SlideShare ist ein Scribd-Unternehmen logo
1 von 13
Downloaden Sie, um offline zu lesen
1

CoFold Ultra 100
Fitting Instructions
Diagram 1

for top hung exterior outward folding doors

SYSTEM CAPACITY
Maximum leaf height - 3300mm
Maximum leaf weight - 100kg
Maximum leaf width - 1000mm
Maximum leaf thickness- 48-68mm

TRACK FIXING
NOT BY COASTAL

* For thicker or thinner doors please contact technical@coastal-group.com.
* If the hypotenues is more than the door width x 1.004 then a risk of
camming exists.

INSIDE

Diagram 2

OUTSIDE

JAMB CAP
IN LINE WITH
TRACK

Diagram 3

Diagram 4

34
140

WHEN USED IN CONJUNCTION WITH
ALUMINIUM SUPPORT CHANNEL 94SC
THE OUTER CHANNEL DIMENSIONS
BECOME 23H x 25W
JAMB CAP IN LINE WITH TRACK
JAMB CAP GASKET

52

39

212

ALTERNATIVE ALUMINIUM THRESHOLD
ALTERNATIVE ALUMINIUM THRESHOLD SF94T94T
BY COASTAL - COMPLETE WITH 94P WITH
BY PCH - COMES COMES COMPLETE AND 94P AND
ENDCAPS AND IS PREDRILLED FOR DRAINAGE
ENDCAPS AND IS PREDRILLED FOR DRAINAGE
2

PREPARATION
U1 2R 2L U2R U2L 3U4 78U9 10 -

Pivot Assembly Set
End Hanger Set Right Hand - for doors meeting a swing door and square-edged doors meeting
End Hanger Set Left Hand - for doors meeting a swing door and square-edged doors meeting
End Hanger Set Right Hand - for doors folding to the frame (i.e. 2 leaf, 4 leaf and 6 leaf)
End Hanger Set Left Hand - for doors folding to the frame (i.e. 2 leaf, 4 leaf and 6 leaf)
Hinge Set with Handle
Intermediate Hanger Set
Hinge Set Offset Outward Opening
Rebated End Hanger Meeting
Pivot Hinge required for Ultra security
Face Fix Handle (Optional)

Diagram 5

Diagram 6

U9
U1

U9
2L

U9

U1

U9

U1

U4

U9
U1

U4

2R

U4

U4

U1

U1

U9
U4

U9

U1

U1

U9
U1

U1

U9

U9
U1

U9

U4

U4

U9
U4

2L

U9

U1

U1

U9
U4

U4

U1
3

Preparing the opening

Preparing the door frame

Ensure the opening is square and all load bearing areas are
suitable for the weight of the system. Take particular care to
ensure there is sufficient strength in the structure above the
opening to take the concentrated weight of the doors, when in
the open stacked position. The CoFold system provides +/3mm of horizontal and vertical adjustment. Use a plumb line to
ensure that the centre line of the track and the centre line of the
channel are offset by 19mm.

=

=

Diagram 10

Preparing the door frame for
U1, 2 & 9 face plates

Ø10 DRILL FOR DRAINAGE AT
1000 CENTRES, 300 CENTRES
FOR EXTREME CONDITIONS
OR US ALUMINIUM THRESHOLD
BY COASTAL

Hinge
Component

25
52

U9 Face Plate

R6

54

36

54

70

50

Diagram 7

79

R2
0

22

50

U1 Face Plate

=

U9 Face Plate

22

26
40
27

27
OUTSIDE

INSIDE

Diagram 8

31

Frame Support Plate

=

U1 Face Plate

54

52

Diagram 9

For details on installation of
the U9 please refer to the U9
fitting instructions

22

79

SILL

Diagram 11
4

Preparing the door leaves

Door leaf width calculation
1. Decide how many door leaves you want in the opening.
2. Add together all the 3mm clearances required between door leaves and the jambs (there will be one more than the number of door
leaves). This is the total clearance figure.
3. Measure the finished opening width (W) and deduct from this the total clearance figure.
4. Divide this new figure (finished opening width minus total clearance) by the number of doors to produce the actual door width. (N.B.
all doors with the Cofold system are the same width).
For example: For a 4 door leaf system with a finished opening width of 2345mm the door leaf width would be 2345mm minus (5x3mm)
divided by 4 (number of door leaves) = 582.5mm.

Door leaf height calculation
Leaf height = finished opening height (see diagram 7) minus 66mm.

Diagram 12
PREPARING THE DOOR LEAF
AT THE JAMB

Door Seals
Prepare the door leaves to accept the
AQ63B seal.

BETWEEN DOOR EDGES

Diagram 13
ADD 10mm TO
WIDTH OF EACH
LEAF TO CREATE
REBATE

ADD 10mm TO
WIDTH OF END
HANGER LEAF
FOR REBATE

Meeting Doors
Use the 8 set for 2+2 rebated timber door
configurations. For all other configurations
use 2L (left hand) or 2R (right hand) end
hanger sets. For kit handing refer to diagram
6.
Diagram 14
5

Door hardware positioning

U9

KIT U1

KIT U4

KIT U2L

Diagram 15

End door leaf Preparation

7.5mm check In for U1, U2, 2 and 8

Diagram 16
6

Door hardware attachment

23

Ø 3mm
PILOT HOLES
14
50
22

100

18

50

CHECK IN
FOR 9
Ø13mm
15mm deep

100

15

3

3

IMPORTANT

Kit U1
BOTH SCREWS MUST BE
FITTED UNDER THE COVERS OF
ALL THE END HINGES

2 WHEEL ASSEMBLY

SIDE THRUST BEARING

FIXING SCREW (6 OFF)

HANGER BODY

COVER (SLIDE)
WASHER
HANGER BOLT

Kit U2L (or U2R)

Kit U4

Diagram 17
7

INSTALLATION
1. Ensure that you have all the required parts. Unpack the
components and identify the parts. Lay the parts on the
ground in the same configuration as they will be when
installed. It is recommended that a light smear of general
purpose grease is applied to all bolts prior to assembly.

