SlideShare ist ein Scribd-Unternehmen logo
1 von 24
SPEAKER:SPEAKER:
A. K. GUPTA
EXECUTIVE ENGINEER (VIGILANCE)
MANDI HOUSE, NEW DELHI
CONTRACT
MANAGEMENT
CPWD CONTRACTS
 Clause 2 (compensation for delay)
 Fails to maintain progress
 Fails to complete work as per schedule
 Liable to pay agreed compensations
 Amount
 Compensation for delay:
@ 1.5% per month of delay to be computer on
per day basis
 Not more than 10% of tendered value
compensation for delay
 Amount of compensation may be adjusted or
set off against any some payable
 With holding amount if fails to achieve mile
stone. Withheld amount to be adjusted against
the compensation levied at the final grant of
extension
 If make up the progress subsequently,
withheld amount to be released
INCENTIVE FOR EARLY
COMPLETION
 Clause 2A
 Complete the work ahead of schedule
 Bonus @ 1% of tendered value per month
computed on daily basis payable to contractor
 Not more than 5 of tendered value
 Amount of bonus payable along with final bill
on completion of work.
DETERMINATION OF
CONTRACT (before completion
date)
 Clause -3
 Causes – delay
- inferior workmanship
- claims for damages
- violation of any other promise of contract
 Determination of contract – after giving notice:
i) Omit to comply with the notice given to contractor to rectify,
reinstruct or replace any defective work.
ii) Suspended the progress of work without any reasonable
cause and unable to secure completion of work and
continues even after notice.
iii) Fails to complete the work within stipulated date
Contd.
DETERMINATION OF
CONTRACT (before completion
date) contd.
iv) Persistently neglects to carry out his obligations
under the contract/commits default
v) Contractor offers or give or agree to give any
person any gift or inducement to favour him
vi) Commission has been paid or agreed to be paid
by him unless they are previously disclosed
vii) Secured contract by wrong tendering or by any
other non-bonafide methods
viii) Becomes insolvent /company woundup
ix) Asignes, transfers or sublets or attempts to do
so.
DETERMINATION OF
CONTRACT (before completion
date)
 Consequences
 To determine the contracts
 SD & PG liable to be forfeited
 Measure the work and get the balance work
executed through other contractor
 Liability of contractor
 SD & PG liable to be forfeited
 No claim for compensation
 Only certified work by the E-in-C is payable.
CLOSURE OF CONTRACT NOT
STARTED
 Clause 3A
 Work not started for reasons not with in the
control of contractor within
1/8 of time of completion or 1 month
whichever is more
 Either partly may close the contract PG of the
contractor to be returned
Works up to Rs. 45 lacs – 15 days
45 lacs and upt to Rs. 2.5 crore – 21 days
More than 2.5 crore – 30 days
CLOSURE OF CONTRACT NOT
STARTED
 Consequences:
 PG not returned, simple interest @ 0.25% per
month payable to contractor
 Compensation for damages @ 0.25% of
tendered amount & max upto Rs. 10 lacs
COMPENSATION
 Clause 4
 If powers under clause (3) not exercised
 E-in-C if he so desires after giving notice
 May use as on hire all tools, plants, materials,
stores belonging to the contractor on work & pay
to the contractor at contract rates/market rates
 Remove such tool plants materials etc. at the
contractor's expenses or sell them by auction or
private sale on account of the contractors
 certification of E-in-C as to expresses of proceeds
shall be final
PROGRESS MONITORING
 Clause – 5
 Time/extended time essence of contract
If failure to start govt. may be forfeit PG and EM
 Clause – 5.1
 Contractor to submit time and progress chart
and get approved.
 More than 5 crores use PM Software
 5 crores to 20 crores – MS projects
 More than 20 crores use Primevera software
PROGRESS MONITORING
 Clause 5.1
 Programme chart:
a) Sequence of activities
b) PERT/CPM/BAR Chart
c) Procurement of materials
 If progress is lacking, E-in-C may ask revised PC contractor
to submit within 7 days
 For delays recovery @ 2500/perday for contracts upto Rs. 20
crores
 Recovery @ 5000/perday for contracts above Rs. 20 crores
 Submit proper report monthly failure impose recovery of
2500/5000
EXTENSION OF TIME
 Clause 5.2
 Work delays by
i) Force majure/act of God
ii) Abnormally bad weather
iii) Fire
iv) Commotion
v) Delay attributable to government
vi) Beyond the control of contractor
 Contractor to give notice to Govt.
 Request for rescheduling and extension of time
 Govt. (authority) to give fair and reasonable extension of time
