SlideShare ist ein Scribd-Unternehmen logo
1 von 36
Master Title
Click to edit Master subtitle style
Computer Simulation
of Pipe Fabrication
Zuhair Haddad
Chief Information Officer
CCC
Ramzi Labban
Manager, Computer Modeling & Simulation
CCC
Agenda
• Introduction
• Simulation at CCC
• Pipe Spool Fabrication
• Discrete Event Simulation Model
• Benchmarking
• Case Study
Simulation at CCC
• Computer Based Modeling and Simulation has been
in use at CCC since late 2005
• Main uses include:
• Low Level Resource Planning
• Performance Improvement
• Process Optimization
• Schedule Validation
• Look Ahead Scheduling
• Assessing Direct and Indirect Impact of Changes (Delay
and Disruption, lost productivity & rework)
• Quantification and Justification of Claims
Simulation at CCC
• Material Forward Planning (piping)
• Earthworks
• Asphalt Paving
• Pipe Fabrication and Erection
• Pipeline Construction
• Building Finishing Activities
• Pipe spool fabrication
– A major component of construction operations on
large industrial projects
– Relatively short term, complex construction process
– Riddled with uncertainty due to the intrinsic unique
nature of its outputs and the numerous factors
affecting its activities
– Directly affects pipe installation
• Important for all stakeholders to have a good grasp
of the performance of pipe fabrication shops and
their ability to meet the site pipe installation
schedules
Pipe Spool Fabrication
Pipe Spool Fabrication
• Fabrication Managers or Subcontractors want to
“optimize” their operations:
– fabricate large bore/heavy spools early in the process
– fabricate even if out of sequence
• For in-house shops: this keeps manpower busy
• For subcontractors: this allows them to earn more
cash up front (usually paid by tonnage)
• Fabricating out of sequence material required for
critical activities leads to delays and disruptions in
the fabrication and site installation process
Example of effect of out of sequence fabrication
Project Progress– Week 53 (1 of 8)
All rights reserved to CCC
Example of effect of out of sequence fabrication
Project Progress– Week 54 (2 of 8)
All rights reserved to CCC
Example of effect of out of sequence fabrication
Project Progress– Week 55 (3 of 8)
All rights reserved to CCC
Example of effect of out of sequence fabrication
Project Progress– Week 56 (4 of 8)
All rights reserved to CCC
Example of effect of out of sequence fabrication
Project Progress– Week 57 (5 of 8)
All rights reserved to CCC
Example of effect of out of sequence fabrication
Lessons Learned – Week 58 (6 of 8)
All rights reserved to CCC
Example of effect of out of sequence fabrication
Project Progress– Week 59 (7 of 8)
All rights reserved to CCC
Example of effect of out of sequence fabrication
Project Progress– Week 60 (8 of 8)
All rights reserved to CCC
Pipe Spool Fabrication
• Fabrication needs to meet site installation
schedule
• Site sequences should drive fabrication
sequences (i.e. Priority areas, levels [bottom to
up], etc…)
• A balance between fabrication shop productivity
and cohesion to site installation schedules and
priorities needs to exist:
– Fabrication of spools adheres to site installation
schedule
– Fabrication shop manpower idle is kept to a minimum
– Critical material is available for critical activities
Pipe Spool Fabrication
• Pipe construction managers need to be able to
quickly come up with alternate
fabrication/installation plans based on changing site
conditions:
– Major piece(s) of equipment delayed or damaged
– Material shortage(s)
– Redesign of a system or structure
• Forecasting pipe spool fabrication activity
completion and optimizing resource allocation and
utilization are complicated by two main factors:
– very large number of spools
– diverse characteristics and resource requirements for each
spool
• A complex task well suited to computer modeling
and simulation
Pipe Spool Fabrication
How can the Pipe Spool Fabrication Simulator help?
• The pipe spool fabrication simulator provides stakeholders and end users
with a tool to proactively perform schedule validation and low level
resource planning on pipe fabrication activities on large industrial projects
• The simulation model can be run during the different phases of a project:
– Ahead of the project in predictive mode
– During execution to aid in optimization and forecasting
– Retrospectively for change impact assessment and/or lessons-learned analysis
• It helps answer questions such as:
– Will we be able to finish the fabrication activities on time with the proposed
resources?
– Which specific resources are bottlenecks?
– Which resources are under-utilized?
– How is actual crew productivity compared to planned and forecast
productivities
Simulation Model
• Abstraction of the real world pipe spool fabrication
process into a simulation model representing the
operations of a pipe spool fabrication shop:
– What are we producing?
• Spools & their characteristics
• Joints & characteristics
– How are we producing them?
• Fabrication activities/flow
• Resources required
Simulation Model: Activity Flow
Simulation Model: Activities to Model
• Major pipe spool fabrication activities modeled:
 Cut
 Bevel
 Fit-up (& tack welding)
 Welding (auto and manual)
 QC inspection
 Post weld heat treatment (PWHT)
 Non-destructive testing (NDT)
 Painting
• For each activity, the type of resource (crew) required and its
relevant productivity were also identified
Simulation Model: Resources – Crew Composition
• Each pipe fabrication activity is associated with a
resource type
• Each resource type is typically a crew composed of a
group of workers required to perform a specific task
Typical crew compositions on a large industrial construction project
Crew Type
Worker
Type 1
Worker
Type 2
Worker
Type 3
Worker
Type 4
Worker
Type 5
Worker
