SlideShare ist ein Scribd-Unternehmen logo
1 von 41
Connecticut River Crossing 2013
Hadley/Hatfield, MA

David M. Grande
Director – Gas Engineering & System Operations
Berkshire Gas Company
115 Cheshire Road
Pittsfield, MA 01202-1388
Phone 413-445-0265
dgrande@berkshiregas.com

Paul Scarpa
Senior Engineer
Berkshire Gas Company
115 Cheshire Road
Pittsfield, MA 01202-1388
Phone 413-445-0383
pscarpa@berkshiregas.com

Confidential – Not for internal distribution or public release.

1
Berkshire Gas Company – Located in Western Massachusetts

Connecticut River

12/19/13

22
Company Information
• 38,000 Customers
• 1,500 Miles – Mains & Services
• 1 Satellite LNG Plant
• 3 Propane Air Plants
• 120 Employees
• 160 Years Old
• 6 City Gate Stations

12/19/13

33
Project Context – Connecticut River Crossing
•

Installation of approximately 2,250 linear feet of 12-inch coated steel gas
main. The project commences on Bridge Lane in Hatfield, MA and continues
beneath the Connecticut River, terminating on Huntington Rd. in Hadley, MA.
Approximately 1,600 linear feet of the proposed gas main shall be installed
beneath the Connecticut River via directional drilling. The remaining 650
linear shall be installed within an open trench.

•

Project is being done to provide additional firm volumes to Amherst College
and provide additional system reliability for the Hadley/Amherst area.

•

New main will run in parallel with existing 6-inch coated steel main which was
installed in 1959 when the Company brought Natural Gas service to the
Hadley/Amherst area.

12/19/13

44
UMASS & Amherst College – Amherst MA

UMASS – Central Heating Plant

Amherst College – Central Heating Plant

12/19/13

55
Confidential – Not for internal distribution or public release.

6
Project Mile Stones
•

Engineering for Project began in November 2012
• The following was performed:
•
•
•
•
•

•

Survey – current easement (Hadley) town ROW (Hatfield)
Test Borings – both sides of the river
Preliminary Design Plans- used to submit wetland filings
Wetland Delineation
Notice of Intent
• Wetland Notice of Intent submission to the Hadley and Hatfield Conservation
Commissions and Mass DEP
• Filing Notice of Intent with the Natural Heritage and Endanger Species Program
(NHESP)
Army Corps of Engineers (ACOE) Category 2 Permit filing
•

Frac Out Plan

Final Design Plans and Details
• Final Permit Approval Received in September 2013
•

12/19/13

77
Project Milestones
•

Request for Proposal (RFP) was issued on 8/19/2013
•

•
•

12/19/13

Bidders
• Hemlock Directional Boring Inc.
• C.B. Utility Co., Inc.
• JS Rae Construction
• Directional Technologies, Inc.
• Mears Group Inc.

RFP’s were due on 9/3/2013
Project Awarded to JS Rae on 9/9/2013

88
Horizontal Directional Drilling (HDD)

12/19/13

99
HDD Steps

 Pilot Hole

 Reaming

 Pull Back

12/19/13

10
10
Current Conditions

Milestone Schedule
Hadley
Existing 6” Coated Steel Main - 1959

Hatfield

12/19/13

11
11
Current Conditions – Hatfield Side

Milestone Schedule

Hatfield – Westside – River Approx. 900 ft. wide

12/19/13

12
12
Current Conditions – Hadley Side

Milestone Schedule

Hadley – Eastside

12/19/13

13
13
Connecticut River Crossing

Milestone Schedule

– Hadley Side

Existing 6” Coated Steel Main

Company has existing 25ft. Permanent and working easement

12/19/13

14
14
Connecticut River Crossing

Milestone Schedule

- Hadley Side

Environmental Protection Installed

12/19/13

15
15
Connecticut River Crossing – Hadley Side

Milestone Schedule

Swamp Mats were required on the Hadley Side

12/19/13

16
16
Connecticut River Crossing – Hatfield Side

Milestone Schedule

1,680 ft. – 12” Coated Steel – Induron Warrior 100 Coating – Designed for HDD
Remaining 12” Coated Steel – Pritec 40 Mil Coating

12/19/13

17
17
Connecticut River Crossing – Hatfield Side

Milestone Schedule

Preformed 100% X-Ray of Pipe Welds

12/19/13

18
18
Connecticut River Crossing – Hatfield Side

Milestone Schedule

12/19/13

19
19
Connecticut River Crossing – Corrosion Control

Milestone Schedule

Warrior 100 Pipe Coating & Rubber Pipe Rollers

12/19/13

20
20
Connecticut River Crossing – Corrosion Control

Milestone Schedule

Powercrete R-95 Epoxy Based Coating Used for Welds – Designed for HDD

12/19/13

21
21
Connecticut River Crossing – Initial Pressure Test

Milestone Schedule

Final Pressure Test – 300 Psig – 4 Hours - Deadweight

12/19/13

22
22
Connecticut River Crossing - Drilling

Milestone Schedule

During the pilot hole drilling, a directional guidance system is used to
navigate the pilot hole along its pre-designed profile.

Down Hole System – Wire Line

12/19/13

23
23
Connecticut River Crossing - Drilling

Milestone Schedule

12/19/13

24
24
Construction - Drilling

Milestone Schedule

12/19/13

25
25
Connecticut River Crossing - Drilling

Milestone Schedule

Shallow Water Depths

12/19/13

26
26
Construction - Drilling Pilot Hole

Milestone Schedule – 120ft. 30” & 130ft. 12”
Conductor barrel were used

•
•

Used to minimize the potential of a drilling frac out and/or ground collapse near the entry location.
The conductor barrel created a clear pathway through the soft soil conditions so that drilling could begin in more preferable geology

12/19/13

27
27
Construction – Drilling Pilot Hole

Milestone Schedule

12/19/13

28
28
Construction – Drilling Pilot Hole

Milestone Schedule

Final Pilot Hole Maximum Depth was 60 ft. Below Existing River Bed,

12/19/13

29
29
Construction - Reaming

Milestone Schedule

22” ream & 18” ream were used.
The 22” ream was used to go through the bedrock

12/19/13

30
30
Construction - Reaming

Milestone Schedule

Reaming consisted of pushing from the drill rig in Hadley and pulling with excavator in Hatfield.