 Authority to take a balance view and delays attributable to both
parties should be mentioned in EOT
FORECLOSURE (Clause -13) (due
to abandonment or reduction in
scope of work)
 On reduction of scope of work E-in-C shall
give notice to contractor
 Contractor to act accordingly
 Contractor not entitled for compensation for
contractor’s profit
 He will be paid for work executed
FORECLOSURE (Clause -13) (due
to abandonment or reduction in
scope of work)
 He will be paid further:
a) On prepatary works 9nuts, roads)
b) Govt. will take over materials and cost shall be paid
c) Govt. materials will be taken back giving allowance for
wastage, paid for transportation
d) For T&P from site to permanent stores
e) Reasonable compensation for repatriation of staff
 Contractor to submit books of accounts and relevant
documents
 (a+b+c+d+e) not more than 2% of the work remain
incomplete
 Compensation for damages will be paid @ .5% of the work
remaining incomplete.
Carrying out part work at risk and
cost of contractor (clause – 14)
 Contractor makes defaulter doesn't execute any part
of work
 Continues to do so after notice
 Violates term and condition of contract
 Fails to complete/the work/part of the time with
stipulated period
 Gives notice to contractor to take the part work/part
incomplete work and of hands of contractor
 E-in-C have power to
 Take possession of site, materials, T&P
 Carryout part work/incomplete work at risk & cost of
contractor
Carrying out part work at risk and
cost of contractor (clause – 14)
 E-in-C will determine
 Recoverable amount from contractor
 Contractor liability on account of loss and damage
suffered by government not more than 10% of
tendered value
 If the expenses by government is less than the
amount payable to contract (@ agreement rates)
difference not payable.
 Excess expenditure to be recovered from contractor
 If contractor fails to pay within 30days, e-in-C shall sell
any or all the contractor’s material and T&P etc.
 Balance as per T/C of contract
 No compensation to contractor
SUSPENSION OF WORK (Clause-
15)
 E-in-C gives in writing to suspend work for reasons
a) Default of contracts
b) Reasons other than default of contractor
c)For safety of work
 Contractor shall protect the work during this period
 For b) and c) above
 Contractor entitled for extension of time for such period +25%
 If exceeds 30 days contractor entitled for wages of
staff/labour sitting idle
 + 2% indirect expenses
 Contractor to submit claim with in 15 days
SUSPENSION OF WORK (Clause-
15)
 If work is suspended for 90 days for reasons b)
and c) the contracts to give notice to government
within 10 days after expiry of 15 days
 Contractor if treats it as abandonment by Govt,
shall have no claim for compensation on account
of loss of profit.
 Contractor is entitled for:
a) Salaries and wages of employees/labours at site
remaining idle
b) +2% indirect charges.
Compensation for delay in supply
of Govt. materials (Clause 15 A)
 No compensation if delay is beyond the
control of Govt.
 Extension of time to be granted
DEFECT LIABILITY PERIOD
(Clause – 17)
 Defect liability period 6 month, less than work
Rs. 10 lacs
 Defect liability period 12 month, more than
work Rs. 10 lacs
 Liable for damages during defect liability
period
 All defects to be made good during the period
 If not firm the SD of the contractor
 For road work 50% of SD to be refunded after
six months
SETTLEMENT OF DISPUTES
(Clause – 25)
 Arbitration clause:
 All questions and disputes during the progress of work, after
cancellation, terminiation, completion/abandonment
 Any dispute, refer it to SE within 15 days, SE to reply within
30 days
 If SE fails or contractor is dissatisfied appeal to CE within 30
days, CE will hear the contractor. Give his decision within 30
days.
 If dissatisfied, appeal before the DRC (Dispute Redressal
committee). DRC will give decision within 90 days.
 Dissatisfied with the decision of DRC, either party may give
notice to CE(C) within 30 days for appointments of arbitrator
failing which decision shall be final/binding.
SETTLEMENT OF DISPUTES
(Clause – 25)
 CE(C) shall refer the matter to sole arbitrator
 Contractor to give list of disputes with amounts
claimed
 If the contractor does not request for
appointment of arbitrator after 120 days of
receiving intimation of final bills, the claims
becomes time barred.
 Arbitration and conciliation Act- 1996
applicable
 Where claim exceeds Rs. 1 lakh, arbitrator to
give reasons.
ThanksThanks
E mail: akgupta07@nic.in