Type 6
Worker
Type 7
Worker
Type 8
Worker
Type 9
Cut 1 2 1 2
Bevel 1
Fit-up 2 2 1 4
Weld Size 1 1 1
Weld Size 2 2 2
PWHT 1 2
Painting 1 3 4
Simulation Model: Resources - Histogram
• Workers available over the duration of the project
make up the required crews (resources) for the
fabrication activities
Typical worker availability over time on an industrial project
1 2 3 4 5 6 7 8
1 21 23 25 25 25 25 25 25
2 85 90 95 95 100 100 100 100
3 80 82 85 86 104 104 104 104
5 37 38 40 41 42 42 42 42
6 90 95 100 100 110 110 110 110
7 92 99 112 129 135 135 135 135
Worker
Type
Month
Simulation Model: Workflow to DES Model
Pipe Fabrication Activity Flow
Simulation Model
Simulation Model: DES Model
Simulation Model: Parameters Interface
Simulation Model: Data Inputs
• Spool and joint characteristics required for simulating
the fabrication activities were specified
Two-level hierarchy for spools and their relevant joints
Spool ID Stauts Material Paint Code Surface Area Priority
3 CS 6D 0.03 180
Weld # Weld Type Weld Inch-Dia PWHT Req'd NDT Req'd
2 SB 0.75 0 0
4 SB 0.75 0 0
5 SB 0.75 0 0
A140-A141-B92SL-15139D-S102 3 CS 6D 0.01 180
A140-A141-B92SL-15139D-S103 3 CS 6D 0.15 180
A140-A141-B92SL-15139D-S101
Simulation Model: Data Outputs
• The simulator produces a comprehensive set of data
comprised of the artificial history of the simulated pipe
fabrication operations
• The result set contains a record of the activities performed on
the corresponding entities (spools or welds) utilizing the
required resources:
– Simulated spool start / end dates and times for each status
– Simulated joints start / end dates and times for welding activities
– Crew man-hour requirements per simulated spool or joint activity
Scenario # Spool ID Weld No Activity Start Date and Time End Date and Time Resources
1304152 A140-A141-B92SL-15139D-S101 2 Welding 4/3/2013 11:01 4/3/2013 11:23 1
1304152 A140-A141-B92SL-15139D-S101 4 Welding 4/3/2013 11:01 4/3/2013 11:23 1
1304152 A140-A141-B92SL-15139D-S101 5 Welding 3/3/2013 15:01 3/3/2013 15:23 1
1304152 A140-A141-B92SL-15139D-S101 Painting 3/14/13 8:00 3/16/13 10:00 1
Benchmarking
• Multiple fab shop data collection exercises at large
CCC industrial construction projects in the Middle
East were performed to collect benchmark
productivity data for the simulator
Benchmarking
• Very practical information was collected by observing
the different fabrication shop operations:
– Actual uninterrupted work productivity timed from start
to finish with a total work scope and number of workers
involved
– Overall actual to-date production data for the
fabrication shops broken down by week including total
inch-dia and total manpower per week
– Daily worker hours breakdown in terms of breaks
related to the current heat index, lunch break, toolbox
talks, arrival and departure allowances, etc.
Case Study: Implementation on Large Gas Plant
Construction Project
Barzan Onshore Project
• Location: Ras Laffan Industrial City – Qatar
• Production Capacity: 2 bcfpd (Train 1 + Train 2)
• Contract: Barzan Central Contract, Package 1
(Process Area & Building Works)
• Client: QP and Exxon Mobil
• Main Contractor (EPC): Japan Gas Company (JGC)
• Scope: Construction of the process plant area, including piping fabrication
and erection, civil works, EPC buildings, steel structure erection,
equipment erection, E&I, painting, insulation and common scaffolding
Phase # of Joints Inch-Dia # of Spools # of ISO's
TRAIN 1 367,572 1,203,882 61,490 17,001
TRAIN 2 337,742 1,181,251 52,349 16,757
Case Study: Implementation on Large Gas Plant
Construction Project
Month
Total Inch-
Dia
Cut
Crew
Bevel
Crew
FitUp
Crew
Weld
Crew
Autoweld
Machines
Actual
Days
Sim
Days
October 50,798 6 20 30 90 8 28 27
November 61,217 10 20 30 102 8 30 30
December 67,091 15 25 40 118 8 31 29
January 68,220 14 24 38 113 8 31 30
February 70,848 15 25 40 137 8 28 25
March 78,159 15 25 40 156 8 31 24
Detecting Productivity Anomalies
• Fabrication activities on site were compared to
simulator runs to detect and emphasize productivity
anomalies
• We can notice a marked decline in February and
increase in March
Cut Bevel Fitup Weld
0% 48 51 53 54
10% 45 47 50 51
20% 39 41 44 45
30% 37 39 43 43
40% 33 36 38 39
50% 32 34 37 38
60% 31 33 36 38
70% 29 31 33 37
80% 27 30 32 37
90% 25 27 30 37
100% 24 26 29 37
Additional Cut / Bevel
/ Fitup Resources
Fabrication Activities End Day
Case Study: Implementation on Large Gas Plant
Construction Project
Detecting Bottlenecks and Optimizing Resource Mixes
Case Study: Implementation on Large Gas Plant
Construction Project
Activity Sim Start Date Sim End Date
Cut 3/2/13 8:00 3/3/13 17:01
Bevel 3/2/13 8:06 3/6/13 9:34
FitUp 3/2/13 8:13 3/9/13 17:06
Welding 3/2/13 8:00 3/30/13 17:18
NDT 3/2/13 19:00 5/16/13 5:00
PWHT 3/1/13 5:00 5/16/13 19:22
Blasting 3/2/13 6:00 5/18/13 14:30
Painting 3/2/13 14:30 5/21/13 16:30
Aea Sim Start Date Sim End Date
A110 3/1/13 5:12 3/17/13 10:00
A120 3/1/13 5:00 5/17/13 10:00
A130 3/1/13 5:00 3/22/13 16:00
A140 3/1/13 5:12 3/27/13 12:00
A150 3/1/13 5:00 3/30/13 10:00
A160 3/1/13 5:00 4/6/13 16:30
A170 3/1/13 5:12 5/17/13 10:00
A210 3/1/13 5:12 5/17/13 10:00
A220 3/1/13 5:00 5/17/13 10:00
A230 3/1/13 5:12 5/21/13 16:30
A240 3/27/13 11:27 5/17/13 10:00
A250 3/1/13 5:12 3/29/13 14:00
A260 3/6/13 6:00 5/21/13 16:30
A270 3/1/13 5:12 5/17/13 10:00
Forecasting Activity and Area Start and Completion Dates
Future Work
• Further development and enhancements to this
model include:
– A material constraint module (Material Forward
Planning)
– Full integration with CCC’s C3D construction
management software
– A pipe installation simulation model covering pipe
spool construction activities up to when spools are
installed on site and given final release
THANK YOU
Zuhair Haddad (ZUHAIR@CCC.ME)
Ramzi Labban (RLABBAN@CCC.COM.LB)

