SlideShare ist ein Scribd-Unternehmen logo
1 von 44
EHV TRANSMISSION LINE
Design Methodology
1
Dr. A.K.TIWARI
ashokktiwari@gmail.com
Dr. A.K.TIWARI ashokktiwari@gmail.com
Component of Transmission Line
2
o Conductor
o Earth wire
o Insulator
o Transmission Tower
o Wave trap and other
hardware(Clamp, Spacer,
Vibration dampers,
connectors etc.
Dr. A.K.TIWARI ashokktiwari@gmail.com
Design Methodology
3
 Gather preliminary line design data and available climatic data
 Select reliability level in terms of return period of design
 Calculate climatic loading on components
 Calculate loads corresponding to security requirements (failure containment)
 Calculate loads related to safety during construction and maintenance
 Select appropriate correction factors, if applicable, to the design components such
as use factor, strength factors related to numbers of components, strength
coordination, quality control, and the characteristic strength.
 Design the components for the above loads and strength.
Dr. A.K.TIWARI ashokktiwari@gmail.com
Reliability Levels
4
 Reliability Level ≥1(One)
 Higher the reliability level means higher safety factor and
ultimately more cost.
Dr. A.K.TIWARI ashokktiwari@gmail.com
Selection of Transmission Voltage
5
 Standard Voltage - 66,110,132, 220, 400 KV
 Tolerances - ±10% up to 220 KV & ±5% for 400 KV
 Selection Criterion of Economic Voltage –
 Quantum of power to be evacuated
 Length of line
 Voltage regulation
 Power loss in Transmission
 Initial and operating cost
 Present and future voltage in neighborhood
Dr. A.K.TIWARI ashokktiwari@gmail.com
6
Economic Voltage of Transmission of Power –
E = Transmission voltage (KV) (L-L).
L = Distance of transmission line in KM
KVA=Power to be transferred
1506.1
5.5
KVAL
E 
Dr. A.K.TIWARI ashokktiwari@gmail.com
Types of Towers
7
 Type A Tower (Tangent Tower with suspension string)
o Used on straight runs and up to 2° line diversion
 Type B Tower (Small Angle Tower with tension string)
o Used for line deviation from 2° to 15°
 Type C Tower (Medium Angle Tower with tension string ).
o Used for line deviation from 15° to 30°.
 Type D Tower (Large angle tower with tension string)
o Used for line deviation from 30° to 60°
 Type E Tower (Dead End Tower with tension string)
o Used for line termination & starting
 Special tower-
 Suspension Tower (Span ≈ 1000 m)
o Used for River crossing, Mountain crossing etc.
 Transposition Tower
o Used for transposition of tower
Dr. A.K.TIWARI ashokktiwari@gmail.com
8
Different Types of Towers
Dr. A.K.TIWARI ashokktiwari@gmail.com
Selection of Tower Structure
9
 Single circuit Tower/ double circuit Tower
 Length of the insulator assembly
 Minimum clearances to be maintained between ground
conductors, and between conductors and tower
 Location of ground wire/wires with respect to the outermost
conductor
 Mid-span clearance required from considerations of the dynamic
behavior of conductors and lightning protection of the line
 Minimum clearance of the lowest conductor above ground level
Dr. A.K.TIWARI ashokktiwari@gmail.com
Tower Design
10
 Tower height
 Base width
 Top damper width
 Cross arms length
Fig. Typical 765 KV Tower Structure
Dr. A.K.TIWARI ashokktiwari@gmail.com
Height of Tower Structure
11
4321 hhhhH 
Height of tower is determine by-
h1=Minimum permissible ground clearance
h2=Maximum sag
h3=Vertical spacing between conductors
h4=Vertical clearance between earthwire and
top conductor
Dr. A.K.TIWARI ashokktiwari@gmail.com
12
Determination of Base Width
The base width(at the concrete level) is the distance between the
centre of gravity at one corner leg and the centre of gravity of the
adjacent corner leg.
 A particular base width which gives the minimum total cost of the tower
and
foundations.
 The ratio of base width to total tower height for most towers is
generally about one-fifth to one-tenth.
12
Ryle
Formula
Dr. A.K.TIWARI ashokktiwari@gmail.com
Spacing and Clearances
13
Ground Clearances
KCL *305.0182.5 





 

33
33V
KWhere-
S.No. Voltage level Ground
clearance(m)
1. ≤33 KV 5.20
2. 66 KV 5.49
3. 132KV 6.10
4. 220 KV 7.01
5. 400 KV 8.84
Minimum permissible ground clearance as per IE Rules, 1956,Rule 77(4)
Dr. A.K.TIWARI ashokktiwari@gmail.com
14
Clearance for Power Line Crossings
 Crossing over rivers:
• 3.05m above maximum flood level.
 Crossing over telecommunication lines
Minimum clearances between the conductors of a power
line and telecommunication wires are-
Voltage Level Minimum
Clearance(mm)
≤33 KV 2440
66KV 2440
132 KV 2740
220 KV 3050
400 KV 4880
Dr. A.K.TIWARI ashokktiwari@gmail.com
15
 Power line Crossing over railway tracks
under maximum sag condition minimum clearance over rail level
stipulated in the regulations for Electrical Crossings of Railway Tracks,
1963
Table. For un-electrified tracks or tracks electrified on 1,500 volts D.C.
system
System Voltage Level Broad Gauge Meter & Narrow
Gauge
Inside station
limits(m)
Out side
station
limits(m)
Inside
station
limits(m)
Out side
station
limits(m)
≤66 KV 10.3 7.9 9.1 6.7
132 KV 10.9 8.5 9.8 7.3
220 KV 11.2 8.8 10.0 7.6
400 KV 13.6 11.2 12.4 10.0
Dr. A.K.TIWARI ashokktiwari@gmail.com
16
Table. Tracks electrified on 25 kV A.C. system
System Voltage Level Broad Gauge
Inside station
limits(m)
Out side
station
limits(m)
≤ 66 KV 10.3 7.9
132 KV 10.9 8.5
220 KV 11.2 8.8
400 KV 13.6 11.2
 Power line Crossing another Power line
System Voltage Level Clearance(m)
≤ 66 KV 2.40
132 KV 2.75
220KV 4.55
400 KV 6.00
Dr. A.K.TIWARI ashokktiwari@gmail.com
17
 Spacing Between Conductor(Phases)
1) Mecomb's formula
1) VDE formula
S
W
D
VcmSpacing 010.43048.0)( * 
Where-
V= Voltage of system in KV
D= Diameter of Conductor in cm
S= Sag in cm
W= weight of conductor in Kg/m
2000
5.7)(
2
VScmSpacing  Where-
V= Voltage of system in KV
S= Sag in cmDr. A.K.TIWARI ashokktiwari@gmail.com
18
 Still's formula




