Duration Types in Primavera P6
Duration Type is a setting which allows the user to control how the duration, resource units, and resource units/time are synchronized for activities, so that
the following equation is always true:

Original, Remaining or Planned Duration = (Budgeted, Remaining or Planned Units) / (Budgeted, Remaining or Planned Units/Time)

If the activity is not started, the names of the values are

: Original Duration x Budgeted Units/Time = Budgeted Units

If the activity has started, the names of the values are

: Remaining Duration x Remaining Units/Time = Remaining Units

The following table lists the value that changes to balance the equation
Duration x Units/Time = Units
The following table illustrates how the variables in the above equation changes when you change one among them in each of the Activity duration types.
Duration Type

Fixed Units/Time
Fixed Duration
and Units/Time
Fixed Units
Fixed Duration
and Units

When You Change
Duration, what
changes?
Units
Units

When you change
units/time,
what changes?
Duration
Units

When you change
units, what
changes?
Duration
Units/Time

When you add a
resource, what
changes?
Duration
Units

Units/Time
Units/Time

Duration
Units

Duration
Units/Time

Duration
Units/Time

Table 1. Activity duration types
The duration type is set at the Project Details level for the Project, but can be modified per activity. Your organization’s project
needs will help to determine which duration type to use. We’ll be discussing in the following section as of what situation forces you to
choose a particular Duration type.
As a hint, if you are adding resources to activities and you do NOT want P6 to recalculate the existing resources units, duration and
units/time, go to Edit, User Preferences from the Menu bar, select the Calculations tab and select the Preserve the Units, Duration and
Units/Time for existing assignments radio button.

Example:Now let us consider a Case and work on it to get a better understanding on the Activity duration types.
Given Case :Consider a software company where a resource is assigned design work of a particular website. It is estimated that the design
work would be completed within 5 working days of the resource. The particular resource has a regular shift duration of 8 hours /day.
Find what happens to values of the Original duration, budgeted units/time and Budgeted units when
i.

Original duration changes to 10 days

ii.

Budgeted units/time changes to 10hours/day

iii.

Budgeted units of work changes to 20 hours

In each of the activity duration types.
Findings:

Original Duration =5 days ,
Budgeted units/time = 8h/d

From the formula we know Budgeted units = Original Duration X Budgeted units/time = 8 x 5 = 40 hours
Type I :-Fixed Units / Time
Units/time for the resources remains fixed; Even when activity duration or budgeted units changes. Used when resources with
productivity output per time period is fixed. Mostly used when Activity type is Resource Dependent. This option is selected if your
organization is concerned with leveling resources and you assign resources specific hours per day on activities.
Original Duration = Budgeted Units / Budgeted Units/Time
Duration Type

When You Change Duration,

When you change units/time,

When you change units, what

what

what changes?

changes?

Duration

Duration

changes?
Fixed Units/Time

Units

Table 1.1.1 Fixes Units / Time
Coming back to our case
Where Original Duration =5 days ; Budgeted units/time = 8h/d And Budgeted units = 40 hours.
i.e. Original Duration = units / (units/time)  5= 40 / 8
We were asked to analyze what would happen if
Changes made

(i) Original Duration Changes

duration

(Units )/
(Units/time)

from 40 to 20

Budgeted

Original

Budgeted

Original

Budgeted

units

units/time

Duration

units

Duration

units/time

80h
=>

from 8 to 10

Budgeted

Original

(iii) Units changes

from 5 to 10 days

Values changed

(ii) Units / time changes

8h/d

4d

40h

2.5d

8h/d

10=> 80/8

4 => 40/10

Table 1.1.2 Fixes Units / Time Workout

2.5 => 20/8
Type II: Fixed Duration & Units/Time
Activity duration and units / time remains fixed; even if remaining unit’s changes. Mostly used when Activity type is Task Dependent
Activity. Organizations which have the project deadline fixed and is also concerned with leveling resources used this activity duration type.
Organization may consider increasing number of resources to keep the resources leveled. Since this activity is Task dependant and activity
duration type is fixed duration & Units/time there would be no layoff in duration time.

Original Duration = Budgeted Units / Budgeted Units/Time
Duration Type

When You Change Duration,

When you change units/time,

When you change units, what

what

what changes?

changes?

Units

Units/Time

changes?
Fixed Duration and

Units

Units/Time
Table 1.2.1 Fixed Duration & Units/Time
Given Original Duration =5 days ; Budgeted units/time = 8h/d And Budgeted units = 40 hours.
Changes made

(i) Original Duration Changes

duration

(Units )/
(Units/time)

from 40 to 20

Budgeted

Original

Budgeted

Original

Budgeted

units

units/time

Duration

units

Duration

units/time

80h
=>

8 to 10

Budgeted

Original

(iii) Units changes

from 5 to 10 days

Values changed

(ii) Units / time changes from

8h/d

5d

50h

5d

4h/d

10=> 80/8

5 => 50/10

Table 1.2.2 Fixed Duration & Units/Time Workout

5 => 20/4*
Type III :-Fixed Units
This duration type is chosen if you want the activity units to be fixed even when duration or resource units per time changes. Total
amount of Work is fixed. Used when Activity type is Resource Dependent Activities. Unlike previous Duration types increasing resources
decreases the activity duration. Generally used when you have resource under contract basis and you have X units of work to get to be done
from that particular resource.
Original Duration = Budgeted Units / Budgeted Units/Time
Duration Type

When You Change Duration,

When you change units/time,

When you change units, what

what

what changes?

changes?