Weitere ähnliche Inhalte

Was ist angesagt?

Antonio R.Delmo updated resume Sept2016docx (1)
Antonio R.Delmo updated resume Sept2016docx (1)Antonio R.Delmo updated resume Sept2016docx (1)
Antonio R.Delmo updated resume Sept2016docx (1)
Antonio Delmo
 
Kaushik Patel Resume
Kaushik Patel ResumeKaushik Patel Resume
Kaushik Patel Resume
Kaushik Patel
 
Anas Khalifa's CV_JAN.-2017
Anas Khalifa's CV_JAN.-2017Anas Khalifa's CV_JAN.-2017
Anas Khalifa's CV_JAN.-2017
Anas Khalifa
 
Wael Azmy_CV + Exp Letters
Wael Azmy_CV + Exp LettersWael Azmy_CV + Exp Letters
Wael Azmy_CV + Exp Letters
Waell Azmy
 

Was ist angesagt? (19)

Make BIM work for you
Make BIM work for youMake BIM work for you
Make BIM work for you
 
6.0 CURT CII - Digital Transformation of Construction Industry
6.0 CURT CII  - Digital Transformation of Construction Industry6.0 CURT CII  - Digital Transformation of Construction Industry
6.0 CURT CII - Digital Transformation of Construction Industry
 
Mandated BIM! Are you ready?
Mandated BIM! Are you ready?Mandated BIM! Are you ready?
Mandated BIM! Are you ready?
 
Designing to Enhance Construction Planning & Monitoring
Designing to Enhance Construction Planning & MonitoringDesigning to Enhance Construction Planning & Monitoring
Designing to Enhance Construction Planning & Monitoring
 
The Information Challenge Managing Construction with BIM
The Information ChallengeManaging Construction with BIMThe Information ChallengeManaging Construction with BIM
The Information Challenge Managing Construction with BIM
 
Epc projects and cad tools
Epc projects and cad toolsEpc projects and cad tools
Epc projects and cad tools
 
Epc presentation robert foxpresentation
Epc presentation robert foxpresentationEpc presentation robert foxpresentation
Epc presentation robert foxpresentation
 
Conquas
ConquasConquas
Conquas
 
Antonio R.Delmo updated resume Sept2016docx (1)
Antonio R.Delmo updated resume Sept2016docx (1)Antonio R.Delmo updated resume Sept2016docx (1)
Antonio R.Delmo updated resume Sept2016docx (1)
 
Kaushik Patel Resume
Kaushik Patel ResumeKaushik Patel Resume
Kaushik Patel Resume
 
Building Commissioning, Ongoing Commissioning and quality management using BACS
Building Commissioning, Ongoing Commissioning and quality management using BACSBuilding Commissioning, Ongoing Commissioning and quality management using BACS
Building Commissioning, Ongoing Commissioning and quality management using BACS
 
Quy trình BIM
Quy trình BIMQuy trình BIM
Quy trình BIM
 
updated cv 2015
updated cv 2015updated cv 2015
updated cv 2015
 
How CIDB could control and manage the construction contractors towards implem...
How CIDB could control and manage the construction contractors towards implem...How CIDB could control and manage the construction contractors towards implem...
How CIDB could control and manage the construction contractors towards implem...
 
Ayman curriculum vitae
Ayman curriculum vitaeAyman curriculum vitae
Ayman curriculum vitae
 
Ayman curriculum vitae2
Ayman curriculum vitae2Ayman curriculum vitae2
Ayman curriculum vitae2
 
Anas Khalifa's CV_JAN.-2017
Anas Khalifa's CV_JAN.-2017Anas Khalifa's CV_JAN.-2017
Anas Khalifa's CV_JAN.-2017
 
Wael Azmy_CV + Exp Letters
Wael Azmy_CV + Exp LettersWael Azmy_CV + Exp Letters
Wael Azmy_CV + Exp Letters
 
The Value of Building Commissioning
The Value of Building CommissioningThe Value of Building Commissioning
The Value of Building Commissioning
 

Andere mochten auch

TANK FABRICATION AND PIPING SYSTEM
TANK FABRICATION AND PIPING SYSTEMTANK FABRICATION AND PIPING SYSTEM
TANK FABRICATION AND PIPING SYSTEM
Ka Chin
 
