SlideShare ist ein Scribd-Unternehmen logo
1 von 43
VARIOUS STAGES
OF
PROJECT
PAVEAPATH
FOR
SUCCESSFULCOMPLETION
STATUS UPDATING THROUGH
NETWORK AND
GIVING EARLYWARNINGS
DATACOLLECTION
PLANNING & SCHEDULING
THINKING
Project :
Converting a vision, a dream or a need to reality.
 A job that has a beginning and an end (Time)
 A specified outcome(Scope)
 At a stated level of Performance (Quality)
 At a budget(Costs).
ProjectCharacteristics :
 Temporary : Has definite Start and Finish
 Unique : Product/Service is different in some
distinguishing way
Management :
Management is the technique of understanding the
problems, needs and controlling the use of Resources,
Cost, Time, Scope and Quality.
ProjectManagement :
Application of knowledge, skills , tools & techniques to
project activities in order to meet stakeholder needs &
expectations from a project.
Needs :stated part of the project
Expectations :unstated part of the project
“Completion of Projecton timewithinBudget without
comprising Quality”
Why do companies use PM?
• To handle projects effectively in an organization.
• To define the project and agree with the customer
• To plan and assess resource needs for the project
• To estimate project cost and make proposals
• To plan & schedule activities in a project.
• To allocate the right resource at the right time.
• To assess risk and failure points and make
backup plans.
• To lead a project team effectively and communicate
well
among team members.
Why do people learn PM?
• To explore the latest concepts and techniques of
project management.
• To increase value/contribution to the organization. To
prove yourself skillful in managing projects.
• To learn a new thought process that helps organized
thinking and structured approach.
• To acquire a professional degree/ recognition and
increase job prospects.
• Endless possibilities and benefits……..
ProjectManagement Plan :
“Tells How work will be done”
The key to a successful project is on the
planning. All the detailed planning work for different aspects
of the project is integrated into one single plan known as
the Project Management Plan.
Input:
Goal
Team
Money
Time
Equipment
Project Output :
Deliverables
Why
• ‘Why’ is from the business case
Why &
What
• ‘Why’ & ‘What’ are management statement of the success criteriaand
should be agreed with the project sponsor
Who
• ‘Who’ will do the work and stakeholder awareness of the project
When
• ‘When’ deals with schedules and phasing for the project
How
• ‘How’ which is the project manager vision to implement project from
beginning to end
How
much
• ‘How Much’ covers the costs and budgets of the project.
ThePMPlanestablishes the projects:
Project Management Overview
Project Management Process
Project Management Process Groups
Most important phase of the project
management.
Planning is an art and science of
converting a set of objectives to
realization through a series of steps
executed in an organized and
predicted way so that there will be
less requirement of changes in the
plan later on.
The old saying “Plan the work, Work
the plan”
PLANNING
CONTROLLING
SCHEDULING
CLOSING
STAGES
Scheduling Phase is the process
of formalizing the planned activities,
assigning the durations, resources and
sequence of occurrence in
consultation with the team members.
Planning and Scheduling phases are
under taken before the actual project
starts.
SCHEDULIN
G
CONTROLLING
PLANNING
CLOSING
STAGES
Controlling phase is undertaken during the
actual project implementation.
Project controlling is a mechanism established to
determine deviations from the project
base schedule, to re-plan& reschedule during
implementation to compensate the deviations
on the basis of commissioning
minima, flow of resources like
finance, manpower, equipment &
application techniques.
CONTROLLING
PLANNING
SCHEDULING
CLOSING
STAGES
Closing phase is the last phase of the
project which brings close out of the complete
project. Whatever the project requirements are
pre-defined, during this phase the total
delivery is made and it is accepted by the
customer.
Maximum conflicts can arise in the project
during this phase between those who have
worked to deliver the outcome (contractor) and
those who are accepting the results of the work
(customer).
CONTROLLING
PLANNING
SCHEDULING
CLOSING
STAGES
PM Knowledge Areas
PM Knowledge
Areas
Cost
Change
Document
Integration
1
Scope
2
Time 3
4
Quality
5
Risk
8
Human
Resource
6
Communi
Cation
7
Procure
ment
9
Project Integration Management
 Project IntegrationManagement supports various
elements of project management which are
identified, defined, combined and coordinated.
 Develop Project Charter
Develop Project Management Plan
Direct and Manage Project execution
Monitor and Control Project Work
Perform Integrate Change Control
Close Project or Close
Project Charter :
 DOCUMENT that formally authorizes a project.
Provide information about internal and external parties involved
in and affected by the project.
Documenting initial requirements that satisfy the stake holders’
needs and expectations.
ISSUED by a project initiator or sponsor, external to project
organization, at a level appropriate to project funding.
 EMPOWERS the project manager to apply resources to project.
 Summary level Milestone schedule and Summary level Budget.
Project Integration Management
Project Scope Management
 Project scope management includes the processes
required to ensure that the project includes all the work
required, and only the work required to complete the
project successfully
 Collect requirements
Define Scope
Create WBS
Verify Scope
WBS – Work Breakdown Structure :
A deliverable-oriented hierarchical decomposition of work to be
executed by the project team to:
•create required deliverables
• accomplish project objectives
 WBS organizes and defines the total scope and represents
specified in the current approved Scope Statement!
 Process of subdividing project deliverables and project work into