Weitere ähnliche Inhalte

Was ist angesagt?

Construction contract
Construction contract Construction contract
Construction contract Rakshith Reddy
 
Conditions of CPWD contract in INDIA
Conditions of CPWD contract in INDIAConditions of CPWD contract in INDIA
Conditions of CPWD contract in INDIAAvinash Kumar Gupta
 
Fidic conditions of contract presentation
Fidic conditions of contract presentationFidic conditions of contract presentation
Fidic conditions of contract presentationJeff B
 
Construction Law Presentation
Construction Law PresentationConstruction Law Presentation
Construction Law Presentationelliotfus
 
Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)mohamed Ismail
 
Construction Contracts: Basics of Contracts and Contract Administration
Construction Contracts:  Basics of Contracts and Contract AdministrationConstruction Contracts:  Basics of Contracts and Contract Administration
Construction Contracts: Basics of Contracts and Contract AdministrationGerald R. (Jerry) Genge
 
Construction planning & management
Construction planning & managementConstruction planning & management
Construction planning & managementManit Agarwal
 
construction project planing
 construction project planing construction project planing
construction project planingSANJEEV Wazir
 
Tenders and procedure of tendering
Tenders and procedure of tenderingTenders and procedure of tendering
Tenders and procedure of tenderingvvsasane
 
Estimation and Costing - Contracts
Estimation and Costing - ContractsEstimation and Costing - Contracts
Estimation and Costing - Contractssrinivas2036
 
What is construction management & its Benefits?
What is construction management & its Benefits?What is construction management & its Benefits?
What is construction management & its Benefits?maria_singh
 
Stages In Construction
Stages In ConstructionStages In Construction
Stages In ConstructionAB MAKASANA
 
Contract payment and variation
Contract payment and variationContract payment and variation
Contract payment and variationVj NiroSh
 
Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)Fakhar-un -Nisa
 
CONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPESCONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPESPundlik Rathod
 
Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...
Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...
Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...Divyanshu Dayal
 
GCC2015 Course_Day2
GCC2015 Course_Day2GCC2015 Course_Day2
GCC2015 Course_Day2JB Nartey
 

Was ist angesagt? (20)

Construction contract
Construction contract Construction contract
Construction contract
 
Conditions of CPWD contract in INDIA
Conditions of CPWD contract in INDIAConditions of CPWD contract in INDIA
Conditions of CPWD contract in INDIA
 
Fidic conditions of contract presentation
Fidic conditions of contract presentationFidic conditions of contract presentation
Fidic conditions of contract presentation
 
Construction Law Presentation
Construction Law PresentationConstruction Law Presentation
Construction Law Presentation
 
Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)
 
Construction Contracts: Basics of Contracts and Contract Administration
Construction Contracts:  Basics of Contracts and Contract AdministrationConstruction Contracts:  Basics of Contracts and Contract Administration
Construction Contracts: Basics of Contracts and Contract Administration
 
Construction planning & management
Construction planning & managementConstruction planning & management
Construction planning & management
 
construction project planing
 construction project planing construction project planing
construction project planing
 
Tenders and procedure of tendering
Tenders and procedure of tenderingTenders and procedure of tendering
Tenders and procedure of tendering
 
Estimation and Costing - Contracts
Estimation and Costing - ContractsEstimation and Costing - Contracts
Estimation and Costing - Contracts
 
What is construction management & its Benefits?
What is construction management & its Benefits?What is construction management & its Benefits?
What is construction management & its Benefits?
 
Stages In Construction
Stages In ConstructionStages In Construction
Stages In Construction
 
Contract payment and variation
Contract payment and variationContract payment and variation
Contract payment and variation
 
Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)
 
CONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPESCONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPES
 
Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...
Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...
Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...
 
Ppt on fidic claims
Ppt on fidic claimsPpt on fidic claims
Ppt on fidic claims
 
GCC2015 Course_Day2
GCC2015 Course_Day2GCC2015 Course_Day2
GCC2015 Course_Day2
 
Contracts
ContractsContracts
Contracts
 
Construction contracts
Construction contractsConstruction contracts
Construction contracts
 

Andere mochten auch

Payments provisions in CPWD CONTRACT
Payments provisions in CPWD CONTRACTPayments provisions in CPWD CONTRACT
Payments provisions in CPWD CONTRACTAvinash Kumar Gupta
 
New Building Materials
New Building MaterialsNew Building Materials
New Building MaterialsDr K M SONI
 
Avoidance of waste and recycling of construction and demolition waste
Avoidance of waste and recycling of construction and demolition waste Avoidance of waste and recycling of construction and demolition waste
Avoidance of waste and recycling of construction and demolition waste Dr K M SONI
 
Safety management in construction
Safety management in construction   Safety management in construction
Safety management in construction Dr K M SONI
 
Contract Management in Civil Engineering Works
Contract Management in Civil Engineering WorksContract Management in Civil Engineering Works
Contract Management in Civil Engineering WorksDr K M SONI
 
Robotics in construction
Robotics in constructionRobotics in construction
Robotics in constructionSaul Lustgarten
 
Seismic Retrofitting of Masonry Structures
Seismic Retrofitting of Masonry StructuresSeismic Retrofitting of Masonry Structures
Seismic Retrofitting of Masonry StructuresDr K M SONI
 
CONCRETE MIX DESIGN AS PER IS 10262:2009
 CONCRETE MIX DESIGN AS PER IS 10262:2009  CONCRETE MIX DESIGN AS PER IS 10262:2009
CONCRETE MIX DESIGN AS PER IS 10262:2009 Avinash Kumar Gupta
 
civil engineering-Contracts
civil engineering-Contractscivil engineering-Contracts
civil engineering-ContractsNikhil Kumar
 