Duration

Duration

changes?
Fixed Units

Units/Time

Table 1.3.1 Fixed Units
Given Original Duration =5 days ; Budgeted units/time = 8h/d And Budgeted units = 40 hours.
Changes made

(i) Original Duration Changes

duration

(Units )/
(Units/time)

from 40 to 20

Budgeted

Original

Budgeted

Original

Budgeted

units

units/time

Duration

units

Duration

units/time

40h
=>

8 to 10

Budgeted

Original

(iii) Units changes

from 5 to 10 days

Values changed

(ii) Units / time changes from

4h/d

4d

40h

2.5d

8h/d

10=> 40/4

4 => 40/4

2.5 => 20/8

Table 1.3.2 Fixed Units Workout

Type IV :-Fixed Duration & Units
Activity duration and Units to remain constant even when the units/time changes. Mostly used when time period and the total
amount of work are fixed. Used when Activity type is Task Dependent Activities. Rate at which a resource can work on the activity can be
changed. You could use this if your organization is more concerned about coming in on the schedule date and within the costs (which are
usually associated with the units)
Original Duration = Budgeted Units / Budgeted Units/Time
Duration Type

When You Change Duration,

When you change units/time,

When you change units, what

what

what changes?

changes?

Units

Units/Time

changes?
Fixed Duration and Units

Units/Time

Table 1.4.1 Fixed Duration & Units
Given Original Duration =5 days ; Budgeted units/time = 8h/d And Budgeted units = 40 hours.
Changes made

(i) Original Duration Changes

duration

(Units )/
(Units/time)

from 40 to 20

Budgeted

Original

Budgeted

Original

Budgeted

units

units/time

Duration

units

Duration

units/time

40h
=>

8 to 10

Budgeted

Original

(iii) Units changes

from 5 to 10 days

Values changed

(ii) Units / time changes from

4h/d

5

50

5d

4h/d

10=> 40/4

5 => 50/5*

Table 1.4.2 Fixed Duration & Units Workout

5 => 20/4
Summary
Given Original Duration 5days; Budgeted Units 40hours; Budgeted Units/ time 8hours/day. The following table summarizes as of what
happens to the variables in each of the activity duration types.
Units / time changes from 8 to 10

Units changes from 40 to 20

Budgeted units

Budgeted

Original Duration

Budgeted units

Original Duration

Budgeted

(Or. Val:- 40h)

Type

Duration

Original Duration Changes from 5 to 10

units/time(Or. Val:-

(Or. Val:- 5d)

(Or. Val:- 40h)

(Or. Val:- 5d)

units/time

8h/d)

Fixed Units / Time

(Or. Val:- 8h/d)

80h

8h/d

4d

40h

2.5d

8h/d

80h

8h/d

5d

50h

5d

4h/d*

Fixed Units

40h

4h/d

4d

40h

2.5d

8h/d

Fixed Duration & Units

40h

4h/d

5d

50h*

5d

4h/d

Fixed Duration &
Units/Time

Table 2: Activity duration table chart
Or.Val - Original Value

* - in certain cases original duration remains fixed and the other fixed variable is forced to changed.

Reference:https://ccsspl123-public.sharepoint.com/Support%20Documents/duration%20types-Activity.pdf
http://www.projectcontrolsonline.com/Forum/tabid/65/forumid/13/threadid/529/scope/posts/Default.aspx

Weitere ähnliche Inhalte

Was ist angesagt?

Pdf primavera tutorial
Pdf primavera tutorialPdf primavera tutorial
Pdf primavera tutorialKetut Swandana
 
Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™Charlie Jackson
 
Delay analysis ... wise after the event.
Delay analysis ... wise after the event.Delay analysis ... wise after the event.
Delay analysis ... wise after the event.Tim Lloyd
 
Delay, dispute (1st annual conf. of planning in cairo 23-8-2014) engr. m maged
Delay, dispute  (1st annual conf. of planning in cairo 23-8-2014) engr. m magedDelay, dispute  (1st annual conf. of planning in cairo 23-8-2014) engr. m maged
Delay, dispute (1st annual conf. of planning in cairo 23-8-2014) engr. m magedM Maged Hegazy, LLM, MBA, CCP, P3O
 
Primavera P6 manual
Primavera P6 manual Primavera P6 manual
Primavera P6 manual Abbas Tahir
 
Understanding Constraints and Relationships in Primavera P6 8.2
Understanding Constraints and Relationships in Primavera P6 8.2Understanding Constraints and Relationships in Primavera P6 8.2
Understanding Constraints and Relationships in Primavera P6 8.2danieljohn810
 
