these can be planned and forecast. With this understanding it is possible to look at tools, technologies and methodologies that can assist the project manager to control, support and deliver a solution. Finally this paper looks at the impact of project leadership techniques and the effect that good estimate efforts can have on the delivery of a project. This paper does not set out to be an exhaustive manual for the management of a data warehouse project, rather a guide to help project managers understand the difference between data warehousing projects and others that they may have been responsible. It also suggests some things that should be considered when managing such projects. © 2008 Data Management & Warehousing Page 4
  • 5. White Paper - Data Warehouse Project Management Common Problems Data warehouse projects often suffer from poorly set expectations, problems with the technical architecture and resource turnover. These common categories have multiple and varied underlying causes: Setting the wrong expectations The failure to set the right expectations of a data warehouse is part of every project and the reason that they are often perceived not to deliver. This failure to set expectations occurs at many levels: • Timescales For most large organisations a data warehouse project will have many phases, take years to build and have to be supported for many more years afterwards. Development and production phases will overlap and once in production the environment will be subject to massive amounts of change. When a Data Warehouse project is conceived it will not be discussed in these terms but as just another project with a finite timescale and a simple set of phases. • Return on Investment The business case generated to justify a data warehouse project will always make a number of promises about return on investment, which are deemed necessary to get the budget. However, the real benefit will either come from an unexpected quarter (e.g. a fraud being discovered or the ability to drop a costly product range) or be from intangible benefits (e.g. business analysts that stop creating their own small database and spreadsheet applications and start analysing the business and delivering indirect business benefit). Business cases should be looked upon as a reason for starting rather than a defined return on investment. The deliverable, and therefore the return on investment should be measured in terms of what benefit was derived rather than against some planned benefit. Some phases will deliver more, and some less than expected. • Vendor set expectations of tools Data Warehousing and Business Intelligence tool are purchased with an expectation of productivity gains and reduced total cost of ownership however the reality is often more complex: o One reporting tool will not be sufficient for all your reporting needs. o An ETL tool provides a well-defined development environment but often does not provide the productivity benefits promised and requires more expensive, specialist resources. o It is often difficult to integrate the tools in the advertised way. o Changing from one tool to another often does not fix the underlying issue, or does so only at significant cost. o Technology sets leapfrog one another; a unique feature in one tool will often be in another with the next release. © 2008 Data Management & Warehousing Page 5
  • 6. White Paper - Data Warehouse Project Management • IT set expectations to the business IT are often guilty of being over-optimistic about the point at which the benefit will occur: o The initial phases of a project are about understanding and infrastructure. It is only when these are in place that the business facing solution can be deployed. o Quick-win solutions, whilst valuable in the short-term, have a long-term cost that has to be accounted for. This is because there is both an on- going management cost and a de-commissioning cost that the business will have to pay later. Quick-win solutions often also compromise data quality that in turn damages user confidence in the system o The final solution can never be reconciled exactly against the current solution, this is because there will be unknown bugs in the currently delivered solution, new sources of data and different treatments of that data. It should, however, be possible to explain all the differences. o The testing and issue resolution of a system will take longer than expected. • Business set expectations to IT The business will often point to IT for its failings but it too will fail to manage expectations. Commonly: o The business will not invest the time required to deliver requirements and analysis. o The data quality will be much worse than the business is prepared to acknowledge and the business will be slow to respond to the need to change working practices to improve the data quality. o The business will not spend enough time or dedicate enough resource to testing. o The business will not spend enough time or dedicate enough resource to training. o There will be phases of the project where they lose focus as other business critical events take place. o When the time comes to de-commission existing solutions and tactical solutions built along the way the business will be unwilling or unable to do so, often fearing that some piece of data has been overlooked. © 2008 Data Management & Warehousing Page 6
  • 7. White Paper - Data Warehouse Project Management Managing the Technical Architecture The technical architecture of a data warehouse is the framework on which the solution is delivered. Data Warehouses are often described as ‘complex’ without further explanation. It is not that the process itself is difficult (copy data from the source systems, format it and write a report on it), nor does it need unusually complex technology to deliver. Instead the complexity comes from the scale of the solution. A reasonable sized data warehouse will have thousands of individual ETL mappings and hundreds of reports all serving a large community of users quickly. In order to do this it is important to observe the following principle: Keep the architecture simple Whilst this may seem obvious, simplicity is hard to do and has to be regularly worked on. Keeping things simple requires a conscientious decision. Some common examples include: o Small is beautiful. Creating more simple ETL mappings rather than large single blocks of code makes change and maintenance easier. Have a larger number of smaller data marts rather than one single ‘super- mart’ which results in complex change management. Have multiple reports for different people instead of one that tries to satisfy everyone. A change to meet a requirement from one user will undoubtedly leave another user unhappy. o Have discreet ‘componentised’ functionality. Use the right tool for the job. For example don’t store data in the ETL tool, don’t use a reporting tool to perform ETL, extract data for downstream sources in a consistent way, etc. o Ensure that the data load process is complete and auditable. It is common for data warehouses to allow direct updates to the database by DBAs etc to maintain reference data. This should be prohibited and an 1 application provided to the business for them to perform this functionality. o Minimise components. There is often a temptation to make tweaks to the technical architecture to have a larger number of ‘best of breed’ tools to accommodate certain requirements. In practice this increases the maintenance costs and support skills required whereas the existing toolset can often provide a sufficient solution. o Keep it clean. A data warehouse whose data is not clean quickly falls into disrepute and becomes unused. The technical architecture has to support data quality monitoring and data cleansing and there must also be processes to deliver change in the source system. 1 This may seem counter-intuitive, how can writing a whole separate application to maintain data be simpler than just writing the SQL? The reason for this requirement is that there is no audit trail and therefore no way of knowing what updates have been done. If instead a business user has to maintain the data via an application and this is loaded into the data warehouse via ETL then the business takes responsibility for maintaining the data and there is an audit trail of where the data change came from. Writing SQL also creates a large number of small, ad-hoc SQL jobs. This takes time and sooner or later someone will make a mistake with the SQL that may take a lot of work to correct. © 2008 Data Management & Warehousing Page 7