Design Of Fibrication And Pipe Inspection Robot
Design Of Fibrication And Pipe Inspection RobotDesign Of Fibrication And Pipe Inspection Robot
Design Of Fibrication And Pipe Inspection Robot
Suchit Moon
 
Scaffolding Power Point
Scaffolding Power PointScaffolding Power Point
Scaffolding Power Point
Ashlow
 
Crane Safety & Rigging
Crane Safety & RiggingCrane Safety & Rigging
Crane Safety & Rigging
fcarlson
 
Piping Training course-How to be an Expert in Pipe & Fittings for Oil & Gas c...
Piping Training course-How to be an Expert in Pipe & Fittings for Oil & Gas c...Piping Training course-How to be an Expert in Pipe & Fittings for Oil & Gas c...
Piping Training course-How to be an Expert in Pipe & Fittings for Oil & Gas c...
Varun Patel
 
Life Cycle of Oil & Gas Wells
Life Cycle of Oil & Gas WellsLife Cycle of Oil & Gas Wells
Life Cycle of Oil & Gas Wells
Mohamed Elnagar
 
Oil & Gas Production and Surface Facilities
Oil & Gas Production and Surface FacilitiesOil & Gas Production and Surface Facilities
Oil & Gas Production and Surface Facilities
Mohamed Elnagar
 
Introduction to piping.......PLEASE give your valuable comments if you like t...
Introduction to piping.......PLEASE give your valuable comments if you like t...Introduction to piping.......PLEASE give your valuable comments if you like t...
Introduction to piping.......PLEASE give your valuable comments if you like t...
Madhur Mahajan
 
Storage tanks basic training (rev 2)
Storage tanks basic training (rev 2)Storage tanks basic training (rev 2)
Storage tanks basic training (rev 2)
ledzung
 

Andere mochten auch (20)

TANK FABRICATION AND PIPING SYSTEM
TANK FABRICATION AND PIPING SYSTEMTANK FABRICATION AND PIPING SYSTEM
TANK FABRICATION AND PIPING SYSTEM
 
Bondstrand bonder training, rev 0 (ptsc m&c)
Bondstrand bonder training, rev 0 (ptsc m&c)Bondstrand bonder training, rev 0 (ptsc m&c)
Bondstrand bonder training, rev 0 (ptsc m&c)
 
Piping ppt1
Piping ppt1Piping ppt1
Piping ppt1
 
Design Of Fibrication And Pipe Inspection Robot
Design Of Fibrication And Pipe Inspection RobotDesign Of Fibrication And Pipe Inspection Robot
Design Of Fibrication And Pipe Inspection Robot
 
I3M 2013 – EMSS Conference - Pipe Spool Fabrication Simulation Model
I3M 2013 – EMSS Conference - Pipe Spool Fabrication Simulation ModelI3M 2013 – EMSS Conference - Pipe Spool Fabrication Simulation Model
I3M 2013 – EMSS Conference - Pipe Spool Fabrication Simulation Model
 
Tank Training
Tank TrainingTank Training
Tank Training
 
Scaffolds ppt construction
Scaffolds ppt constructionScaffolds ppt construction
Scaffolds ppt construction
 
Scaffolding Power Point
Scaffolding Power PointScaffolding Power Point
Scaffolding Power Point
 
Introduction to Storage Tanks
Introduction to Storage TanksIntroduction to Storage Tanks
Introduction to Storage Tanks
 
Oil & Gas Plant Construction, Project Execution Plan
Oil & Gas Plant Construction, Project Execution PlanOil & Gas Plant Construction, Project Execution Plan
Oil & Gas Plant Construction, Project Execution Plan
 
OIL AND GAS SURFACE WELLHEAD AND CHRISTMAS TREE
OIL AND GAS SURFACE WELLHEAD AND CHRISTMAS TREEOIL AND GAS SURFACE WELLHEAD AND CHRISTMAS TREE
OIL AND GAS SURFACE WELLHEAD AND CHRISTMAS TREE
 
Crane Safety & Rigging
Crane Safety & RiggingCrane Safety & Rigging
Crane Safety & Rigging
 
Piping Training course-How to be an Expert in Pipe & Fittings for Oil & Gas c...
Piping Training course-How to be an Expert in Pipe & Fittings for Oil & Gas c...Piping Training course-How to be an Expert in Pipe & Fittings for Oil & Gas c...
Piping Training course-How to be an Expert in Pipe & Fittings for Oil & Gas c...
 
Life Cycle of Oil & Gas Wells
Life Cycle of Oil & Gas WellsLife Cycle of Oil & Gas Wells
Life Cycle of Oil & Gas Wells
 
Oil & Gas Production and Surface Facilities
Oil & Gas Production and Surface FacilitiesOil & Gas Production and Surface Facilities
Oil & Gas Production and Surface Facilities
 
Introduction to piping.......PLEASE give your valuable comments if you like t...
Introduction to piping.......PLEASE give your valuable comments if you like t...Introduction to piping.......PLEASE give your valuable comments if you like t...
Introduction to piping.......PLEASE give your valuable comments if you like t...
 