Avoiding unrealistic schedules
Avoiding unrealistic schedulesAvoiding unrealistic schedules
Avoiding unrealistic schedulesHatem Hegazi
 
EOT Related Cost Compensation Determination
EOT Related Cost Compensation DeterminationEOT Related Cost Compensation Determination
EOT Related Cost Compensation DeterminationVimal Daluwatta
 
Clause 14.2 Advance Payment-Understanding Clauses in FIDIC ‘Conditions of Con...
Clause 14.2 Advance Payment-Understanding Clauses in FIDIC ‘Conditions of Con...Clause 14.2 Advance Payment-Understanding Clauses in FIDIC ‘Conditions of Con...
Clause 14.2 Advance Payment-Understanding Clauses in FIDIC ‘Conditions of Con...Divyanshu Dayal
 
Primavera - Tutorial
Primavera - TutorialPrimavera - Tutorial
Primavera - TutorialRajeev Sharma
 
Primavera P6 Tips and Tricks
Primavera P6 Tips and TricksPrimavera P6 Tips and Tricks
Primavera P6 Tips and Tricksp6academy
 
Extension of time Analysis
Extension of time AnalysisExtension of time Analysis
Extension of time AnalysisFarhan Moosa
 

Was ist angesagt? (20)

Pdf primavera tutorial
Pdf primavera tutorialPdf primavera tutorial
Pdf primavera tutorial
 
Primavera p6 advanced project planning
Primavera p6 advanced project planningPrimavera p6 advanced project planning
Primavera p6 advanced project planning
 
tcc primavera
tcc primaveratcc primavera
tcc primavera
 
ppt for primevera
ppt for primeverappt for primevera
ppt for primevera
 
Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™
 
Introduction, development and analysis of banana curve in project management....
Introduction, development and analysis of banana curve in project management....Introduction, development and analysis of banana curve in project management....
Introduction, development and analysis of banana curve in project management....
 
Delay analysis ... wise after the event.
Delay analysis ... wise after the event.Delay analysis ... wise after the event.
Delay analysis ... wise after the event.
 
Delay, dispute (1st annual conf. of planning in cairo 23-8-2014) engr. m maged
Delay, dispute  (1st annual conf. of planning in cairo 23-8-2014) engr. m magedDelay, dispute  (1st annual conf. of planning in cairo 23-8-2014) engr. m maged
Delay, dispute (1st annual conf. of planning in cairo 23-8-2014) engr. m maged
 
Primavera P6 manual
Primavera P6 manual Primavera P6 manual
Primavera P6 manual
 
Understanding Constraints and Relationships in Primavera P6 8.2
Understanding Constraints and Relationships in Primavera P6 8.2Understanding Constraints and Relationships in Primavera P6 8.2
Understanding Constraints and Relationships in Primavera P6 8.2
 
Avoiding unrealistic schedules
Avoiding unrealistic schedulesAvoiding unrealistic schedules
Avoiding unrealistic schedules
 
EOT Related Cost Compensation Determination
EOT Related Cost Compensation DeterminationEOT Related Cost Compensation Determination
EOT Related Cost Compensation Determination
 
S Curves Made Easy With Primavera P6
S Curves Made Easy With Primavera P6S Curves Made Easy With Primavera P6
S Curves Made Easy With Primavera P6
 
Clause 14.2 Advance Payment-Understanding Clauses in FIDIC ‘Conditions of Con...
Clause 14.2 Advance Payment-Understanding Clauses in FIDIC ‘Conditions of Con...Clause 14.2 Advance Payment-Understanding Clauses in FIDIC ‘Conditions of Con...
Clause 14.2 Advance Payment-Understanding Clauses in FIDIC ‘Conditions of Con...
 
Forensic schedule analysis acesss
Forensic schedule analysis acesssForensic schedule analysis acesss
Forensic schedule analysis acesss
 
Loading cost in primavera schedule using resources and expenses r01
Loading cost in primavera schedule using resources and expenses r01Loading cost in primavera schedule using resources and expenses r01
Loading cost in primavera schedule using resources and expenses r01
 
Primavera - Tutorial
Primavera - TutorialPrimavera - Tutorial
Primavera - Tutorial
 
Primavera P6 Tips and Tricks
Primavera P6 Tips and TricksPrimavera P6 Tips and Tricks
Primavera P6 Tips and Tricks
 
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
Extension of Time (EOT) & Related Costs in Construction - Presentation SlidesExtension of Time (EOT) & Related Costs in Construction - Presentation Slides
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
 
Extension of time Analysis
Extension of time AnalysisExtension of time Analysis
Extension of time Analysis
 

Andere mochten auch

Primavera Project Management
Primavera Project ManagementPrimavera Project Management
Primavera Project ManagementTotalSoft
 
Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14
Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14
Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14p6academy
 
P6 Version 7 Tricks and Traps
P6 Version 7 Tricks and TrapsP6 Version 7 Tricks and Traps
P6 Version 7 Tricks and TrapsInSync Conference
 