3Com 734938-003
3Com 734938-0033Com 734938-003
3Com 734938-003savomir
 

Andere mochten auch (17)

The busy developer guide to Docker
The busy developer guide to DockerThe busy developer guide to Docker
The busy developer guide to Docker
 
Use of Glass
Use of GlassUse of Glass
Use of Glass
 
Payments provisions in CPWD CONTRACT
Payments provisions in CPWD CONTRACTPayments provisions in CPWD CONTRACT
Payments provisions in CPWD CONTRACT
 
Construction safety ii
Construction safety iiConstruction safety ii
Construction safety ii
 
New Building Materials
New Building MaterialsNew Building Materials
New Building Materials
 
Ready mix concrete
Ready mix concreteReady mix concrete
Ready mix concrete
 
Integrity pact
Integrity pactIntegrity pact
Integrity pact
 
Avoidance of waste and recycling of construction and demolition waste
Avoidance of waste and recycling of construction and demolition waste Avoidance of waste and recycling of construction and demolition waste
Avoidance of waste and recycling of construction and demolition waste
 
Safety management in construction
Safety management in construction   Safety management in construction
Safety management in construction
 
Contract Management in Civil Engineering Works
Contract Management in Civil Engineering WorksContract Management in Civil Engineering Works
Contract Management in Civil Engineering Works
 
Robotics in construction
Robotics in constructionRobotics in construction
Robotics in construction
 
Handbook of repair
Handbook of repairHandbook of repair
Handbook of repair
 
Seismic Retrofitting of Masonry Structures
Seismic Retrofitting of Masonry StructuresSeismic Retrofitting of Masonry Structures
Seismic Retrofitting of Masonry Structures
 
CONCRETE MIX DESIGN AS PER IS 10262:2009
 CONCRETE MIX DESIGN AS PER IS 10262:2009  CONCRETE MIX DESIGN AS PER IS 10262:2009
CONCRETE MIX DESIGN AS PER IS 10262:2009
 
Robotics
RoboticsRobotics
Robotics
 
civil engineering-Contracts
civil engineering-Contractscivil engineering-Contracts
civil engineering-Contracts
 
3Com 734938-003
3Com 734938-0033Com 734938-003
3Com 734938-003
 

Ähnlich wie Suspensions and Delays in Construction Contract

CONTRACTS AND CLAIMS MANAGEMENT PPT.pptx
CONTRACTS AND CLAIMS MANAGEMENT PPT.pptxCONTRACTS AND CLAIMS MANAGEMENT PPT.pptx
CONTRACTS AND CLAIMS MANAGEMENT PPT.pptxssuserb7dd601
 
DEFECTS LIABILITY AND TAKING OVER CLAUSES
DEFECTS LIABILITY AND TAKING OVER CLAUSESDEFECTS LIABILITY AND TAKING OVER CLAUSES
DEFECTS LIABILITY AND TAKING OVER CLAUSESShivam Sood
 
Lecture 8-determination-of-own-employment-by
Lecture 8-determination-of-own-employment-byLecture 8-determination-of-own-employment-by
Lecture 8-determination-of-own-employment-byseenyeeyong
 
How to Build Successful Projects: A Guide for Owners and Developers
How to Build Successful Projects: A Guide for Owners and DevelopersHow to Build Successful Projects: A Guide for Owners and Developers
How to Build Successful Projects: A Guide for Owners and DevelopersKegler Brown Hill + Ritter
 
Suspension and Termination by Contractor Presentation.pptx
Suspension and Termination by Contractor Presentation.pptxSuspension and Termination by Contractor Presentation.pptx
Suspension and Termination by Contractor Presentation.pptxNathannielGonzales1
 
Pp2 coursework 1 p10
Pp2 coursework 1 p10 Pp2 coursework 1 p10
Pp2 coursework 1 p10 Farah Sham
 
INFRA_PPP_FewControl points for growth.ppt
INFRA_PPP_FewControl points for growth.pptINFRA_PPP_FewControl points for growth.ppt
INFRA_PPP_FewControl points for growth.pptGovind Raj
 
Extension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentationExtension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentationAyush Joshi
 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2ahmong4
 
Key terms to consider when negotiating cm at-risk agreements + gmp amendments
Key terms to consider when negotiating cm at-risk agreements + gmp amendmentsKey terms to consider when negotiating cm at-risk agreements + gmp amendments
Key terms to consider when negotiating cm at-risk agreements + gmp amendmentsKegler Brown Hill + Ritter
 
1. ERS PPT - 20 OCT 2022.ppt
1. ERS PPT - 20 OCT 2022.ppt1. ERS PPT - 20 OCT 2022.ppt
1. ERS PPT - 20 OCT 2022.pptGeorgeKGeorge3
 