12/19/13

31
31
Construction - Reaming

Milestone Schedule

12/19/13

32
32
Construction - Reaming

Milestone Schedule

12/19/13

33
33
Construction - Reaming

Milestone Schedule

12/19/13

34
34
Construction – Pull Back

Milestone Schedule

Pull back began at approx. 12:30 PM on 11/20/2013 and took 5 Hrs. to complete.

12/19/13

35
35
Construction – Pull Back

Milestone Schedule

12/19/13

36
36
Construction – Pull Back Hatfield Side

Milestone Schedule

12/19/13

37
37
Construction – Pull Back Hadley Side

Milestone Schedule

12/19/13

38
38
Construction – Testing & Tie-In

Milestone Schedule

12/19/13

39
39
Construction – Testing & Tie -In

Milestone Schedule

12/19/13

40
40
Questions

David M. Grande
Director – Gas Engineering & System Operations
Berkshire Gas Company
115 Cheshire Road
Pittsfield, MA 01202-1388
Phone 413-445-0265
dgrande@berkshiregas.com

12/19/13

41
41

Weitere ähnliche Inhalte

Was ist angesagt?

Scott Smith-complete-employment-history
Scott Smith-complete-employment-historyScott Smith-complete-employment-history
Scott Smith-complete-employment-historyScott Smith
 
Jan. 27: Waste Management Daily Report
Jan. 27: Waste Management Daily ReportJan. 27: Waste Management Daily Report
Jan. 27: Waste Management Daily ReportHonolulu Civil Beat
 
2006 AEG Godwin presentation
2006 AEG Godwin presentation2006 AEG Godwin presentation
2006 AEG Godwin presentationWilliam Godwin
 
Oil and Gas Undergrond Storage Keystone Project.
Oil and Gas Undergrond Storage Keystone Project.Oil and Gas Undergrond Storage Keystone Project.
Oil and Gas Undergrond Storage Keystone Project.Jeffrey Pickett
 
2016 FMA-presentation-Collaborateve FRR Projects (REV8)
2016 FMA-presentation-Collaborateve FRR Projects (REV8)2016 FMA-presentation-Collaborateve FRR Projects (REV8)
2016 FMA-presentation-Collaborateve FRR Projects (REV8)Jason Brabec, PE, CFM
 
Natural Gas an Inside Propective 2-19-14
Natural Gas an Inside Propective 2-19-14Natural Gas an Inside Propective 2-19-14
Natural Gas an Inside Propective 2-19-14James M. Bright, P.E.
 
RV Thuwal - Refit project overview by Maritime Survey Australia
RV Thuwal - Refit project overview by Maritime Survey AustraliaRV Thuwal - Refit project overview by Maritime Survey Australia
RV Thuwal - Refit project overview by Maritime Survey AustraliaMichaelUberti
 
Accelerated Delivery - NDOT Design-Build Project
Accelerated Delivery - NDOT Design-Build ProjectAccelerated Delivery - NDOT Design-Build Project
Accelerated Delivery - NDOT Design-Build ProjectJill Reeves
 
Oil and Gas Undergrond Storage Keystone Project.
Oil and Gas Undergrond Storage Keystone Project.Oil and Gas Undergrond Storage Keystone Project.
Oil and Gas Undergrond Storage Keystone Project.Jeffrey Pickett
 
48. ss-esmmp-for-foundationerection-and-stringing-work-may-2015
48. ss-esmmp-for-foundationerection-and-stringing-work-may-201548. ss-esmmp-for-foundationerection-and-stringing-work-may-2015
48. ss-esmmp-for-foundationerection-and-stringing-work-may-2015Sandeep Bhowmick
 
Vol.9 appendices to environmental impact assessment and resettlement aspects
Vol.9  appendices to environmental impact assessment and resettlement aspectsVol.9  appendices to environmental impact assessment and resettlement aspects
Vol.9 appendices to environmental impact assessment and resettlement aspectszubeditufail
 
Office of River Protection Manager Scott Samuelson’s tank waste cleanup updat...
Office of River Protection Manager Scott Samuelson’s tank waste cleanup updat...Office of River Protection Manager Scott Samuelson’s tank waste cleanup updat...
Office of River Protection Manager Scott Samuelson’s tank waste cleanup updat...DOE Office of River Protection
 
E J Piekenbrock Resume 5-2014 Revised
E  J  Piekenbrock Resume 5-2014 RevisedE  J  Piekenbrock Resume 5-2014 Revised
E J Piekenbrock Resume 5-2014 RevisedEugene Piekenbrock
 
Stormwater and Wastewater Consolidation
Stormwater and Wastewater Consolidation Stormwater and Wastewater Consolidation
Stormwater and Wastewater Consolidation Fairfax County
 
Power Point BLCC End of year Review
Power Point BLCC End of year ReviewPower Point BLCC End of year Review
Power Point BLCC End of year ReviewTom Atkinson
 
Partial Repowering of Wind Turbines: technical risks, opportunities and trends
Partial Repowering of Wind Turbines: technical risks, opportunities and trendsPartial Repowering of Wind Turbines: technical risks, opportunities and trends
Partial Repowering of Wind Turbines: technical risks, opportunities and trendsAlex Byrne
 
3.3 everglades restoration plans
3.3 everglades restoration plans3.3 everglades restoration plans
3.3 everglades restoration plansascemiami-dade
 
Public Facilities Manual Flexibility Project : Update to the Development Proc...
Public Facilities Manual Flexibility Project : Update to the Development Proc...Public Facilities Manual Flexibility Project : Update to the Development Proc...
Public Facilities Manual Flexibility Project : Update to the Development Proc...Fairfax County
 

Was ist angesagt? (20)

Scott Smith-complete-employment-history
Scott Smith-complete-employment-historyScott Smith-complete-employment-history
Scott Smith-complete-employment-history
 
Jan. 27: Waste Management Daily Report
Jan. 27: Waste Management Daily ReportJan. 27: Waste Management Daily Report
Jan. 27: Waste Management Daily Report
 
2006 AEG Godwin presentation
2006 AEG Godwin presentation2006 AEG Godwin presentation
2006 AEG Godwin presentation
 
Oil and Gas Undergrond Storage Keystone Project.
Oil and Gas Undergrond Storage Keystone Project.Oil and Gas Undergrond Storage Keystone Project.
Oil and Gas Undergrond Storage Keystone Project.
 