Diagram 18

2. Cut the track to the required length and pre-drill for
fixings in accordance with diagram 18. Please note that the
extra fixings are required where the doors stack together.

TOP PIVOT SECURING BLOCK

3. Cut the channel to the required length and fit in the sill.
Drill drainage holes (see diagram 1).
PIVOT SECURING BLOCK HEX
BOLTS

4. Remove all the wheel assemblies and pivot block from
the hanger and pivot bolts, and disassemble top pivot
block assembly.

PIVOT CAM

5. Slide the wheel assemblies and track pivot block into
the track in the correct order, orientation, and position
and fix the track in position. Reassemble top pivot block
assembly (see diagram 19).

PIVOT ADJUSTER

PIVOT CLAMP PLATE

6. Remove the bottom pivot assembly and guide roller
assembly (see diagram 20). Disassemble the bottom pivot
assembly.

ADJUSTMENT LOCK OFF
BOLTS

Diagram 19

7. For installation, assemble leaves in pairs via the hinges.
To improve the ease of installation pre-drill pilot holes for
all hinge parts. Fit kits U1, 7,U4 and U9 (optional) to first
pair of leaves.
Please ensure all 4 screws are fixed per end hinge.
8. Screw the bottom anchor of the bottom pivot assembly
to the base of the channel 11mm from the jamb. Please
note, the screw nearest the end of the bottom anchor is
closest to the jamb (see diagram 21). Reassemble the pivot
assembly leaving the clamping screws loose (see diagram 25).
9. Suspend pairs of leaves by engaging top pivot and
hanger bolts using 5mm Allen key supplied (see top of
diagram 20).
10. Attach the bottom pivot and guide assembly to their
respective hinges, adjust the bottom pivot side plates
position so that it engages with the hinge bolt. Tighten
pivot and guide strap bolts (see diagram 22).
11. Lift the next pair of leaves into position and support
their weight by screwing the hanger strap bolt into the
hanger wheel assembly and fixing the second and third
leaves together.

Diagram 20

JAMB

CHANNEL

12. Continue this procedure until all leaves are fitted.
BOTTOM ANCHOR

Diagram 21

Diagram 22
8

ADJUSTMENT
Height Adjustment (± 3mm)

1. Close leaves and adjust the door height to achieve an
equal gap between the top of the leaves and the track (a
9mm gap is recommended). (see diagram 23).

INSIDE
LOCKING HANGER
GRUB SCREW
ON INSIDE OF DOOR

2. Once the adjustment is complete use the Allen key to
tighten the locking hanger grub screw until secure.

Lateral Adjustment

1. With the unit still in the closed position, slide the set of
leaves towards the jamb to obtain the desired gap
between the jamb and the pivot door. A gap of 3mm is
recommended using the adjustment cam. Once in
position tighten the clamp screws. (see diagram 25).

U4 ILLUSTRATED.
SAME METHOD OF
ADJUSTMENT APPLIED
TO U1, U2L, U2R AND 8.

Diagram 23

2. Fold the leaves and adjust the bottom side plate using
the Allen key provided so that the gap between the door
and the jamb is the same over the full length of the door.
3. Tighten the two clamping screws to lock the side plate
to the bottom anchor.
4. Once the pivot door is in the correct position insert
and tighten the locking pivot grub screw from the inside
position. (as shown in diagram 24)

INSIDE
CLAMP SCREW

LOCKING PIVOT
GRUB SCREW
ON INSIDE OF
DOOR

CLAMP SCREW
ADJUSTMENT CAM

Locking Off
Tighten grub screws on hangers, guides and pivots.
Diagram 24

CARE AND MAINTENANCE
To provide years of trouble free operation, it is
recommended that the track is kept free from dirt and
debris. Periodically replace the general purpose grease on
all bolts. To prolong the appearance of the exposed hinge
parts, it is recommended they are periodically washed
with soap and water. Maintenance is required on all
components including stainless steel to validate
manufacturers warranty. For further maintenance details
please refer to our website.

TIGHTEN
GRUB SCREW

CLAMP SCREW
ADJUSTMENT CAM
CLAMP SCREW

BOTTOM ANCHOR
JAMB SIDE

BOTTOM SIDE
PLATE

ADJUSTMENT

Diagram 25
9

Aluminium Threshold Jamb Kit

51
25.5
25.5

21
94

25

Jamb Cap

Jamb Cap Gasket

51

15

34

19

Threshold 94T

8

27

2.5

83

Pre-drilled 10mm diameter drainage
holes at 300mm centres

Endcap
2.5

51

140
51

25.5
25.5

23
27

8
15

34

Jamb Cap
Jamb Cap

2.5
2.5

Jamb Cap Gasket
Jamb Cap Gasket

51

140

21
94

25

52

39

Endcap
Endcap

83
Jamb Cap
Jamb Cap Gasket

52

(All dimensions in mm)

39
Endcap
10

U9 Intermediate Pivot Set
1. The CoFold U9 intermediate pivot set shown in Diagram 1, should
be fitted to the pivot door mid way between the U1 top and bottom
pivot assemblies. The U9 hinge must be positioned on the same centre
line as the U1 top and bottom pivot hinge bodies.

5. Screw the frame support plate and the face plate onto the opening frame
preparation, as shown in Diagrams 3 and 5.

2. Rout the door and drill the pilot holes as shown on Diagram 2. Fit the
hinge body using the four screws provided.

7. Fit the U9 cover sleeve on to the U9 hinge body and drop the main
strap bolt into position, as shown in Diagram 6.

3. Using Diagram 3, 4 and 6 locate the position of the threaded link arm
receiving hole on the the opening frame. Starting from the central point of
the threaded link arm receiving hole (as indicated on Diagrams 4 and 5)
mark the location of the two screw holes for the face plate. Using the face
plate as a template mark out the routing detail for the face plate and rout.