Pipe flange fittings by Madhur
Pipe flange fittings by MadhurPipe flange fittings by Madhur
Pipe flange fittings by Madhur
 
Introduction to Offshore Oil and Gas Surface Facilities
Introduction to Offshore Oil and Gas Surface FacilitiesIntroduction to Offshore Oil and Gas Surface Facilities
Introduction to Offshore Oil and Gas Surface Facilities
 
Piping components, materials, codes and standards part 1- pipe
Piping components, materials, codes and standards   part 1- pipePiping components, materials, codes and standards   part 1- pipe
Piping components, materials, codes and standards part 1- pipe
 
Storage tanks basic training (rev 2)
Storage tanks basic training (rev 2)Storage tanks basic training (rev 2)
Storage tanks basic training (rev 2)
 

Ähnlich wie Fiatech 2014 - Computer Simulation of Pipe Fabrication, Ramzi Labban

Using lean to reduce prototype lead time 2006
Using lean to reduce prototype lead time 2006Using lean to reduce prototype lead time 2006
Using lean to reduce prototype lead time 2006
Chris Baichoo
 
Eng.Kamel Mahmoud(UPDATED)
Eng.Kamel Mahmoud(UPDATED)Eng.Kamel Mahmoud(UPDATED)
Eng.Kamel Mahmoud(UPDATED)
Kamel Mahmoud
 
Company Presentation 2015
Company Presentation 2015Company Presentation 2015
Company Presentation 2015
Mach Cao Xuan
 
Lisa_zhang2016 piping designer -new
Lisa_zhang2016 piping designer -newLisa_zhang2016 piping designer -new
Lisa_zhang2016 piping designer -new
lisa zhang
 

Ähnlich wie Fiatech 2014 - Computer Simulation of Pipe Fabrication, Ramzi Labban (20)

Using lean to reduce prototype lead time 2006
Using lean to reduce prototype lead time 2006Using lean to reduce prototype lead time 2006
Using lean to reduce prototype lead time 2006
 
Nirmal_Resume
Nirmal_ResumeNirmal_Resume
Nirmal_Resume
 
Episode 30 : Project Execution ( Part 1 )
Episode 30 :  Project Execution ( Part 1 ) Episode 30 :  Project Execution ( Part 1 )
Episode 30 : Project Execution ( Part 1 )
 
Eng.Kamel Mahmoud(UPDATED)
Eng.Kamel Mahmoud(UPDATED)Eng.Kamel Mahmoud(UPDATED)
Eng.Kamel Mahmoud(UPDATED)
 
Summary of previous projects
Summary of previous projectsSummary of previous projects
Summary of previous projects
 
CV- Piping Engineer (EPC)
CV- Piping  Engineer (EPC)CV- Piping  Engineer (EPC)
CV- Piping Engineer (EPC)
 
Project Management
Project ManagementProject Management
Project Management
 
Resume_Hariprasad
Resume_HariprasadResume_Hariprasad
Resume_Hariprasad
 
STAGE 1 PRESENTATION.pptx
STAGE 1 PRESENTATION.pptxSTAGE 1 PRESENTATION.pptx
STAGE 1 PRESENTATION.pptx
 
Sachin Mohelay
Sachin MohelaySachin Mohelay
Sachin Mohelay
 
Anitha Vanga
Anitha VangaAnitha Vanga
Anitha Vanga
 
Introduction to Cellular Manufacturing - ADDVALUE - Nilesh Arora
Introduction to Cellular Manufacturing - ADDVALUE - Nilesh AroraIntroduction to Cellular Manufacturing - ADDVALUE - Nilesh Arora
Introduction to Cellular Manufacturing - ADDVALUE - Nilesh Arora
 
Company Presentation 2015
Company Presentation 2015Company Presentation 2015
Company Presentation 2015
 
Final project report
Final project reportFinal project report
Final project report
 
Sachin Mohelay
Sachin MohelaySachin Mohelay
Sachin Mohelay
 
agile constructsim overview
agile constructsim overviewagile constructsim overview
agile constructsim overview
 
Presntation (MNIT).pptx
Presntation (MNIT).pptxPresntation (MNIT).pptx
Presntation (MNIT).pptx
 
Process optimization of pressure die casting to eliminate defect using cae so...
Process optimization of pressure die casting to eliminate defect using cae so...Process optimization of pressure die casting to eliminate defect using cae so...
Process optimization of pressure die casting to eliminate defect using cae so...
 
Lisa_zhang2016 piping designer -new
Lisa_zhang2016 piping designer -newLisa_zhang2016 piping designer -new
Lisa_zhang2016 piping designer -new
 
CV
CVCV
CV
 

Mehr von CCT International

Mehr von CCT International (20)

Digital Transformation of the Construction Industry
Digital Transformation of the Construction IndustryDigital Transformation of the Construction Industry
Digital Transformation of the Construction Industry
 
BIM In Practice Seminar
BIM In Practice Seminar BIM In Practice Seminar
BIM In Practice Seminar
 
Adding Intelligence to AWP
Adding Intelligence to AWPAdding Intelligence to AWP
Adding Intelligence to AWP
 
BIM Based Project Controls
BIM Based Project ControlsBIM Based Project Controls
BIM Based Project Controls
 
The Future is Now (5th BIM and Lean Conference 2017)
The Future is Now (5th BIM and Lean Conference 2017)The Future is Now (5th BIM and Lean Conference 2017)
The Future is Now (5th BIM and Lean Conference 2017)
 
Contractors: Get BIM Ready!
Contractors: Get BIM Ready!Contractors: Get BIM Ready!
Contractors: Get BIM Ready!
 