CE-CONTRACTS-REPORT.pdf
CE-CONTRACTS-REPORT.pdfCE-CONTRACTS-REPORT.pdf
CE-CONTRACTS-REPORT.pdfChelDems
 
PP2 Seminar - Determination of Contractor's Employment by Employer
PP2 Seminar - Determination of Contractor's Employment by EmployerPP2 Seminar - Determination of Contractor's Employment by Employer
PP2 Seminar - Determination of Contractor's Employment by EmployerTrace96
 
PP2 presentation
PP2 presentationPP2 presentation
PP2 presentationYong Sy
 
Professional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOTProfessional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOTYee Len Wan
 
Clause 14.9 Payment of Retention Money-Understanding Clauses in FIDIC ‘Condit...
Clause 14.9 Payment of Retention Money-Understanding Clauses in FIDIC ‘Condit...Clause 14.9 Payment of Retention Money-Understanding Clauses in FIDIC ‘Condit...
Clause 14.9 Payment of Retention Money-Understanding Clauses in FIDIC ‘Condit...Divyanshu Dayal
 
CSCM Sla cscm
CSCM Sla cscmCSCM Sla cscm
CSCM Sla cscmEst
 

Ähnlich wie Suspensions and Delays in Construction Contract (20)

CONTRACTS AND CLAIMS MANAGEMENT PPT.pptx
CONTRACTS AND CLAIMS MANAGEMENT PPT.pptxCONTRACTS AND CLAIMS MANAGEMENT PPT.pptx
CONTRACTS AND CLAIMS MANAGEMENT PPT.pptx
 
DEFECTS LIABILITY AND TAKING OVER CLAUSES
DEFECTS LIABILITY AND TAKING OVER CLAUSESDEFECTS LIABILITY AND TAKING OVER CLAUSES
DEFECTS LIABILITY AND TAKING OVER CLAUSES
 
Lecture 8-determination-of-own-employment-by
Lecture 8-determination-of-own-employment-byLecture 8-determination-of-own-employment-by
Lecture 8-determination-of-own-employment-by
 
How to Build Successful Projects: A Guide for Owners and Developers
How to Build Successful Projects: A Guide for Owners and DevelopersHow to Build Successful Projects: A Guide for Owners and Developers
How to Build Successful Projects: A Guide for Owners and Developers
 
Suspension and Termination by Contractor Presentation.pptx
Suspension and Termination by Contractor Presentation.pptxSuspension and Termination by Contractor Presentation.pptx
Suspension and Termination by Contractor Presentation.pptx
 
Pp2 coursework 1 p10
Pp2 coursework 1 p10 Pp2 coursework 1 p10
Pp2 coursework 1 p10
 
Cl report final
Cl report finalCl report final
Cl report final
 
INFRA_PPP_FewControl points for growth.ppt
INFRA_PPP_FewControl points for growth.pptINFRA_PPP_FewControl points for growth.ppt
INFRA_PPP_FewControl points for growth.ppt
 
Extension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentationExtension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentation
 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2
 
Key terms to consider when negotiating cm at-risk agreements + gmp amendments
Key terms to consider when negotiating cm at-risk agreements + gmp amendmentsKey terms to consider when negotiating cm at-risk agreements + gmp amendments
Key terms to consider when negotiating cm at-risk agreements + gmp amendments
 
M/s Subhash Singh
M/s Subhash SinghM/s Subhash Singh
M/s Subhash Singh
 
1. ERS PPT - 20 OCT 2022.ppt
1. ERS PPT - 20 OCT 2022.ppt1. ERS PPT - 20 OCT 2022.ppt
1. ERS PPT - 20 OCT 2022.ppt
 
CE-CONTRACTS-REPORT.pdf
CE-CONTRACTS-REPORT.pdfCE-CONTRACTS-REPORT.pdf
CE-CONTRACTS-REPORT.pdf
 
PP2 Seminar - Determination of Contractor's Employment by Employer
PP2 Seminar - Determination of Contractor's Employment by EmployerPP2 Seminar - Determination of Contractor's Employment by Employer
PP2 Seminar - Determination of Contractor's Employment by Employer
 
PP2 presentation
PP2 presentationPP2 presentation
PP2 presentation
 
Professional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOTProfessional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOT
 
Clause 14.9 Payment of Retention Money-Understanding Clauses in FIDIC ‘Condit...
Clause 14.9 Payment of Retention Money-Understanding Clauses in FIDIC ‘Condit...Clause 14.9 Payment of Retention Money-Understanding Clauses in FIDIC ‘Condit...
Clause 14.9 Payment of Retention Money-Understanding Clauses in FIDIC ‘Condit...
 