8. Screw the threaded link arm fully into the frame support plate. The
centre of the threaded hole in the link arm should be positioned to
receive the strap bolt. Screw the strap bolt in to the link arm until there
is a 2mm gap between the head of the strap bolt and the hinge body, as
shown in Diagram 6.

4. Drill the Ø12mm hole for the threaded link arm receiving hole and rout
the opening frame to mount the Frame Support Plate flush if required
(Diagram 3).

9. Adjust the U9 pivot set to ensure the clearance between the pivot door
and the frame is uniform (Diagram 7).

6. Fit the pivot door into position using the U1 pivot set.

Note: These fitting instructions should be used in conjunction with the CoFold Ultra Fitting Instructions

7.5

17.5
Main strap bolt

U1

Hinge body

100
U9

Cover plate
R17.5

U1
Cover sleeve

Diagram 1.

ole
ph
dee
m
28m

Diagram 2.

Ø12

Optional 2.5
deep rebate
for face plate

Pilot holes

36

18

R12.5
R6

mm

2.5

dee

25mm

p

26

41m
m

Opening frame

INSIDE

Door in closed
position

28mm

Hole centre to
door face 8mm

OUTSIDE

Ø12 Threaded link
arm receiving hole

Diagram 3.
Locating and drilling guide for U9 face place
22

Ø6

Face plate

53

Threaded link arm
receiving hole
31

50

100

OUTSIDE

INSIDE

Frame support
plate

Diagram 5.
Door shown in the open position
8mm

HALF DOOR
HEIGHT +79mm

Face plate

2mm gap

53

Threaded link arm
receiving hole

Main strap
bolt

Line from bottom
of the hinge body

31

20mm
22

Frame support
plate
Threaded link arm
Frame support plate
Screw the frame support plate and the face
plate onto the opening frame preparation,
as shown in Diagrams 3 and 4.

100

Diagram 6.

Door shown in the open position
50

2mm gap
Adjustment:
3mm in to the frame
6mm out to the frame

Diagram 4.

Diagram 7.
11

Outward Opening Flush Bolt
For top hung exterior folding doors. For use in conjunction with standard outward opening fitting
instructions. Follow routing instructions for the bolt keep and flush bolt length to be fitted, fit both with
the screws supplied. Suitable pilot holes for screws are recommended.

Routing detail for
450mm Top Flush Bolt

Routing detail for
600mm Top Flush Bolt

HEAD BOARD
LINTEL

12.5
FASCIA

Routing detail for
190mm Top Flush Bolt

18

Routing detail for
190mm Bottom
Flush Bolt

PLATE

600

450

580

190

430

170

30

INSIDE

4

190

Enlarged detail showing the
sectional routing dimensions
for all 3 bolt sizes
40

OUTSIDE

170

TOP FLUSH
BOLT

22

17

Note:

Routing detail is the
same for both locking
and non-locking flush
bolts.

Door height

Recommended
Bolt length for top of door

Recommended
Bolt length for bottom of door

Upto 2200mm

190mm

190mm

Upto 2450mm

450mm

190mm

Over 2450mm

600mm

190mm

BOTTOM
FLUSH
BOLT

Routing detail for bolt keep sockets
Top Flush Bolt into Head

Bottom Flush Bolt into Sill
Fixing screw centres
40

Ø18

PLATE
Ø18

10
12.5
4

10

12.5
40
10

40

30
25

12

KEEP LINER

SILL
REBATE

65
40mm fixing screw centres - Use fixing plate as drilling template

SILL

18
12.5

Section through door showing
flush bolt rebate detail
(All dimensions in mm)

Coastal Joinery Hardware, Global House, Bojea Industrial Estate, Trethowel, St Austell, Cornwall, PL25 5RJ.
Tel: 01726 871726 Fax: 01726 871731 Email: sales@coastal-group.com

Part No: 220946
Issue 8 - January 2013
ENQUIRY FORM FOR BI-FOLD DOORS

Please enter your address here:
Your Details/FAO
Address

Telephone:

Fax:

PROJECT TITLE:

Email:

LOCATION:

SPECIFICATION SHEET
System Capacity:

1. Opening Size:

BI-FOLD DOORS
Maximum Leaf Height: 3300mm
Maximum Leaf Width: 1000mm
Maximum Leaf Weight: 100kg
Leaf Thickness: 35mm-68mm

mm

Height:
2. Door Configuration:
Number of leaves sliding (viewed from the outside)

Width:

mm

RH
LH

3. Outward Opening:
Due to weathering, outward opening Is
highly recomended.

Yes
No

4. Locking

None
Espagnolette
Sash lock

5. Finish

Satin Stainless Steel
PVD Brass
Polished Stainless Steel

6. System

CoFold
CoFold Ultra (High Security)

7. Gear Types
Choice only applies to CoFold system &
not the CoFold Ultra.

Mortice
Non Mortice

8. Weatherseal Required:

None

Brown

White
PRE-TENSION

Coastal Group | T 01726 871726 | F 01726 871731
Email sales@coastal-group.com | Visit www.coastal-group.com

Weitere ähnliche Inhalte

Was ist angesagt?

Was ist angesagt? (20)

Partitions and panelling
Partitions and panellingPartitions and panelling
Partitions and panelling
 
Glass partition 002
Glass partition 002Glass partition 002
Glass partition 002
 
curtain wall -skin of building
 curtain wall -skin of building curtain wall -skin of building
curtain wall -skin of building
 
FALSE CEILING
FALSE CEILINGFALSE CEILING
FALSE CEILING
 
Curtain wall system
Curtain wall systemCurtain wall system
Curtain wall system
 
warm and humid climate
warm and humid climatewarm and humid climate
warm and humid climate
 
Hot & dry climate
Hot & dry climateHot & dry climate
Hot & dry climate
 
Shelter for composite climate
Shelter for composite climateShelter for composite climate
Shelter for composite climate
 
False ceiling
False ceilingFalse ceiling
False ceiling
 
Partition walls
Partition walls Partition walls
Partition walls
 
False ceiling
False ceilingFalse ceiling
False ceiling
 
Thermal insulation of building
Thermal insulation of buildingThermal insulation of building
Thermal insulation of building
 