Activity Types and Relationships in Primavera p6
Activity Types and Relationships in Primavera p6 Activity Types and Relationships in Primavera p6
Activity Types and Relationships in Primavera p6 Nikhil Raj
 
Authentic Global Connections Learning2 Saigon2016
Authentic Global Connections Learning2 Saigon2016 Authentic Global Connections Learning2 Saigon2016
Authentic Global Connections Learning2 Saigon2016 Jason Graham
 
Configuring Primavera Team Member for Project Updates
Configuring Primavera Team Member for Project UpdatesConfiguring Primavera Team Member for Project Updates
Configuring Primavera Team Member for Project Updatesp6academy
 
200850 oracle primavera p6 eppm performance tuning, testing, and monitoring
200850 oracle primavera p6 eppm performance tuning, testing, and monitoring200850 oracle primavera p6 eppm performance tuning, testing, and monitoring
200850 oracle primavera p6 eppm performance tuning, testing, and monitoringp6academy
 
Oracle PPM. What's new in P6release 8.2?
Oracle PPM.  What's new in P6release 8.2?Oracle PPM.  What's new in P6release 8.2?
Oracle PPM. What's new in P6release 8.2?Vladimir Ivanov
 
What's New in Primavera 15.2 Webcast
What's New in Primavera 15.2 WebcastWhat's New in Primavera 15.2 Webcast
What's New in Primavera 15.2 Webcastp6academy
 
Primavera P6 EPPM Portlets Index
Primavera P6 EPPM Portlets IndexPrimavera P6 EPPM Portlets Index
Primavera P6 EPPM Portlets IndexTen Six Consulting
 
Primavera P6 Professional Windows 10 Installation Instructions
Primavera P6 Professional Windows 10 Installation InstructionsPrimavera P6 Professional Windows 10 Installation Instructions
Primavera P6 Professional Windows 10 Installation InstructionsTen Six Consulting
 
Whats new in Primavera P6 EPPM 15.2?
Whats new in Primavera P6 EPPM 15.2?Whats new in Primavera P6 EPPM 15.2?
Whats new in Primavera P6 EPPM 15.2?p6academy
 

Andere mochten auch (15)

Primavera Project Management
Primavera Project ManagementPrimavera Project Management
Primavera Project Management
 
Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14
Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14
Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14
 
P6 Version 7 Tricks and Traps
P6 Version 7 Tricks and TrapsP6 Version 7 Tricks and Traps
P6 Version 7 Tricks and Traps
 
Activity Types and Relationships in Primavera p6
Activity Types and Relationships in Primavera p6 Activity Types and Relationships in Primavera p6
Activity Types and Relationships in Primavera p6
 
Primavera p6 v8.2 session 1
Primavera p6 v8.2 session 1Primavera p6 v8.2 session 1
Primavera p6 v8.2 session 1
 
Authentic Global Connections Learning2 Saigon2016
Authentic Global Connections Learning2 Saigon2016 Authentic Global Connections Learning2 Saigon2016
Authentic Global Connections Learning2 Saigon2016
 
P6 brief
P6 briefP6 brief
P6 brief
 
Configuring Primavera Team Member for Project Updates
Configuring Primavera Team Member for Project UpdatesConfiguring Primavera Team Member for Project Updates
Configuring Primavera Team Member for Project Updates
 
200850 oracle primavera p6 eppm performance tuning, testing, and monitoring
200850 oracle primavera p6 eppm performance tuning, testing, and monitoring200850 oracle primavera p6 eppm performance tuning, testing, and monitoring
200850 oracle primavera p6 eppm performance tuning, testing, and monitoring
 
User preference Option in Oracle Primavera EPPM P6
User preference Option in Oracle Primavera EPPM P6User preference Option in Oracle Primavera EPPM P6
User preference Option in Oracle Primavera EPPM P6
 
Oracle PPM. What's new in P6release 8.2?
Oracle PPM.  What's new in P6release 8.2?Oracle PPM.  What's new in P6release 8.2?
Oracle PPM. What's new in P6release 8.2?
 
What's New in Primavera 15.2 Webcast
What's New in Primavera 15.2 WebcastWhat's New in Primavera 15.2 Webcast
What's New in Primavera 15.2 Webcast
 
Primavera P6 EPPM Portlets Index
Primavera P6 EPPM Portlets IndexPrimavera P6 EPPM Portlets Index
Primavera P6 EPPM Portlets Index
 
Primavera P6 Professional Windows 10 Installation Instructions
Primavera P6 Professional Windows 10 Installation InstructionsPrimavera P6 Professional Windows 10 Installation Instructions
Primavera P6 Professional Windows 10 Installation Instructions
 
Whats new in Primavera P6 EPPM 15.2?
Whats new in Primavera P6 EPPM 15.2?Whats new in Primavera P6 EPPM 15.2?
Whats new in Primavera P6 EPPM 15.2?
 

