1. Bathroom Renovation Carpenter Plan and Prepare
Preliminaries
Particulars Day 1 Day 2 Day 3 Day 4 Day 5 Day 6 Day 7 Day 8 Day 9 Day 10 Day 11
Contact Client
Asbestos
Site Services
Rubbish
Electrician
Plumber
Materials
PC item
Materials Storage
Site Toilet
Client Bathroom
Plasterer
Waterproofing
Tiler
Joiner
Electrician
Plumber
Painter
Shower Screen
Carpenter
2. Organise Carpentry Tasks page 1
Task Day 1 Day 2 Day 3 Day 4 Day 5 Day 6 Day 7 Day 8 Day 9 Day 10 Day 11
Carpenter
Carpenter
Carpenter
Carpenter
Carpenter
Carpenter
Carpenter
Carpenter
Electrician
Plumber
Carpenter
Carpenter
Carpenter
Carpenter
Carpenter
Plasterer
Carpenter
Waterproofing
Electrician
Tiler
Tiler
Carpenter
Tiler
Shower screen
i ll
Carpenter
Plumber
Carpenter
Electrician
Painter
Shower screen
i ll
Carpenter
Carpenter
Carpenter
3. Tasks
Notify start day
Notify start day
Notify start day
Notify start day
wet seal
Tidy up for client return. call plumber
book in fit off and shower screen
installer for site measure
Site measure
Tiler walls
Architraves window &door
Tile floor
Beds shower base and floor
Install under-tile heating
Install shower screen and mirrors
Paint ceiling architrave reveals, door
Fit off
Towel rails, fixtures and fittings
including mirror
Fit off
Fit vanity
Sheet ceiling/walls
Call electrician confirm under tile
heating install and fit off
Install Tile underlay over existing floor
Set joins Plasterboard ceiling villa
board walls ensure plasterer uses wet
area base coat to walls
Hand over to builder to inspect
Silicone
Clean and detail
Notify start day
Notify start day
Notify start day
Rough in
Rough in
Tidy ready for client/ call plasterer for
day 5
Batten ceiling ensure battens don’t
coincide with downlight or exhaust fan
positions
Clean and vacuum dust from
framework prior to sheeting
Mark out Position of services prior to
sheeting Insulate ceiling/walls
Organise from stock & cut temporary
floor covering , drop sheets &
temporary wall & door protection
Tentatively book day 3 morning
plumber afternoon electrician
Strip out existing Bathroom Remove
rubbish as you go. Remove to skip
Make good De-nail /remove and
replace bad frame/floor
Pre sheet
Block, trimmers for fixtures
Install ducting for exhaust fan to
eaves.
Tidy ready for client
Confirm electrician & plumber for
rough in
Ensure all PC items are onsite prior to
starting
Arrange with client an appropriate
storage area
Order /client
Prepare for portable bathroom i
Notify start day
Arrangements
Confirm Start date
- Schedule
- What to expect ie dust, noise,
household disruption
-Temp bathroom and toilet facilities
Check with builder That existing FC
sheeting has been tested and clear of
asbestos
Identify and locate Electrical switch
board and main switch, Locate water
main and check it works correctly,
Locate gas main and bidcock prior to
starting.
Organise site skip
Make Safe for demolition
Cap off plumbing and drainage prior to
demolition