Cladding
CladdingCladding
Cladding
 
Building materials and construction technlogoy- FALSE CEILING & FLOORING
Building materials and construction technlogoy- FALSE CEILING & FLOORINGBuilding materials and construction technlogoy- FALSE CEILING & FLOORING
Building materials and construction technlogoy- FALSE CEILING & FLOORING
 
How to install false ceiling
How to install false ceilingHow to install false ceiling
How to install false ceiling
 
Bhopal mohneys table
Bhopal mohneys tableBhopal mohneys table
Bhopal mohneys table
 
Hot and dry climate architecture
Hot and dry climate architectureHot and dry climate architecture
Hot and dry climate architecture
 
Structural glazing
Structural glazingStructural glazing
Structural glazing
 
Structural glazing final
Structural glazing finalStructural glazing final
Structural glazing final
 
Monama house
Monama houseMonama house
Monama house
 

Ähnlich wie CoFold Ultra Sliding Folding Door Gear Installation Instructions

CoFold Non-Mortice Sliding Folding Door Gear Installation Instructions
CoFold Non-Mortice Sliding Folding Door Gear Installation InstructionsCoFold Non-Mortice Sliding Folding Door Gear Installation Instructions
CoFold Non-Mortice Sliding Folding Door Gear Installation Instructions
Coastal Joinery Hardware
 
Jcb 4 cx t4f backhoe loader service repair manual from 02254521 to 02274521
Jcb 4 cx t4f backhoe loader service repair manual from 02254521 to 02274521Jcb 4 cx t4f backhoe loader service repair manual from 02254521 to 02274521
Jcb 4 cx t4f backhoe loader service repair manual from 02254521 to 02274521
fjjskekfsemmd
 
Jcb 4 cx t4f backhoe loader service repair manual from 02254521 to 02274521
Jcb 4 cx t4f backhoe loader service repair manual from 02254521 to 02274521Jcb 4 cx t4f backhoe loader service repair manual from 02254521 to 02274521
Jcb 4 cx t4f backhoe loader service repair manual from 02254521 to 02274521
fujdjjksekmem
 
Jcb 3 cx t4f backhoe loader service repair manual from 02254521 to 02274521
Jcb 3 cx t4f backhoe loader service repair manual from 02254521 to 02274521Jcb 3 cx t4f backhoe loader service repair manual from 02254521 to 02274521
Jcb 3 cx t4f backhoe loader service repair manual from 02254521 to 02274521
fjjskekfsemmd
 
Jcb 3 cx t4f backhoe loader service repair manual from 02254521 to 02274521
Jcb 3 cx t4f backhoe loader service repair manual from 02254521 to 02274521Jcb 3 cx t4f backhoe loader service repair manual from 02254521 to 02274521
Jcb 3 cx t4f backhoe loader service repair manual from 02254521 to 02274521
fujdjjksekmem
 

Ähnlich wie CoFold Ultra Sliding Folding Door Gear Installation Instructions (20)

CoFold Non-Mortice Sliding Folding Door Gear Installation Instructions
CoFold Non-Mortice Sliding Folding Door Gear Installation InstructionsCoFold Non-Mortice Sliding Folding Door Gear Installation Instructions
CoFold Non-Mortice Sliding Folding Door Gear Installation Instructions
 
Yale b967 glc050 lx lift truck service repair manual
Yale b967 glc050 lx lift truck service repair manualYale b967 glc050 lx lift truck service repair manual
Yale b967 glc050 lx lift truck service repair manual
 
Jcb 4 cx t4f backhoe loader service repair manual from 02254521 to 02274521
Jcb 4 cx t4f backhoe loader service repair manual from 02254521 to 02274521Jcb 4 cx t4f backhoe loader service repair manual from 02254521 to 02274521
Jcb 4 cx t4f backhoe loader service repair manual from 02254521 to 02274521
 
Jcb 4 cx t4f backhoe loader service repair manual from 02254521 to 02274521
Jcb 4 cx t4f backhoe loader service repair manual from 02254521 to 02274521Jcb 4 cx t4f backhoe loader service repair manual from 02254521 to 02274521
Jcb 4 cx t4f backhoe loader service repair manual from 02254521 to 02274521
 
Jcb 4 cx t4f backhoe loader service repair manual from 02254521 to 02274521
Jcb 4 cx t4f backhoe loader service repair manual from 02254521 to 02274521Jcb 4 cx t4f backhoe loader service repair manual from 02254521 to 02274521
Jcb 4 cx t4f backhoe loader service repair manual from 02254521 to 02274521
 
Jcb 3 cx t4f backhoe loader service repair manual from 02254521 to 02274521
Jcb 3 cx t4f backhoe loader service repair manual from 02254521 to 02274521Jcb 3 cx t4f backhoe loader service repair manual from 02254521 to 02274521
Jcb 3 cx t4f backhoe loader service repair manual from 02254521 to 02274521
 
Jcb 3 cx t4f backhoe loader service repair manual from 02254521 to 02274521
Jcb 3 cx t4f backhoe loader service repair manual from 02254521 to 02274521Jcb 3 cx t4f backhoe loader service repair manual from 02254521 to 02274521
Jcb 3 cx t4f backhoe loader service repair manual from 02254521 to 02274521
 
Jcb 3 cx t4f backhoe loader service repair manual from 02254521 to 02274521
Jcb 3 cx t4f backhoe loader service repair manual from 02254521 to 02274521Jcb 3 cx t4f backhoe loader service repair manual from 02254521 to 02274521
Jcb 3 cx t4f backhoe loader service repair manual from 02254521 to 02274521
 
Z (30)
Z (30)Z (30)
Z (30)
 
Instruction- 3 Core Polymeric (XLPE EPR) 6.6kV-7.2kV Heat Shrink Cable Termin...
Instruction- 3 Core Polymeric (XLPE EPR) 6.6kV-7.2kV Heat Shrink Cable Termin...Instruction- 3 Core Polymeric (XLPE EPR) 6.6kV-7.2kV Heat Shrink Cable Termin...
Instruction- 3 Core Polymeric (XLPE EPR) 6.6kV-7.2kV Heat Shrink Cable Termin...
 