Ähnlich wie Activity Duration Types Explained with example in Primavera

Understanding How Microsoft Project Thinks
Understanding How Microsoft Project ThinksUnderstanding How Microsoft Project Thinks
Understanding How Microsoft Project Thinksjblack34
 
Duration - The Holy Grail of MS Project?
Duration - The Holy Grail of MS Project?Duration - The Holy Grail of MS Project?
Duration - The Holy Grail of MS Project?dmdk12
 
How to choose the right task type in Microsoft Project?
How to choose the right task type in Microsoft Project?How to choose the right task type in Microsoft Project?
How to choose the right task type in Microsoft Project?SPC Adriatics
 
09 Fine-tuning Assignment Details
09 Fine-tuning Assignment Details09 Fine-tuning Assignment Details
09 Fine-tuning Assignment DetailsSoe Naing Win
 
Lecture 4 - Engineering project Scheduling.pptx
Lecture 4 - Engineering project Scheduling.pptxLecture 4 - Engineering project Scheduling.pptx
Lecture 4 - Engineering project Scheduling.pptxmuhammadbilalzahid4
 
7. work study and method measurement
7. work study and method measurement7. work study and method measurement
7. work study and method measurementAkash Bakshi
 
PREDETERMINED MOTION TIME SYSTEM (PMTS).pptx
PREDETERMINED MOTION TIME SYSTEM (PMTS).pptxPREDETERMINED MOTION TIME SYSTEM (PMTS).pptx
PREDETERMINED MOTION TIME SYSTEM (PMTS).pptxLakshayKumar504432
 
How to use timesheet in orangescrum
How to use timesheet in orangescrumHow to use timesheet in orangescrum
How to use timesheet in orangescrumOrangescrum
 
Methods of Wage Fixation
Methods of Wage FixationMethods of Wage Fixation
Methods of Wage FixationRaja Adapa
 
Microsoft_Project_101_How_to_Build_a_Project_Plan.
Microsoft_Project_101_How_to_Build_a_Project_Plan.Microsoft_Project_101_How_to_Build_a_Project_Plan.
Microsoft_Project_101_How_to_Build_a_Project_Plan.TURKI , PMP
 
Manpower optimization using full time equivalent (FTE)
Manpower optimization using full time equivalent (FTE)Manpower optimization using full time equivalent (FTE)
Manpower optimization using full time equivalent (FTE)Mohammed Matar,PMP
 

Ähnlich wie Activity Duration Types Explained with example in Primavera (20)

Understanding How Microsoft Project Thinks
Understanding How Microsoft Project ThinksUnderstanding How Microsoft Project Thinks
Understanding How Microsoft Project Thinks
 
Duration - The Holy Grail of MS Project?
Duration - The Holy Grail of MS Project?Duration - The Holy Grail of MS Project?
Duration - The Holy Grail of MS Project?
 
Unit 3 problems
Unit 3 problemsUnit 3 problems
Unit 3 problems
 
How to choose the right task type in Microsoft Project?
How to choose the right task type in Microsoft Project?How to choose the right task type in Microsoft Project?
How to choose the right task type in Microsoft Project?
 
09 Fine-tuning Assignment Details
09 Fine-tuning Assignment Details09 Fine-tuning Assignment Details
09 Fine-tuning Assignment Details
 
Lecture 4 - Engineering project Scheduling.pptx
Lecture 4 - Engineering project Scheduling.pptxLecture 4 - Engineering project Scheduling.pptx
Lecture 4 - Engineering project Scheduling.pptx
 
COA B2.pptx
COA B2.pptxCOA B2.pptx
COA B2.pptx
 
7. work study and method measurement
7. work study and method measurement7. work study and method measurement
7. work study and method measurement
 
Good work measurement
Good work measurementGood work measurement
Good work measurement
 
Work Measurement
Work MeasurementWork Measurement
Work Measurement
 
PREDETERMINED MOTION TIME SYSTEM (PMTS).pptx
PREDETERMINED MOTION TIME SYSTEM (PMTS).pptxPREDETERMINED MOTION TIME SYSTEM (PMTS).pptx
PREDETERMINED MOTION TIME SYSTEM (PMTS).pptx
 
How to use timesheet in orangescrum
How to use timesheet in orangescrumHow to use timesheet in orangescrum
How to use timesheet in orangescrum
 
Process Costing
Process CostingProcess Costing
Process Costing
 
4th-IE-BSS.pptx.pptx
4th-IE-BSS.pptx.pptx4th-IE-BSS.pptx.pptx
4th-IE-BSS.pptx.pptx
 
Ms Project
Ms ProjectMs Project
Ms Project
 
Methods of Wage Fixation
Methods of Wage FixationMethods of Wage Fixation
Methods of Wage Fixation
 
cumulative and flyback timing.pdf
cumulative and flyback timing.pdfcumulative and flyback timing.pdf
cumulative and flyback timing.pdf
 
Cumulative and flyback timing
Cumulative and flyback timingCumulative and flyback timing
Cumulative and flyback timing
 
Microsoft_Project_101_How_to_Build_a_Project_Plan.
Microsoft_Project_101_How_to_Build_a_Project_Plan.Microsoft_Project_101_How_to_Build_a_Project_Plan.
Microsoft_Project_101_How_to_Build_a_Project_Plan.
 