8.27
2
*814.108.5)(
l
VcmSpacing
Where-
l = Average span length(m)
 NESC formula
2
681.3*762.0)(
L
SVcmSpacing 
Where-
V= Voltage of system in KV
S= Sag in cm
L= Length of insulator string in cm
Dr. A.K.TIWARI ashokktiwari@gmail.com
19
 Swedish formula
EScmSpacing *7.05.6)( 
Where-
E= Line Voltage in KV
S= Sag in cm
 French formula
Where-
E= Line Voltage in KV
S= Sag in cm
L= length of insulating string(cm)Dr. A.K.TIWARI ashokktiwari@gmail.com
20
 Offset of conductors (under ice-loading conditions)
Sleet Jump:
The jump of the conductor, resulting from ice dropping off
one span of an ice-covered line, has been the cause of many serious
outages on long-span lines where conductors are arranged in the same
vertical plane.
Offset in cm = 60 + Span in cm / 400
Dr. A.K.TIWARI ashokktiwari@gmail.com
Clearances b/n Conductors
21
SYSTEM
VOLTAG
E
TYPE OF
TOWER
Vertical spacing
b/n
conductors(mm)
Horizontal spacing
b/n
conductors(mm)
66 kV
SINGLE
CIRCUIT
A(0-2°) 1080 4040
B(2-30°) 1080 4270
C(30-60°) 1220 4880
DOUBLE
CIRCUIT
A(0-2°) 2170 4270
B(2-30°) 2060 4880
C(30-60°) 2440 6000
132 KV
SINGLE
CIRCUIT
A(0-2°) 4200 7140
B(2-30°) 4200 6290
C(30-60°) 4200 7150
D(30-60°) 4200 8820
DOUBLE
CIRCUIT
A(0-2°) 3965 7020
B(2-15°) 3965 7320
C(15-30°) 3965 7320
D(30-60°) 4270 8540
Dr. A.K.TIWARI ashokktiwari@gmail.com
22
220 kV
SINGLE
CIRCUIT
A(0-2°) 5200 8500
B(2-15°) 5250 10500
C(15-30°) 6700 12600
D(30-60°) 7800 14000
DOUBLE
CIRCUIT
A(0-2°) 5200 9900
B(2-15°) 5200 10100
C(15-30°) 5200 10500
D(30-60°) 6750 12600
400 KV
SINGLE
CIRCUIT
A(0-2°) 7800 12760
B(2-15°) 7800 12760
C(15-30°) 7800 14000
D(30-60°) 8100 16200
Dr. A.K.TIWARI ashokktiwari@gmail.com
Sag and Tension Calculation
23
 Parabolic formula:  Catenary formula:
Span >300 mSag & TensionSpan ≤300 m
Dr. A.K.TIWARI ashokktiwari@gmail.com
Types of Conductors
24
 ACSR Conductor(Aluminium Conductor Steel Reinforced)
 AAC(All Aluminium Conductor)
 AAAC(All Alloy Aluminium Conductor)
Dr. A.K.TIWARI ashokktiwari@gmail.com
Selection of Conductor Size
25
Mechanical Requirement
 Tensile Strength(For Tension)
 Strain Strength(For Vibration)
Use vibration damper for vibration control.
 Mechanical Requirement
 Electrical Requirement
Dr. A.K.TIWARI ashokktiwari@gmail.com
Electrical Requirement
26
o Continuous current rating.
o Short time current carrying rating.
o Voltage drop
o Power loss
o Minimum dia to avoid corona
o Length of line
o Charging current
Dr. A.K.TIWARI ashokktiwari@gmail.com
Continuous Current Rating.
27
21
12
12
*
*
*
Rt
Rt
II



I1=current rating for temp rise ∆t1
I2=current rating required to produced temp rise ∆t2
R1= conductor resistance at conductor total temp T1(say 75°C)
R2= conductor resistance at required conductor total temp T2
Dr. A.K.TIWARI ashokktiwari@gmail.com
Short Time Rating
28
According to short time rating conductor size is given by-
Where A=area of conductor(mm2)
IF= fault current(KA)
t= fault duration(1 sec.)
tIA F **58.7
Dr. A.K.TIWARI ashokktiwari@gmail.com
Corona
29
Visual corona voltage in fair weather condition is given
by-
 V0= corona starting voltage, KV(rms)
 r= radius of conductor in cm
 D= GMD equivalent spacing b/n conductors in cm
 m= roughness factor
= 1.0 for clean smooth conductor
=0.85 for stranded conductor





 
 r
D
n
r
r
mV log
)3.01(
1.210

Dr. A.K.TIWARI ashokktiwari@gmail.com
30
Voltage gradient at the surface of conductor at operating voltage-







r
D
Log
V
n
g 3
0
Corona discharge form at the surface of conductor if g0≥ corona
starting gradient i.e.
r
rmg
)3.01(
1.21
0

  
(rms kv/cm)
 Conductor size will be so chosen that normal gradient of
conductor should not exceed 17.5 KV/cm.
 For EHV transmission line 400KV and above use bundle
conductor from point view of corona.
Dr. A.K.TIWARI ashokktiwari@gmail.com
Optimization of Conductor
31
When more than one conductor satisfied the requirement of current capacity and corona performance than study required for conductor optimization
C= cost in Rs. Per Km of 3-ø line
A= Annual fixed charge on capital in Rs./ Rupees of capital cost(interest 14%+depreciation 5%+ operation and maintenance cost 1-3%)
Pm= Maximum demand(KW)
V= Line voltage(KV)
R= Resistance of conductor/Km/phase
Cosø=Power factor
H= Loss load factor
= 0.3[LF+0.7(LF)2] (For normal load variation)
= 0.2[LF+0.8(LF)2] (For more uniform load variation)
Annual energy generated
8760*maximum demand
LF=
L= Energy charge in Rs/Kwh
M= Demand charge in Rs/Kwh
Dr. A.K.TIWARI ashokktiwari@gmail.com
32
Total annual fixed charge (C1)=C*A
Total annual running charges(C2)= (P2
m*R*J)/(V2 Cos2 ø)
Total charges(T)= C*A + (P2
m*R*J)/(V2 Cos2 ø)
Conductor giving minimum T will be optimum
Cost/KW/Km will be minimum i.e. T/Pm will be minimum when
 