more manageable components.
 Lowest level of WBS is work package can be scheduled, cost
estimated, monitored, and controlled.
Project Scope Management
TYPICAL WBS OFA PROJECT
OVERALLPROJECT
ENGINEERING
BASIC ENGINEERING
DETAILED
ENGINEERING
PROJECT
ENGINERING
PROCUREMENT
PLACEMENT OF
ORDER ON VENDORS
MANUFACTURING &
DELIVERY
EQUIPMENT
RECEIVED AT SITE
( …%)
CONSTRUCTION
SITE MOBILISATION
CIVIL WORK
STRUCTURAL STEEL WORK
EQUIPMENT INSTALLATION
PIPING INSTALLATION
ELEC. INSTALLATION
INSTRUMEN. INSTALLATION
INSULATION & PAINTING
COLD COMMISSIONING
HOT COMMISSIONING
Civil work for
Main equipment
Civil work for
Aux. Facilities
Piling work
• KPL - WBS
Project Time Management
 Project Time Management ensures the timely
completion of the project.
 Plan Schedule Management
 Define Activities
 Sequence Activities
 Estimate Activity Resources
 Estimate Activity Durations
 Develop Schedule
 Control Schedule
Project Time Management
 Schedule once finalized is set as a baseline
 Progress of work are tracked against the baseline
 Current progress is arrived from various (Engineering, Proc,
Manufacturing and Construction) Trackers developed for
the purpose. These schedules are called current schedules
 Analysis and forecasting is done in progress reports.
Schedule using MS Project
Schedule using Primavera (P6)
Engineering Tracker
Manufacturing & Supply Tracker
construction tracker
Project Time Management
Project Cost Management
 Project cost Management includes the processes
involved in estimating, budgeting, and controlling
costs so that the project can be completed within the
approved budget.
 Estimate cost
Convert it into budget
Load the cost into schedule
Perform earned value (EV) analysis
Perform estimate at complete (EAC)
Administer changes
Control cost
Project Quality Management
 Project Quality Management ensures the project will
satisfy NEEDS for which it was undertaken.
 Plan Quality
Perform Quality Assurance
Perform Quality control
What is Quality?
 Conformance to specifications
 Fitness for use
Project Quality Management
Plan Quality
Techniques
• Cost benefit
analysis
• Cost of quality
• Benchmarking
• Design of
experiments
• Seven quality
tools
• Statistical
sampling
PerformQuality
Assurance
Techniques
• Quality
management and
control tools
• Quality audits
• Process analysis
PerformQuality
Control Techniques
• Statistical sampling
• Inspection
• Seven quality tools
and techniques
√ Cause and effect
diagram
√ Flowcharts
√ Check sheets
√ Pareto diagrams
√ Histogram
√ Control charts
√ Scatter diagram
Project Human Resource Management
 Project human resource management includes the
processes that organize, manage, and lead the project
team and to make most effective use of people
involved in the project.
Develop Human Resource Plan
(Role & Responsibility, Organization
chart, Staffing Management Plan)
 Acquire project team
 Develop project team
 Manage project team
Organization Chart
Project Human Resource Management
Project Communications Management
 Project communication management include processes
required to ensure timely and appropriate generation,
collection, distribution, storage, retrieval, a nd ultimate
disposal of project information.
 Identify Stakeholders
 Plan Communication
 Distribute Information
 Manage Stakeholders expectations
 Report Performance
RACI
Project Stakeholders :
 Customers/users
 Sponsor
 Portfolio managers/portfolio review board
 Program managers
 Project management office
 Project managers
 Project team
 Functional managers
 Operations management
 Sellers/business partners
Project Communications Management
Project Communications Management
Project Risk Management
Risk
Assessment
Risk
Control
Risk
Ranking
Risk
Mitigation
 Project Risk Management is concerned with identifying,
analyzing and responding to project risks.
 Plan Risk Management
Identify Risks
Perform Qualitative Risk Analysis
Perform Quantitative Risk Analysis
Plan Risk responses
Monitor and Control Risks
Risk Register
Project Procurement Management
 Project Procurement Management is needed to
acquire material, goods and services outside
performing organization to meet project scope.
 Plan Procurements
 Conduct Procurement
 Administer Contracts
 Close Procurement
 Projects generally don’t go 100%as planned
resulting into variations from plans in
scope, time, cost, quality
 Change control boards (CCBs)
Project Change Management
Document management is very important (but largely
ignored) aspect of project management
 This can be a sophisticated software or simple excel
sheets depending on the organization strategy
 Once adopted its use should be fully exploited viz. 100%
documents should pass through it and document
reviews should be done as per the matrix defined
 MIS of document status be generated at the end of
period
Project Document Management
 Proper DMS ensures right information to all
stakeholders at all times
 Avoid using obsolete drawings and designs for
execution
 Serves a very good engine for future use of project
data
 Example of a simple document management system
Document control log
Project Document Management
S-Curve in Monthly Progress Report
Progress reporting is done through different formats and curves.
S- Curve is the graphic display of cumulative progress
plotted against time.
Ideal S - Curve is a sinusoidal curve based on the
following formulae:
Y=[1- sin(x/xn
*180+90)*
5
0
]
Y –Percent progress
x –Period at which s-curve value required xn
–Total period
The name is derived from the 'S' like nature of the curve.
S-Curve
Whatis“SCurve”
Progress
Cumulative progress Curve
Plotted in a different scale
Time
I
tisan ideal distributioncurve. Depending upon thevarious
guiding factors itmay vary.
Progress distribution curve
Starting Period Finishing Period
Peak Period
“SCurve” orProject Life Cycle
projectmanagement-130721095616-phpapp01-converted.pptx
projectmanagement-130721095616-phpapp01-converted.pptx