  • 8. White Paper - Data Warehouse Project Management o Tactical Solutions. Every project has them and there is often a very good case for them but they always cost more to remove than to create and often de-rail the ‘keep it simple’ principle. If tactical solutions become necessary then they should have an implementation, an expected lifetime, maintenance cost for the lifetime, a lifetime-overrun cost and a decommissioning cost. When presented with these costs tactical solutions often look a lot less appealing. o Have an active de-commissioning policy. Data Warehouses have a lot of code that needs to be maintained and takes time to run. If database entities are no longer used then de-commission them and the ETL that feeds them. The same is true for a report that has been replaced or just fallen into disuse. Resource Turnover Data Warehouses are long-term projects and are likely to engage internal and external staff for several years. For a variety of reasons staff will come and go during that time. It is also possible for the new arrivals to bring new ideas and ways to improve what is being done. Whilst this is to be welcomed it also presents a very specific and potentially expensive risk. This often manifests itself when new members of staff come in and say ‘I wouldn’t have done it this way – let’s start doing it another way’ For whatever reason a significant change in direction most often results in one of two outcomes; expensive re-work to keep a consistent architecture or a complex architecture that requires more 2 support and documenting the route to the current point can avoid such re-work. In addition ensure that there is sufficient briefing material available so that new starters can get up to speed quickly and before launching into the ‘I wouldn’t have done it this way’ discussions. 2 Key Design Decisions – a template for documenting critical decisions in the design process. See the ‘Data Warehouse Documentation Roadmap’ white paper from Data Management & Warehousing © 2008 Data Management & Warehousing Page 8
  • 9. White Paper - Data Warehouse Project Management The building blocks of a project control The following section offers a description of the components of the project control (the project plan in conjunction with project risks, issues and defects). Whilst all the terms will be familiar to readers they are described here to ensure consistent use and discuss the interaction between them. Phases The phase of the program is a set of work with a defined outcome that delivers benefit to the project as a whole. Note that there should be phases of the project that do not deliver direct business benefit but are required for the project to succeed. It would be common for a data warehouse project to have the following initial phases: • Phase 1: Mobilisation (2 weeks). This short phase at the start of a project aims to get everything ready for the team to begin. It includes getting building passes, office space, network access, systems permissions and other basic structures in place. Too often 3 there is a perceived need to see everyone on site and working on day one. In reality this normally wastes a significant amount of resource that will be required in the later phases of the project. • Phase 2: Technical Architecture & Initial Business Requirements (4-8 weeks). This second phase is about putting a sound basic infrastructure in place. The technical architecture provides a solid platform on which to build whilst the initial business requirements are used to develop a list of priorities for development. These also provide the basis for developing the initial resourcing plans for enlarging the team. • Phase 3: Data Warehouse Infrastructure Deployment (4-8 weeks). With this phase sufficient hardware and software is deployed and the initial data warehouse logical data model created and a plan for the subsequent phases of data mart deployment is developed. • Subsequent Phases: Data Mart Delivery (3-6 months each). From this point on the iterative development of data marts and reporting solutions can begin. Each phase represents a deliverable of direct business benefit. Phases can overlap but only in a controlled way such as not to cause resourcing or technical conflict between phases. The above outline means that whilst the speed of delivery gets faster later in the project the initial delivery will be six to nine months from inception. 4 Phases are often driven by an enhancement packaging process that groups together a series of requirements and enhancements into a phase scope definition. 3 This is particularly common in system integrator run projects where the client often says “How big is your team and when will they arrive?” because the client want to see movement on the project. 4 See Appendix 1 for a description of governance processes for a data warehouse environment © 2008 Data Management & Warehousing Page 9
  • 10. White Paper - Data Warehouse Project Management Milestones Milestones are the checkpoints within a phase of the project. For example each data mart phase may have milestones that indicate the completion of Requirements Gathering, Analysis, Design, Build, Test, Deployment, Training, etc. Activities Activities describe what needs to be done to complete a specific milestone. Therefore the milestone ‘Analysis Complete’ may have activities such as ‘Identify Potential Source Systems’, ‘Perform Data Quality Analysis’, ‘Perform Source System Analysis’, etc. These are normally carried out by a team or group of people and normally have estimated elapsed durations associated with them. Whilst some activities are dependent on others many will have dependencies at a lower level. For example whilst the activity ‘Indentify Potential Source Systems’ is going on there may be no reason why the ‘Perform Data Quality Analysis’ for the first identified system cannot start. It is often difficult to represent this in a project management tool and common for project managers to reflect the situation as a number of activities of fixed duration that are dependent on the completion of one before the next starts, or not to have any dependencies between activities. Both methods cause the plan to slip. Tasks Tasks are the specific items of work to be carried out by an individual. It is important that a named individual is responsible for the task, not a group or a team. Where a task is not yet assigned to an individual it should be assigned to the team leader so that they are aware that they have to (re-)assign it on to someone to actually do the work. It should also be noted that tasks can have sub-tasks, for example the task ‘Document Technical Architecture’ may require sub-tasks of ‘Document Database Architecture’ and ‘Document Hardware Architecture’. All three of these tasks should also have an individual owner who may or may not be the same person as the person responsible for bringing the whole document together. Tasks also have real dependencies on other tasks being completed. Individuals can work very effectively if they have a bank of outstanding tasks, each with a priority and if they cannot work on one task can move to the next one quickly and easily. Issues may hold up tasks. © 2008 Data Management & Warehousing Page 10