Seminar p8x
Seminar p8xSeminar p8x
Seminar p8x
 
CSCM Sla cscm
CSCM Sla cscmCSCM Sla cscm
CSCM Sla cscm
 

Mehr von Avinash Kumar Gupta

Time schedule for preparation &and completion of APAR
Time schedule for preparation &and completion of APARTime schedule for preparation &and completion of APAR
Time schedule for preparation &and completion of APARAvinash Kumar Gupta
 
Engaging consultants, service providers in govrnment part i
Engaging consultants, service providers in govrnment part iEngaging consultants, service providers in govrnment part i
Engaging consultants, service providers in govrnment part iAvinash Kumar Gupta
 
Procurement of goods , GFR provisions
Procurement of goods , GFR provisionsProcurement of goods , GFR provisions
Procurement of goods , GFR provisionsAvinash Kumar Gupta
 
Construction and repair chemicals
Construction and repair  chemicalsConstruction and repair  chemicals
Construction and repair chemicalsAvinash Kumar Gupta
 
Illustrations. repairing of structures
Illustrations. repairing of structuresIllustrations. repairing of structures
Illustrations. repairing of structuresAvinash Kumar Gupta
 
Condition survey and non destructive evalution of concrete
Condition survey and non destructive evalution of concreteCondition survey and non destructive evalution of concrete
Condition survey and non destructive evalution of concreteAvinash Kumar Gupta
 
Materials for rcc repairs and rehabilitation
Materials for rcc repairs and rehabilitationMaterials for rcc repairs and rehabilitation
Materials for rcc repairs and rehabilitationAvinash Kumar Gupta
 
AMENDMENT IN ARBITRATION LAW IN INDIA 2016
AMENDMENT IN ARBITRATION LAW IN INDIA 2016AMENDMENT IN ARBITRATION LAW IN INDIA 2016
AMENDMENT IN ARBITRATION LAW IN INDIA 2016Avinash Kumar Gupta
 

Mehr von Avinash Kumar Gupta (20)

Principles of natural justice
Principles of natural justicePrinciples of natural justice
Principles of natural justice
 
Time schedule for preparation &and completion of APAR
Time schedule for preparation &and completion of APARTime schedule for preparation &and completion of APAR
Time schedule for preparation &and completion of APAR
 
Orders regarding apar
Orders regarding apar Orders regarding apar
Orders regarding apar
 
APAR guidelines
APAR  guidelinesAPAR  guidelines
APAR guidelines
 
Total station
Total stationTotal station
Total station
 
GPS surveying/DIGITAL SURVEYING
GPS  surveying/DIGITAL SURVEYINGGPS  surveying/DIGITAL SURVEYING
GPS surveying/DIGITAL SURVEYING
 
Service contracts ii
Service contracts iiService contracts ii
Service contracts ii
 
Engaging consultants, service providers in govrnment part i
Engaging consultants, service providers in govrnment part iEngaging consultants, service providers in govrnment part i
Engaging consultants, service providers in govrnment part i
 
Procurement of goods , GFR provisions
Procurement of goods , GFR provisionsProcurement of goods , GFR provisions
Procurement of goods , GFR provisions
 
Procurement of services
Procurement of  servicesProcurement of  services
Procurement of services
 
GST on works contract
GST on  works contractGST on  works contract
GST on works contract
 
Soil penetration tests
Soil penetration testsSoil penetration tests
Soil penetration tests
 
Soil exploration part i
Soil exploration part  iSoil exploration part  i
Soil exploration part i
 
Construction and repair chemicals
Construction and repair  chemicalsConstruction and repair  chemicals
Construction and repair chemicals
 
Illustrations. repairing of structures
Illustrations. repairing of structuresIllustrations. repairing of structures
Illustrations. repairing of structures
 
Condition survey and non destructive evalution of concrete
Condition survey and non destructive evalution of concreteCondition survey and non destructive evalution of concrete
Condition survey and non destructive evalution of concrete
 
Materials for rcc repairs and rehabilitation
Materials for rcc repairs and rehabilitationMaterials for rcc repairs and rehabilitation
Materials for rcc repairs and rehabilitation
 
Rehabilitation methods
Rehabilitation methodsRehabilitation methods
Rehabilitation methods
 
AMENDMENT IN ARBITRATION LAW IN INDIA 2016
AMENDMENT IN ARBITRATION LAW IN INDIA 2016AMENDMENT IN ARBITRATION LAW IN INDIA 2016
AMENDMENT IN ARBITRATION LAW IN INDIA 2016
 
WORKS MANAGEMENT IN CPWD PART-I
WORKS MANAGEMENT IN CPWD PART-IWORKS MANAGEMENT IN CPWD PART-I
WORKS MANAGEMENT IN CPWD PART-I
 

Kürzlich hochgeladen

Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills KuwaitKuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwaitjaanualu31
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxJuliansyahHarahap1
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Arindam Chakraborty, Ph.D., P.E. (CA, TX)
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"mphochane1998
 