Weitere ähnliche Inhalte

Ähnlich wie projectmanagement-130721095616-phpapp01-converted.pptx

Introduction to project management
Introduction to project management Introduction to project management
Introduction to project management ervissmakaj
 
Project Management Toolkit_Final v1.0
Project Management Toolkit_Final v1.0Project Management Toolkit_Final v1.0
Project Management Toolkit_Final v1.0lee_anderson40
 
Presintation on Project constraint
Presintation on Project constraint Presintation on Project constraint
Presintation on Project constraint university(kust)
 
Intro to Project Management
Intro to Project ManagementIntro to Project Management
Intro to Project ManagementNoman Aftab
 
Scope and Time Management
Scope and Time ManagementScope and Time Management
Scope and Time ManagementSabrinaScott22
 
Managing the Consulting Engagement
Managing the Consulting EngagementManaging the Consulting Engagement
Managing the Consulting EngagementSaumya Ganguly
 
Construction company business plan
Construction company business planConstruction company business plan
Construction company business planfarouq umar
 
Project Management
Project ManagementProject Management
Project ManagementXubitech
 
DISE - Introduction to Project Management
DISE - Introduction to Project ManagementDISE - Introduction to Project Management
DISE - Introduction to Project ManagementRasan Samarasinghe
 
Project Execution and Project management (GT IV batch) 2.pptx
Project Execution and Project management (GT IV batch) 2.pptxProject Execution and Project management (GT IV batch) 2.pptx
Project Execution and Project management (GT IV batch) 2.pptxbhanu852126
 
Project management professional
Project management professionalProject management professional
Project management professionalReema
 
Project Management
Project ManagementProject Management
Project ManagementPrarthan P
 
2. PAE AcFn621 Ch-2 Principle ppt.pptx
2. PAE AcFn621 Ch-2 Principle ppt.pptx2. PAE AcFn621 Ch-2 Principle ppt.pptx
2. PAE AcFn621 Ch-2 Principle ppt.pptxProfDrAnbalaganChinn
 

Ähnlich wie projectmanagement-130721095616-phpapp01-converted.pptx (20)

Introduction to project management
Introduction to project management Introduction to project management
Introduction to project management
 
PME UNIT-3.pptx
PME UNIT-3.pptxPME UNIT-3.pptx
PME UNIT-3.pptx
 
Project Management Toolkit_Final v1.0
Project Management Toolkit_Final v1.0Project Management Toolkit_Final v1.0
Project Management Toolkit_Final v1.0
 
MODULE III - M.ARCH.pptx
MODULE III - M.ARCH.pptxMODULE III - M.ARCH.pptx
MODULE III - M.ARCH.pptx
 
Presintation on Project constraint
Presintation on Project constraint Presintation on Project constraint
Presintation on Project constraint
 
Intro to Project Management
Intro to Project ManagementIntro to Project Management
Intro to Project Management
 
Scope and Time Management
Scope and Time ManagementScope and Time Management
Scope and Time Management
 
Unit 1.pptx
Unit 1.pptxUnit 1.pptx
Unit 1.pptx
 
Managing the Consulting Engagement
Managing the Consulting EngagementManaging the Consulting Engagement
Managing the Consulting Engagement
 
Construction company business plan
Construction company business planConstruction company business plan
Construction company business plan
 
Project Management
Project ManagementProject Management
Project Management
 
DISE - Introduction to Project Management
DISE - Introduction to Project ManagementDISE - Introduction to Project Management
DISE - Introduction to Project Management
 
Project Execution and Project management (GT IV batch) 2.pptx
Project Execution and Project management (GT IV batch) 2.pptxProject Execution and Project management (GT IV batch) 2.pptx
Project Execution and Project management (GT IV batch) 2.pptx
 
Project management professional
Project management professionalProject management professional
Project management professional
 
pmppgoav14.ppt
pmppgoav14.pptpmppgoav14.ppt
pmppgoav14.ppt
 
Project Cost.pptx
Project Cost.pptxProject Cost.pptx
Project Cost.pptx
 
PM & PM LC.pptx
PM & PM LC.pptxPM & PM LC.pptx
PM & PM LC.pptx
 
Project Management
Project ManagementProject Management
Project Management
 
Project Mangement
Project MangementProject Mangement
Project Mangement
 
2. PAE AcFn621 Ch-2 Principle ppt.pptx
2. PAE AcFn621 Ch-2 Principle ppt.pptx2. PAE AcFn621 Ch-2 Principle ppt.pptx
2. PAE AcFn621 Ch-2 Principle ppt.pptx
 

Mehr von Chandrasen Sharma

SMED- Single Minute Exchange of DIE .pptx
SMED- Single Minute Exchange of DIE .pptxSMED- Single Minute Exchange of DIE .pptx
SMED- Single Minute Exchange of DIE .pptxChandrasen Sharma
 
bprchina1999-09122723372722-phpapp02.ppt
bprchina1999-09122723372722-phpapp02.pptbprchina1999-09122723372722-phpapp02.ppt
bprchina1999-09122723372722-phpapp02.pptChandrasen Sharma
 
worldclassmanufacturing-111213232400-phpapp01.pptx
worldclassmanufacturing-111213232400-phpapp01.pptxworldclassmanufacturing-111213232400-phpapp01.pptx
worldclassmanufacturing-111213232400-phpapp01.pptxChandrasen Sharma
 
world class manufacturing practices for mms
world class manufacturing practices for mmsworld class manufacturing practices for mms
world class manufacturing practices for mmsChandrasen Sharma
 
agvandasrs-150401235654-conversion-gate01.pptx
agvandasrs-150401235654-conversion-gate01.pptxagvandasrs-150401235654-conversion-gate01.pptx
agvandasrs-150401235654-conversion-gate01.pptxChandrasen Sharma
 