  • 11. White Paper - Data Warehouse Project Management Issues An issue is something that affects the progress of the project. Issues can occur at a project level or affecting an individual task. For example: • A team member going off unexpectedly on long-term sick leave is a project level issue that needs to be resolved. • The inability to get a username and password for an individual system that prevents someone completing a source systems analysis is a task level issue. Issues introduce delays in the project and so it is important to see the impact of issues as soon as possible. • Project level issues should be driven down to task level as quickly as possible. Using the example above of long term sickness the process of driving it down to task level would be to re-assign tasks that belonged to that individual to others. • Task level issues often mean that the person responsible moves onto the next task in the task bank and can come back to the other task when the issue is resolved. Mistakes and consequently issues are inevitable on a project. As such active management and an environment where mistakes are accepted, learnt from and documented is to be favoured over one in which people try to hide their mistakes. An understanding of the types of issues over the lifecycle of the project is the first step towards improving both the quality and speed of delivery. An Issue Management 5 Process should manage issues Enhancements An enhancement is a change to the system with the aim of improving it. In a development such as a data warehouse where new requirements are continuously being developed it usual that an enhancement is captured, considered and if appropriate worked into the requirements documentation for inclusion in a subsequent phase via the enhancement packaging process. Not all enhancements need to go through the requirements process. Some, such as an improved navigation paradigm for the user interface, may be considered and passed directly as a task to the person who can affect the change. This rapid response process is very useful if there are separate teams responsible for issues and maintenance as well as the main development teams. 5 See Appendix 1 for a description of governance processes for a data warehouse environment © 2008 Data Management & Warehousing Page 11
  • 12. White Paper - Data Warehouse Project Management Test cases Test cases are a special type of task associated with testing. A test case is a set of tasks supported by scripts and routines that help automate and manage the testing of software. Every piece of code developed should have an associated test case. Where an issue is found with the code it becomes a defect that has to be rectified. A test case may reveal many defects, or none and test cases may have to be repeated a number of times until the code is defect free. In some environments it is useful to consider not only code but also the review of documents as test cases and the issues raised from the review as defects. This allows a separation in the reporting between tasks originally associated with the plan and work carried out because of the incompleteness of the deliverable (i.e. defects). The test case for a document would simply be to review it. As with issues above, mistakes are inevitable in the development process and therefore should be accepted and documented as part of improving the process rather than being hidden away. Defects Defects are a special type of issue associated with testing. A defect is a material error with a deliverable. In the case of code this may be as a result of an undelivered but promised requirement, a misinterpretation of the requirements, unexpected results (common when testing boundary conditions and exceptional usage) etc. A defect should be resolved before the code is deployed (even if the resolution is to say that the functionality will be delivered in a subsequent phase). This can also be applied to review comments for documentation that are, in effect, defects in the deliverable. Each defect should be reviewed and changes applied where appropriate before the defect is closed. Risks There may be external circumstances or events that cannot occur for the project to be successful. If you believe such an event is likely to happen, then it would be a risk. Identifying something as a risk increases its visibility, and allows a proactive risk 6 management plan to be put into place. If an event is within control of the project team, such as having testing complete by a certain date, then it is not a risk. If an event has a one hundred percent chance of occurring, then it is not a risk, since there is no "likelihood" or risk involved but it is an issue. Examples of risks might be a "Re-organization may result in key people being reassigned," or "The new hardware may not be able handle the expected volume." Risks are managed by developing mitigations or ways in which to avoid the risk or prevent it from becoming a reality. 6 http://www.mariosalexandrou.com/definition/risk.asp © 2008 Data Management & Warehousing Page 12
  • 13. White Paper - Data Warehouse Project Management A risk can be quantified in two dimensions: • The first is the probability of it happening which is a measure of how likely it is that a risk will become an issue. • The second is the impact that is a measure of the impact in terms of resource, time or scope. Projects usually measure both of these dimensions on a High/Med/Low type scale. This can produce a grid as illustrated. The grid can then be used to assess the level of mitigation (or actions to prevent the risk from becoming an issue) that should be associated with each of the risks. Obviously the ‘hotter’ the risk the more attention that should be paid to developing mitigation for that risk. This can all be summarised in the diagram below: Figure 1 - Project Control © 2008 Data Management & Warehousing Page 13
  • 14. White Paper - Data Warehouse Project Management The Event Horizon Projects are often expected to have detailed plans from start to finish; in practice this is both unrealistic and impossible to maintain for data warehouse projects. Instead projects should aim to deal with the plan depending on when events are likely to happen. Short Term Current or near term phases need to be tracking every aspect of the work from the scope (enhancements) through milestones, activities, risks, tasks, test cases and for the current and next phase issues and defects. It is the issues and defects that will cause the current phase to be delayed or have other resource impact. The financial implications in the short term are over-spending or use of contingency because there is no space in which to manoeuvre. Medium Term Phases further out need to have the scope, milestones, activities, risks and where possible tasks planned out. These plans, their timescales and the budget for these phases should be adjusted in the light of experience gained on current and previous phases should influence the work being defined for these phases. Long Term Long-term plans are normally limited to rough scopes of work and timescales (for example we hope to add market segmentation to the data warehouse and expect it to take 5 people 3 months). This allows estimated budget requirements to be calculated but is highly dependent on the timescales and successful delivery of the previous phases. Learning from current work will improve the estimating over time. Using the above definitions it is possible to indicate what information a project manager should ideally have available in the following graphical way: Figure 2 - Information available to a project manager In practice managers normally have even less information available (indicated by the red line). This means that both the short-term and medium-term horizons each cover two phases rather than the three phases of the ideal situation. The long-term view is then restricted to knowing what enhancements are needed. © 2008 Data Management & Warehousing Page 14