Hyster d007 (h280 xl) forklift service repair manual
Hyster d007 (h280 xl) forklift service repair manualHyster d007 (h280 xl) forklift service repair manual
Hyster d007 (h280 xl) forklift service repair manual
 
Hyster d007 (h280 xl) forklift service repair manual
Hyster d007 (h280 xl) forklift service repair manualHyster d007 (h280 xl) forklift service repair manual
Hyster d007 (h280 xl) forklift service repair manual
 
Hyster d007 (h280 xl) forklift service repair manual
Hyster d007 (h280 xl) forklift service repair manualHyster d007 (h280 xl) forklift service repair manual
Hyster d007 (h280 xl) forklift service repair manual
 
Hyster d007 (h250 xl) forklift service repair manual
Hyster d007 (h250 xl) forklift service repair manualHyster d007 (h250 xl) forklift service repair manual
Hyster d007 (h250 xl) forklift service repair manual
 
Hyster d007 (h250 xl) forklift service repair manual
Hyster d007 (h250 xl) forklift service repair manualHyster d007 (h250 xl) forklift service repair manual
Hyster d007 (h250 xl) forklift service repair manual
 
Hyster d007 (h280 xl) forklift service repair manual
Hyster d007 (h280 xl) forklift service repair manualHyster d007 (h280 xl) forklift service repair manual
Hyster d007 (h280 xl) forklift service repair manual
 
Hyster d007 (h230 xl) forklift service repair manual
Hyster d007 (h230 xl) forklift service repair manualHyster d007 (h230 xl) forklift service repair manual
Hyster d007 (h230 xl) forklift service repair manual
 
Hyster d007 (h230 xl) forklift service repair manual
Hyster d007 (h230 xl) forklift service repair manualHyster d007 (h230 xl) forklift service repair manual
Hyster d007 (h230 xl) forklift service repair manual
 
Hyster d007 (h230 xl) forklift service repair manual
Hyster d007 (h230 xl) forklift service repair manualHyster d007 (h230 xl) forklift service repair manual
Hyster d007 (h230 xl) forklift service repair manual
 
Hyster d007 (h230 xl) forklift service repair manual
Hyster d007 (h230 xl) forklift service repair manualHyster d007 (h230 xl) forklift service repair manual
Hyster d007 (h230 xl) forklift service repair manual
 

Kürzlich hochgeladen

call Now 9811711561 Cash Payment乂 Call Girls in Dwarka Mor
call Now 9811711561 Cash Payment乂 Call Girls in Dwarka Morcall Now 9811711561 Cash Payment乂 Call Girls in Dwarka Mor
call Now 9811711561 Cash Payment乂 Call Girls in Dwarka Mor
vikas rana
 

Kürzlich hochgeladen (15)

(Aarini) Russian Call Girls Surat Call Now 8250077686 Surat Escorts 24x7
(Aarini) Russian Call Girls Surat Call Now 8250077686 Surat Escorts 24x7(Aarini) Russian Call Girls Surat Call Now 8250077686 Surat Escorts 24x7
(Aarini) Russian Call Girls Surat Call Now 8250077686 Surat Escorts 24x7
 
call Now 9811711561 Cash Payment乂 Call Girls in Dwarka Mor
call Now 9811711561 Cash Payment乂 Call Girls in Dwarka Morcall Now 9811711561 Cash Payment乂 Call Girls in Dwarka Mor
call Now 9811711561 Cash Payment乂 Call Girls in Dwarka Mor
 
2k Shots ≽ 9205541914 ≼ Call Girls In Dashrath Puri (Delhi)
2k Shots ≽ 9205541914 ≼ Call Girls In Dashrath Puri (Delhi)2k Shots ≽ 9205541914 ≼ Call Girls In Dashrath Puri (Delhi)
2k Shots ≽ 9205541914 ≼ Call Girls In Dashrath Puri (Delhi)
 
2k Shots ≽ 9205541914 ≼ Call Girls In Mukherjee Nagar (Delhi)
2k Shots ≽ 9205541914 ≼ Call Girls In Mukherjee Nagar (Delhi)2k Shots ≽ 9205541914 ≼ Call Girls In Mukherjee Nagar (Delhi)
2k Shots ≽ 9205541914 ≼ Call Girls In Mukherjee Nagar (Delhi)
 
8377087607 Full Enjoy @24/7-CLEAN-Call Girls In Chhatarpur,
8377087607 Full Enjoy @24/7-CLEAN-Call Girls In Chhatarpur,8377087607 Full Enjoy @24/7-CLEAN-Call Girls In Chhatarpur,
8377087607 Full Enjoy @24/7-CLEAN-Call Girls In Chhatarpur,
 
Top Rated Pune Call Girls Tingre Nagar ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Tingre Nagar ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Tingre Nagar ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Tingre Nagar ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
2k Shots ≽ 9205541914 ≼ Call Girls In Jasola (Delhi)
2k Shots ≽ 9205541914 ≼ Call Girls In Jasola (Delhi)2k Shots ≽ 9205541914 ≼ Call Girls In Jasola (Delhi)
2k Shots ≽ 9205541914 ≼ Call Girls In Jasola (Delhi)
 
The Selfspace Journal Preview by Mindbrush
The Selfspace Journal Preview by MindbrushThe Selfspace Journal Preview by Mindbrush
The Selfspace Journal Preview by Mindbrush
 
Pokemon Go... Unraveling the Conspiracy Theory
Pokemon Go... Unraveling the Conspiracy TheoryPokemon Go... Unraveling the Conspiracy Theory
Pokemon Go... Unraveling the Conspiracy Theory
 
9892124323, Call Girls in mumbai, Vashi Call Girls , Kurla Call girls
9892124323, Call Girls in mumbai, Vashi Call Girls , Kurla Call girls9892124323, Call Girls in mumbai, Vashi Call Girls , Kurla Call girls
9892124323, Call Girls in mumbai, Vashi Call Girls , Kurla Call girls
 