PRODUCTION MGT-world-class-manufacturing.pptx
PRODUCTION MGT-world-class-manufacturing.pptxPRODUCTION MGT-world-class-manufacturing.pptx
PRODUCTION MGT-world-class-manufacturing.pptxChandrasen Sharma
 
World class manufacturing practices in the SCM-2.pptx
World class manufacturing practices in the SCM-2.pptxWorld class manufacturing practices in the SCM-2.pptx
World class manufacturing practices in the SCM-2.pptxChandrasen Sharma
 
transhistory-131013090124-phpapp02.pptx
transhistory-131013090124-phpapp02.pptxtranshistory-131013090124-phpapp02.pptx
transhistory-131013090124-phpapp02.pptxChandrasen Sharma
 
Complete supply chain view.ppt
Complete supply chain view.pptComplete supply chain view.ppt
Complete supply chain view.pptChandrasen Sharma
 
Multi-Echelon Inventory Optimization.pptx
Multi-Echelon Inventory Optimization.pptxMulti-Echelon Inventory Optimization.pptx
Multi-Echelon Inventory Optimization.pptxChandrasen Sharma
 
Inventory accounting & costing methods.pptx
Inventory accounting & costing methods.pptxInventory accounting & costing methods.pptx
Inventory accounting & costing methods.pptxChandrasen Sharma
 
bprchina1999-091227233727-phpapp02.ppt
bprchina1999-091227233727-phpapp02.pptbprchina1999-091227233727-phpapp02.ppt
bprchina1999-091227233727-phpapp02.pptChandrasen Sharma
 
businessprocessreengineering-5.pptx
businessprocessreengineering-5.pptxbusinessprocessreengineering-5.pptx
businessprocessreengineering-5.pptxChandrasen Sharma
 
unitiiimtrlhandlingmodif-181029120211.pptx
unitiiimtrlhandlingmodif-181029120211.pptxunitiiimtrlhandlingmodif-181029120211.pptx
unitiiimtrlhandlingmodif-181029120211.pptxChandrasen Sharma
 
principlesofmaterialhandling-131022105441-phpapp01.pptx
principlesofmaterialhandling-131022105441-phpapp01.pptxprinciplesofmaterialhandling-131022105441-phpapp01.pptx
principlesofmaterialhandling-131022105441-phpapp01.pptxChandrasen Sharma
 

Mehr von Chandrasen Sharma (20)

SMED- Single Minute Exchange of DIE .pptx
SMED- Single Minute Exchange of DIE .pptxSMED- Single Minute Exchange of DIE .pptx
SMED- Single Minute Exchange of DIE .pptx
 
bprchina1999-09122723372722-phpapp02.ppt
bprchina1999-09122723372722-phpapp02.pptbprchina1999-09122723372722-phpapp02.ppt
bprchina1999-09122723372722-phpapp02.ppt
 
worldclassmanufacturing-111213232400-phpapp01.pptx
worldclassmanufacturing-111213232400-phpapp01.pptxworldclassmanufacturing-111213232400-phpapp01.pptx
worldclassmanufacturing-111213232400-phpapp01.pptx
 
world class manufacturing practices for mms
world class manufacturing practices for mmsworld class manufacturing practices for mms
world class manufacturing practices for mms
 
agvandasrs-150401235654-conversion-gate01.pptx
agvandasrs-150401235654-conversion-gate01.pptxagvandasrs-150401235654-conversion-gate01.pptx
agvandasrs-150401235654-conversion-gate01.pptx
 
PRODUCTION MGT-world-class-manufacturing.pptx
PRODUCTION MGT-world-class-manufacturing.pptxPRODUCTION MGT-world-class-manufacturing.pptx
PRODUCTION MGT-world-class-manufacturing.pptx
 
World class manufacturing practices in the SCM-2.pptx
World class manufacturing practices in the SCM-2.pptxWorld class manufacturing practices in the SCM-2.pptx
World class manufacturing practices in the SCM-2.pptx
 
ISO Intro.-1.pptx
ISO Intro.-1.pptxISO Intro.-1.pptx
ISO Intro.-1.pptx
 
ISO Intro1.pptx
ISO Intro1.pptxISO Intro1.pptx
ISO Intro1.pptx
 
transhistory-131013090124-phpapp02.pptx
transhistory-131013090124-phpapp02.pptxtranshistory-131013090124-phpapp02.pptx
transhistory-131013090124-phpapp02.pptx
 
Complete supply chain view.ppt
Complete supply chain view.pptComplete supply chain view.ppt
Complete supply chain view.ppt
 
Multi-Echelon Inventory Optimization.pptx
Multi-Echelon Inventory Optimization.pptxMulti-Echelon Inventory Optimization.pptx
Multi-Echelon Inventory Optimization.pptx
 
Inventory accounting & costing methods.pptx
Inventory accounting & costing methods.pptxInventory accounting & costing methods.pptx
Inventory accounting & costing methods.pptx
 
Inventory and EOQ.pptx
Inventory and EOQ.pptxInventory and EOQ.pptx
Inventory and EOQ.pptx
 
bprchina1999-091227233727-phpapp02.ppt
bprchina1999-091227233727-phpapp02.pptbprchina1999-091227233727-phpapp02.ppt
bprchina1999-091227233727-phpapp02.ppt
 