  • 15. White Paper - Data Warehouse Project Management Tools and Technology In order to manage such a large-scale project it is important to use a number of tools to help keep track of all the aspects of the project. 7 There are six major groups of software that are needed for corporate programme/project management: 8 • Project Management Software 9 • Collaborative Software 10 • Ticket Tracking Systems 11 • Project Portfolio Management 12 • Resource Management 13 • Revision Control For a data warehouse it would be common to use the following tools in the following way: Project Management Software Most organisations either have a large centralised project management system such as Primavera P3 or desktop project management systems such as Microsoft Project. These provide the high-level Gantt charts and resource management. In the components outlined above it is most common to put the phases, milestones and activities into this type of tool. The detailed and changing nature of the tasks makes most of the tools unsuitable for the level of detail required. Also the tools tend to be inaccessible to those doing the work for a number of reasons: • Organisations are unwilling to invest in licences for every team member. • Applications require a desktop/laptop install. • Developers are unwilling to engage in using a project management tool. • Project managers don’t share the plan with developers for fear of contradiction about the proposed timescales As a result these tools are useful for holding the phase, milestone and activity level information but are rarely useful for task level information in data warehouse projects due to the large number of interlinking tasks required to manage the environment. Ticketing Ticketing systems are often used to track issues with software but their use can be much broader. Most ticketing systems allow the classification of tickets as well as dependencies between tickets and a workflow element that allows tickets to be assigned to others. A well-configured system is therefore the ideal tool for managing tasks, issues, risks, test cases, defects and individual enhancement requests. Tasks are initially raised; as the team member works on the task they may create dependant or sub-tasks (often as simple reminders to themselves or others). When issues arise they are captured against the task that is being affected allowing project 7 http://en.wikipedia.org/wiki/List_of_project_management_software 8 http://en.wikipedia.org/wiki/Project_management_software 9 http://en.wikipedia.org/wiki/Collaborative_software 10 http://en.wikipedia.org/wiki/Issue_tracking_system 11 http://en.wikipedia.org/wiki/Project_Portfolio_Management 12 http://en.wikipedia.org/wiki/Resource_Management 13 http://en.wikipedia.org/wiki/Revision_control © 2008 Data Management & Warehousing Page 15
  • 16. White Paper - Data Warehouse Project Management managers to see what is impacting the project timelines. The same is true for the other ticket types (enhancement, risk, test case and defect). Deploying a ticketing system, and opening it to everyone involved in the project from business user to developer, allowing everyone to see everything, can have dramatic effects on the speed and quality of development. It is important that the culture around the system is one of mutual trust and respect. It is easy for a poor manager to go and count the number of defects in an individual developer’s code as a KPI of that developer’s performance. This is very naïve for two reasons: it discourages honesty and it does not measure performance at all. Discouraging honesty is a disaster, because the manager will never know the true state of the project again. The number of defects against one developer may be high because that person is the most skilled developer and therefore gets the most difficult work to do, because the specification was wrong, because the source system has changed, or because the requirements changed when the users saw the initial 14 results. An effective ticketing system will also highlight delays and bottlenecks in the process where, for example, critical blocking tasks go unanswered. Careful review of this information allows risks and issues to be addressed early, thus reducing impact and for an understanding of the root cause of delays to be gained which can be used to speed up subsequent phases. It also removes the process whereby the project manager each week goes around and disturbs everyone else on the project to get an update on the status of each task, which wastes huge amounts of time for those disturbed. A project manager can get the status from the system and then talk to those individuals whose tasks and issues have a material effect on the status of the project. This is management by exception rather than micro-management of the process. Version Control A version control system is vital to the development of a data warehouse, not just for the code developed but every document used throughout the life of the project and subsequent maintenance. Whilst there are products especially built for document rather than code version control it is often sufficient just to use the same piece of software. The advantages of source code control have long been established but documentation control is often not addressed. If there is a requirements document on a shared drive that is updated when a new requirement emerges and (if the author remembers) the version number on the front page or in the file name is updated this does not mean that everyone working on the project has the same document. If someone copies it to their laptop to work on it at home over the weekend and on their return copies back to the shared drive all would appear well. The issue arises if two people have had the same idea, when the second person copies their work back to the shared drive the first person’s work is simply overwritten. 14 This is a failing in the requirements capture process that should be picked up by the project manager from these tickets and corrected © 2008 Data Management & Warehousing Page 16
  • 17. White Paper - Data Warehouse Project Management Using a version control system also means that the development team can work against a fixed version of requirements for a period of time, even if others in the organisation are still updating the requirements. This stability allows the development process to be smoother and a gap analysis performed at a later stage to understand what has changes allows the developers to catch up with the requirement (normally in another phase). Finally the repository provides an auditable trail of the changes in all aspects of the project documentation that again can help with improving future phases. Wiki The introduction to this section described collaborative software that covers a broad swathe of technology. In practice the most useful software that one can use is a wiki. This provides a number of web pages that any user can update with a syntax that is simpler than standard HTML. The pages that get created are often part of the informal structure that helps the programme move along. Wikis can be used for frequently asked questions, staff lists, announcements, social events, guides to using other parts of the project, etc. Since they are a shared resource, editable by all they can provide a productive communication tool that is far more effective than email for encouraging collaboration. Wikis are more common than most people realise with websites such as Wikipedia using the same quick, cheap, easy software to build an encyclopaedia that can be deployed as the team’s main source of information for the project. It can also have the ‘water-cooler’ effect where people from IT and the business collect to share information in an informal manner rather than through formal documentation or review processes. © 2008 Data Management & Warehousing Page 17