2016 FMA-presentation-Collaborateve FRR Projects (REV8)
2016 FMA-presentation-Collaborateve FRR Projects (REV8)2016 FMA-presentation-Collaborateve FRR Projects (REV8)
2016 FMA-presentation-Collaborateve FRR Projects (REV8)
 
Natural Gas an Inside Propective 2-19-14
Natural Gas an Inside Propective 2-19-14Natural Gas an Inside Propective 2-19-14
Natural Gas an Inside Propective 2-19-14
 
RV Thuwal - Refit project overview by Maritime Survey Australia
RV Thuwal - Refit project overview by Maritime Survey AustraliaRV Thuwal - Refit project overview by Maritime Survey Australia
RV Thuwal - Refit project overview by Maritime Survey Australia
 
Accelerated Delivery - NDOT Design-Build Project
Accelerated Delivery - NDOT Design-Build ProjectAccelerated Delivery - NDOT Design-Build Project
Accelerated Delivery - NDOT Design-Build Project
 
Oil and Gas Undergrond Storage Keystone Project.
Oil and Gas Undergrond Storage Keystone Project.Oil and Gas Undergrond Storage Keystone Project.
Oil and Gas Undergrond Storage Keystone Project.
 
48. ss-esmmp-for-foundationerection-and-stringing-work-may-2015
48. ss-esmmp-for-foundationerection-and-stringing-work-may-201548. ss-esmmp-for-foundationerection-and-stringing-work-may-2015
48. ss-esmmp-for-foundationerection-and-stringing-work-may-2015
 
Vol.9 appendices to environmental impact assessment and resettlement aspects
Vol.9  appendices to environmental impact assessment and resettlement aspectsVol.9  appendices to environmental impact assessment and resettlement aspects
Vol.9 appendices to environmental impact assessment and resettlement aspects
 
Office of River Protection Manager Scott Samuelson’s tank waste cleanup updat...
Office of River Protection Manager Scott Samuelson’s tank waste cleanup updat...Office of River Protection Manager Scott Samuelson’s tank waste cleanup updat...
Office of River Protection Manager Scott Samuelson’s tank waste cleanup updat...
 
E J Piekenbrock Resume 5-2014 Revised
E  J  Piekenbrock Resume 5-2014 RevisedE  J  Piekenbrock Resume 5-2014 Revised
E J Piekenbrock Resume 5-2014 Revised
 
Resume pe civil
Resume pe civilResume pe civil
Resume pe civil
 
Stormwater and Wastewater Consolidation
Stormwater and Wastewater Consolidation Stormwater and Wastewater Consolidation
Stormwater and Wastewater Consolidation
 
Power Point BLCC End of year Review
Power Point BLCC End of year ReviewPower Point BLCC End of year Review
Power Point BLCC End of year Review
 
Partial Repowering of Wind Turbines: technical risks, opportunities and trends
Partial Repowering of Wind Turbines: technical risks, opportunities and trendsPartial Repowering of Wind Turbines: technical risks, opportunities and trends
Partial Repowering of Wind Turbines: technical risks, opportunities and trends
 
BAZYAN CCPP – Phase 1
BAZYAN CCPP – Phase 1BAZYAN CCPP – Phase 1
BAZYAN CCPP – Phase 1
 
3.3 everglades restoration plans
3.3 everglades restoration plans3.3 everglades restoration plans
3.3 everglades restoration plans
 
Public Facilities Manual Flexibility Project : Update to the Development Proc...
Public Facilities Manual Flexibility Project : Update to the Development Proc...Public Facilities Manual Flexibility Project : Update to the Development Proc...
Public Facilities Manual Flexibility Project : Update to the Development Proc...
 

Andere mochten auch

REDES SOCIALES
REDES SOCIALESREDES SOCIALES
REDES SOCIALESmeryetc
 
Surat edaran ralat uas 2015 2016
Surat edaran ralat uas 2015 2016Surat edaran ralat uas 2015 2016
Surat edaran ralat uas 2015 2016fitryalba99
 
Power point aplicacion interactiva
Power point aplicacion interactivaPower point aplicacion interactiva
Power point aplicacion interactivasieteochonueve
 
Non-Surgical Mid-Facial Expansion with Micro-Implant Assisted Maxillary Skele...
Non-Surgical Mid-Facial Expansion with Micro-Implant Assisted Maxillary Skele...Non-Surgical Mid-Facial Expansion with Micro-Implant Assisted Maxillary Skele...
Non-Surgical Mid-Facial Expansion with Micro-Implant Assisted Maxillary Skele...CHAULONG NGUYEN
 
Estado del arte de la carrera de informática
Estado del arte de la carrera de informáticaEstado del arte de la carrera de informática
Estado del arte de la carrera de informáticaCaleb Flores
 
élaborer un questionnaire
élaborer un questionnaireélaborer un questionnaire
élaborer un questionnaireDrag'n Survey
 

Andere mochten auch (13)

REDES SOCIALES
REDES SOCIALESREDES SOCIALES
REDES SOCIALES
 
Surat edaran ralat uas 2015 2016
Surat edaran ralat uas 2015 2016Surat edaran ralat uas 2015 2016
Surat edaran ralat uas 2015 2016
 