Manpower optimization using full time equivalent (FTE)
Manpower optimization using full time equivalent (FTE)Manpower optimization using full time equivalent (FTE)
Manpower optimization using full time equivalent (FTE)
 

Mehr von CADD Centre Software Solutions Private Limited

Mehr von CADD Centre Software Solutions Private Limited (20)

Primavera manual
Primavera manual Primavera manual
Primavera manual
 
A b-c-d-(e) of ccsspl corporate presentation
A b-c-d-(e) of ccsspl corporate presentationA b-c-d-(e) of ccsspl corporate presentation
A b-c-d-(e) of ccsspl corporate presentation
 
Login methodology for Primavera V8.3 (EPPM)
Login methodology for Primavera V8.3 (EPPM)Login methodology for Primavera V8.3 (EPPM)
Login methodology for Primavera V8.3 (EPPM)
 
Oracle Primavera Team member 8.3
Oracle Primavera Team member 8.3Oracle Primavera Team member 8.3
Oracle Primavera Team member 8.3
 
Oracle Primavera contractor
Oracle Primavera  contractorOracle Primavera  contractor
Oracle Primavera contractor
 
Recurring task IN MS project
Recurring task IN MS project Recurring task IN MS project
Recurring task IN MS project
 
CPCL Case study
CPCL Case studyCPCL Case study
CPCL Case study
 
Oracle Primavera contract management
Oracle Primavera  contract managementOracle Primavera  contract management
Oracle Primavera contract management
 
Uses of Project Status field
Uses of  Project Status field Uses of  Project Status field
Uses of Project Status field
 
Oracle primavera Universal content management
Oracle primavera Universal content management Oracle primavera Universal content management
Oracle primavera Universal content management
 
Pert master risk analysis tool
Pert master   risk analysis toolPert master   risk analysis tool
Pert master risk analysis tool
 
Oracle Primavera P6 PRO R8 Tips & tricks
Oracle Primavera P6 PRO R8 Tips & tricksOracle Primavera P6 PRO R8 Tips & tricks
Oracle Primavera P6 PRO R8 Tips & tricks
 
Team member in iphones and android
Team member in iphones and androidTeam member in iphones and android
Team member in iphones and android
 
Primavera portlets
Primavera portletsPrimavera portlets
Primavera portlets
 
Tested configuration for different Primavera versions
Tested configuration for different Primavera versionsTested configuration for different Primavera versions
Tested configuration for different Primavera versions
 
Difference between versions of primavera 6,7,R8.1,R8.2,R8.3
Difference between versions of primavera 6,7,R8.1,R8.2,R8.3Difference between versions of primavera 6,7,R8.1,R8.2,R8.3
Difference between versions of primavera 6,7,R8.1,R8.2,R8.3
 
Features comparison between Primavera and Microsoft Project
Features comparison between Primavera and Microsoft ProjectFeatures comparison between Primavera and Microsoft Project
Features comparison between Primavera and Microsoft Project
 
Project management software consulting
Project management software consultingProject management software consulting
Project management software consulting
 
Oracle Autovue
Oracle AutovueOracle Autovue
Oracle Autovue
 
Primavera vs microsoft project
Primavera vs microsoft projectPrimavera vs microsoft project
Primavera vs microsoft project
 

Kürzlich hochgeladen

Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service AvailableCall Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service AvailableSeo
 
Call Girls From Raj Nagar Extension Ghaziabad❤️8448577510 ⊹Best Escorts Servi...
Call Girls From Raj Nagar Extension Ghaziabad❤️8448577510 ⊹Best Escorts Servi...Call Girls From Raj Nagar Extension Ghaziabad❤️8448577510 ⊹Best Escorts Servi...
Call Girls From Raj Nagar Extension Ghaziabad❤️8448577510 ⊹Best Escorts Servi...lizamodels9
 
Whitefield CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
Whitefield CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRLWhitefield CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
Whitefield CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRLkapoorjyoti4444
 
Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st CenturyFamous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Centuryrwgiffor
 
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...allensay1
 
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...lizamodels9
 
Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxWorkforce Group
 
Business Model Canvas (BMC)- A new venture concept
Business Model Canvas (BMC)-  A new venture conceptBusiness Model Canvas (BMC)-  A new venture concept
Business Model Canvas (BMC)- A new venture conceptP&CO
 
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service BangaloreCall Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangaloreamitlee9823
 
Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...
Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...
Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...Sheetaleventcompany
 
Eluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort Service
Eluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort ServiceEluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort Service
Eluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort ServiceDamini Dixit
 
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRLBAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRLkapoorjyoti4444
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756dollysharma2066
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...amitlee9823
 
Falcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investorsFalcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investorsFalcon Invoice Discounting
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsP&CO
 
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...Sheetaleventcompany
 
Malegaon Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort Service
Malegaon Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort ServiceMalegaon Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort Service
Malegaon Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort ServiceDamini Dixit
 

Kürzlich hochgeladen (20)

Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service AvailableCall Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
 
Call Girls From Raj Nagar Extension Ghaziabad❤️8448577510 ⊹Best Escorts Servi...
Call Girls From Raj Nagar Extension Ghaziabad❤️8448577510 ⊹Best Escorts Servi...Call Girls From Raj Nagar Extension Ghaziabad❤️8448577510 ⊹Best Escorts Servi...
Call Girls From Raj Nagar Extension Ghaziabad❤️8448577510 ⊹Best Escorts Servi...
 