2k Shots ≽ 9205541914 ≼ Call Girls In Palam (Delhi)
2k Shots ≽ 9205541914 ≼ Call Girls In Palam (Delhi)2k Shots ≽ 9205541914 ≼ Call Girls In Palam (Delhi)
2k Shots ≽ 9205541914 ≼ Call Girls In Palam (Delhi)
 
WOMEN EMPOWERMENT women empowerment.pptx
WOMEN EMPOWERMENT women empowerment.pptxWOMEN EMPOWERMENT women empowerment.pptx
WOMEN EMPOWERMENT women empowerment.pptx
 
(Anamika) VIP Call Girls Navi Mumbai Call Now 8250077686 Navi Mumbai Escorts ...
(Anamika) VIP Call Girls Navi Mumbai Call Now 8250077686 Navi Mumbai Escorts ...(Anamika) VIP Call Girls Navi Mumbai Call Now 8250077686 Navi Mumbai Escorts ...
(Anamika) VIP Call Girls Navi Mumbai Call Now 8250077686 Navi Mumbai Escorts ...
 
LC_YouSaidYes_NewBelieverBookletDone.pdf
LC_YouSaidYes_NewBelieverBookletDone.pdfLC_YouSaidYes_NewBelieverBookletDone.pdf
LC_YouSaidYes_NewBelieverBookletDone.pdf
 
$ Love Spells^ 💎 (310) 882-6330 in West Virginia, WV | Psychic Reading Best B...
$ Love Spells^ 💎 (310) 882-6330 in West Virginia, WV | Psychic Reading Best B...$ Love Spells^ 💎 (310) 882-6330 in West Virginia, WV | Psychic Reading Best B...
$ Love Spells^ 💎 (310) 882-6330 in West Virginia, WV | Psychic Reading Best B...
 