Word 2010 bordes y sombreado
Word 2010 bordes y sombreadoWord 2010 bordes y sombreado
Word 2010 bordes y sombreado
 
Power point aplicacion interactiva
Power point aplicacion interactivaPower point aplicacion interactiva
Power point aplicacion interactiva
 
Alguem 1
Alguem 1Alguem 1
Alguem 1
 
Tarea 1
Tarea 1Tarea 1
Tarea 1
 
Bachelors Degree Certificate
Bachelors Degree CertificateBachelors Degree Certificate
Bachelors Degree Certificate
 
Selection
SelectionSelection
Selection
 
Non-Surgical Mid-Facial Expansion with Micro-Implant Assisted Maxillary Skele...
Non-Surgical Mid-Facial Expansion with Micro-Implant Assisted Maxillary Skele...Non-Surgical Mid-Facial Expansion with Micro-Implant Assisted Maxillary Skele...
Non-Surgical Mid-Facial Expansion with Micro-Implant Assisted Maxillary Skele...
 
Estado del arte de la carrera de informática
Estado del arte de la carrera de informáticaEstado del arte de la carrera de informática
Estado del arte de la carrera de informática
 
M.i.s I.T infrastructure
M.i.s I.T infrastructure M.i.s I.T infrastructure
M.i.s I.T infrastructure
 
CRM Trends
CRM TrendsCRM Trends
CRM Trends
 
élaborer un questionnaire
élaborer un questionnaireélaborer un questionnaire
élaborer un questionnaire
 

Ähnlich wie Negdc presentation december 2013

Hayfield Road Project Citizens Association Meeting Oct. 18, 2017
Hayfield Road Project Citizens Association Meeting Oct. 18, 2017Hayfield Road Project Citizens Association Meeting Oct. 18, 2017
Hayfield Road Project Citizens Association Meeting Oct. 18, 2017Fairfax County
 
Hayfield Road Project Citizens Association Meeting Jan. 17, 2018
Hayfield Road Project Citizens Association Meeting Jan. 17, 2018Hayfield Road Project Citizens Association Meeting Jan. 17, 2018
Hayfield Road Project Citizens Association Meeting Jan. 17, 2018Fairfax County
 
Pike Branch at Wilton Road Stream Stabilization Project
Pike Branch at Wilton Road Stream Stabilization ProjectPike Branch at Wilton Road Stream Stabilization Project
Pike Branch at Wilton Road Stream Stabilization ProjectFairfax County
 
20220817 Presentation wapda.pptx
20220817 Presentation wapda.pptx20220817 Presentation wapda.pptx
20220817 Presentation wapda.pptxAmirShafiq25
 
Stormwater Wastewater Consolidation
Stormwater Wastewater ConsolidationStormwater Wastewater Consolidation
Stormwater Wastewater ConsolidationFairfax County
 
Little Hunting Creek Sewer Replacement Community Meeting: 12-11-2017
Little Hunting Creek Sewer Replacement Community Meeting: 12-11-2017Little Hunting Creek Sewer Replacement Community Meeting: 12-11-2017
Little Hunting Creek Sewer Replacement Community Meeting: 12-11-2017Fairfax County
 
Bay Delta Conservation Plan - Infrastructure Review - Feb. 13, 2014
Bay Delta Conservation Plan - Infrastructure Review - Feb. 13, 2014Bay Delta Conservation Plan - Infrastructure Review - Feb. 13, 2014
Bay Delta Conservation Plan - Infrastructure Review - Feb. 13, 2014San Diego County Water Authority
 
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptxFairfax County
 
Bradley Acres Pond Retrofit Project
Bradley Acres Pond Retrofit ProjectBradley Acres Pond Retrofit Project
Bradley Acres Pond Retrofit ProjectFairfax County
 
DSD-NL 2014 - Geo Klantendag - 1. leidinginstallatie met direct pipe
DSD-NL 2014 - Geo Klantendag - 1. leidinginstallatie met direct pipeDSD-NL 2014 - Geo Klantendag - 1. leidinginstallatie met direct pipe
DSD-NL 2014 - Geo Klantendag - 1. leidinginstallatie met direct pipeDeltares
 
Dead Run Stream Restoration Segment 2 – 3
Dead Run Stream Restoration Segment 2 – 3Dead Run Stream Restoration Segment 2 – 3
Dead Run Stream Restoration Segment 2 – 3Fairfax County
 
Columbia Road/Randolph Court Stream Restoration July 2015
Columbia Road/Randolph Court Stream Restoration July 2015Columbia Road/Randolph Court Stream Restoration July 2015
Columbia Road/Randolph Court Stream Restoration July 2015Fairfax County
 
Project Leaders presentation
Project Leaders  presentationProject Leaders  presentation
Project Leaders presentationZiad el-Balbisi
 
4P - CAPSTONE FINAL POWERPOINT
4P - CAPSTONE FINAL POWERPOINT4P - CAPSTONE FINAL POWERPOINT
4P - CAPSTONE FINAL POWERPOINTThomas Bryce
 
Tuscarora Lateral Project - Open House Presentation on New 17-Mile Pipeline i...
Tuscarora Lateral Project - Open House Presentation on New 17-Mile Pipeline i...Tuscarora Lateral Project - Open House Presentation on New 17-Mile Pipeline i...
Tuscarora Lateral Project - Open House Presentation on New 17-Mile Pipeline i...Marcellus Drilling News
 
Bull Neck Stream Restoration Pardon Our Dust Meeting May 2, 2018
Bull Neck Stream Restoration Pardon Our Dust Meeting May 2, 2018Bull Neck Stream Restoration Pardon Our Dust Meeting May 2, 2018
Bull Neck Stream Restoration Pardon Our Dust Meeting May 2, 2018Fairfax County
 
Abtrex field installations and repairs on site
Abtrex field installations and repairs on siteAbtrex field installations and repairs on site
Abtrex field installations and repairs on siteAbtrex Inc
 