Whitefield CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
Whitefield CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRLWhitefield CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
Whitefield CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
 
Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st CenturyFamous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Century
 
Falcon Invoice Discounting platform in india
Falcon Invoice Discounting platform in indiaFalcon Invoice Discounting platform in india
Falcon Invoice Discounting platform in india
 
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
 
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
 
Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptx
 
Business Model Canvas (BMC)- A new venture concept
Business Model Canvas (BMC)-  A new venture conceptBusiness Model Canvas (BMC)-  A new venture concept
Business Model Canvas (BMC)- A new venture concept
 
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabiunwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
 
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service BangaloreCall Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
 
Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...
Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...
Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...
 
Eluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort Service
Eluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort ServiceEluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort Service
Eluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort Service
 
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRLBAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
 
Falcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investorsFalcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investors
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and pains
 
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
 
Malegaon Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort Service
Malegaon Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort ServiceMalegaon Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort Service
Malegaon Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort Service
 

Activity Duration Types Explained with example in Primavera

  • 1. Duration Types in Primavera P6 Duration Type is a setting which allows the user to control how the duration, resource units, and resource units/time are synchronized for activities, so that the following equation is always true: Original, Remaining or Planned Duration = (Budgeted, Remaining or Planned Units) / (Budgeted, Remaining or Planned Units/Time) If the activity is not started, the names of the values are : Original Duration x Budgeted Units/Time = Budgeted Units If the activity has started, the names of the values are : Remaining Duration x Remaining Units/Time = Remaining Units The following table lists the value that changes to balance the equation Duration x Units/Time = Units The following table illustrates how the variables in the above equation changes when you change one among them in each of the Activity duration types. Duration Type Fixed Units/Time Fixed Duration and Units/Time Fixed Units Fixed Duration and Units When You Change Duration, what changes? Units Units When you change units/time, what changes? Duration Units When you change units, what changes? Duration Units/Time When you add a resource, what changes? Duration Units Units/Time Units/Time Duration Units Duration Units/Time Duration Units/Time Table 1. Activity duration types
  • 2. The duration type is set at the Project Details level for the Project, but can be modified per activity. Your organization’s project needs will help to determine which duration type to use. We’ll be discussing in the following section as of what situation forces you to choose a particular Duration type. As a hint, if you are adding resources to activities and you do NOT want P6 to recalculate the existing resources units, duration and units/time, go to Edit, User Preferences from the Menu bar, select the Calculations tab and select the Preserve the Units, Duration and Units/Time for existing assignments radio button. Example:Now let us consider a Case and work on it to get a better understanding on the Activity duration types. Given Case :Consider a software company where a resource is assigned design work of a particular website. It is estimated that the design work would be completed within 5 working days of the resource. The particular resource has a regular shift duration of 8 hours /day. Find what happens to values of the Original duration, budgeted units/time and Budgeted units when i. Original duration changes to 10 days ii. Budgeted units/time changes to 10hours/day iii. Budgeted units of work changes to 20 hours In each of the activity duration types.
  • 3. Findings: Original Duration =5 days , Budgeted units/time = 8h/d From the formula we know Budgeted units = Original Duration X Budgeted units/time = 8 x 5 = 40 hours Type I :-Fixed Units / Time Units/time for the resources remains fixed; Even when activity duration or budgeted units changes. Used when resources with productivity output per time period is fixed. Mostly used when Activity type is Resource Dependent. This option is selected if your organization is concerned with leveling resources and you assign resources specific hours per day on activities. Original Duration = Budgeted Units / Budgeted Units/Time Duration Type When You Change Duration, When you change units/time, When you change units, what what what changes? changes? Duration Duration changes? Fixed Units/Time Units Table 1.1.1 Fixes Units / Time