CoFold Ultra Sliding Folding Door Gear Installation Instructions

  • 1. 1 CoFold Ultra 100 Fitting Instructions Diagram 1 for top hung exterior outward folding doors SYSTEM CAPACITY Maximum leaf height - 3300mm Maximum leaf weight - 100kg Maximum leaf width - 1000mm Maximum leaf thickness- 48-68mm TRACK FIXING NOT BY COASTAL * For thicker or thinner doors please contact technical@coastal-group.com. * If the hypotenues is more than the door width x 1.004 then a risk of camming exists. INSIDE Diagram 2 OUTSIDE JAMB CAP IN LINE WITH TRACK Diagram 3 Diagram 4 34 140 WHEN USED IN CONJUNCTION WITH ALUMINIUM SUPPORT CHANNEL 94SC THE OUTER CHANNEL DIMENSIONS BECOME 23H x 25W JAMB CAP IN LINE WITH TRACK JAMB CAP GASKET 52 39 212 ALTERNATIVE ALUMINIUM THRESHOLD ALTERNATIVE ALUMINIUM THRESHOLD SF94T94T BY COASTAL - COMPLETE WITH 94P WITH BY PCH - COMES COMES COMPLETE AND 94P AND ENDCAPS AND IS PREDRILLED FOR DRAINAGE ENDCAPS AND IS PREDRILLED FOR DRAINAGE
  • 2. 2 PREPARATION U1 2R 2L U2R U2L 3U4 78U9 10 - Pivot Assembly Set End Hanger Set Right Hand - for doors meeting a swing door and square-edged doors meeting End Hanger Set Left Hand - for doors meeting a swing door and square-edged doors meeting End Hanger Set Right Hand - for doors folding to the frame (i.e. 2 leaf, 4 leaf and 6 leaf) End Hanger Set Left Hand - for doors folding to the frame (i.e. 2 leaf, 4 leaf and 6 leaf) Hinge Set with Handle Intermediate Hanger Set Hinge Set Offset Outward Opening Rebated End Hanger Meeting Pivot Hinge required for Ultra security Face Fix Handle (Optional) Diagram 5 Diagram 6 U9 U1 U9 2L U9 U1 U9 U1 U4 U9 U1 U4 2R U4 U4 U1 U1 U9 U4 U9 U1 U1 U9 U1 U1 U9 U9 U1 U9 U4 U4 U9 U4 2L U9 U1 U1 U9 U4 U4 U1
  • 3. 3 Preparing the opening Preparing the door frame Ensure the opening is square and all load bearing areas are suitable for the weight of the system. Take particular care to ensure there is sufficient strength in the structure above the opening to take the concentrated weight of the doors, when in the open stacked position. The CoFold system provides +/3mm of horizontal and vertical adjustment. Use a plumb line to ensure that the centre line of the track and the centre line of the channel are offset by 19mm. = = Diagram 10 Preparing the door frame for U1, 2 & 9 face plates Ø10 DRILL FOR DRAINAGE AT 1000 CENTRES, 300 CENTRES FOR EXTREME CONDITIONS OR US ALUMINIUM THRESHOLD BY COASTAL Hinge Component 25 52 U9 Face Plate R6 54 36 54 70 50 Diagram 7 79 R2 0 22 50 U1 Face Plate = U9 Face Plate 22 26 40 27 27 OUTSIDE INSIDE Diagram 8 31 Frame Support Plate = U1 Face Plate 54 52 Diagram 9 For details on installation of the U9 please refer to the U9 fitting instructions 22 79 SILL Diagram 11
  • 4. 4 Preparing the door leaves Door leaf width calculation 1. Decide how many door leaves you want in the opening. 2. Add together all the 3mm clearances required between door leaves and the jambs (there will be one more than the number of door leaves). This is the total clearance figure. 3. Measure the finished opening width (W) and deduct from this the total clearance figure. 4. Divide this new figure (finished opening width minus total clearance) by the number of doors to produce the actual door width. (N.B. all doors with the Cofold system are the same width). For example: For a 4 door leaf system with a finished opening width of 2345mm the door leaf width would be 2345mm minus (5x3mm) divided by 4 (number of door leaves) = 582.5mm. Door leaf height calculation Leaf height = finished opening height (see diagram 7) minus 66mm. Diagram 12 PREPARING THE DOOR LEAF AT THE JAMB Door Seals Prepare the door leaves to accept the AQ63B seal. BETWEEN DOOR EDGES Diagram 13 ADD 10mm TO WIDTH OF EACH LEAF TO CREATE REBATE ADD 10mm TO WIDTH OF END HANGER LEAF FOR REBATE Meeting Doors Use the 8 set for 2+2 rebated timber door configurations. For all other configurations use 2L (left hand) or 2R (right hand) end hanger sets. For kit handing refer to diagram 6. Diagram 14
  • 5. 5 Door hardware positioning U9 KIT U1 KIT U4 KIT U2L Diagram 15 End door leaf Preparation 7.5mm check In for U1, U2, 2 and 8 Diagram 16
  • 6. 6 Door hardware attachment 23 Ø 3mm PILOT HOLES 14 50 22 100 18 50 CHECK IN FOR 9 Ø13mm 15mm deep 100 15 3 3 IMPORTANT Kit U1 BOTH SCREWS MUST BE FITTED UNDER THE COVERS OF ALL THE END HINGES 2 WHEEL ASSEMBLY SIDE THRUST BEARING FIXING SCREW (6 OFF) HANGER BODY COVER (SLIDE) WASHER HANGER BOLT Kit U2L (or U2R) Kit U4 Diagram 17
  • 7. 7 INSTALLATION 1. Ensure that you have all the required parts. Unpack the components and identify the parts. Lay the parts on the ground in the same configuration as they will be when installed. It is recommended that a light smear of general purpose grease is applied to all bolts prior to assembly. Diagram 18 2. Cut the track to the required length and pre-drill for fixings in accordance with diagram 18. Please note that the extra fixings are required where the doors stack together. TOP PIVOT SECURING BLOCK 3. Cut the channel to the required length and fit in the sill. Drill drainage holes (see diagram 1). PIVOT SECURING BLOCK HEX BOLTS 4. Remove all the wheel assemblies and pivot block from the hanger and pivot bolts, and disassemble top pivot block assembly. PIVOT CAM 5. Slide the wheel assemblies and track pivot block into the track in the correct order, orientation, and position and fix the track in position. Reassemble top pivot block assembly (see diagram 19). PIVOT ADJUSTER PIVOT CLAMP PLATE 6. Remove the bottom pivot assembly and guide roller assembly (see diagram 20). Disassemble the bottom pivot assembly. ADJUSTMENT LOCK OFF BOLTS Diagram 19 7. For installation, assemble leaves in pairs via the hinges. To improve the ease of installation pre-drill pilot holes for all hinge parts. Fit kits U1, 7,U4 and U9 (optional) to first pair of leaves. Please ensure all 4 screws are fixed per end hinge. 8. Screw the bottom anchor of the bottom pivot assembly to the base of the channel 11mm from the jamb. Please note, the screw nearest the end of the bottom anchor is closest to the jamb (see diagram 21). Reassemble the pivot assembly leaving the clamping screws loose (see diagram 25). 9. Suspend pairs of leaves by engaging top pivot and hanger bolts using 5mm Allen key supplied (see top of diagram 20). 10. Attach the bottom pivot and guide assembly to their respective hinges, adjust the bottom pivot side plates position so that it engages with the hinge bolt. Tighten pivot and guide strap bolts (see diagram 22). 11. Lift the next pair of leaves into position and support their weight by screwing the hanger strap bolt into the hanger wheel assembly and fixing the second and third leaves together. Diagram 20 JAMB CHANNEL 12. Continue this procedure until all leaves are fitted. BOTTOM ANCHOR Diagram 21 Diagram 22