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Fairfax County
 

Ähnlich wie Negdc presentation december 2013 (20)

Hayfield Road Project Citizens Association Meeting Oct. 18, 2017
Hayfield Road Project Citizens Association Meeting Oct. 18, 2017Hayfield Road Project Citizens Association Meeting Oct. 18, 2017
Hayfield Road Project Citizens Association Meeting Oct. 18, 2017
 
Hayfield Road Project Citizens Association Meeting Jan. 17, 2018
Hayfield Road Project Citizens Association Meeting Jan. 17, 2018Hayfield Road Project Citizens Association Meeting Jan. 17, 2018
Hayfield Road Project Citizens Association Meeting Jan. 17, 2018
 
Pike Branch at Wilton Road Stream Stabilization Project
Pike Branch at Wilton Road Stream Stabilization ProjectPike Branch at Wilton Road Stream Stabilization Project
Pike Branch at Wilton Road Stream Stabilization Project
 
20220817 Presentation wapda.pptx
20220817 Presentation wapda.pptx20220817 Presentation wapda.pptx
20220817 Presentation wapda.pptx
 
Stormwater Wastewater Consolidation
Stormwater Wastewater ConsolidationStormwater Wastewater Consolidation
Stormwater Wastewater Consolidation
 
Little Hunting Creek Sewer Replacement Community Meeting: 12-11-2017
Little Hunting Creek Sewer Replacement Community Meeting: 12-11-2017Little Hunting Creek Sewer Replacement Community Meeting: 12-11-2017
Little Hunting Creek Sewer Replacement Community Meeting: 12-11-2017
 
Bay Delta Conservation Plan - Infrastructure Review - Feb. 13, 2014
Bay Delta Conservation Plan - Infrastructure Review - Feb. 13, 2014Bay Delta Conservation Plan - Infrastructure Review - Feb. 13, 2014
Bay Delta Conservation Plan - Infrastructure Review - Feb. 13, 2014
 
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 
Bradley Acres Pond Retrofit Project
Bradley Acres Pond Retrofit ProjectBradley Acres Pond Retrofit Project
Bradley Acres Pond Retrofit Project
 
DSD-NL 2014 - Geo Klantendag - 1. leidinginstallatie met direct pipe
DSD-NL 2014 - Geo Klantendag - 1. leidinginstallatie met direct pipeDSD-NL 2014 - Geo Klantendag - 1. leidinginstallatie met direct pipe
DSD-NL 2014 - Geo Klantendag - 1. leidinginstallatie met direct pipe
 
Dead Run Stream Restoration Segment 2 – 3
Dead Run Stream Restoration Segment 2 – 3Dead Run Stream Restoration Segment 2 – 3
Dead Run Stream Restoration Segment 2 – 3
 
ASCE San Ramon Canyon Storm Drain 6 4-15
ASCE San Ramon Canyon Storm Drain 6 4-15 ASCE San Ramon Canyon Storm Drain 6 4-15
ASCE San Ramon Canyon Storm Drain 6 4-15
 
Columbia Road/Randolph Court Stream Restoration July 2015
Columbia Road/Randolph Court Stream Restoration July 2015Columbia Road/Randolph Court Stream Restoration July 2015
Columbia Road/Randolph Court Stream Restoration July 2015
 
Downsview Area Long Term Water Servicing
Downsview Area Long Term Water Servicing Downsview Area Long Term Water Servicing
Downsview Area Long Term Water Servicing
 
Project Leaders presentation
Project Leaders  presentationProject Leaders  presentation
Project Leaders presentation
 
4P - CAPSTONE FINAL POWERPOINT
4P - CAPSTONE FINAL POWERPOINT4P - CAPSTONE FINAL POWERPOINT
4P - CAPSTONE FINAL POWERPOINT
 
Tuscarora Lateral Project - Open House Presentation on New 17-Mile Pipeline i...
Tuscarora Lateral Project - Open House Presentation on New 17-Mile Pipeline i...Tuscarora Lateral Project - Open House Presentation on New 17-Mile Pipeline i...
Tuscarora Lateral Project - Open House Presentation on New 17-Mile Pipeline i...
 
Bull Neck Stream Restoration Pardon Our Dust Meeting May 2, 2018
Bull Neck Stream Restoration Pardon Our Dust Meeting May 2, 2018Bull Neck Stream Restoration Pardon Our Dust Meeting May 2, 2018
Bull Neck Stream Restoration Pardon Our Dust Meeting May 2, 2018
 
Abtrex field installations and repairs on site
Abtrex field installations and repairs on siteAbtrex field installations and repairs on site
Abtrex field installations and repairs on site
 
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
 

Kürzlich hochgeladen

Rekha Agarkar Escorts Service Kollam ❣️ 7014168258 ❣️ High Cost Unlimited Har...
Rekha Agarkar Escorts Service Kollam ❣️ 7014168258 ❣️ High Cost Unlimited Har...Rekha Agarkar Escorts Service Kollam ❣️ 7014168258 ❣️ High Cost Unlimited Har...
Rekha Agarkar Escorts Service Kollam ❣️ 7014168258 ❣️ High Cost Unlimited Har...nirzagarg
 
Sanjay Nagar Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalor...
Sanjay Nagar Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalor...Sanjay Nagar Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalor...
Sanjay Nagar Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalor...amitlee9823
 
What Causes BMW Chassis Stabilization Malfunction Warning To Appear
What Causes BMW Chassis Stabilization Malfunction Warning To AppearWhat Causes BMW Chassis Stabilization Malfunction Warning To Appear
What Causes BMW Chassis Stabilization Malfunction Warning To AppearJCL Automotive
 
Hyundai World Rally Team in action at 2024 WRC
Hyundai World Rally Team in action at 2024 WRCHyundai World Rally Team in action at 2024 WRC
Hyundai World Rally Team in action at 2024 WRCHyundai Motor Group
 