Fiatech 2016 - Advanced Work Packaging: from Theory to Practice
Fiatech 2016 - Advanced Work Packaging: from Theory to PracticeFiatech 2016 - Advanced Work Packaging: from Theory to Practice
Fiatech 2016 - Advanced Work Packaging: from Theory to Practice
 
IBM Case Study of Maximo Implementation at CCC
IBM Case Study of Maximo Implementation at CCCIBM Case Study of Maximo Implementation at CCC
IBM Case Study of Maximo Implementation at CCC
 
AF-1438: Transportation MUG: CCC's Use of Maximo for Fleet Management on Infr...
AF-1438: Transportation MUG: CCC's Use of Maximo for Fleet Management on Infr...AF-1438: Transportation MUG: CCC's Use of Maximo for Fleet Management on Infr...
AF-1438: Transportation MUG: CCC's Use of Maximo for Fleet Management on Infr...
 
Computer Simulation: Quantifying and Substantiating a Claim for Extension of ...
Computer Simulation: Quantifying and Substantiating a Claim for Extension of ...Computer Simulation: Quantifying and Substantiating a Claim for Extension of ...
Computer Simulation: Quantifying and Substantiating a Claim for Extension of ...
 
Asset Management - Bridging Boundaries in Ongoing Asset Management
Asset Management - Bridging Boundaries in Ongoing Asset ManagementAsset Management - Bridging Boundaries in Ongoing Asset Management
Asset Management - Bridging Boundaries in Ongoing Asset Management
 
Imagine a World Without Isometric
Imagine a World Without IsometricImagine a World Without Isometric
Imagine a World Without Isometric
 
Advanced Work Packaging (AWP) - Reduction to Practice
Advanced Work Packaging (AWP) - Reduction to PracticeAdvanced Work Packaging (AWP) - Reduction to Practice
Advanced Work Packaging (AWP) - Reduction to Practice
 
Smart Construction Site
Smart Construction SiteSmart Construction Site
Smart Construction Site
 
AF-1438: Transportation MUG: CCC's Use of Maximo for Fleet Management on Infr...
AF-1438: Transportation MUG: CCC's Use of Maximo for Fleet Management on Infr...AF-1438: Transportation MUG: CCC's Use of Maximo for Fleet Management on Infr...
AF-1438: Transportation MUG: CCC's Use of Maximo for Fleet Management on Infr...
 
Digital Pens - Firas Hijazi - FIATECH and COMIT
Digital Pens - Firas Hijazi - FIATECH and COMITDigital Pens - Firas Hijazi - FIATECH and COMIT
Digital Pens - Firas Hijazi - FIATECH and COMIT
 
Advanced Work Packaging - CCT Solutions at a Glance
Advanced Work Packaging - CCT Solutions at a GlanceAdvanced Work Packaging - CCT Solutions at a Glance
Advanced Work Packaging - CCT Solutions at a Glance
 
Advanced Work Packaging - Real Life Implementation
Advanced Work Packaging - Real Life ImplementationAdvanced Work Packaging - Real Life Implementation
Advanced Work Packaging - Real Life Implementation
 
Top 10 BIM Tips for Contractors
Top 10 BIM Tips for ContractorsTop 10 BIM Tips for Contractors
Top 10 BIM Tips for Contractors
 
A discrete Event Simulation Model of Asphalt Paving Operations, Ramzi Labban ...
A discrete Event Simulation Model of Asphalt Paving Operations, Ramzi Labban ...A discrete Event Simulation Model of Asphalt Paving Operations, Ramzi Labban ...
A discrete Event Simulation Model of Asphalt Paving Operations, Ramzi Labban ...
 

Kürzlich hochgeladen

"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
mphochane1998
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Kandungan 087776558899
 
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills KuwaitKuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
jaanualu31
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
ssuser89054b
 

Kürzlich hochgeladen (20)

Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 
Learn the concepts of Thermodynamics on Magic Marks
Learn the concepts of Thermodynamics on Magic MarksLearn the concepts of Thermodynamics on Magic Marks
Learn the concepts of Thermodynamics on Magic Marks
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
kiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal loadkiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal load
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
Air Compressor reciprocating single stage
Air Compressor reciprocating single stageAir Compressor reciprocating single stage
Air Compressor reciprocating single stage
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills KuwaitKuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
 
Rums floating Omkareshwar FSPV IM_16112021.pdf
Rums floating Omkareshwar FSPV IM_16112021.pdfRums floating Omkareshwar FSPV IM_16112021.pdf
Rums floating Omkareshwar FSPV IM_16112021.pdf
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptx
 
Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdf
 
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdf
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects
 