  • 8. 8 ADJUSTMENT Height Adjustment (± 3mm) 1. Close leaves and adjust the door height to achieve an equal gap between the top of the leaves and the track (a 9mm gap is recommended). (see diagram 23). INSIDE LOCKING HANGER GRUB SCREW ON INSIDE OF DOOR 2. Once the adjustment is complete use the Allen key to tighten the locking hanger grub screw until secure. Lateral Adjustment 1. With the unit still in the closed position, slide the set of leaves towards the jamb to obtain the desired gap between the jamb and the pivot door. A gap of 3mm is recommended using the adjustment cam. Once in position tighten the clamp screws. (see diagram 25). U4 ILLUSTRATED. SAME METHOD OF ADJUSTMENT APPLIED TO U1, U2L, U2R AND 8. Diagram 23 2. Fold the leaves and adjust the bottom side plate using the Allen key provided so that the gap between the door and the jamb is the same over the full length of the door. 3. Tighten the two clamping screws to lock the side plate to the bottom anchor. 4. Once the pivot door is in the correct position insert and tighten the locking pivot grub screw from the inside position. (as shown in diagram 24) INSIDE CLAMP SCREW LOCKING PIVOT GRUB SCREW ON INSIDE OF DOOR CLAMP SCREW ADJUSTMENT CAM Locking Off Tighten grub screws on hangers, guides and pivots. Diagram 24 CARE AND MAINTENANCE To provide years of trouble free operation, it is recommended that the track is kept free from dirt and debris. Periodically replace the general purpose grease on all bolts. To prolong the appearance of the exposed hinge parts, it is recommended they are periodically washed with soap and water. Maintenance is required on all components including stainless steel to validate manufacturers warranty. For further maintenance details please refer to our website. TIGHTEN GRUB SCREW CLAMP SCREW ADJUSTMENT CAM CLAMP SCREW BOTTOM ANCHOR JAMB SIDE BOTTOM SIDE PLATE ADJUSTMENT Diagram 25
  • 9. 9 Aluminium Threshold Jamb Kit 51 25.5 25.5 21 94 25 Jamb Cap Jamb Cap Gasket 51 15 34 19 Threshold 94T 8 27 2.5 83 Pre-drilled 10mm diameter drainage holes at 300mm centres Endcap 2.5 51 140 51 25.5 25.5 23 27 8 15 34 Jamb Cap Jamb Cap 2.5 2.5 Jamb Cap Gasket Jamb Cap Gasket 51 140 21 94 25 52 39 Endcap Endcap 83 Jamb Cap Jamb Cap Gasket 52 (All dimensions in mm) 39 Endcap
  • 10. 10 U9 Intermediate Pivot Set 1. The CoFold U9 intermediate pivot set shown in Diagram 1, should be fitted to the pivot door mid way between the U1 top and bottom pivot assemblies. The U9 hinge must be positioned on the same centre line as the U1 top and bottom pivot hinge bodies. 5. Screw the frame support plate and the face plate onto the opening frame preparation, as shown in Diagrams 3 and 5. 2. Rout the door and drill the pilot holes as shown on Diagram 2. Fit the hinge body using the four screws provided. 7. Fit the U9 cover sleeve on to the U9 hinge body and drop the main strap bolt into position, as shown in Diagram 6. 3. Using Diagram 3, 4 and 6 locate the position of the threaded link arm receiving hole on the the opening frame. Starting from the central point of the threaded link arm receiving hole (as indicated on Diagrams 4 and 5) mark the location of the two screw holes for the face plate. Using the face plate as a template mark out the routing detail for the face plate and rout. 8. Screw the threaded link arm fully into the frame support plate. The centre of the threaded hole in the link arm should be positioned to receive the strap bolt. Screw the strap bolt in to the link arm until there is a 2mm gap between the head of the strap bolt and the hinge body, as shown in Diagram 6. 4. Drill the Ø12mm hole for the threaded link arm receiving hole and rout the opening frame to mount the Frame Support Plate flush if required (Diagram 3). 9. Adjust the U9 pivot set to ensure the clearance between the pivot door and the frame is uniform (Diagram 7). 6. Fit the pivot door into position using the U1 pivot set. Note: These fitting instructions should be used in conjunction with the CoFold Ultra Fitting Instructions 7.5 17.5 Main strap bolt U1 Hinge body 100 U9 Cover plate R17.5 U1 Cover sleeve Diagram 1. ole ph dee m 28m Diagram 2. Ø12 Optional 2.5 deep rebate for face plate Pilot holes 36 18 R12.5 R6 mm 2.5 dee 25mm p 26 41m m Opening frame INSIDE Door in closed position 28mm Hole centre to door face 8mm OUTSIDE Ø12 Threaded link arm receiving hole Diagram 3.
  • 11. Locating and drilling guide for U9 face place 22 Ø6 Face plate 53 Threaded link arm receiving hole 31 50 100 OUTSIDE INSIDE Frame support plate Diagram 5. Door shown in the open position 8mm HALF DOOR HEIGHT +79mm Face plate 2mm gap 53 Threaded link arm receiving hole Main strap bolt Line from bottom of the hinge body 31 20mm 22 Frame support plate Threaded link arm Frame support plate Screw the frame support plate and the face plate onto the opening frame preparation, as shown in Diagrams 3 and 4. 100 Diagram 6. Door shown in the open position 50 2mm gap Adjustment: 3mm in to the frame 6mm out to the frame Diagram 4. Diagram 7.
  • 12. 11 Outward Opening Flush Bolt For top hung exterior folding doors. For use in conjunction with standard outward opening fitting instructions. Follow routing instructions for the bolt keep and flush bolt length to be fitted, fit both with the screws supplied. Suitable pilot holes for screws are recommended. Routing detail for 450mm Top Flush Bolt Routing detail for 600mm Top Flush Bolt HEAD BOARD LINTEL 12.5 FASCIA Routing detail for 190mm Top Flush Bolt 18 Routing detail for 190mm Bottom Flush Bolt PLATE 600 450 580 190 430 170 30 INSIDE 4 190 Enlarged detail showing the sectional routing dimensions for all 3 bolt sizes 40 OUTSIDE 170 TOP FLUSH BOLT 22 17 Note: Routing detail is the same for both locking and non-locking flush bolts. Door height Recommended Bolt length for top of door Recommended Bolt length for bottom of door Upto 2200mm 190mm 190mm Upto 2450mm 450mm 190mm Over 2450mm 600mm 190mm BOTTOM FLUSH BOLT Routing detail for bolt keep sockets Top Flush Bolt into Head Bottom Flush Bolt into Sill Fixing screw centres 40 Ø18 PLATE Ø18 10 12.5 4 10 12.5 40 10 40 30 25 12 KEEP LINER SILL REBATE 65 40mm fixing screw centres - Use fixing plate as drilling template SILL 18 12.5 Section through door showing flush bolt rebate detail (All dimensions in mm) Coastal Joinery Hardware, Global House, Bojea Industrial Estate, Trethowel, St Austell, Cornwall, PL25 5RJ. Tel: 01726 871726 Fax: 01726 871731 Email: sales@coastal-group.com Part No: 220946 Issue 8 - January 2013
  • 13. ENQUIRY FORM FOR BI-FOLD DOORS Please enter your address here: Your Details/FAO Address Telephone: Fax: PROJECT TITLE: Email: LOCATION: SPECIFICATION SHEET System Capacity: 1. Opening Size: BI-FOLD DOORS Maximum Leaf Height: 3300mm Maximum Leaf Width: 1000mm Maximum Leaf Weight: 100kg Leaf Thickness: 35mm-68mm mm Height: 2. Door Configuration: Number of leaves sliding (viewed from the outside) Width: mm RH LH 3. Outward Opening: Due to weathering, outward opening Is highly recomended. Yes No 4. Locking None Espagnolette Sash lock 5. Finish Satin Stainless Steel PVD Brass Polished Stainless Steel 6. System CoFold CoFold Ultra (High Security) 7. Gear Types Choice only applies to CoFold system & not the CoFold Ultra. Mortice Non Mortice 8. Weatherseal Required: None Brown White PRE-TENSION Coastal Group | T 01726 871726 | F 01726 871731 Email sales@coastal-group.com | Visit www.coastal-group.com