Benchmarking.ppt
Benchmarking.pptBenchmarking.ppt
Benchmarking.ppt
 
businessprocessreengineering-5.pptx
businessprocessreengineering-5.pptxbusinessprocessreengineering-5.pptx
businessprocessreengineering-5.pptx
 
tacobell-BPR-1.pptx
tacobell-BPR-1.pptxtacobell-BPR-1.pptx
tacobell-BPR-1.pptx
 
unitiiimtrlhandlingmodif-181029120211.pptx
unitiiimtrlhandlingmodif-181029120211.pptxunitiiimtrlhandlingmodif-181029120211.pptx
unitiiimtrlhandlingmodif-181029120211.pptx
 
principlesofmaterialhandling-131022105441-phpapp01.pptx
principlesofmaterialhandling-131022105441-phpapp01.pptxprinciplesofmaterialhandling-131022105441-phpapp01.pptx
principlesofmaterialhandling-131022105441-phpapp01.pptx
 

Kürzlich hochgeladen

Log Analysis using OSSEC sasoasasasas.pptx
Log Analysis using OSSEC sasoasasasas.pptxLog Analysis using OSSEC sasoasasasas.pptx
Log Analysis using OSSEC sasoasasasas.pptxJohnnyPlasten
 
FESE Capital Markets Fact Sheet 2024 Q1.pdf
FESE Capital Markets Fact Sheet 2024 Q1.pdfFESE Capital Markets Fact Sheet 2024 Q1.pdf
FESE Capital Markets Fact Sheet 2024 Q1.pdfMarinCaroMartnezBerg
 
代办国外大学文凭《原版美国UCLA文凭证书》加州大学洛杉矶分校毕业证制作成绩单修改
代办国外大学文凭《原版美国UCLA文凭证书》加州大学洛杉矶分校毕业证制作成绩单修改代办国外大学文凭《原版美国UCLA文凭证书》加州大学洛杉矶分校毕业证制作成绩单修改
代办国外大学文凭《原版美国UCLA文凭证书》加州大学洛杉矶分校毕业证制作成绩单修改atducpo
 
Halmar dropshipping via API with DroFx
Halmar  dropshipping  via API with DroFxHalmar  dropshipping  via API with DroFx
Halmar dropshipping via API with DroFxolyaivanovalion
 
Smarteg dropshipping via API with DroFx.pptx
Smarteg dropshipping via API with DroFx.pptxSmarteg dropshipping via API with DroFx.pptx
Smarteg dropshipping via API with DroFx.pptxolyaivanovalion
 
BabyOno dropshipping via API with DroFx.pptx
BabyOno dropshipping via API with DroFx.pptxBabyOno dropshipping via API with DroFx.pptx
BabyOno dropshipping via API with DroFx.pptxolyaivanovalion
 
(PARI) Call Girls Wanowrie ( 7001035870 ) HI-Fi Pune Escorts Service
(PARI) Call Girls Wanowrie ( 7001035870 ) HI-Fi Pune Escorts Service(PARI) Call Girls Wanowrie ( 7001035870 ) HI-Fi Pune Escorts Service
(PARI) Call Girls Wanowrie ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
定制英国白金汉大学毕业证(UCB毕业证书) 成绩单原版一比一
定制英国白金汉大学毕业证(UCB毕业证书)																			成绩单原版一比一定制英国白金汉大学毕业证(UCB毕业证书)																			成绩单原版一比一
定制英国白金汉大学毕业证(UCB毕业证书) 成绩单原版一比一ffjhghh
 
Brighton SEO | April 2024 | Data Storytelling
Brighton SEO | April 2024 | Data StorytellingBrighton SEO | April 2024 | Data Storytelling
Brighton SEO | April 2024 | Data StorytellingNeil Barnes
 
VIP High Profile Call Girls Amravati Aarushi 8250192130 Independent Escort Se...
VIP High Profile Call Girls Amravati Aarushi 8250192130 Independent Escort Se...VIP High Profile Call Girls Amravati Aarushi 8250192130 Independent Escort Se...
VIP High Profile Call Girls Amravati Aarushi 8250192130 Independent Escort Se...Suhani Kapoor
 
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...apidays
 
Schema on read is obsolete. Welcome metaprogramming..pdf
Schema on read is obsolete. Welcome metaprogramming..pdfSchema on read is obsolete. Welcome metaprogramming..pdf
Schema on read is obsolete. Welcome metaprogramming..pdfLars Albertsson
 
RA-11058_IRR-COMPRESS Do 198 series of 1998
RA-11058_IRR-COMPRESS Do 198 series of 1998RA-11058_IRR-COMPRESS Do 198 series of 1998
RA-11058_IRR-COMPRESS Do 198 series of 1998YohFuh
 
Data-Analysis for Chicago Crime Data 2023
Data-Analysis for Chicago Crime Data  2023Data-Analysis for Chicago Crime Data  2023
Data-Analysis for Chicago Crime Data 2023ymrp368
 
Introduction-to-Machine-Learning (1).pptx
Introduction-to-Machine-Learning (1).pptxIntroduction-to-Machine-Learning (1).pptx
Introduction-to-Machine-Learning (1).pptxfirstjob4
 
Delhi Call Girls CP 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip Call
Delhi Call Girls CP 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip CallDelhi Call Girls CP 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip Call
Delhi Call Girls CP 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip Callshivangimorya083
 