  • 18. White Paper - Data Warehouse Project Management Methodologies Most organisations will have a preferred IT development methodology. It is likely that the 15 larger the organization the more structured the methodology (for example PRINCE2 or other 16 waterfall approaches). These processes are often assessed by mechanisms such as CMMI. 17 Few large organisations are willing to adopt agile approaches despite both the business side saying that IT should deliver faster and meet requirements more completely and the IT side saying that they are trying to be flexible and meet that demand. As a result the organisations’ methodologies will not be well suited for the development of a data warehouse. This is because most methodologies have a fixed scope and a clear objective. The deployment of a new financial package covers certain well-defined business processes, has well understood inputs and outputs and bears scrutiny by use cases to examine the steps. A data warehouse is a system that will have a number of fixed outputs but also the intangible ‘just load up the data and I will know what I need when I see it‘ type requirement. It has a 18 huge number of changing inputs from the source systems and often has large parts that will be in production whilst others are under development causing a crossover between the deployment and maintenance phases. Data warehouses are therefore inherently risky ventures and yet assessments such as CMMI 19 set out to avoid projects that carry risk. In Peopleware it suggests of CMMI assessments: The projects most worth doing are the ones that will move you DOWN one full level on your process scale Trying to deploy large-scale data warehouses in large organisations is what has lead to the concepts described in this document, whereby phases, milestones and activities can be managed within the organisation’s standard structures but allowing more agile development methods at the task level as well as detailed tracking of the relationship between issues and tasks which improves time and resource management. Remember that it is the deliverable and not the methodology used to get there that is important. It is all too easy to get trapped in trying to complete a methodology rather than the deliverable. 15 http://en.wikipedia.org/wiki/Prince2 16 http://en.wikipedia.org/wiki/CMMI 17 http://en.wikipedia.org/wiki/Agile_software_development 18 Imagine an organisation that has 25 source systems and two software upgrades/patches a year to each of them. This means that there are 50 changes a year or one a week to be analysed, designed, build and tested as well as managing maintenance and other issues that arise. 19 Peopleware – Productive Projects and Team: Tom DeMarco and Timothy Lister, Dorset House Publishing, Second Edition 1999, Chapter 29: Process Improvement Programmes © 2008 Data Management & Warehousing Page 18
  • 19. White Paper - Data Warehouse Project Management Project Leadership The single biggest impact on any project comes from the leadership it receives. Since a data warehouse is such a long-term commitment the leadership staff should understand that they are entering into a project that they may be engaged in for several years. A revolving door policy of leaders will only slow the project down. The project leadership comes in two parts: • The sponsors: An executive sponsor and his delegate, the project sponsor, who commission the project and will ultimately, control its use. • The project team: Leadership within the team normally consists of three individuals, a project manager, a senior technical architect and a senior business analyst who must work together to deliver, each taking responsibility for their own area but deferring to the others for their respective areas of responsibility. The roles are outlined in more detail below: The Executive Sponsor The Executive Sponsor is a senior manager or executive with demonstrable interest in the outcome of the project, who is ultimately responsible for securing spending authority and resources for the project. Ideally, the Executive Sponsor should be the highest-ranking manager possible, in proportion to the project size and scope. The Executive Sponsor acts as a vocal and visible champion, legitimizes the project’s goals and objectives, keeps abreast of major project activities, and is the ultimate decision-maker for the project. The Executive Sponsor provides support for the Project Sponsor and the Project Manager. They have final approval of all scope changes, and signs off on approvals to proceed to each succeeding project phase. The Executive Sponsor may elect to delegate some of the above responsibilities to the Project Sponsor (sometimes known as the Executive Sponsor’s Agent). Project Sponsor 20 The Project Sponsor is someone who strongly supports the objectives of the project and is willing to act as a champion and advocate on behalf of the project. To this end they are the primary source of business input and take ownership from a business and governance perspective. This can be broken down into six main responsibilities: • Accountability The project sponsor is responsible for holding the project manager to account and consequently keeping the project on track. The project sponsors must also make themselves available to provide support and address risks and issues. 20 Adapted from: http://www.stanford.edu/dept/its/projects/PMO/files/linked_files/guidelines_sponsors.pdf http://ithelp.lincoln.ac.nz/site/story_images/3021_project_sponsor_s8869.pdf http://www.cit.cornell.edu/computer/robohelp/cpmm/Project_Roles_and_Responsibilities.htm © 2008 Data Management & Warehousing Page 19
  • 20. White Paper - Data Warehouse Project Management • Strategic Fit Assure that the project is aligned with the organization’s strategic goals. • Resources Provide or locate resources for the project especially where these are outside the control of the project manager and protect resources from being pulled away. • Project Finances Provide or locate funding for the project and track the budget in conjunction with the project manager. • Lead Political Charge Help the project manager navigate the organization’s political environment. • Own the Final Product Be clear on what is expected in the end and help celebrate & transition. Project Manager The Project Manager is the person responsible for ensuring that the Project Team completes the project. The Project Manager develops the project plan with the team and manages the team’s performance of project activities. It is also the responsibility of the Project Manager to secure acceptance and approval of deliverables from the Project Sponsor and other stakeholders. The Project Manager is responsible for communication, including status reporting, risk management, escalation of issues that cannot be resolved in the team, and, in general, making sure the project is delivered in budget, on schedule, and within scope. Technical Architect The Technical Architect is the single point of responsibility for the technical solution from an application and system perspective. The main responsibilities of the Technical Architect are to: • Define the technical architecture • Solve technical issues • Ensure that all components of the technical architecture are properly integrated and implemented • Define the development tools and environment • Coach the technical team in the development of the technical architecture • Provide technical support and technical quality control throughout all stages of the project • Co-ordinate vendor services related to technology selection and implementation • Work with the Senior Business Analyst to determine how the technology can be applied to meet the business needs • Work with the Project Manager to ensure the smooth running of the project • Evangelise the technical solution to the rest of the IT community and the business © 2008 Data Management & Warehousing Page 20