R
VP
ACm

2/1
cos
 
1000
876012
2
HLM
J
LF 

Dr. A.K.TIWARI ashokktiwari@gmail.com
Some Others Consideration in
Conductor Selection
33
 AL/St Area (For longer span & less sag with economic consider)
 River crossing (Span≥1000 m use AAAC conductor because of more
tendency to vibration and twisting)
 Weight/ Dia (Less Weight/Dia ratio conductor swing more hence require longer
cross arms witch increase torsional load. Consider optimum value W/d in design.)
Dr. A.K.TIWARI ashokktiwari@gmail.com
INSULATOR
34
Insulator are required to support the line conductor and provide
clearance from ground and structure.
 Insulator material-
 High grade Electrical Porcelain
 Toughened Glass
 Fiber Glass
 Choice of insulator material is govern by availability, price and ease of
maintenance.
 Porcelain insulator are largely used in India.
Dr. A.K.TIWARI ashokktiwari@gmail.com
35
Type of Insulator-
 Disc Type
 Strut Type
 Disc type Insulator
 It consist of central suitable shaped porcelain/ glass body like a
disc with an metal clamp on one side and metal ball pin on other
side
 Cap is made of malleable cost iron and the ball pins is of forged
steel.
Dr. A.K.TIWARI ashokktiwari@gmail.com
 Strut Type Insulator
36
 It consist of several insulator disc cemented altogether without
any link.
 It is rigid and can take both tension and compression load.
 These are used for holding the conductor out of way of
structure.
 Long Rod Insulator
Dr. A.K.TIWARI ashokktiwari@gmail.com
INSULATOR STRING
37
 Disc insulator are joint by their ball pins and
socket in their caps to form string.
 No of insulator disc is decided by system
voltage, switching and lighting over voltage
amplitude and pollution level.
 Insulator string can be used either suspension
or tension.
 Two suspension string in parallel used at
railways, road and river crossing as statutory
requirement.
 Swing of suspension string due to wind has to
be taken into consider.
Fig. single string
Fig. Double string
Dr. A.K.TIWARI ashokktiwari@gmail.com
Earth Wire
38
Earth wire provided above the phase conductor across the line and
grounded at every tower.
o It shield the line conductor from direct strokes
o Reduces voltage stress across the insulating strings during lightning strokes
Design criterion:
 Shield angle
 25°-30° up to 220 KV
 20° for 400 KV and above
 Earth wire should be adequate to carry very short duration lightning
surge current of 100 KA without excessive over heating
 Duration should be consider as 200 µ-sec
 Safe temp rise limited to 300°C
Dr. A.K.TIWARI ashokktiwari@gmail.com
39
tIA  5
A= Area(in mm2) of cu conductor
I =current in KA
t = Time insecond
Area of Steel Wire = 3*A(cu mm2)
 From mechanical consideration, size become higher than required
for current carrying rating.
 For EHV line it is suggested as 70 mm2 (7/3.66 mm).
 ACSR is used as earth wire (12/3.0 mm AL+7/3.0 mm steel) in
consideration of corrosion and resistance.
Dr. A.K.TIWARI ashokktiwari@gmail.com
40
System voltage Mid span clearance(m)
≤ 66 KV 3.0
110 KV 4.5
132 KV 6.1
220 KV 8.5
400 KV 9.0
Mid span clearance:
Direct distance b/n earth wire and top power conductor.
As per IS 5613 following value of mid span clearance should be
considered
Dr. A.K.TIWARI ashokktiwari@gmail.com
Tower Grounding
41
Used to reduce earth wire potential and stress on insulators at the
time of stroke and also for safety
 Tower footing resistance will be 10Ω and should not be more than
20 Ω under any condition throughout the year.
 Earth resistance depend upon soil resistivity(general 100 Ω-m)
Dr. A.K.TIWARI ashokktiwari@gmail.com
Method of Tower Grounding
42
 Buried Conductor
One or more conductor are connected to tower lags and buried in back
filled of tower foundation.
o Used where soil resistivity is low
 Counterpoise Wire
A length of wire/ Strip of 50 m is buried horizontally at depth of 0.5 m bellow
ground. This wire is connected to tower lags.
o Used when earth resistance is very high and soil conductivity is mostly
confined to upper layer)
 Rod Pipe
Pipe/Rod of 3 to 4 m is driven into ground near the tower and top of rod is
connected to tower by suitable wire/strip
o Used where ground conductivity increase with depth
 Treated Earth Pits
Pipe/Rod of 3 to 4 m are buried in treated earth pits and top of rod is
connected to tower by suitable wire/strip.
o Used in very high resistivity near tower
Dr. A.K.TIWARI ashokktiwari@gmail.com
Reference Standards
43
 IS-398
 IS-802
 IS 3853
 IS 4091
 IS 5613
 CBIP
 IE Rules,
Specification of Aluminium Conductor for Over Head
Transmission Line(ACSR)
Code of Practice for use of Structural Steel in over head
Transmission Line Tower
Specification of Aluminium Steel Core Wire for Aluminium
Conductor
Code Practice for Design and Construction of Foundation of
Transmission Line Tower and Pole
Specification of Design, Installation and Maintenance of Line
above 11 KV and up to 220 KV
Manual on Transmission Line Tower, Technical Report N0. 9,
March 1977
Dr. A.K.TIWARI ashokktiwari@gmail.com
Thank You….
44 Dr. A.K.TIWARI ashokktiwari@gmail.com

Weitere ähnliche Inhalte

Was ist angesagt?

SAG TENSION CALCULATION METHODS FOR OVERHEAD LINES
SAG TENSION CALCULATION METHODS FOR OVERHEAD LINESSAG TENSION CALCULATION METHODS FOR OVERHEAD LINES
SAG TENSION CALCULATION METHODS FOR OVERHEAD LINESPower System Operation
 
ABB - TRANSFORMERS-PROTECTION-COURSE (2001)
ABB - TRANSFORMERS-PROTECTION-COURSE (2001)ABB - TRANSFORMERS-PROTECTION-COURSE (2001)
ABB - TRANSFORMERS-PROTECTION-COURSE (2001)J. FR
 
Training report by shubham sachan
Training report by shubham sachanTraining report by shubham sachan
Training report by shubham sachanShubham Sachan
 
Transmission and distribution line design final
Transmission and distribution line design finalTransmission and distribution line design final
Transmission and distribution line design finalBhanu Poudyal
 
Principles of Cable Selection
Principles of Cable SelectionPrinciples of Cable Selection
Principles of Cable SelectionLeonardo ENERGY
 
cable ampacity calculations- IEC
cable ampacity calculations- IECcable ampacity calculations- IEC
cable ampacity calculations- IECJoe Khan
 
transmission line
transmission line transmission line
transmission line singh1515
 
SAG-TENSION CALCULATION METHODS FOR OVERHEAD LINES
SAG-TENSION CALCULATION METHODS FOR OVERHEAD LINESSAG-TENSION CALCULATION METHODS FOR OVERHEAD LINES
SAG-TENSION CALCULATION METHODS FOR OVERHEAD LINESPower System Operation
 
Insulation coordination.
Insulation coordination.Insulation coordination.
Insulation coordination.Parth Patel
 
33/11 kV substation (u.p.p.c.l.)
33/11 kV substation (u.p.p.c.l.)33/11 kV substation (u.p.p.c.l.)
33/11 kV substation (u.p.p.c.l.)Prateek Agarwal
 
Overhead line work ppt
Overhead line work pptOverhead line work ppt
Overhead line work pptDemsew Mitiku
 
High voltage technology & insulation testing
High voltage technology & insulation testingHigh voltage technology & insulation testing
High voltage technology & insulation testingZeeshan Akhtar
 
Ipsa mv relay co-ordiantion shaik adam
Ipsa  mv relay  co-ordiantion shaik adamIpsa  mv relay  co-ordiantion shaik adam
Ipsa mv relay co-ordiantion shaik adamShaik Abdullah Adam
 
Exp 7 for Impulse Voltage Breakdown.pdf
Exp 7 for Impulse Voltage Breakdown.pdfExp 7 for Impulse Voltage Breakdown.pdf
Exp 7 for Impulse Voltage Breakdown.pdfvenkataraoHanumanthu1
 
OPGW Optical Ground Wire
OPGW Optical Ground WireOPGW Optical Ground Wire
OPGW Optical Ground WireSourabh sharma
 

Was ist angesagt? (20)

SAG TENSION CALCULATION METHODS FOR OVERHEAD LINES
SAG TENSION CALCULATION METHODS FOR OVERHEAD LINESSAG TENSION CALCULATION METHODS FOR OVERHEAD LINES
SAG TENSION CALCULATION METHODS FOR OVERHEAD LINES
 
ABB - TRANSFORMERS-PROTECTION-COURSE (2001)
ABB - TRANSFORMERS-PROTECTION-COURSE (2001)ABB - TRANSFORMERS-PROTECTION-COURSE (2001)
ABB - TRANSFORMERS-PROTECTION-COURSE (2001)
 
Training report by shubham sachan
Training report by shubham sachanTraining report by shubham sachan
Training report by shubham sachan
 
Chapter 09 - Measurement of Partial Discharge
Chapter 09 - Measurement of Partial DischargeChapter 09 - Measurement of Partial Discharge
Chapter 09 - Measurement of Partial Discharge
 
Transmission and distribution line design final
Transmission and distribution line design finalTransmission and distribution line design final
Transmission and distribution line design final
 
Principles of Cable Selection
Principles of Cable SelectionPrinciples of Cable Selection
Principles of Cable Selection
 
cable ampacity calculations- IEC
cable ampacity calculations- IECcable ampacity calculations- IEC
cable ampacity calculations- IEC
 
Transformer tests
Transformer testsTransformer tests
Transformer tests
 
transmission line
transmission line transmission line
transmission line
 
SAG-TENSION CALCULATION METHODS FOR OVERHEAD LINES
SAG-TENSION CALCULATION METHODS FOR OVERHEAD LINESSAG-TENSION CALCULATION METHODS FOR OVERHEAD LINES
SAG-TENSION CALCULATION METHODS FOR OVERHEAD LINES
 
Insulation coordination.
Insulation coordination.Insulation coordination.
Insulation coordination.
 