VIP High Class Call Girls Jamshedpur Anushka 8250192130 Independent Escort Se...
VIP High Class Call Girls Jamshedpur Anushka 8250192130 Independent Escort Se...VIP High Class Call Girls Jamshedpur Anushka 8250192130 Independent Escort Se...
VIP High Class Call Girls Jamshedpur Anushka 8250192130 Independent Escort Se...Suhani Kapoor
 

Kürzlich hochgeladen (20)

Log Analysis using OSSEC sasoasasasas.pptx
Log Analysis using OSSEC sasoasasasas.pptxLog Analysis using OSSEC sasoasasasas.pptx
Log Analysis using OSSEC sasoasasasas.pptx
 
FESE Capital Markets Fact Sheet 2024 Q1.pdf
FESE Capital Markets Fact Sheet 2024 Q1.pdfFESE Capital Markets Fact Sheet 2024 Q1.pdf
FESE Capital Markets Fact Sheet 2024 Q1.pdf
 
代办国外大学文凭《原版美国UCLA文凭证书》加州大学洛杉矶分校毕业证制作成绩单修改
代办国外大学文凭《原版美国UCLA文凭证书》加州大学洛杉矶分校毕业证制作成绩单修改代办国外大学文凭《原版美国UCLA文凭证书》加州大学洛杉矶分校毕业证制作成绩单修改
代办国外大学文凭《原版美国UCLA文凭证书》加州大学洛杉矶分校毕业证制作成绩单修改
 
Halmar dropshipping via API with DroFx
Halmar  dropshipping  via API with DroFxHalmar  dropshipping  via API with DroFx
Halmar dropshipping via API with DroFx
 
Smarteg dropshipping via API with DroFx.pptx
Smarteg dropshipping via API with DroFx.pptxSmarteg dropshipping via API with DroFx.pptx
Smarteg dropshipping via API with DroFx.pptx
 
BabyOno dropshipping via API with DroFx.pptx
BabyOno dropshipping via API with DroFx.pptxBabyOno dropshipping via API with DroFx.pptx
BabyOno dropshipping via API with DroFx.pptx
 
Delhi 99530 vip 56974 Genuine Escort Service Call Girls in Kishangarh
Delhi 99530 vip 56974 Genuine Escort Service Call Girls in  KishangarhDelhi 99530 vip 56974 Genuine Escort Service Call Girls in  Kishangarh
Delhi 99530 vip 56974 Genuine Escort Service Call Girls in Kishangarh
 
(PARI) Call Girls Wanowrie ( 7001035870 ) HI-Fi Pune Escorts Service
(PARI) Call Girls Wanowrie ( 7001035870 ) HI-Fi Pune Escorts Service(PARI) Call Girls Wanowrie ( 7001035870 ) HI-Fi Pune Escorts Service
(PARI) Call Girls Wanowrie ( 7001035870 ) HI-Fi Pune Escorts Service
 
定制英国白金汉大学毕业证(UCB毕业证书) 成绩单原版一比一
定制英国白金汉大学毕业证(UCB毕业证书)																			成绩单原版一比一定制英国白金汉大学毕业证(UCB毕业证书)																			成绩单原版一比一
定制英国白金汉大学毕业证(UCB毕业证书) 成绩单原版一比一
 
Brighton SEO | April 2024 | Data Storytelling
Brighton SEO | April 2024 | Data StorytellingBrighton SEO | April 2024 | Data Storytelling
Brighton SEO | April 2024 | Data Storytelling
 
VIP High Profile Call Girls Amravati Aarushi 8250192130 Independent Escort Se...
VIP High Profile Call Girls Amravati Aarushi 8250192130 Independent Escort Se...VIP High Profile Call Girls Amravati Aarushi 8250192130 Independent Escort Se...
VIP High Profile Call Girls Amravati Aarushi 8250192130 Independent Escort Se...
 
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
 
Schema on read is obsolete. Welcome metaprogramming..pdf
Schema on read is obsolete. Welcome metaprogramming..pdfSchema on read is obsolete. Welcome metaprogramming..pdf
Schema on read is obsolete. Welcome metaprogramming..pdf
 
RA-11058_IRR-COMPRESS Do 198 series of 1998
RA-11058_IRR-COMPRESS Do 198 series of 1998RA-11058_IRR-COMPRESS Do 198 series of 1998
RA-11058_IRR-COMPRESS Do 198 series of 1998
 
꧁❤ Aerocity Call Girls Service Aerocity Delhi ❤꧂ 9999965857 ☎️ Hard And Sexy ...
꧁❤ Aerocity Call Girls Service Aerocity Delhi ❤꧂ 9999965857 ☎️ Hard And Sexy ...꧁❤ Aerocity Call Girls Service Aerocity Delhi ❤꧂ 9999965857 ☎️ Hard And Sexy ...
꧁❤ Aerocity Call Girls Service Aerocity Delhi ❤꧂ 9999965857 ☎️ Hard And Sexy ...
 
VIP Call Girls Service Charbagh { Lucknow Call Girls Service 9548273370 } Boo...
VIP Call Girls Service Charbagh { Lucknow Call Girls Service 9548273370 } Boo...VIP Call Girls Service Charbagh { Lucknow Call Girls Service 9548273370 } Boo...
VIP Call Girls Service Charbagh { Lucknow Call Girls Service 9548273370 } Boo...
 