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxSCMS School of Architecture
 
Computer Lecture 01.pptxIntroduction to Computers
Computer Lecture 01.pptxIntroduction to ComputersComputer Lecture 01.pptxIntroduction to Computers
Computer Lecture 01.pptxIntroduction to ComputersMairaAshraf6
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfJiananWang21
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayEpec Engineered Technologies
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdfKamal Acharya
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueBhangaleSonal
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityMorshed Ahmed Rahath
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdfKamal Acharya
 
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Call Girls Mumbai
 
Engineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planesEngineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planesRAJNEESHKUMAR341697
 
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...soginsider
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VDineshKumar4165
 
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...HenryBriggs2
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . pptDineshKumar4165
 

Kürzlich hochgeladen (20)

Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills KuwaitKuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
 
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptx
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
 
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
 
Computer Lecture 01.pptxIntroduction to Computers
Computer Lecture 01.pptxIntroduction to ComputersComputer Lecture 01.pptxIntroduction to Computers
Computer Lecture 01.pptxIntroduction to Computers
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdf
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna Municipality
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdf
 
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
 
Engineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planesEngineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planes
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 

Suspensions and Delays in Construction Contract

  • 1. SPEAKER:SPEAKER: A. K. GUPTA EXECUTIVE ENGINEER (VIGILANCE) MANDI HOUSE, NEW DELHI CONTRACT MANAGEMENT
  • 2. CPWD CONTRACTS  Clause 2 (compensation for delay)  Fails to maintain progress  Fails to complete work as per schedule  Liable to pay agreed compensations  Amount  Compensation for delay: @ 1.5% per month of delay to be computer on per day basis  Not more than 10% of tendered value
  • 3. compensation for delay  Amount of compensation may be adjusted or set off against any some payable  With holding amount if fails to achieve mile stone. Withheld amount to be adjusted against the compensation levied at the final grant of extension  If make up the progress subsequently, withheld amount to be released
  • 4. INCENTIVE FOR EARLY COMPLETION  Clause 2A  Complete the work ahead of schedule  Bonus @ 1% of tendered value per month computed on daily basis payable to contractor  Not more than 5 of tendered value  Amount of bonus payable along with final bill on completion of work.
  • 5. DETERMINATION OF CONTRACT (before completion date)  Clause -3  Causes – delay - inferior workmanship - claims for damages - violation of any other promise of contract  Determination of contract – after giving notice: i) Omit to comply with the notice given to contractor to rectify, reinstruct or replace any defective work. ii) Suspended the progress of work without any reasonable cause and unable to secure completion of work and continues even after notice. iii) Fails to complete the work within stipulated date Contd.
  • 6. DETERMINATION OF CONTRACT (before completion date) contd. iv) Persistently neglects to carry out his obligations under the contract/commits default v) Contractor offers or give or agree to give any person any gift or inducement to favour him vi) Commission has been paid or agreed to be paid by him unless they are previously disclosed vii) Secured contract by wrong tendering or by any other non-bonafide methods viii) Becomes insolvent /company woundup ix) Asignes, transfers or sublets or attempts to do so.
  • 7. DETERMINATION OF CONTRACT (before completion date)  Consequences  To determine the contracts  SD & PG liable to be forfeited  Measure the work and get the balance work executed through other contractor  Liability of contractor  SD & PG liable to be forfeited  No claim for compensation  Only certified work by the E-in-C is payable.
  • 8. CLOSURE OF CONTRACT NOT STARTED  Clause 3A  Work not started for reasons not with in the control of contractor within 1/8 of time of completion or 1 month whichever is more  Either partly may close the contract PG of the contractor to be returned Works up to Rs. 45 lacs – 15 days 45 lacs and upt to Rs. 2.5 crore – 21 days More than 2.5 crore – 30 days
  • 9. CLOSURE OF CONTRACT NOT STARTED  Consequences:  PG not returned, simple interest @ 0.25% per month payable to contractor  Compensation for damages @ 0.25% of tendered amount & max upto Rs. 10 lacs
  • 10. COMPENSATION  Clause 4  If powers under clause (3) not exercised  E-in-C if he so desires after giving notice  May use as on hire all tools, plants, materials, stores belonging to the contractor on work & pay to the contractor at contract rates/market rates  Remove such tool plants materials etc. at the contractor's expenses or sell them by auction or private sale on account of the contractors  certification of E-in-C as to expresses of proceeds shall be final