  • 21. White Paper - Data Warehouse Project Management Senior Business Analyst The Senior Business Analyst is responsible for: • Analysing and Defining the business requirements and solution • Quickly and clearly understanding the business issues and data challenges • Identifying the organization's strengths and weaknesses and suggesting areas of improvement. • Reviewing and editing requirements, specifications, business processes and recommendations related to proposed solution. • Leading the testing efforts • Working with the business to identify required changes • Communicating the required changes to the development team • Work with the Technical Architect to determine how the business need will be met by the technology • Work with the Project Manager to ensure the smooth running of the project • Evangelise the business solution to the rest of the IT community and the business Leadership Style Managing a small team to develop a large complex environment requires a degree of skill and the ability to adjust the style of leadership to match the situation. This type of flexibility is known as situational leadership and is a necessary quality in a data warehouse project. 21 Kenneth Blanchard wrote “... managers should work for their people, ... and not Supporting Coaching the reverse. ... If you think that your people are responsible and that your job Supportive Behaviour is to be responsive, you really work hard to provide them with the resources and working conditions they need to Delegating Directing accomplish the goals you've agreed to. You realize your job is not to do all the work yourself or sit back and wait to 'catch them doing something wrong', but to roll up your sleeves and help them Directive Behaviour win. If they win, you win.” As staff develop on a data warehouse project it is typical for a good leadership team to move from a directive style through the coaching style and supporting style and ultimately reaching the delegating style. For example the technical architect may start with ‘Build the data warehouse this way’ moving through ‘We build the data warehouse this way because …’ and ‘I like what you have done but have you considered …’ and ending with ‘Thanks, that’s just what I envisioned’. To this end a strong relationship and shared vision between project manager, technical architect and senior business analyst is essential. 21 "Leadership and the One-Minute Manager", Kenneth Blanchard, Patricia Zigarmi, and Drea Zigarmi, p18. This is a refinement of Path-Goal Theory developed by Robert House in 1971 © 2008 Data Management & Warehousing Page 21
  • 22. White Paper - Data Warehouse Project Management Organisational Learning Most people working on a project will learn in some way, but this knowledge, locked away in an individual, is of little value to the business as a whole. The team have to become a learning organisation that actively creates, captures, transfers and mobilizes 22 knowledge to enable it to adapt to a changing environment. 23 “Knowledge is not knowledge until someone else knows that one knows.” For a data warehouse project organisational learning is critical, as, not only is the environment rapidly changing but the number of places from which information is sourced is larger than any other IT project the business is likely to engage in. In this context information is more than data being transferred inside systems, it also includes information about how business processes work, key contacts both inside and outside the organisation, critical business requirements, data quality issues, etc. Organisational learning is a cultural phenomenon that requires team members to actively participate in developing knowledge. To this end a ticketing system, wiki and document versioning system provide tools but it is the people who have to engage in the concept and as a result be willing to: • Share information in a timely fashion • Capture even the most incidental information • Provide access to work in progress • Be open about issues and mistakes • Submit everything to a rapid peer review processes • Re-use rather than re-invent • Research and capture research for others to use • Have largely unrestricted access to the entire project knowledge repository • Accept change as inevitable and be prepared to adapt A team that has a culture capable of organisational learning will be: • More productive because they have the information to do the job • Happier because they are learning and their contribution is recognised • Less prone to expensive re-work as issues are addressed earlier All of this leads to faster, more successful projects. 22 http://en.wikipedia.org/wiki/Organizational_learning 23 Gaius Lucilius c180Bc-103BC © 2008 Data Management & Warehousing Page 22
  • 23. White Paper - Data Warehouse Project Management Team Rotation It is common practice for the most experienced developers to be put in change of major enhancements and then in a sliding scale of experience to assign people to maintenance work and issue resolution. This has initial benefits of getting the best developers to do the largest chunk of work but projects can also benefit from rotating people so that after the enhancement is developed those resources move to the issue handling and other developers move up to maintenance from issues and to enhancements from maintenance. This has a number of very positive aspects. Firstly the most skilled developers have done the first development, and have therefore laid down the principles and standards for future development that the others will follow. By moving these people into issue handling they also become aware of the consequences of their work and any quality or design issues that have been introduced. For the other less experienced teams they see career development as they can learn new skills and have an opportunity to show that they can move up to the next level. If problems occur they can still be supported by more senior developers but it is better to allow people learn early. This practice is also helpful in staff retention because it creates varied work and an opportunity to learn. It also means that people will work across subject areas and therefore have a greater understanding of the whole. This in turn makes it easier when individuals do leave as combined with the organisational learning discussed above the team is greater than the sum of its parts. © 2008 Data Management & Warehousing Page 23
  • 24. White Paper - Data Warehouse Project Management Estimating and Effort Initial estimating on a data warehouse project will always be very subjective and therefore wrong. Plans will often start with what the developer feels is required (and therefore very high) and then adjusted down to meet what the project manager feels is acceptable (and therefore very low). The final value will be somewhere between the two. It is important that everyone understands that the timescales will change in light of experience. Subsequent re-assessments of effort will become more accurate if the organisation is willing to learn. This is often done by the organisational learning process described above, combined with end of milestone or phase reviews and detailed reviews of the ticketing system – what issues arose, will similar issues arise in the next development and how to allow or compensate for them. Tasks are also non-uniform, some tasks will take a short amount of time – often those at the start and the end of a phase, others will take a longer period – often those in the middle of the 24 phase. Project monitoring systems that determine completeness by the number of tasks complete as a percentage of the total number of tasks will see the project initially getting ‘ahead of schedule’ before ‘falling massively behind schedule’ and finally ‘recovering some of the lost time’. This is exacerbated by the fact that if a ticketing system is used additional tasks will be created and therefore the percentage complete will appear to drop at some points in the project. Better measures are around the ratio of tasks to issues and the completion of activities to planned activity duration. Agile and other similar methodologies provide several techniques for improving the estimation. 25 The first of these is velocity (or sometimes better known as load factor). This is the ratio between the developers’ estimate and what is actually achieved. So if a task is estimated as taking 4 days and then takes 10 days the “velocity” is 10/4 or 2.5. For the next phase the developers’ estimates are taken and multiplied by 2.5 to determine the likely timescale. The velocity is measured for each estimate and whilst initially it will oscillate widely after a few iterations it will settle to a factor that can regularly be used calculate elapsed time. The accuracy comes from allowing for two factors. The first factor is the developers own tendency to over or under estimate the effort required to do any given piece of work. The second factor is the distraction that the work environment provides with telephone calls, e- mails and meetings, etc. These work distractions usually have an organisation specific pattern that is not normally factored in by developers but needs to be consistently applied to plans Over a period of time developers will come to understand their own estimating and their velocity will tend to a constant. The consistency of this number is what allows project managers to be able to estimate accurately. 26 Agile development processes also introduce the concept of technical debt . This is the obligation that an organization incurs when it chooses a design or construction approach that is expedient in the short term but that increases complexity and is more costly in the long term. 24 See the Data Management & warehousing white paper “How Data Works” for a discussion of volume vs. complexity in data and how this affects the timescales in a data warehouse project. 25 Version One discussion of Velocity: http://www.versionone.com/Resources/Velocity.asp 26 First proposed by Ward Cunningham in 1992 at the OOPSLA92 conference (http://c2.com/doc/oopsla92.html) © 2008 Data Management & Warehousing Page 24