Clearences
ClearencesClearences
Clearences
 
33/11 kV substation (u.p.p.c.l.)
33/11 kV substation (u.p.p.c.l.)33/11 kV substation (u.p.p.c.l.)
33/11 kV substation (u.p.p.c.l.)
 
Overhead line work ppt
Overhead line work pptOverhead line work ppt
Overhead line work ppt
 
High voltage technology & insulation testing
High voltage technology & insulation testingHigh voltage technology & insulation testing
High voltage technology & insulation testing
 
Power quality.ppt
Power quality.pptPower quality.ppt
Power quality.ppt
 
Ipsa mv relay co-ordiantion shaik adam
Ipsa  mv relay  co-ordiantion shaik adamIpsa  mv relay  co-ordiantion shaik adam
Ipsa mv relay co-ordiantion shaik adam
 
Voltage Drop Calculation.pdf
Voltage Drop Calculation.pdfVoltage Drop Calculation.pdf
Voltage Drop Calculation.pdf
 
Exp 7 for Impulse Voltage Breakdown.pdf
Exp 7 for Impulse Voltage Breakdown.pdfExp 7 for Impulse Voltage Breakdown.pdf
Exp 7 for Impulse Voltage Breakdown.pdf
 
OPGW Optical Ground Wire
OPGW Optical Ground WireOPGW Optical Ground Wire
OPGW Optical Ground Wire
 

Andere mochten auch

Ppt of ehv ac transmission
Ppt of ehv ac transmissionPpt of ehv ac transmission
Ppt of ehv ac transmissionSumit Kumar
 
Construction EHV Transmission Line
Construction EHV Transmission LineConstruction EHV Transmission Line
Construction EHV Transmission LineSURESH GOPAL
 
Generation shift factor and line outage factor
Generation shift factor and line outage factorGeneration shift factor and line outage factor
Generation shift factor and line outage factorViren Pandya
 
Contingency analysis
Contingency analysisContingency analysis
Contingency analysisSajan Sahu
 
Electrical transmission line
Electrical transmission lineElectrical transmission line
Electrical transmission lineDhananjay Jha
 
Hybrid applications — your product on multiple platforms
Hybrid applications — your product on multiple platformsHybrid applications — your product on multiple platforms
Hybrid applications — your product on multiple platformsAntti Salonen
 
Testing of c.b.(hk & hr) nihal
Testing of c.b.(hk & hr) nihalTesting of c.b.(hk & hr) nihal
Testing of c.b.(hk & hr) nihalNihal Shiroya
 
Energy management and energy audit in rupandehi
Energy management and energy audit in rupandehiEnergy management and energy audit in rupandehi
Energy management and energy audit in rupandehiMohammad Abul Hasan Khan
 
Schering bridge
Schering bridge Schering bridge
Schering bridge mihir jain
 
Indian Power Sector- A Study of Effectiveness of Past Power Sector Reforms an...
Indian Power Sector- A Study of Effectiveness of Past Power Sector Reforms an...Indian Power Sector- A Study of Effectiveness of Past Power Sector Reforms an...
Indian Power Sector- A Study of Effectiveness of Past Power Sector Reforms an...Anshuman Batra
 
High voltage engineering
High voltage engineeringHigh voltage engineering
High voltage engineeringHari Kumar
 
Energy management and energy audit consultancy
Energy management and energy audit consultancyEnergy management and energy audit consultancy
Energy management and energy audit consultancyVISCAR INDUSTRIAL CAPACITY
 
1200 kv ultra high voltage transmission system by prannaya kumar giri & b...
1200 kv  ultra high voltage transmission system  by   prannaya kumar giri & b...1200 kv  ultra high voltage transmission system  by   prannaya kumar giri & b...
1200 kv ultra high voltage transmission system by prannaya kumar giri & b...Prannay Kumar Giri
 

Andere mochten auch (19)

Ppt of ehv ac transmission
Ppt of ehv ac transmissionPpt of ehv ac transmission
Ppt of ehv ac transmission
 
Construction EHV Transmission Line
Construction EHV Transmission LineConstruction EHV Transmission Line
Construction EHV Transmission Line
 
Ehv ac transmission line
Ehv ac transmission lineEhv ac transmission line
Ehv ac transmission line
 
Tl pre-foundation
Tl pre-foundationTl pre-foundation
Tl pre-foundation
 
Generation shift factor and line outage factor
Generation shift factor and line outage factorGeneration shift factor and line outage factor
Generation shift factor and line outage factor
 
Contingency analysis
Contingency analysisContingency analysis
Contingency analysis
 
Transmission Line
Transmission LineTransmission Line
Transmission Line
 
Earthing
EarthingEarthing
Earthing
 
Electrical transmission line
Electrical transmission lineElectrical transmission line
Electrical transmission line
 
Hybrid applications — your product on multiple platforms
Hybrid applications — your product on multiple platformsHybrid applications — your product on multiple platforms
Hybrid applications — your product on multiple platforms
 
Testing of c.b.(hk & hr) nihal
Testing of c.b.(hk & hr) nihalTesting of c.b.(hk & hr) nihal
Testing of c.b.(hk & hr) nihal
 
Energy management and energy audit in rupandehi
Energy management and energy audit in rupandehiEnergy management and energy audit in rupandehi
Energy management and energy audit in rupandehi
 
Schering bridge
Schering bridge Schering bridge
Schering bridge
 
EHV AC
EHV ACEHV AC
EHV AC
 
Indian Power Sector- A Study of Effectiveness of Past Power Sector Reforms an...
Indian Power Sector- A Study of Effectiveness of Past Power Sector Reforms an...Indian Power Sector- A Study of Effectiveness of Past Power Sector Reforms an...
Indian Power Sector- A Study of Effectiveness of Past Power Sector Reforms an...
 
High voltage engineering
High voltage engineeringHigh voltage engineering
High voltage engineering
 
Energy management and energy audit consultancy
Energy management and energy audit consultancyEnergy management and energy audit consultancy
Energy management and energy audit consultancy
 
1200 kv ultra high voltage transmission system by prannaya kumar giri & b...
1200 kv  ultra high voltage transmission system  by   prannaya kumar giri & b...1200 kv  ultra high voltage transmission system  by   prannaya kumar giri & b...
1200 kv ultra high voltage transmission system by prannaya kumar giri & b...
 