John Deere 7430 7530 Tractors Diagnostic Service Manual W.pdf
John Deere 7430 7530 Tractors Diagnostic Service Manual W.pdfJohn Deere 7430 7530 Tractors Diagnostic Service Manual W.pdf
John Deere 7430 7530 Tractors Diagnostic Service Manual W.pdfExcavator
 
John Deere Tractors 6130M 6140M Diagnostic Manual
John Deere Tractors  6130M 6140M Diagnostic ManualJohn Deere Tractors  6130M 6140M Diagnostic Manual
John Deere Tractors 6130M 6140M Diagnostic ManualExcavator
 
Greenery-Palette Pitch Deck by Slidesgo.pptx
Greenery-Palette Pitch Deck by Slidesgo.pptxGreenery-Palette Pitch Deck by Slidesgo.pptx
Greenery-Palette Pitch Deck by Slidesgo.pptxzohiiimughal286
 
Business Bay Escorts $#$ O56521286O $#$ Escort Service In Business Bay Dubai
Business Bay Escorts $#$ O56521286O $#$ Escort Service In Business Bay DubaiBusiness Bay Escorts $#$ O56521286O $#$ Escort Service In Business Bay Dubai
Business Bay Escorts $#$ O56521286O $#$ Escort Service In Business Bay DubaiAroojKhan71
 
Delhi Call Girls Mayur Vihar 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip Call
Delhi Call Girls Mayur Vihar 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip CallDelhi Call Girls Mayur Vihar 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip Call
Delhi Call Girls Mayur Vihar 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip Callshivangimorya083
 
Delhi Call Girls Vikaspuri 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip Call
Delhi Call Girls Vikaspuri 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip CallDelhi Call Girls Vikaspuri 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip Call
Delhi Call Girls Vikaspuri 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip Callshivangimorya083
 
如何办理女王大学毕业证(QU毕业证书)成绩单原版一比一
如何办理女王大学毕业证(QU毕业证书)成绩单原版一比一如何办理女王大学毕业证(QU毕业证书)成绩单原版一比一
如何办理女王大学毕业证(QU毕业证书)成绩单原版一比一opyff
 
What Could Cause Your Subaru's Touch Screen To Stop Working
What Could Cause Your Subaru's Touch Screen To Stop WorkingWhat Could Cause Your Subaru's Touch Screen To Stop Working
What Could Cause Your Subaru's Touch Screen To Stop WorkingBruce Cox Imports
 
一比一原版(UdeM学位证书)蒙特利尔大学毕业证学历认证怎样办
一比一原版(UdeM学位证书)蒙特利尔大学毕业证学历认证怎样办一比一原版(UdeM学位证书)蒙特利尔大学毕业证学历认证怎样办
一比一原版(UdeM学位证书)蒙特利尔大学毕业证学历认证怎样办ezgenuh
 
一比一原版(UVic学位证书)维多利亚大学毕业证学历认证买留学回国
一比一原版(UVic学位证书)维多利亚大学毕业证学历认证买留学回国一比一原版(UVic学位证书)维多利亚大学毕业证学历认证买留学回国
一比一原版(UVic学位证书)维多利亚大学毕业证学历认证买留学回国ezgenuh
 
Call Girls in Malviya Nagar Delhi 💯 Call Us 🔝9205541914 🔝( Delhi) Escorts Ser...
Call Girls in Malviya Nagar Delhi 💯 Call Us 🔝9205541914 🔝( Delhi) Escorts Ser...Call Girls in Malviya Nagar Delhi 💯 Call Us 🔝9205541914 🔝( Delhi) Escorts Ser...
Call Girls in Malviya Nagar Delhi 💯 Call Us 🔝9205541914 🔝( Delhi) Escorts Ser...Delhi Call girls
 
Tata_Nexon_brochure tata nexon brochure tata
Tata_Nexon_brochure tata nexon brochure tataTata_Nexon_brochure tata nexon brochure tata
Tata_Nexon_brochure tata nexon brochure tataaritradey27234
 
Call Girls Kanakapura Road Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Kanakapura Road Just Call 👗 7737669865 👗 Top Class Call Girl Servi...Call Girls Kanakapura Road Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Kanakapura Road Just Call 👗 7737669865 👗 Top Class Call Girl Servi...amitlee9823
 

Kürzlich hochgeladen (20)

(INDIRA) Call Girl Nashik Call Now 8617697112 Nashik Escorts 24x7
(INDIRA) Call Girl Nashik Call Now 8617697112 Nashik Escorts 24x7(INDIRA) Call Girl Nashik Call Now 8617697112 Nashik Escorts 24x7
(INDIRA) Call Girl Nashik Call Now 8617697112 Nashik Escorts 24x7
 
Rekha Agarkar Escorts Service Kollam ❣️ 7014168258 ❣️ High Cost Unlimited Har...
Rekha Agarkar Escorts Service Kollam ❣️ 7014168258 ❣️ High Cost Unlimited Har...Rekha Agarkar Escorts Service Kollam ❣️ 7014168258 ❣️ High Cost Unlimited Har...
Rekha Agarkar Escorts Service Kollam ❣️ 7014168258 ❣️ High Cost Unlimited Har...
 
Sanjay Nagar Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalor...
Sanjay Nagar Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalor...Sanjay Nagar Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalor...
Sanjay Nagar Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalor...
 