Fiatech 2014 - Computer Simulation of Pipe Fabrication, Ramzi Labban

  • 1. Master Title Click to edit Master subtitle style Computer Simulation of Pipe Fabrication Zuhair Haddad Chief Information Officer CCC Ramzi Labban Manager, Computer Modeling & Simulation CCC
  • 2. Agenda • Introduction • Simulation at CCC • Pipe Spool Fabrication • Discrete Event Simulation Model • Benchmarking • Case Study
  • 3. Simulation at CCC • Computer Based Modeling and Simulation has been in use at CCC since late 2005 • Main uses include: • Low Level Resource Planning • Performance Improvement • Process Optimization • Schedule Validation • Look Ahead Scheduling • Assessing Direct and Indirect Impact of Changes (Delay and Disruption, lost productivity & rework) • Quantification and Justification of Claims
  • 4. Simulation at CCC • Material Forward Planning (piping) • Earthworks • Asphalt Paving • Pipe Fabrication and Erection • Pipeline Construction • Building Finishing Activities
  • 5. • Pipe spool fabrication – A major component of construction operations on large industrial projects – Relatively short term, complex construction process – Riddled with uncertainty due to the intrinsic unique nature of its outputs and the numerous factors affecting its activities – Directly affects pipe installation • Important for all stakeholders to have a good grasp of the performance of pipe fabrication shops and their ability to meet the site pipe installation schedules Pipe Spool Fabrication
  • 6. Pipe Spool Fabrication • Fabrication Managers or Subcontractors want to “optimize” their operations: – fabricate large bore/heavy spools early in the process – fabricate even if out of sequence • For in-house shops: this keeps manpower busy • For subcontractors: this allows them to earn more cash up front (usually paid by tonnage) • Fabricating out of sequence material required for critical activities leads to delays and disruptions in the fabrication and site installation process
  • 7. Example of effect of out of sequence fabrication Project Progress– Week 53 (1 of 8) All rights reserved to CCC
  • 8. Example of effect of out of sequence fabrication Project Progress– Week 54 (2 of 8) All rights reserved to CCC
  • 9. Example of effect of out of sequence fabrication Project Progress– Week 55 (3 of 8) All rights reserved to CCC
  • 10. Example of effect of out of sequence fabrication Project Progress– Week 56 (4 of 8) All rights reserved to CCC
  • 11. Example of effect of out of sequence fabrication Project Progress– Week 57 (5 of 8) All rights reserved to CCC
  • 12. Example of effect of out of sequence fabrication Lessons Learned – Week 58 (6 of 8) All rights reserved to CCC
  • 13. Example of effect of out of sequence fabrication Project Progress– Week 59 (7 of 8) All rights reserved to CCC
  • 14. Example of effect of out of sequence fabrication Project Progress– Week 60 (8 of 8) All rights reserved to CCC
  • 15. Pipe Spool Fabrication • Fabrication needs to meet site installation schedule • Site sequences should drive fabrication sequences (i.e. Priority areas, levels [bottom to up], etc…) • A balance between fabrication shop productivity and cohesion to site installation schedules and priorities needs to exist: – Fabrication of spools adheres to site installation schedule – Fabrication shop manpower idle is kept to a minimum – Critical material is available for critical activities
  • 16. Pipe Spool Fabrication • Pipe construction managers need to be able to quickly come up with alternate fabrication/installation plans based on changing site conditions: – Major piece(s) of equipment delayed or damaged – Material shortage(s) – Redesign of a system or structure
  • 17. • Forecasting pipe spool fabrication activity completion and optimizing resource allocation and utilization are complicated by two main factors: – very large number of spools – diverse characteristics and resource requirements for each spool • A complex task well suited to computer modeling and simulation Pipe Spool Fabrication
  • 18. How can the Pipe Spool Fabrication Simulator help? • The pipe spool fabrication simulator provides stakeholders and end users with a tool to proactively perform schedule validation and low level resource planning on pipe fabrication activities on large industrial projects • The simulation model can be run during the different phases of a project: – Ahead of the project in predictive mode – During execution to aid in optimization and forecasting – Retrospectively for change impact assessment and/or lessons-learned analysis • It helps answer questions such as: – Will we be able to finish the fabrication activities on time with the proposed resources? – Which specific resources are bottlenecks? – Which resources are under-utilized? – How is actual crew productivity compared to planned and forecast productivities
  • 19. Simulation Model • Abstraction of the real world pipe spool fabrication process into a simulation model representing the operations of a pipe spool fabrication shop: – What are we producing? • Spools & their characteristics • Joints & characteristics – How are we producing them? • Fabrication activities/flow • Resources required
  • 21. Simulation Model: Activities to Model • Major pipe spool fabrication activities modeled:  Cut  Bevel  Fit-up (& tack welding)  Welding (auto and manual)  QC inspection  Post weld heat treatment (PWHT)  Non-destructive testing (NDT)  Painting • For each activity, the type of resource (crew) required and its relevant productivity were also identified
  • 22. Simulation Model: Resources – Crew Composition • Each pipe fabrication activity is associated with a resource type • Each resource type is typically a crew composed of a group of workers required to perform a specific task Typical crew compositions on a large industrial construction project Crew Type Worker Type 1 Worker Type 2 Worker Type 3 Worker Type 4 Worker Type 5 Worker Type 6 Worker Type 7 Worker Type 8 Worker Type 9 Cut 1 2 1 2 Bevel 1 Fit-up 2 2 1 4 Weld Size 1 1 1 Weld Size 2 2 2 PWHT 1 2 Painting 1 3 4
