The city council reviewed two projects - a pool renovation project and a river project. For the pool renovation, the project was completed on budget at $3.2 million and is scheduled to have a soft opening in mid-May and grand opening in late May. For the river project, the project is also within its $14.7 million budget and over 80% complete, with additional enhancements planned over the next year.
2. Pool Renovation Project, Budget
Project is within budget.
Funding: $3,241,197 Half Cent Sales Tax Allocations
$21,225 Donation for rotunda roofing upgrade
Total Funding: $3,262,422
Expenses: ($345,000) Design and oversight
($2,767,282) Construction work w/ change orders
($36,190) Supplemental costs (assessments,
asbestos removal, demo., power lines, tests, etc.)
($25,000) Landscaping
($45,000) Furniture and fixtures
($43,950) Contingency
Total Expenses ($3,262,422)
3. Pool Renovation Project, Schedule
• Presentation of operations plan, 2nd mtg. March (tent.)
• Construction complete: early April
• Remaining: pool coping installation, concrete pool decking,
roofing for wings, final hook up of pool equipment, solid surface
tops & benches w/ lockers, millwork & punch list
• Staff training, addition of furniture/fixtures: April & May
• Irrigation & Landscaping
• DS II – postponed planting
• DS I – limited planting
• Soft opening (rentals and evenings): mid May
• Grand opening: late May
17. River Project, Budget
Project is within budget.
Funding: $12,893,175 Half Cent Sales Tax Allocations
$142,500 HUD Stimulus Funding
$570,000 SAHF Grant
$200,000 TPWD Trails Grant
$500,000 TPWD Outdoor Recreation Grant
$323,512 TCEQ Grant
$120,000 NEA Grant
Total Funding: $14,749,187
18. River Project, Budget
Expenses: ($1,500,000) Dredging project -- complete
($1,742,333) Design, studies, assessments, permits
($9,300,000) Construction
($300,000) Paseo completion project
($864,082) Property purchase – Edgewater
($170,492) Property purchase -- btwn. 19th & 29th
($115,625) UCRA – project coordination/oversight
Total Expenses: ($13,992,532)
Remaining funds of about $750,000 for:
water feature enhancements ($500,000) and
project contingency ($250,000).
32. River Project, Additional Work
• Water features in the central section:
• RFPs – 4 submittals received.
• 2 interviews.
• Proposal recommendation to Council in March.
• Additional bank stabilization from Sulphur Draw upriver
to 1st Street.
• Trail on SAHF property.
• Putt-putt golf area.