  • 4. Coming back to our case Where Original Duration =5 days ; Budgeted units/time = 8h/d And Budgeted units = 40 hours. i.e. Original Duration = units / (units/time)  5= 40 / 8 We were asked to analyze what would happen if Changes made (i) Original Duration Changes duration (Units )/ (Units/time) from 40 to 20 Budgeted Original Budgeted Original Budgeted units units/time Duration units Duration units/time 80h => from 8 to 10 Budgeted Original (iii) Units changes from 5 to 10 days Values changed (ii) Units / time changes 8h/d 4d 40h 2.5d 8h/d 10=> 80/8 4 => 40/10 Table 1.1.2 Fixes Units / Time Workout 2.5 => 20/8
  • 5. Type II: Fixed Duration & Units/Time Activity duration and units / time remains fixed; even if remaining unit’s changes. Mostly used when Activity type is Task Dependent Activity. Organizations which have the project deadline fixed and is also concerned with leveling resources used this activity duration type. Organization may consider increasing number of resources to keep the resources leveled. Since this activity is Task dependant and activity duration type is fixed duration & Units/time there would be no layoff in duration time. Original Duration = Budgeted Units / Budgeted Units/Time Duration Type When You Change Duration, When you change units/time, When you change units, what what what changes? changes? Units Units/Time changes? Fixed Duration and Units Units/Time Table 1.2.1 Fixed Duration & Units/Time
  • 6. Given Original Duration =5 days ; Budgeted units/time = 8h/d And Budgeted units = 40 hours. Changes made (i) Original Duration Changes duration (Units )/ (Units/time) from 40 to 20 Budgeted Original Budgeted Original Budgeted units units/time Duration units Duration units/time 80h => 8 to 10 Budgeted Original (iii) Units changes from 5 to 10 days Values changed (ii) Units / time changes from 8h/d 5d 50h 5d 4h/d 10=> 80/8 5 => 50/10 Table 1.2.2 Fixed Duration & Units/Time Workout 5 => 20/4*
  • 7. Type III :-Fixed Units This duration type is chosen if you want the activity units to be fixed even when duration or resource units per time changes. Total amount of Work is fixed. Used when Activity type is Resource Dependent Activities. Unlike previous Duration types increasing resources decreases the activity duration. Generally used when you have resource under contract basis and you have X units of work to get to be done from that particular resource. Original Duration = Budgeted Units / Budgeted Units/Time Duration Type When You Change Duration, When you change units/time, When you change units, what what what changes? changes? Duration Duration changes? Fixed Units Units/Time Table 1.3.1 Fixed Units
  • 8. Given Original Duration =5 days ; Budgeted units/time = 8h/d And Budgeted units = 40 hours. Changes made (i) Original Duration Changes duration (Units )/ (Units/time) from 40 to 20 Budgeted Original Budgeted Original Budgeted units units/time Duration units Duration units/time 40h => 8 to 10 Budgeted Original (iii) Units changes from 5 to 10 days Values changed (ii) Units / time changes from 4h/d 4d 40h 2.5d 8h/d 10=> 40/4 4 => 40/4 2.5 => 20/8 Table 1.3.2 Fixed Units Workout Type IV :-Fixed Duration & Units Activity duration and Units to remain constant even when the units/time changes. Mostly used when time period and the total amount of work are fixed. Used when Activity type is Task Dependent Activities. Rate at which a resource can work on the activity can be changed. You could use this if your organization is more concerned about coming in on the schedule date and within the costs (which are usually associated with the units) Original Duration = Budgeted Units / Budgeted Units/Time
  • 9. Duration Type When You Change Duration, When you change units/time, When you change units, what what what changes? changes? Units Units/Time changes? Fixed Duration and Units Units/Time Table 1.4.1 Fixed Duration & Units Given Original Duration =5 days ; Budgeted units/time = 8h/d And Budgeted units = 40 hours. Changes made (i) Original Duration Changes duration (Units )/ (Units/time) from 40 to 20 Budgeted Original Budgeted Original Budgeted units units/time Duration units Duration units/time 40h => 8 to 10 Budgeted Original (iii) Units changes from 5 to 10 days Values changed (ii) Units / time changes from 4h/d 5 50 5d 4h/d 10=> 40/4 5 => 50/5* Table 1.4.2 Fixed Duration & Units Workout 5 => 20/4
  • 10. Summary Given Original Duration 5days; Budgeted Units 40hours; Budgeted Units/ time 8hours/day. The following table summarizes as of what happens to the variables in each of the activity duration types. Units / time changes from 8 to 10 Units changes from 40 to 20 Budgeted units Budgeted Original Duration Budgeted units Original Duration Budgeted (Or. Val:- 40h) Type Duration Original Duration Changes from 5 to 10 units/time(Or. Val:- (Or. Val:- 5d) (Or. Val:- 40h) (Or. Val:- 5d) units/time 8h/d) Fixed Units / Time (Or. Val:- 8h/d) 80h 8h/d 4d 40h 2.5d 8h/d 80h 8h/d 5d 50h 5d 4h/d* Fixed Units 40h 4h/d 4d 40h 2.5d 8h/d Fixed Duration & Units 40h 4h/d 5d 50h* 5d 4h/d Fixed Duration & Units/Time Table 2: Activity duration table chart Or.Val - Original Value * - in certain cases original duration remains fixed and the other fixed variable is forced to changed. Reference:https://ccsspl123-public.sharepoint.com/Support%20Documents/duration%20types-Activity.pdf http://www.projectcontrolsonline.com/Forum/tabid/65/forumid/13/threadid/529/scope/posts/Default.aspx