  • 23. Simulation Model: Resources - Histogram • Workers available over the duration of the project make up the required crews (resources) for the fabrication activities Typical worker availability over time on an industrial project 1 2 3 4 5 6 7 8 1 21 23 25 25 25 25 25 25 2 85 90 95 95 100 100 100 100 3 80 82 85 86 104 104 104 104 5 37 38 40 41 42 42 42 42 6 90 95 100 100 110 110 110 110 7 92 99 112 129 135 135 135 135 Worker Type Month
  • 24. Simulation Model: Workflow to DES Model Pipe Fabrication Activity Flow Simulation Model
  • 27. Simulation Model: Data Inputs • Spool and joint characteristics required for simulating the fabrication activities were specified Two-level hierarchy for spools and their relevant joints Spool ID Stauts Material Paint Code Surface Area Priority 3 CS 6D 0.03 180 Weld # Weld Type Weld Inch-Dia PWHT Req'd NDT Req'd 2 SB 0.75 0 0 4 SB 0.75 0 0 5 SB 0.75 0 0 A140-A141-B92SL-15139D-S102 3 CS 6D 0.01 180 A140-A141-B92SL-15139D-S103 3 CS 6D 0.15 180 A140-A141-B92SL-15139D-S101
  • 28. Simulation Model: Data Outputs • The simulator produces a comprehensive set of data comprised of the artificial history of the simulated pipe fabrication operations • The result set contains a record of the activities performed on the corresponding entities (spools or welds) utilizing the required resources: – Simulated spool start / end dates and times for each status – Simulated joints start / end dates and times for welding activities – Crew man-hour requirements per simulated spool or joint activity Scenario # Spool ID Weld No Activity Start Date and Time End Date and Time Resources 1304152 A140-A141-B92SL-15139D-S101 2 Welding 4/3/2013 11:01 4/3/2013 11:23 1 1304152 A140-A141-B92SL-15139D-S101 4 Welding 4/3/2013 11:01 4/3/2013 11:23 1 1304152 A140-A141-B92SL-15139D-S101 5 Welding 3/3/2013 15:01 3/3/2013 15:23 1 1304152 A140-A141-B92SL-15139D-S101 Painting 3/14/13 8:00 3/16/13 10:00 1
  • 29. Benchmarking • Multiple fab shop data collection exercises at large CCC industrial construction projects in the Middle East were performed to collect benchmark productivity data for the simulator
  • 30. Benchmarking • Very practical information was collected by observing the different fabrication shop operations: – Actual uninterrupted work productivity timed from start to finish with a total work scope and number of workers involved – Overall actual to-date production data for the fabrication shops broken down by week including total inch-dia and total manpower per week – Daily worker hours breakdown in terms of breaks related to the current heat index, lunch break, toolbox talks, arrival and departure allowances, etc.
  • 31. Case Study: Implementation on Large Gas Plant Construction Project Barzan Onshore Project • Location: Ras Laffan Industrial City – Qatar • Production Capacity: 2 bcfpd (Train 1 + Train 2) • Contract: Barzan Central Contract, Package 1 (Process Area & Building Works) • Client: QP and Exxon Mobil • Main Contractor (EPC): Japan Gas Company (JGC) • Scope: Construction of the process plant area, including piping fabrication and erection, civil works, EPC buildings, steel structure erection, equipment erection, E&I, painting, insulation and common scaffolding Phase # of Joints Inch-Dia # of Spools # of ISO's TRAIN 1 367,572 1,203,882 61,490 17,001 TRAIN 2 337,742 1,181,251 52,349 16,757
  • 32. Case Study: Implementation on Large Gas Plant Construction Project Month Total Inch- Dia Cut Crew Bevel Crew FitUp Crew Weld Crew Autoweld Machines Actual Days Sim Days October 50,798 6 20 30 90 8 28 27 November 61,217 10 20 30 102 8 30 30 December 67,091 15 25 40 118 8 31 29 January 68,220 14 24 38 113 8 31 30 February 70,848 15 25 40 137 8 28 25 March 78,159 15 25 40 156 8 31 24 Detecting Productivity Anomalies • Fabrication activities on site were compared to simulator runs to detect and emphasize productivity anomalies • We can notice a marked decline in February and increase in March
  • 33. Cut Bevel Fitup Weld 0% 48 51 53 54 10% 45 47 50 51 20% 39 41 44 45 30% 37 39 43 43 40% 33 36 38 39 50% 32 34 37 38 60% 31 33 36 38 70% 29 31 33 37 80% 27 30 32 37 90% 25 27 30 37 100% 24 26 29 37 Additional Cut / Bevel / Fitup Resources Fabrication Activities End Day Case Study: Implementation on Large Gas Plant Construction Project Detecting Bottlenecks and Optimizing Resource Mixes
  • 34. Case Study: Implementation on Large Gas Plant Construction Project Activity Sim Start Date Sim End Date Cut 3/2/13 8:00 3/3/13 17:01 Bevel 3/2/13 8:06 3/6/13 9:34 FitUp 3/2/13 8:13 3/9/13 17:06 Welding 3/2/13 8:00 3/30/13 17:18 NDT 3/2/13 19:00 5/16/13 5:00 PWHT 3/1/13 5:00 5/16/13 19:22 Blasting 3/2/13 6:00 5/18/13 14:30 Painting 3/2/13 14:30 5/21/13 16:30 Aea Sim Start Date Sim End Date A110 3/1/13 5:12 3/17/13 10:00 A120 3/1/13 5:00 5/17/13 10:00 A130 3/1/13 5:00 3/22/13 16:00 A140 3/1/13 5:12 3/27/13 12:00 A150 3/1/13 5:00 3/30/13 10:00 A160 3/1/13 5:00 4/6/13 16:30 A170 3/1/13 5:12 5/17/13 10:00 A210 3/1/13 5:12 5/17/13 10:00 A220 3/1/13 5:00 5/17/13 10:00 A230 3/1/13 5:12 5/21/13 16:30 A240 3/27/13 11:27 5/17/13 10:00 A250 3/1/13 5:12 3/29/13 14:00 A260 3/6/13 6:00 5/21/13 16:30 A270 3/1/13 5:12 5/17/13 10:00 Forecasting Activity and Area Start and Completion Dates
  • 35. Future Work • Further development and enhancements to this model include: – A material constraint module (Material Forward Planning) – Full integration with CCC’s C3D construction management software – A pipe installation simulation model covering pipe spool construction activities up to when spools are installed on site and given final release
  • 36. THANK YOU Zuhair Haddad (ZUHAIR@CCC.ME) Ramzi Labban (RLABBAN@CCC.COM.LB)

Hinweis der Redaktion

  1. The ability of computer based modeling and simulation to model resource and activity interactions, queuing, and uncertainties renders it a good fit for modeling the pipe spool fabrication process.
  2. Start date of BOP: Sep 2011, 34 months duration for contractMechanical completion is June 2014 (scheduled)