  • 11. PROGRESS MONITORING  Clause – 5  Time/extended time essence of contract If failure to start govt. may be forfeit PG and EM  Clause – 5.1  Contractor to submit time and progress chart and get approved.  More than 5 crores use PM Software  5 crores to 20 crores – MS projects  More than 20 crores use Primevera software
  • 12. PROGRESS MONITORING  Clause 5.1  Programme chart: a) Sequence of activities b) PERT/CPM/BAR Chart c) Procurement of materials  If progress is lacking, E-in-C may ask revised PC contractor to submit within 7 days  For delays recovery @ 2500/perday for contracts upto Rs. 20 crores  Recovery @ 5000/perday for contracts above Rs. 20 crores  Submit proper report monthly failure impose recovery of 2500/5000
  • 13. EXTENSION OF TIME  Clause 5.2  Work delays by i) Force majure/act of God ii) Abnormally bad weather iii) Fire iv) Commotion v) Delay attributable to government vi) Beyond the control of contractor  Contractor to give notice to Govt.  Request for rescheduling and extension of time  Govt. (authority) to give fair and reasonable extension of time  Authority to take a balance view and delays attributable to both parties should be mentioned in EOT
  • 14. FORECLOSURE (Clause -13) (due to abandonment or reduction in scope of work)  On reduction of scope of work E-in-C shall give notice to contractor  Contractor to act accordingly  Contractor not entitled for compensation for contractor’s profit  He will be paid for work executed
  • 15. FORECLOSURE (Clause -13) (due to abandonment or reduction in scope of work)  He will be paid further: a) On prepatary works 9nuts, roads) b) Govt. will take over materials and cost shall be paid c) Govt. materials will be taken back giving allowance for wastage, paid for transportation d) For T&P from site to permanent stores e) Reasonable compensation for repatriation of staff  Contractor to submit books of accounts and relevant documents  (a+b+c+d+e) not more than 2% of the work remain incomplete  Compensation for damages will be paid @ .5% of the work remaining incomplete.
  • 16. Carrying out part work at risk and cost of contractor (clause – 14)  Contractor makes defaulter doesn't execute any part of work  Continues to do so after notice  Violates term and condition of contract  Fails to complete/the work/part of the time with stipulated period  Gives notice to contractor to take the part work/part incomplete work and of hands of contractor  E-in-C have power to  Take possession of site, materials, T&P  Carryout part work/incomplete work at risk & cost of contractor
  • 17. Carrying out part work at risk and cost of contractor (clause – 14)  E-in-C will determine  Recoverable amount from contractor  Contractor liability on account of loss and damage suffered by government not more than 10% of tendered value  If the expenses by government is less than the amount payable to contract (@ agreement rates) difference not payable.  Excess expenditure to be recovered from contractor  If contractor fails to pay within 30days, e-in-C shall sell any or all the contractor’s material and T&P etc.  Balance as per T/C of contract  No compensation to contractor
  • 18. SUSPENSION OF WORK (Clause- 15)  E-in-C gives in writing to suspend work for reasons a) Default of contracts b) Reasons other than default of contractor c)For safety of work  Contractor shall protect the work during this period  For b) and c) above  Contractor entitled for extension of time for such period +25%  If exceeds 30 days contractor entitled for wages of staff/labour sitting idle  + 2% indirect expenses  Contractor to submit claim with in 15 days
  • 19. SUSPENSION OF WORK (Clause- 15)  If work is suspended for 90 days for reasons b) and c) the contracts to give notice to government within 10 days after expiry of 15 days  Contractor if treats it as abandonment by Govt, shall have no claim for compensation on account of loss of profit.  Contractor is entitled for: a) Salaries and wages of employees/labours at site remaining idle b) +2% indirect charges.
  • 20. Compensation for delay in supply of Govt. materials (Clause 15 A)  No compensation if delay is beyond the control of Govt.  Extension of time to be granted
  • 21. DEFECT LIABILITY PERIOD (Clause – 17)  Defect liability period 6 month, less than work Rs. 10 lacs  Defect liability period 12 month, more than work Rs. 10 lacs  Liable for damages during defect liability period  All defects to be made good during the period  If not firm the SD of the contractor  For road work 50% of SD to be refunded after six months
  • 22. SETTLEMENT OF DISPUTES (Clause – 25)  Arbitration clause:  All questions and disputes during the progress of work, after cancellation, terminiation, completion/abandonment  Any dispute, refer it to SE within 15 days, SE to reply within 30 days  If SE fails or contractor is dissatisfied appeal to CE within 30 days, CE will hear the contractor. Give his decision within 30 days.  If dissatisfied, appeal before the DRC (Dispute Redressal committee). DRC will give decision within 90 days.  Dissatisfied with the decision of DRC, either party may give notice to CE(C) within 30 days for appointments of arbitrator failing which decision shall be final/binding.
  • 23. SETTLEMENT OF DISPUTES (Clause – 25)  CE(C) shall refer the matter to sole arbitrator  Contractor to give list of disputes with amounts claimed  If the contractor does not request for appointment of arbitrator after 120 days of receiving intimation of final bills, the claims becomes time barred.  Arbitration and conciliation Act- 1996 applicable  Where claim exceeds Rs. 1 lakh, arbitrator to give reasons.