Heat Exchangers
Heat ExchangersHeat Exchangers
Heat Exchangers
 

Ähnlich wie Akt tl design01

Transmission Line presentation______.ppt
Transmission Line presentation______.pptTransmission Line presentation______.ppt
Transmission Line presentation______.pptssuserc3b807
 
Concept of energy transmission & distribution
Concept of energy transmission & distribution Concept of energy transmission & distribution
Concept of energy transmission & distribution ZunAib Ali
 
Earthing and bonding - Power cables
Earthing and bonding - Power cablesEarthing and bonding - Power cables
Earthing and bonding - Power cablesLeonardo ENERGY
 
A mini project on the transmission tower
A mini project on the transmission towerA mini project on the transmission tower
A mini project on the transmission towernaqeeb04
 
Principles of Cable Sizing
Principles of Cable SizingPrinciples of Cable Sizing
Principles of Cable SizingLeonardo ENERGY
 
Jmv presentation national desaster management authority
Jmv  presentation  national desaster management authorityJmv  presentation  national desaster management authority
Jmv presentation national desaster management authorityMahesh Chandra Manav
 
presentation national desaster management and JMV LPS Ltd
 presentation  national desaster management  and JMV LPS Ltd presentation  national desaster management  and JMV LPS Ltd
presentation national desaster management and JMV LPS LtdMahesh Chandra Manav
 
Jmv presentation national desaster management authority
Jmv  presentation  national desaster management authorityJmv  presentation  national desaster management authority
Jmv presentation national desaster management authorityMahesh Chandra Manav
 
IRJET- Comparative Study of Dynamic Analysis of Transmission Towers
IRJET- Comparative Study of Dynamic Analysis of Transmission TowersIRJET- Comparative Study of Dynamic Analysis of Transmission Towers
IRJET- Comparative Study of Dynamic Analysis of Transmission TowersIRJET Journal
 
presentation defence and police and JMV LPS LTD
 presentation  defence and police  and JMV LPS LTD presentation  defence and police  and JMV LPS LTD
presentation defence and police and JMV LPS LTDMahesh Chandra Manav
 
Le.h insulation coordination - Digsilent
Le.h insulation coordination - DigsilentLe.h insulation coordination - Digsilent
Le.h insulation coordination - DigsilentGilberto Mejía
 
Introduction-to-MV-Design-Guide.ppt
Introduction-to-MV-Design-Guide.pptIntroduction-to-MV-Design-Guide.ppt
Introduction-to-MV-Design-Guide.pptAhmed Ramadan
 
Road train-tunnel project presentation by jmv lps (1)
Road  train-tunnel project presentation by jmv lps (1)Road  train-tunnel project presentation by jmv lps (1)
Road train-tunnel project presentation by jmv lps (1)Mahesh Chandra Manav
 
Presentation indian railway electrical and s&t by jmv
Presentation indian railway electrical and s&t by jmvPresentation indian railway electrical and s&t by jmv
Presentation indian railway electrical and s&t by jmvMahesh Chandra Manav
 
Presentation water way journey by jmv lps
Presentation water way journey by jmv lpsPresentation water way journey by jmv lps
Presentation water way journey by jmv lpsMahesh Chandra Manav
 
UNIT - 06 TRANSMISSION LINES AND SUBSTATIONS
UNIT - 06 TRANSMISSION LINES AND SUBSTATIONSUNIT - 06 TRANSMISSION LINES AND SUBSTATIONS
UNIT - 06 TRANSMISSION LINES AND SUBSTATIONSPremanandDesai
 
ANALISIS DESAIN SISTEM GRID PENTANAHAN PLTU BERAU KALIMANTAN TIMUR 2 X 7 MW
ANALISIS DESAIN SISTEM GRID PENTANAHAN PLTU BERAU KALIMANTAN TIMUR 2 X 7 MWANALISIS DESAIN SISTEM GRID PENTANAHAN PLTU BERAU KALIMANTAN TIMUR 2 X 7 MW
ANALISIS DESAIN SISTEM GRID PENTANAHAN PLTU BERAU KALIMANTAN TIMUR 2 X 7 MWSyamsirAbduh2
 
Analysis-And-Design-Of-220kv-Transmission-Line-Tower-In-Different-Zones-I-&-V...
Analysis-And-Design-Of-220kv-Transmission-Line-Tower-In-Different-Zones-I-&-V...Analysis-And-Design-Of-220kv-Transmission-Line-Tower-In-Different-Zones-I-&-V...
Analysis-And-Design-Of-220kv-Transmission-Line-Tower-In-Different-Zones-I-&-V...Deepak Saxena
 

Ähnlich wie Akt tl design01 (20)

Transmission Line presentation______.ppt
Transmission Line presentation______.pptTransmission Line presentation______.ppt
Transmission Line presentation______.ppt
 
Concept of energy transmission & distribution
Concept of energy transmission & distribution Concept of energy transmission & distribution
Concept of energy transmission & distribution
 
Earthing and bonding - Power cables
Earthing and bonding - Power cablesEarthing and bonding - Power cables
Earthing and bonding - Power cables
 
A mini project on the transmission tower
A mini project on the transmission towerA mini project on the transmission tower
A mini project on the transmission tower
 
Principles of Cable Sizing
Principles of Cable SizingPrinciples of Cable Sizing
Principles of Cable Sizing
 
H046044147
H046044147H046044147
H046044147
 
Ce31533536
Ce31533536Ce31533536
Ce31533536
 
Jmv presentation national desaster management authority
Jmv  presentation  national desaster management authorityJmv  presentation  national desaster management authority
Jmv presentation national desaster management authority
 
presentation national desaster management and JMV LPS Ltd
 presentation  national desaster management  and JMV LPS Ltd presentation  national desaster management  and JMV LPS Ltd
presentation national desaster management and JMV LPS Ltd
 
Jmv presentation national desaster management authority
Jmv  presentation  national desaster management authorityJmv  presentation  national desaster management authority
Jmv presentation national desaster management authority
 
IRJET- Comparative Study of Dynamic Analysis of Transmission Towers
IRJET- Comparative Study of Dynamic Analysis of Transmission TowersIRJET- Comparative Study of Dynamic Analysis of Transmission Towers
IRJET- Comparative Study of Dynamic Analysis of Transmission Towers
 
presentation defence and police and JMV LPS LTD
 presentation  defence and police  and JMV LPS LTD presentation  defence and police  and JMV LPS LTD
presentation defence and police and JMV LPS LTD
 
Le.h insulation coordination - Digsilent
Le.h insulation coordination - DigsilentLe.h insulation coordination - Digsilent
Le.h insulation coordination - Digsilent
 
Introduction-to-MV-Design-Guide.ppt
Introduction-to-MV-Design-Guide.pptIntroduction-to-MV-Design-Guide.ppt
Introduction-to-MV-Design-Guide.ppt
 
Road train-tunnel project presentation by jmv lps (1)
Road  train-tunnel project presentation by jmv lps (1)Road  train-tunnel project presentation by jmv lps (1)
Road train-tunnel project presentation by jmv lps (1)
 
Presentation indian railway electrical and s&t by jmv
Presentation indian railway electrical and s&t by jmvPresentation indian railway electrical and s&t by jmv
Presentation indian railway electrical and s&t by jmv
 
Presentation water way journey by jmv lps
Presentation water way journey by jmv lpsPresentation water way journey by jmv lps
Presentation water way journey by jmv lps
 
UNIT - 06 TRANSMISSION LINES AND SUBSTATIONS
UNIT - 06 TRANSMISSION LINES AND SUBSTATIONSUNIT - 06 TRANSMISSION LINES AND SUBSTATIONS
UNIT - 06 TRANSMISSION LINES AND SUBSTATIONS
 