Data-Analysis for Chicago Crime Data 2023
Data-Analysis for Chicago Crime Data  2023Data-Analysis for Chicago Crime Data  2023
Data-Analysis for Chicago Crime Data 2023
 
Introduction-to-Machine-Learning (1).pptx
Introduction-to-Machine-Learning (1).pptxIntroduction-to-Machine-Learning (1).pptx
Introduction-to-Machine-Learning (1).pptx
 
Delhi Call Girls CP 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip Call
Delhi Call Girls CP 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip CallDelhi Call Girls CP 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip Call
Delhi Call Girls CP 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip Call
 
VIP High Class Call Girls Jamshedpur Anushka 8250192130 Independent Escort Se...
VIP High Class Call Girls Jamshedpur Anushka 8250192130 Independent Escort Se...VIP High Class Call Girls Jamshedpur Anushka 8250192130 Independent Escort Se...
VIP High Class Call Girls Jamshedpur Anushka 8250192130 Independent Escort Se...
 

projectmanagement-130721095616-phpapp01-converted.pptx

  • 1.
  • 2. VARIOUS STAGES OF PROJECT PAVEAPATH FOR SUCCESSFULCOMPLETION STATUS UPDATING THROUGH NETWORK AND GIVING EARLYWARNINGS DATACOLLECTION PLANNING & SCHEDULING THINKING
  • 3. Project : Converting a vision, a dream or a need to reality.  A job that has a beginning and an end (Time)  A specified outcome(Scope)  At a stated level of Performance (Quality)  At a budget(Costs). ProjectCharacteristics :  Temporary : Has definite Start and Finish  Unique : Product/Service is different in some distinguishing way
  • 4. Management : Management is the technique of understanding the problems, needs and controlling the use of Resources, Cost, Time, Scope and Quality. ProjectManagement : Application of knowledge, skills , tools & techniques to project activities in order to meet stakeholder needs & expectations from a project. Needs :stated part of the project Expectations :unstated part of the project “Completion of Projecton timewithinBudget without comprising Quality”
  • 5. Why do companies use PM? • To handle projects effectively in an organization. • To define the project and agree with the customer • To plan and assess resource needs for the project • To estimate project cost and make proposals • To plan & schedule activities in a project. • To allocate the right resource at the right time. • To assess risk and failure points and make backup plans. • To lead a project team effectively and communicate well among team members.
  • 6. Why do people learn PM? • To explore the latest concepts and techniques of project management. • To increase value/contribution to the organization. To prove yourself skillful in managing projects. • To learn a new thought process that helps organized thinking and structured approach. • To acquire a professional degree/ recognition and increase job prospects. • Endless possibilities and benefits……..
  • 7. ProjectManagement Plan : “Tells How work will be done” The key to a successful project is on the planning. All the detailed planning work for different aspects of the project is integrated into one single plan known as the Project Management Plan. Input: Goal Team Money Time Equipment Project Output : Deliverables
  • 8. Why • ‘Why’ is from the business case Why & What • ‘Why’ & ‘What’ are management statement of the success criteriaand should be agreed with the project sponsor Who • ‘Who’ will do the work and stakeholder awareness of the project When • ‘When’ deals with schedules and phasing for the project How • ‘How’ which is the project manager vision to implement project from beginning to end How much • ‘How Much’ covers the costs and budgets of the project. ThePMPlanestablishes the projects:
  • 12. Most important phase of the project management. Planning is an art and science of converting a set of objectives to realization through a series of steps executed in an organized and predicted way so that there will be less requirement of changes in the plan later on. The old saying “Plan the work, Work the plan” PLANNING CONTROLLING SCHEDULING CLOSING STAGES
  • 13. Scheduling Phase is the process of formalizing the planned activities, assigning the durations, resources and sequence of occurrence in consultation with the team members. Planning and Scheduling phases are under taken before the actual project starts. SCHEDULIN G CONTROLLING PLANNING CLOSING STAGES
  • 14. Controlling phase is undertaken during the actual project implementation. Project controlling is a mechanism established to determine deviations from the project base schedule, to re-plan& reschedule during implementation to compensate the deviations on the basis of commissioning minima, flow of resources like finance, manpower, equipment & application techniques. CONTROLLING PLANNING SCHEDULING CLOSING STAGES
  • 15. Closing phase is the last phase of the project which brings close out of the complete project. Whatever the project requirements are pre-defined, during this phase the total delivery is made and it is accepted by the customer. Maximum conflicts can arise in the project during this phase between those who have worked to deliver the outcome (contractor) and those who are accepting the results of the work (customer). CONTROLLING PLANNING SCHEDULING CLOSING STAGES
  • 16. PM Knowledge Areas PM Knowledge Areas Cost Change Document Integration 1 Scope 2 Time 3 4 Quality 5 Risk 8 Human Resource 6 Communi Cation 7 Procure ment 9
  • 17. Project Integration Management  Project IntegrationManagement supports various elements of project management which are identified, defined, combined and coordinated.  Develop Project Charter Develop Project Management Plan Direct and Manage Project execution Monitor and Control Project Work Perform Integrate Change Control Close Project or Close
  • 18. Project Charter :  DOCUMENT that formally authorizes a project. Provide information about internal and external parties involved in and affected by the project. Documenting initial requirements that satisfy the stake holders’ needs and expectations. ISSUED by a project initiator or sponsor, external to project organization, at a level appropriate to project funding.  EMPOWERS the project manager to apply resources to project.  Summary level Milestone schedule and Summary level Budget. Project Integration Management