What Causes BMW Chassis Stabilization Malfunction Warning To Appear
What Causes BMW Chassis Stabilization Malfunction Warning To AppearWhat Causes BMW Chassis Stabilization Malfunction Warning To Appear
What Causes BMW Chassis Stabilization Malfunction Warning To Appear
 
Hyundai World Rally Team in action at 2024 WRC
Hyundai World Rally Team in action at 2024 WRCHyundai World Rally Team in action at 2024 WRC
Hyundai World Rally Team in action at 2024 WRC
 
Call Girls in Shri Niwas Puri Delhi 💯Call Us 🔝9953056974🔝
Call Girls in  Shri Niwas Puri  Delhi 💯Call Us 🔝9953056974🔝Call Girls in  Shri Niwas Puri  Delhi 💯Call Us 🔝9953056974🔝
Call Girls in Shri Niwas Puri Delhi 💯Call Us 🔝9953056974🔝
 
John Deere 7430 7530 Tractors Diagnostic Service Manual W.pdf
John Deere 7430 7530 Tractors Diagnostic Service Manual W.pdfJohn Deere 7430 7530 Tractors Diagnostic Service Manual W.pdf
John Deere 7430 7530 Tractors Diagnostic Service Manual W.pdf
 
John Deere Tractors 6130M 6140M Diagnostic Manual
John Deere Tractors  6130M 6140M Diagnostic ManualJohn Deere Tractors  6130M 6140M Diagnostic Manual
John Deere Tractors 6130M 6140M Diagnostic Manual
 
Greenery-Palette Pitch Deck by Slidesgo.pptx
Greenery-Palette Pitch Deck by Slidesgo.pptxGreenery-Palette Pitch Deck by Slidesgo.pptx
Greenery-Palette Pitch Deck by Slidesgo.pptx
 
Business Bay Escorts $#$ O56521286O $#$ Escort Service In Business Bay Dubai
Business Bay Escorts $#$ O56521286O $#$ Escort Service In Business Bay DubaiBusiness Bay Escorts $#$ O56521286O $#$ Escort Service In Business Bay Dubai
Business Bay Escorts $#$ O56521286O $#$ Escort Service In Business Bay Dubai
 
Delhi Call Girls Mayur Vihar 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip Call
Delhi Call Girls Mayur Vihar 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip CallDelhi Call Girls Mayur Vihar 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip Call
Delhi Call Girls Mayur Vihar 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip Call
 
Delhi Call Girls Vikaspuri 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip Call
Delhi Call Girls Vikaspuri 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip CallDelhi Call Girls Vikaspuri 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip Call
Delhi Call Girls Vikaspuri 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip Call
 
如何办理女王大学毕业证(QU毕业证书)成绩单原版一比一
如何办理女王大学毕业证(QU毕业证书)成绩单原版一比一如何办理女王大学毕业证(QU毕业证书)成绩单原版一比一
如何办理女王大学毕业证(QU毕业证书)成绩单原版一比一
 
What Could Cause Your Subaru's Touch Screen To Stop Working
What Could Cause Your Subaru's Touch Screen To Stop WorkingWhat Could Cause Your Subaru's Touch Screen To Stop Working
What Could Cause Your Subaru's Touch Screen To Stop Working
 
一比一原版(UdeM学位证书)蒙特利尔大学毕业证学历认证怎样办
一比一原版(UdeM学位证书)蒙特利尔大学毕业证学历认证怎样办一比一原版(UdeM学位证书)蒙特利尔大学毕业证学历认证怎样办
一比一原版(UdeM学位证书)蒙特利尔大学毕业证学历认证怎样办
 
Stay Cool and Compliant: Know Your Window Tint Laws Before You Tint
Stay Cool and Compliant: Know Your Window Tint Laws Before You TintStay Cool and Compliant: Know Your Window Tint Laws Before You Tint
Stay Cool and Compliant: Know Your Window Tint Laws Before You Tint
 
一比一原版(UVic学位证书)维多利亚大学毕业证学历认证买留学回国
一比一原版(UVic学位证书)维多利亚大学毕业证学历认证买留学回国一比一原版(UVic学位证书)维多利亚大学毕业证学历认证买留学回国
一比一原版(UVic学位证书)维多利亚大学毕业证学历认证买留学回国
 
Call Girls in Malviya Nagar Delhi 💯 Call Us 🔝9205541914 🔝( Delhi) Escorts Ser...
Call Girls in Malviya Nagar Delhi 💯 Call Us 🔝9205541914 🔝( Delhi) Escorts Ser...Call Girls in Malviya Nagar Delhi 💯 Call Us 🔝9205541914 🔝( Delhi) Escorts Ser...
Call Girls in Malviya Nagar Delhi 💯 Call Us 🔝9205541914 🔝( Delhi) Escorts Ser...
 
Tata_Nexon_brochure tata nexon brochure tata
Tata_Nexon_brochure tata nexon brochure tataTata_Nexon_brochure tata nexon brochure tata
Tata_Nexon_brochure tata nexon brochure tata
 
Call Girls Kanakapura Road Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Kanakapura Road Just Call 👗 7737669865 👗 Top Class Call Girl Servi...Call Girls Kanakapura Road Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Kanakapura Road Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
 