  • 25. White Paper - Data Warehouse Project Management Technical debt can occur accidentally (when a mistake is made) or deliberately (when a conscience decision is made to put something off). The secret to a successful implementation is to continually work to manage and reduce the debt, just like debt in real life. It is technical debt, so often unaccounted for, that often derails large projects as they run out of resource and don’t understand where it has gone. Debt can be classified just as in real life financial situations: • Debt incurred un-intentionally o Usually due to low quality work (the uninsured loss) • Debt incurred intentionally o Short-term debt, usually incurred reactively, for tactical reasons such as numerous tiny shortcuts (credit card expenditure) o Medium-term debt incurred by individually identifiable shortcuts such as the creation of a tactical data mart (the car loan) o Long-term debt, usually incurred proactively, for strategic reasons such as the delay in purchasing significant technical infrastructure (the mortgage) • Non Debt o Some things are not technical debt such as feature backlog, deferred features, cut features, etc. Not all incomplete work is debt. These aren't debt, because they don't require resource to correct them (the interest payment). Debt requires re-payment with interest, i.e. whatever has been done has cost something (the debt) and correcting it requires additional resource (the interest) to put it to how it should be. 27 As in financial circumstances delaying repayment always costs more in the long term. It should be noted that a well-defined technical architecture as discussed above is needed in order to identify technical debt. This is because there must be a blueprint and baseline against which to draw comparisons against. This also re-enforces the need for a simple architecture as measurement is more difficult against complex architectures. It is often thought that time-boxing project phases either cannot be done for data warehouse projects or will force developers to deliver something. Neither is true. A time-boxed project will deliver something but can incur technical debt for those things that get omitted or compromised. The delivered solution may be of little value if the time allowed is insufficient. If the techniques described above are employed then early phases should be run as scope or benefit driven rather than relying on time boxing. As velocity and technical debt are better understood in the environment the project can switch to time-boxed activities to allow the business to see tangible time-scaled development and deployment roadmap. Finally the project manager must understand the cost of their actions. By putting good communication, processes and systems in place the project manager can effectively monitor and manage a project by exception, allowing the senior business analyst to handle the business aspects and the technical architect to manage the technology and together progress the delivery. If a team of eight people is brought together once a week for a two-hour status meeting with the project manager, then two working days out of the forty working days (eight people for five days a week assuming eight hour days) available in the week are lost. That weekly status meeting reflects 5% of all the available resource! 28 The ultimate management sin is wasting people’s time 27 Note: The original draft of this paper was written before the 2008 financial crisis. The failure to manage debt in the real world caused significant institutional melt down. This is mirrored by the meltdown of large data warehouse projects within large organisations that have failed to manage technical debt. 28 Peopleware – Productive Projects and Team: Tom DeMarco and Timothy Lister, Dorset House Publishing, Second Edition 1999, Chapter 33 © 2008 Data Management & Warehousing Page 25
  • 26. White Paper - Data Warehouse Project Management Tips and Tricks The following section lists some items that are useful for a project manager to remember. It is not exhaustive but provides some high level reminders: • Phase 1: Mobilisation Setting up a project has a cost, having a Mobilisation phase allows time and resource to be allocated to the setup. If there is no allowance for it then at the end of the first phase the cost of setup will be at least equal to the delay in the delivery of the phase. • Team Members Wiki Page If the project has a wiki (which it should) take photographs of everyone and add them to a page that has everyone on it, order it alphabetically by first name rather than in any organisational structure, include their contact details. This is again something that makes people feel involved and is a useful resource when someone remote to the core team or a new starter wants to contact another member of the team. • Develop a no blame culture Mistakes happen – they come from a lack of understanding or knowledge or poor communication and everyone on the team will make them at different times. It is therefore important that people are willing to admit to their mistakes and learn from them and that the project manager understands why mistakes are occurring and then take corrective action (e.g. training, improved communication channels, etc.) Where mistakes are hidden there is a build up of issues and technical debt that appear, inevitably, at critical points in the project. • Large Teams & Parallel Streams Avoid large teams and large numbers of parallel streams of work. Data warehouses are complex intertwined systems and the impact of a large number of teams trying to work simultaneously across the system will out-weigh any benefit from parallel working. Parallel teams work where there are discreet non-interacting areas, otherwise the contention between components and resources becomes too much of an overhead. Also as a team gets larger the degree of effective communication within the team drops. The balance is to have sufficient people to do the work and yet few enough to ensure effective communication between them. • Transparency By default let everyone involved with the project see everything. Exceptionally restrict access to sensitive documents. Always challenge any request to categorise a document as “sensitive”. This helps for many reasons; delays are not a sudden surprise to users, others on the project often volunteer help or expertise about issues in unexpected areas, it develops an inclusive aspect to the team dynamic, it provides an opportunity for people to learn from the work of others, etc. • Document and version everything As this document has discussed, having a ticketing and version control system in place makes management of a rapidly changing environment possible. No individual or group of individuals can effectively manage all the tasks, risks, issues, changes and documents of a large project with manual systems and if the system is easy to use then documenting everything is preferable to trying to decide what might be needed in the future. © 2008 Data Management & Warehousing Page 26