  • 19. Project Scope Management  Project scope management includes the processes required to ensure that the project includes all the work required, and only the work required to complete the project successfully  Collect requirements Define Scope Create WBS Verify Scope
  • 20. WBS – Work Breakdown Structure : A deliverable-oriented hierarchical decomposition of work to be executed by the project team to: •create required deliverables • accomplish project objectives  WBS organizes and defines the total scope and represents specified in the current approved Scope Statement!  Process of subdividing project deliverables and project work into more manageable components.  Lowest level of WBS is work package can be scheduled, cost estimated, monitored, and controlled. Project Scope Management
  • 21. TYPICAL WBS OFA PROJECT OVERALLPROJECT ENGINEERING BASIC ENGINEERING DETAILED ENGINEERING PROJECT ENGINERING PROCUREMENT PLACEMENT OF ORDER ON VENDORS MANUFACTURING & DELIVERY EQUIPMENT RECEIVED AT SITE ( …%) CONSTRUCTION SITE MOBILISATION CIVIL WORK STRUCTURAL STEEL WORK EQUIPMENT INSTALLATION PIPING INSTALLATION ELEC. INSTALLATION INSTRUMEN. INSTALLATION INSULATION & PAINTING COLD COMMISSIONING HOT COMMISSIONING Civil work for Main equipment Civil work for Aux. Facilities Piling work • KPL - WBS
  • 22. Project Time Management  Project Time Management ensures the timely completion of the project.  Plan Schedule Management  Define Activities  Sequence Activities  Estimate Activity Resources  Estimate Activity Durations  Develop Schedule  Control Schedule
  • 24.  Schedule once finalized is set as a baseline  Progress of work are tracked against the baseline  Current progress is arrived from various (Engineering, Proc, Manufacturing and Construction) Trackers developed for the purpose. These schedules are called current schedules  Analysis and forecasting is done in progress reports. Schedule using MS Project Schedule using Primavera (P6) Engineering Tracker Manufacturing & Supply Tracker construction tracker Project Time Management
  • 25. Project Cost Management  Project cost Management includes the processes involved in estimating, budgeting, and controlling costs so that the project can be completed within the approved budget.  Estimate cost Convert it into budget Load the cost into schedule Perform earned value (EV) analysis Perform estimate at complete (EAC) Administer changes Control cost
  • 26. Project Quality Management  Project Quality Management ensures the project will satisfy NEEDS for which it was undertaken.  Plan Quality Perform Quality Assurance Perform Quality control What is Quality?  Conformance to specifications  Fitness for use
  • 27. Project Quality Management Plan Quality Techniques • Cost benefit analysis • Cost of quality • Benchmarking • Design of experiments • Seven quality tools • Statistical sampling PerformQuality Assurance Techniques • Quality management and control tools • Quality audits • Process analysis PerformQuality Control Techniques • Statistical sampling • Inspection • Seven quality tools and techniques √ Cause and effect diagram √ Flowcharts √ Check sheets √ Pareto diagrams √ Histogram √ Control charts √ Scatter diagram
  • 28. Project Human Resource Management  Project human resource management includes the processes that organize, manage, and lead the project team and to make most effective use of people involved in the project. Develop Human Resource Plan (Role & Responsibility, Organization chart, Staffing Management Plan)  Acquire project team  Develop project team  Manage project team Organization Chart
  • 30. Project Communications Management  Project communication management include processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, a nd ultimate disposal of project information.  Identify Stakeholders  Plan Communication  Distribute Information  Manage Stakeholders expectations  Report Performance RACI
  • 31. Project Stakeholders :  Customers/users  Sponsor  Portfolio managers/portfolio review board  Program managers  Project management office  Project managers  Project team  Functional managers  Operations management  Sellers/business partners Project Communications Management
  • 33. Project Risk Management Risk Assessment Risk Control Risk Ranking Risk Mitigation  Project Risk Management is concerned with identifying, analyzing and responding to project risks.  Plan Risk Management Identify Risks Perform Qualitative Risk Analysis Perform Quantitative Risk Analysis Plan Risk responses Monitor and Control Risks Risk Register
  • 34. Project Procurement Management  Project Procurement Management is needed to acquire material, goods and services outside performing organization to meet project scope.  Plan Procurements  Conduct Procurement  Administer Contracts  Close Procurement
  • 35.  Projects generally don’t go 100%as planned resulting into variations from plans in scope, time, cost, quality  Change control boards (CCBs) Project Change Management
  • 36. Document management is very important (but largely ignored) aspect of project management  This can be a sophisticated software or simple excel sheets depending on the organization strategy  Once adopted its use should be fully exploited viz. 100% documents should pass through it and document reviews should be done as per the matrix defined  MIS of document status be generated at the end of period Project Document Management
  • 37.  Proper DMS ensures right information to all stakeholders at all times  Avoid using obsolete drawings and designs for execution  Serves a very good engine for future use of project data  Example of a simple document management system Document control log Project Document Management
  • 38. S-Curve in Monthly Progress Report Progress reporting is done through different formats and curves.
  • 39. S- Curve is the graphic display of cumulative progress plotted against time. Ideal S - Curve is a sinusoidal curve based on the following formulae: Y=[1- sin(x/xn *180+90)* 5 0 ] Y –Percent progress x –Period at which s-curve value required xn –Total period The name is derived from the 'S' like nature of the curve. S-Curve Whatis“SCurve”
  • 40. Progress Cumulative progress Curve Plotted in a different scale Time I tisan ideal distributioncurve. Depending upon thevarious guiding factors itmay vary. Progress distribution curve Starting Period Finishing Period Peak Period