ANALISIS DESAIN SISTEM GRID PENTANAHAN PLTU BERAU KALIMANTAN TIMUR 2 X 7 MW
ANALISIS DESAIN SISTEM GRID PENTANAHAN PLTU BERAU KALIMANTAN TIMUR 2 X 7 MWANALISIS DESAIN SISTEM GRID PENTANAHAN PLTU BERAU KALIMANTAN TIMUR 2 X 7 MW
ANALISIS DESAIN SISTEM GRID PENTANAHAN PLTU BERAU KALIMANTAN TIMUR 2 X 7 MW
 
Analysis-And-Design-Of-220kv-Transmission-Line-Tower-In-Different-Zones-I-&-V...
Analysis-And-Design-Of-220kv-Transmission-Line-Tower-In-Different-Zones-I-&-V...Analysis-And-Design-Of-220kv-Transmission-Line-Tower-In-Different-Zones-I-&-V...
Analysis-And-Design-Of-220kv-Transmission-Line-Tower-In-Different-Zones-I-&-V...
 

Mehr von Dr Ashok Tiwari (20)

Vector Space.pptx
Vector Space.pptxVector Space.pptx
Vector Space.pptx
 
LINEAR TRANSFORMATION22.pdf
LINEAR TRANSFORMATION22.pdfLINEAR TRANSFORMATION22.pdf
LINEAR TRANSFORMATION22.pdf
 
AI in science.pptx
AI in science.pptxAI in science.pptx
AI in science.pptx
 
cv2.pdf
cv2.pdfcv2.pdf
cv2.pdf
 
syllabus_GATE_ee_2022.pdf
syllabus_GATE_ee_2022.pdfsyllabus_GATE_ee_2022.pdf
syllabus_GATE_ee_2022.pdf
 
Probability (1) (1).pdf
Probability (1) (1).pdfProbability (1) (1).pdf
Probability (1) (1).pdf
 
LINEAR TRANSFORMATION22.pptx
LINEAR TRANSFORMATION22.pptxLINEAR TRANSFORMATION22.pptx
LINEAR TRANSFORMATION22.pptx
 
stat1.pptx
stat1.pptxstat1.pptx
stat1.pptx
 
proba dist questions (1).pdf
proba dist questions (1).pdfproba dist questions (1).pdf
proba dist questions (1).pdf
 
T-test (1).pptx
T-test (1).pptxT-test (1).pptx
T-test (1).pptx
 
stat2.pptx
stat2.pptxstat2.pptx
stat2.pptx
 
SCR3.pptx
SCR3.pptxSCR3.pptx
SCR3.pptx
 
SCR2.pptx
SCR2.pptxSCR2.pptx
SCR2.pptx
 
SCR1 missing concepts22.pptx
SCR1 missing concepts22.pptxSCR1 missing concepts22.pptx
SCR1 missing concepts22.pptx
 
Diode circuits for GATE
Diode circuits for GATEDiode circuits for GATE
Diode circuits for GATE
 
Indian Women in power
Indian Women in powerIndian Women in power
Indian Women in power
 
ANN load forecasting
ANN load forecastingANN load forecasting
ANN load forecasting
 
Energy Meters
Energy Meters Energy Meters
Energy Meters
 
Heffron phillips model
Heffron phillips modelHeffron phillips model
Heffron phillips model
 
Meter Monitoring cell
Meter Monitoring cellMeter Monitoring cell
Meter Monitoring cell
 

Kürzlich hochgeladen

The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdfankushspencer015
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)simmis5
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...Call Girls in Nagpur High Profile
 
Glass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesGlass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesPrabhanshu Chaturvedi
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Christo Ananth
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdfKamal Acharya
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfKamal Acharya
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 

Kürzlich hochgeladen (20)

The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
 
Glass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesGlass Ceramics: Processing and Properties
Glass Ceramics: Processing and Properties
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 