  • 27. White Paper - Data Warehouse Project Management • Use Storyboards but avoid Use Cases 29 Many formal methodologies for OLTP systems have use-cases that describe how a user must get through a system. This is fine for such solutions where a pre-defined path is essential. For a data warehouse the individual use case is irrelevant as the user is unlikely to follow the same route regularly. Instead a story is required that talks of a user being asked to produce a specific report and then having to do analysis of another set of data and incorporate it in the results, etc. The storyboard should describe the process of moving around the system but not prescribe specific routes for users to take, instead focusing on how to transition between aspects of the system. • Key Design Decisions Whilst the idea of documenting everything has already been described it is particularly important to document key design decisions such that when a problem occurs it is easy to follow the intended route rather than revert to a re-evaluation of possible solutions. • Manage Technical Debt Ensure that everyone can quantify the cost implications of the decisions they make and document them in such a way that the project can assess the technical debt they are accruing and schedule the debt reduction appropriately. 29 “UML Distilled” Martin Fowler “The more I see of use cases, the less valuable the use case diagram seems to be. With use cases, concentrate your energy on their text rather than on the diagram. Despite the fact that the UML has nothing to say about the use case text, it is the text that contains all the value in the technique.” © 2008 Data Management & Warehousing Page 27
  • 28. White Paper - Data Warehouse Project Management Summary Data warehouse projects pose a specific set of challenges for the project manager. Projects often have poorly set expectations in terms of timescales, the likely return on investment, the vendors’ promises for tools or the expectations set between the business and IT within an organisation. They also have large technical architectures and resourcing issues that need to be handled. This document has outlined the building blocks of good project control including the definition of phases, milestones, activities, tasks, issues, enhancements, test cases, defects and risks and discussed how they can be managed, and when, using an event horizon the project manager can expect to get information. To help manage these building blocks this paper has looked at the types of tools and technology and how they can be used to assist the project manager. These tools include project management software, ticketing systems, version control and wikis. It has also looked at how these tools fit into methodologies. The final section of the paper has looked at how effective project leadership and estimating can improve the chances of success for a project. This has included understanding the roles of the executive sponsor, project manager, technical architect and senior business analyst along with the use of different leadership styles, organisational learning and team rotation. © 2008 Data Management & Warehousing Page 28
  • 29. White Paper - Data Warehouse Project Management Appendix 1 – Governance Procedures Each organisation will create its own processes for the governance of the data warehouse project. Data Management & Warehousing have defined and used processes in three major groups: • Change Management Processes Identifying and controlling enhancements, maintenance and issues with the system • Data Warehouse Processes The processes associated with the build and deployment of the data warehouse itself • Data Management Processes The processes associated with the management of the data held within the data warehouse Outlined below are the major components of each of the processes. These are given as examples only and are shown only with the high level summary diagrams and short descriptions as indicators to what should be developed by an organisation to service its environment Change Management Processes Enhancements and maintenance processes are required to ensure the communication of the organisation’s requirements of the data warehouse and to ensure that those requirements are costed and prioritised in such a way as to deliver maximum benefit. The issue management process is required to ensure that all issues found with business intelligence outputs are captured and resolved consistently, allowing for KPI capture and process visibility for active management. © 2008 Data Management & Warehousing Page 29
  • 30. White Paper - Data Warehouse Project Management Data Warehouse Processes The requirements process is required to ensure that the user requirements are met effectively by creating a statement of what is required and a process for changing the definition of what is required The enhancement request packaging process is required to ensure that the scope is limited to user requirements that deliver benefit at reasonable cost and project timescales are predictable. The ETL design & build process is required to ensure that a reliable, robust, accurate and performant data loading process is designed and build. The report design and build process is required to ensure that a reliable, robust, accurate and easy to use reporting solution is designed and build. The testing process is required to ensure that the solution is a robust and accurate reflection of the requirements; that changes and issues are handled promptly, and performance is adequate. © 2008 Data Management & Warehousing Page 30
  • 31. White Paper - Data Warehouse Project Management Data Management Processes The data quality process is required to measure, control and improve the quality of data held in the data warehouse, reacting to new issues quickly and ensuring source systems are responsible for the data they provide. The data model process is required to develop and maintain both the logical and physical data models against set standards, and aligned with metadata. The data lifecycle process is required to give structure to the adding and removing of data from the data warehouse, and maintaining a balance between business, hardware, cost and compliance considerations. The data security process is required to ensure that the organization complies with legal requirements related to data protection, and that the data warehouse complies with all the organizations' internal data policies. The metadata process is required to ensure that metadata is captured consistently as part of the data warehouse development, such that it can be effectively used in applications including data quality checking, data profiling and data security. © 2008 Data Management & Warehousing Page 31
  • 32. White Paper - Data Warehouse Project Management Appendix 2 – Project Services Data Management & Warehousing have a web based project management service configured for the development and management of data warehouses. The solution provides a complete environment including version control, ticketing, wiki and many other features using free, widely available, open source software. A full description of the service can be found at: http://projects.datamgmt.com A demonstration system can be found at: http://projects.datamgmt.com/demo The Data Management & Warehousing internal project management (screenshot above) can be found at: http://projects.datamgmt.com/datamgmt A description of how to build the system on your own server can be found at: http://projects.datamgmt.com/howto The company also hosts the service for clients who require a fast start on their projects. Copyright © 2008 Data Management & Warehousing. All rights reserved. Reproduction not permitted without written authorisation. References to other companies and their products use trademarks owned by the respective companies and are for reference purposes only. Some terms and definitions taken from Wikipedia © 2008 Data Management & Warehousing Page 32