Negdc presentation december 2013

  • 1. Connecticut River Crossing 2013 Hadley/Hatfield, MA David M. Grande Director – Gas Engineering & System Operations Berkshire Gas Company 115 Cheshire Road Pittsfield, MA 01202-1388 Phone 413-445-0265 dgrande@berkshiregas.com Paul Scarpa Senior Engineer Berkshire Gas Company 115 Cheshire Road Pittsfield, MA 01202-1388 Phone 413-445-0383 pscarpa@berkshiregas.com Confidential – Not for internal distribution or public release. 1
  • 2. Berkshire Gas Company – Located in Western Massachusetts Connecticut River 12/19/13 22
  • 3. Company Information • 38,000 Customers • 1,500 Miles – Mains & Services • 1 Satellite LNG Plant • 3 Propane Air Plants • 120 Employees • 160 Years Old • 6 City Gate Stations 12/19/13 33
  • 4. Project Context – Connecticut River Crossing • Installation of approximately 2,250 linear feet of 12-inch coated steel gas main. The project commences on Bridge Lane in Hatfield, MA and continues beneath the Connecticut River, terminating on Huntington Rd. in Hadley, MA. Approximately 1,600 linear feet of the proposed gas main shall be installed beneath the Connecticut River via directional drilling. The remaining 650 linear shall be installed within an open trench. • Project is being done to provide additional firm volumes to Amherst College and provide additional system reliability for the Hadley/Amherst area. • New main will run in parallel with existing 6-inch coated steel main which was installed in 1959 when the Company brought Natural Gas service to the Hadley/Amherst area. 12/19/13 44
  • 5. UMASS & Amherst College – Amherst MA UMASS – Central Heating Plant Amherst College – Central Heating Plant 12/19/13 55
  • 6. Confidential – Not for internal distribution or public release. 6
  • 7. Project Mile Stones • Engineering for Project began in November 2012 • The following was performed: • • • • • • Survey – current easement (Hadley) town ROW (Hatfield) Test Borings – both sides of the river Preliminary Design Plans- used to submit wetland filings Wetland Delineation Notice of Intent • Wetland Notice of Intent submission to the Hadley and Hatfield Conservation Commissions and Mass DEP • Filing Notice of Intent with the Natural Heritage and Endanger Species Program (NHESP) Army Corps of Engineers (ACOE) Category 2 Permit filing • Frac Out Plan Final Design Plans and Details • Final Permit Approval Received in September 2013 • 12/19/13 77
  • 8. Project Milestones • Request for Proposal (RFP) was issued on 8/19/2013 • • • 12/19/13 Bidders • Hemlock Directional Boring Inc. • C.B. Utility Co., Inc. • JS Rae Construction • Directional Technologies, Inc. • Mears Group Inc. RFP’s were due on 9/3/2013 Project Awarded to JS Rae on 9/9/2013 88
  • 10. HDD Steps  Pilot Hole  Reaming  Pull Back 12/19/13 10 10
  • 11. Current Conditions Milestone Schedule Hadley Existing 6” Coated Steel Main - 1959 Hatfield 12/19/13 11 11
  • 12. Current Conditions – Hatfield Side Milestone Schedule Hatfield – Westside – River Approx. 900 ft. wide 12/19/13 12 12
  • 13. Current Conditions – Hadley Side Milestone Schedule Hadley – Eastside 12/19/13 13 13
  • 14. Connecticut River Crossing Milestone Schedule – Hadley Side Existing 6” Coated Steel Main Company has existing 25ft. Permanent and working easement 12/19/13 14 14
  • 15. Connecticut River Crossing Milestone Schedule - Hadley Side Environmental Protection Installed 12/19/13 15 15
  • 16. Connecticut River Crossing – Hadley Side Milestone Schedule Swamp Mats were required on the Hadley Side 12/19/13 16 16
  • 17. Connecticut River Crossing – Hatfield Side Milestone Schedule 1,680 ft. – 12” Coated Steel – Induron Warrior 100 Coating – Designed for HDD Remaining 12” Coated Steel – Pritec 40 Mil Coating 12/19/13 17 17
  • 18. Connecticut River Crossing – Hatfield Side Milestone Schedule Preformed 100% X-Ray of Pipe Welds 12/19/13 18 18
  • 19. Connecticut River Crossing – Hatfield Side Milestone Schedule 12/19/13 19 19
  • 20. Connecticut River Crossing – Corrosion Control Milestone Schedule Warrior 100 Pipe Coating & Rubber Pipe Rollers 12/19/13 20 20
  • 21. Connecticut River Crossing – Corrosion Control Milestone Schedule Powercrete R-95 Epoxy Based Coating Used for Welds – Designed for HDD 12/19/13 21 21
  • 22. Connecticut River Crossing – Initial Pressure Test Milestone Schedule Final Pressure Test – 300 Psig – 4 Hours - Deadweight 12/19/13 22 22
  • 23. Connecticut River Crossing - Drilling Milestone Schedule During the pilot hole drilling, a directional guidance system is used to navigate the pilot hole along its pre-designed profile. Down Hole System – Wire Line 12/19/13 23 23
  • 24. Connecticut River Crossing - Drilling Milestone Schedule 12/19/13 24 24
  • 25. Construction - Drilling Milestone Schedule 12/19/13 25 25
  • 26. Connecticut River Crossing - Drilling Milestone Schedule Shallow Water Depths 12/19/13 26 26
  • 27. Construction - Drilling Pilot Hole Milestone Schedule – 120ft. 30” & 130ft. 12” Conductor barrel were used • • Used to minimize the potential of a drilling frac out and/or ground collapse near the entry location. The conductor barrel created a clear pathway through the soft soil conditions so that drilling could begin in more preferable geology 12/19/13 27 27
  • 28. Construction – Drilling Pilot Hole Milestone Schedule 12/19/13 28 28
  • 29. Construction – Drilling Pilot Hole Milestone Schedule Final Pilot Hole Maximum Depth was 60 ft. Below Existing River Bed, 12/19/13 29 29
  • 30. Construction - Reaming Milestone Schedule 22” ream & 18” ream were used. The 22” ream was used to go through the bedrock 12/19/13 30 30
  • 31. Construction - Reaming Milestone Schedule Reaming consisted of pushing from the drill rig in Hadley and pulling with excavator in Hatfield. 12/19/13 31 31
  • 32. Construction - Reaming Milestone Schedule 12/19/13 32 32
  • 33. Construction - Reaming Milestone Schedule 12/19/13 33 33
  • 34. Construction - Reaming Milestone Schedule 12/19/13 34 34
  • 35. Construction – Pull Back Milestone Schedule Pull back began at approx. 12:30 PM on 11/20/2013 and took 5 Hrs. to complete. 12/19/13 35 35
  • 36. Construction – Pull Back Milestone Schedule 12/19/13 36 36
  • 37. Construction – Pull Back Hatfield Side Milestone Schedule 12/19/13 37 37
  • 38. Construction – Pull Back Hadley Side Milestone Schedule 12/19/13 38 38
  • 39. Construction – Testing & Tie-In Milestone Schedule 12/19/13 39 39
  • 40. Construction – Testing & Tie -In Milestone Schedule 12/19/13 40 40
  • 41. Questions David M. Grande Director – Gas Engineering & System Operations Berkshire Gas Company 115 Cheshire Road Pittsfield, MA 01202-1388 Phone 413-445-0265 dgrande@berkshiregas.com 12/19/13 41 41