Akt tl design01

  • 1. EHV TRANSMISSION LINE Design Methodology 1 Dr. A.K.TIWARI ashokktiwari@gmail.com Dr. A.K.TIWARI ashokktiwari@gmail.com
  • 2. Component of Transmission Line 2 o Conductor o Earth wire o Insulator o Transmission Tower o Wave trap and other hardware(Clamp, Spacer, Vibration dampers, connectors etc. Dr. A.K.TIWARI ashokktiwari@gmail.com
  • 3. Design Methodology 3  Gather preliminary line design data and available climatic data  Select reliability level in terms of return period of design  Calculate climatic loading on components  Calculate loads corresponding to security requirements (failure containment)  Calculate loads related to safety during construction and maintenance  Select appropriate correction factors, if applicable, to the design components such as use factor, strength factors related to numbers of components, strength coordination, quality control, and the characteristic strength.  Design the components for the above loads and strength. Dr. A.K.TIWARI ashokktiwari@gmail.com
  • 4. Reliability Levels 4  Reliability Level ≥1(One)  Higher the reliability level means higher safety factor and ultimately more cost. Dr. A.K.TIWARI ashokktiwari@gmail.com
  • 5. Selection of Transmission Voltage 5  Standard Voltage - 66,110,132, 220, 400 KV  Tolerances - ±10% up to 220 KV & ±5% for 400 KV  Selection Criterion of Economic Voltage –  Quantum of power to be evacuated  Length of line  Voltage regulation  Power loss in Transmission  Initial and operating cost  Present and future voltage in neighborhood Dr. A.K.TIWARI ashokktiwari@gmail.com
  • 6. 6 Economic Voltage of Transmission of Power – E = Transmission voltage (KV) (L-L). L = Distance of transmission line in KM KVA=Power to be transferred 1506.1 5.5 KVAL E  Dr. A.K.TIWARI ashokktiwari@gmail.com
  • 7. Types of Towers 7  Type A Tower (Tangent Tower with suspension string) o Used on straight runs and up to 2° line diversion  Type B Tower (Small Angle Tower with tension string) o Used for line deviation from 2° to 15°  Type C Tower (Medium Angle Tower with tension string ). o Used for line deviation from 15° to 30°.  Type D Tower (Large angle tower with tension string) o Used for line deviation from 30° to 60°  Type E Tower (Dead End Tower with tension string) o Used for line termination & starting  Special tower-  Suspension Tower (Span ≈ 1000 m) o Used for River crossing, Mountain crossing etc.  Transposition Tower o Used for transposition of tower Dr. A.K.TIWARI ashokktiwari@gmail.com
  • 8. 8 Different Types of Towers Dr. A.K.TIWARI ashokktiwari@gmail.com
  • 9. Selection of Tower Structure 9  Single circuit Tower/ double circuit Tower  Length of the insulator assembly  Minimum clearances to be maintained between ground conductors, and between conductors and tower  Location of ground wire/wires with respect to the outermost conductor  Mid-span clearance required from considerations of the dynamic behavior of conductors and lightning protection of the line  Minimum clearance of the lowest conductor above ground level Dr. A.K.TIWARI ashokktiwari@gmail.com
  • 10. Tower Design 10  Tower height  Base width  Top damper width  Cross arms length Fig. Typical 765 KV Tower Structure Dr. A.K.TIWARI ashokktiwari@gmail.com
  • 11. Height of Tower Structure 11 4321 hhhhH  Height of tower is determine by- h1=Minimum permissible ground clearance h2=Maximum sag h3=Vertical spacing between conductors h4=Vertical clearance between earthwire and top conductor Dr. A.K.TIWARI ashokktiwari@gmail.com
  • 12. 12 Determination of Base Width The base width(at the concrete level) is the distance between the centre of gravity at one corner leg and the centre of gravity of the adjacent corner leg.  A particular base width which gives the minimum total cost of the tower and foundations.  The ratio of base width to total tower height for most towers is generally about one-fifth to one-tenth. 12 Ryle Formula Dr. A.K.TIWARI ashokktiwari@gmail.com
  • 13. Spacing and Clearances 13 Ground Clearances KCL *305.0182.5          33 33V KWhere- S.No. Voltage level Ground clearance(m) 1. ≤33 KV 5.20 2. 66 KV 5.49 3. 132KV 6.10 4. 220 KV 7.01 5. 400 KV 8.84 Minimum permissible ground clearance as per IE Rules, 1956,Rule 77(4) Dr. A.K.TIWARI ashokktiwari@gmail.com
  • 14. 14 Clearance for Power Line Crossings  Crossing over rivers: • 3.05m above maximum flood level.  Crossing over telecommunication lines Minimum clearances between the conductors of a power line and telecommunication wires are- Voltage Level Minimum Clearance(mm) ≤33 KV 2440 66KV 2440 132 KV 2740 220 KV 3050 400 KV 4880 Dr. A.K.TIWARI ashokktiwari@gmail.com
  • 15. 15  Power line Crossing over railway tracks under maximum sag condition minimum clearance over rail level stipulated in the regulations for Electrical Crossings of Railway Tracks, 1963 Table. For un-electrified tracks or tracks electrified on 1,500 volts D.C. system System Voltage Level Broad Gauge Meter & Narrow Gauge Inside station limits(m) Out side station limits(m) Inside station limits(m) Out side station limits(m) ≤66 KV 10.3 7.9 9.1 6.7 132 KV 10.9 8.5 9.8 7.3 220 KV 11.2 8.8 10.0 7.6 400 KV 13.6 11.2 12.4 10.0 Dr. A.K.TIWARI ashokktiwari@gmail.com
  • 16. 16 Table. Tracks electrified on 25 kV A.C. system System Voltage Level Broad Gauge Inside station limits(m) Out side station limits(m) ≤ 66 KV 10.3 7.9 132 KV 10.9 8.5 220 KV 11.2 8.8 400 KV 13.6 11.2  Power line Crossing another Power line System Voltage Level Clearance(m) ≤ 66 KV 2.40 132 KV 2.75 220KV 4.55 400 KV 6.00 Dr. A.K.TIWARI ashokktiwari@gmail.com
  • 17. 17  Spacing Between Conductor(Phases) 1) Mecomb's formula 1) VDE formula S W D VcmSpacing 010.43048.0)( *  Where- V= Voltage of system in KV D= Diameter of Conductor in cm S= Sag in cm W= weight of conductor in Kg/m 2000 5.7)( 2 VScmSpacing  Where- V= Voltage of system in KV S= Sag in cmDr. A.K.TIWARI ashokktiwari@gmail.com
  • 18. 18  Still's formula     8.27 2 *814.108.5)( l VcmSpacing Where- l = Average span length(m)  NESC formula 2 681.3*762.0)( L SVcmSpacing  Where- V= Voltage of system in KV S= Sag in cm L= Length of insulator string in cm Dr. A.K.TIWARI ashokktiwari@gmail.com
  • 19. 19  Swedish formula EScmSpacing *7.05.6)(  Where- E= Line Voltage in KV S= Sag in cm  French formula Where- E= Line Voltage in KV S= Sag in cm L= length of insulating string(cm)Dr. A.K.TIWARI ashokktiwari@gmail.com
  • 20. 20  Offset of conductors (under ice-loading conditions) Sleet Jump: The jump of the conductor, resulting from ice dropping off one span of an ice-covered line, has been the cause of many serious outages on long-span lines where conductors are arranged in the same vertical plane. Offset in cm = 60 + Span in cm / 400 Dr. A.K.TIWARI ashokktiwari@gmail.com
  • 21. Clearances b/n Conductors 21 SYSTEM VOLTAG E TYPE OF TOWER Vertical spacing b/n conductors(mm) Horizontal spacing b/n conductors(mm) 66 kV SINGLE CIRCUIT A(0-2°) 1080 4040 B(2-30°) 1080 4270 C(30-60°) 1220 4880 DOUBLE CIRCUIT A(0-2°) 2170 4270 B(2-30°) 2060 4880 C(30-60°) 2440 6000 132 KV SINGLE CIRCUIT A(0-2°) 4200 7140 B(2-30°) 4200 6290 C(30-60°) 4200 7150 D(30-60°) 4200 8820 DOUBLE CIRCUIT A(0-2°) 3965 7020 B(2-15°) 3965 7320 C(15-30°) 3965 7320 D(30-60°) 4270 8540 Dr. A.K.TIWARI ashokktiwari@gmail.com
  • 22. 22 220 kV SINGLE CIRCUIT A(0-2°) 5200 8500 B(2-15°) 5250 10500 C(15-30°) 6700 12600 D(30-60°) 7800 14000 DOUBLE CIRCUIT A(0-2°) 5200 9900 B(2-15°) 5200 10100 C(15-30°) 5200 10500 D(30-60°) 6750 12600 400 KV SINGLE CIRCUIT A(0-2°) 7800 12760 B(2-15°) 7800 12760 C(15-30°) 7800 14000 D(30-60°) 8100 16200 Dr. A.K.TIWARI ashokktiwari@gmail.com
  • 23. Sag and Tension Calculation 23  Parabolic formula:  Catenary formula: Span >300 mSag & TensionSpan ≤300 m Dr. A.K.TIWARI ashokktiwari@gmail.com
  • 24. Types of Conductors 24  ACSR Conductor(Aluminium Conductor Steel Reinforced)  AAC(All Aluminium Conductor)  AAAC(All Alloy Aluminium Conductor) Dr. A.K.TIWARI ashokktiwari@gmail.com
  • 25. Selection of Conductor Size 25 Mechanical Requirement  Tensile Strength(For Tension)  Strain Strength(For Vibration) Use vibration damper for vibration control.  Mechanical Requirement  Electrical Requirement Dr. A.K.TIWARI ashokktiwari@gmail.com
  • 26. Electrical Requirement 26 o Continuous current rating. o Short time current carrying rating. o Voltage drop o Power loss o Minimum dia to avoid corona o Length of line o Charging current Dr. A.K.TIWARI ashokktiwari@gmail.com
  • 27. Continuous Current Rating. 27 21 12 12 * * * Rt Rt II    I1=current rating for temp rise ∆t1 I2=current rating required to produced temp rise ∆t2 R1= conductor resistance at conductor total temp T1(say 75°C) R2= conductor resistance at required conductor total temp T2 Dr. A.K.TIWARI ashokktiwari@gmail.com
  • 28. Short Time Rating 28 According to short time rating conductor size is given by- Where A=area of conductor(mm2) IF= fault current(KA) t= fault duration(1 sec.) tIA F **58.7 Dr. A.K.TIWARI ashokktiwari@gmail.com
  • 29. Corona 29 Visual corona voltage in fair weather condition is given by-  V0= corona starting voltage, KV(rms)  r= radius of conductor in cm  D= GMD equivalent spacing b/n conductors in cm  m= roughness factor = 1.0 for clean smooth conductor =0.85 for stranded conductor         r D n r r mV log )3.01( 1.210  Dr. A.K.TIWARI ashokktiwari@gmail.com
  • 30. 30 Voltage gradient at the surface of conductor at operating voltage-        r D Log V n g 3 0 Corona discharge form at the surface of conductor if g0≥ corona starting gradient i.e. r rmg )3.01( 1.21 0     (rms kv/cm)  Conductor size will be so chosen that normal gradient of conductor should not exceed 17.5 KV/cm.  For EHV transmission line 400KV and above use bundle conductor from point view of corona. Dr. A.K.TIWARI ashokktiwari@gmail.com
  • 31. Optimization of Conductor 31 When more than one conductor satisfied the requirement of current capacity and corona performance than study required for conductor optimization C= cost in Rs. Per Km of 3-ø line A= Annual fixed charge on capital in Rs./ Rupees of capital cost(interest 14%+depreciation 5%+ operation and maintenance cost 1-3%) Pm= Maximum demand(KW) V= Line voltage(KV) R= Resistance of conductor/Km/phase Cosø=Power factor H= Loss load factor = 0.3[LF+0.7(LF)2] (For normal load variation) = 0.2[LF+0.8(LF)2] (For more uniform load variation) Annual energy generated 8760*maximum demand LF= L= Energy charge in Rs/Kwh M= Demand charge in Rs/Kwh Dr. A.K.TIWARI ashokktiwari@gmail.com
  • 32. 32 Total annual fixed charge (C1)=C*A Total annual running charges(C2)= (P2 m*R*J)/(V2 Cos2 ø) Total charges(T)= C*A + (P2 m*R*J)/(V2 Cos2 ø) Conductor giving minimum T will be optimum Cost/KW/Km will be minimum i.e. T/Pm will be minimum when   R VP ACm  2/1 cos   1000 876012 2 HLM J LF   Dr. A.K.TIWARI ashokktiwari@gmail.com
  • 33. Some Others Consideration in Conductor Selection 33  AL/St Area (For longer span & less sag with economic consider)  River crossing (Span≥1000 m use AAAC conductor because of more tendency to vibration and twisting)  Weight/ Dia (Less Weight/Dia ratio conductor swing more hence require longer cross arms witch increase torsional load. Consider optimum value W/d in design.) Dr. A.K.TIWARI ashokktiwari@gmail.com
  • 34. INSULATOR 34 Insulator are required to support the line conductor and provide clearance from ground and structure.  Insulator material-  High grade Electrical Porcelain  Toughened Glass  Fiber Glass  Choice of insulator material is govern by availability, price and ease of maintenance.  Porcelain insulator are largely used in India. Dr. A.K.TIWARI ashokktiwari@gmail.com
  • 35. 35 Type of Insulator-  Disc Type  Strut Type  Disc type Insulator  It consist of central suitable shaped porcelain/ glass body like a disc with an metal clamp on one side and metal ball pin on other side  Cap is made of malleable cost iron and the ball pins is of forged steel. Dr. A.K.TIWARI ashokktiwari@gmail.com
  • 36.  Strut Type Insulator 36  It consist of several insulator disc cemented altogether without any link.  It is rigid and can take both tension and compression load.  These are used for holding the conductor out of way of structure.  Long Rod Insulator Dr. A.K.TIWARI ashokktiwari@gmail.com
  • 37. INSULATOR STRING 37  Disc insulator are joint by their ball pins and socket in their caps to form string.  No of insulator disc is decided by system voltage, switching and lighting over voltage amplitude and pollution level.  Insulator string can be used either suspension or tension.  Two suspension string in parallel used at railways, road and river crossing as statutory requirement.  Swing of suspension string due to wind has to be taken into consider. Fig. single string Fig. Double string Dr. A.K.TIWARI ashokktiwari@gmail.com
  • 38. Earth Wire 38 Earth wire provided above the phase conductor across the line and grounded at every tower. o It shield the line conductor from direct strokes o Reduces voltage stress across the insulating strings during lightning strokes Design criterion:  Shield angle  25°-30° up to 220 KV  20° for 400 KV and above  Earth wire should be adequate to carry very short duration lightning surge current of 100 KA without excessive over heating  Duration should be consider as 200 µ-sec  Safe temp rise limited to 300°C Dr. A.K.TIWARI ashokktiwari@gmail.com
  • 39. 39 tIA  5 A= Area(in mm2) of cu conductor I =current in KA t = Time insecond Area of Steel Wire = 3*A(cu mm2)  From mechanical consideration, size become higher than required for current carrying rating.  For EHV line it is suggested as 70 mm2 (7/3.66 mm).  ACSR is used as earth wire (12/3.0 mm AL+7/3.0 mm steel) in consideration of corrosion and resistance. Dr. A.K.TIWARI ashokktiwari@gmail.com
  • 40. 40 System voltage Mid span clearance(m) ≤ 66 KV 3.0 110 KV 4.5 132 KV 6.1 220 KV 8.5 400 KV 9.0 Mid span clearance: Direct distance b/n earth wire and top power conductor. As per IS 5613 following value of mid span clearance should be considered Dr. A.K.TIWARI ashokktiwari@gmail.com
  • 41. Tower Grounding 41 Used to reduce earth wire potential and stress on insulators at the time of stroke and also for safety  Tower footing resistance will be 10Ω and should not be more than 20 Ω under any condition throughout the year.  Earth resistance depend upon soil resistivity(general 100 Ω-m) Dr. A.K.TIWARI ashokktiwari@gmail.com
  • 42. Method of Tower Grounding 42  Buried Conductor One or more conductor are connected to tower lags and buried in back filled of tower foundation. o Used where soil resistivity is low  Counterpoise Wire A length of wire/ Strip of 50 m is buried horizontally at depth of 0.5 m bellow ground. This wire is connected to tower lags. o Used when earth resistance is very high and soil conductivity is mostly confined to upper layer)  Rod Pipe Pipe/Rod of 3 to 4 m is driven into ground near the tower and top of rod is connected to tower by suitable wire/strip o Used where ground conductivity increase with depth  Treated Earth Pits Pipe/Rod of 3 to 4 m are buried in treated earth pits and top of rod is connected to tower by suitable wire/strip. o Used in very high resistivity near tower Dr. A.K.TIWARI ashokktiwari@gmail.com
  • 43. Reference Standards 43  IS-398  IS-802  IS 3853  IS 4091  IS 5613  CBIP  IE Rules, Specification of Aluminium Conductor for Over Head Transmission Line(ACSR) Code of Practice for use of Structural Steel in over head Transmission Line Tower Specification of Aluminium Steel Core Wire for Aluminium Conductor Code Practice for Design and Construction of Foundation of Transmission Line Tower and Pole Specification of Design, Installation and Maintenance of Line above 11 KV and up to 220 KV Manual on Transmission Line Tower, Technical Report N0. 9, March 1977 Dr. A.K.TIWARI ashokktiwari@gmail.com
  • 44. Thank You…. 44 Dr. A.K.TIWARI ashokktiwari@gmail.com

Hinweis der Redaktion

  1. Different types of towers
  2. Fig. Typical 400 KV tower structure
  3. Height of tower is determine by-
  4. Where-
  5. asf
  6. Tower are at same level
  7. Copper aluminium
  8. I1=current rating for temp rise
  9. (rms kv/cm)
  10. L=
  11. Fig. single string
  12. Area of steel wire will be