2. SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE
DOYLE DRIVE
Public Private Partnership
Industry Workshop
July 6, 2009
3. SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE
Doyle Drive Overview
Project Purpose
Environmental Approval
Project Setting
Early Schedule
4. SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE
Project Setting
Location Map
5. SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE
DOYLE DRIVE
Project Purpose and
Environmental Approval
6. SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE
Project Purpose
“Improve the seismic, structural, and
traffic safety of the roadway within the
setting and context of the Presidio of
San Francisco and its purpose as a
National Park.”
- Doyle Drive EIS/R
7. SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE
Project Consensus
FHWA
Doyle Drive Subcommittee
8. SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE
Environmental Process
2000 Initiate Environmental Process
2003 Introduce Parkway Concept
2005 Circulate Draft EIS/R
October 2008 Release Final EIS/R
January 2009 Record of Decision
9. SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE
The Presidio
10. SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE
Why Replace Doyle Drive?
11. SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE
Presidio Parkway
Replace deficient facility Two new tunnels
Wide landscaped median New direct access to Presidio
Continuous shoulders
12. SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE
Presidio Parkway
13. SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE
Original Project Timeline
Preferred Alt Fall 2010
Feb. Sept.
2000 Dec. Winter Spring
2006
Summer 2005 Dec 2014
2011
2000 2008
Detailed Design
Environmental Completed Project
Draft ESI/EIR Complete
Studies begin Public Comment Final Construction
ID Begins EIS/EIR Start
Alternatives
Begin Prelim
Engineering
Draft Final Start
EIS/EIR EIS/EIR Construction
For Comment ROD
= Milestones Completed
14. SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE
DOYLE DRIVE
Project Status
15. SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE
DOYLE DRIVE
Project Description and Status
16. SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE
Presentation Overview
Project Acceleration
Project Description
Conditions, Constraints, Limitations
Maintenance Requirements
Operations Requirements
17. SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE
Project Acceleration
To achieve seismic safety earlier (Feb. 2011)
To reduce risk of cost growth
To meet Economic Stimulus timetable
To take advantage of the favorable market
conditions
Help create jobs and support the local and
regional economy
18. SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE
Contracts
Pre-Construction Contracts:
Contract 1: Environmental mitigation (Built-Environmental Treatment
Plan) – Active through roadway contracts
Contract 2: Utility Plan and Relocation
Roadway Construction Contracts:
Contract 3: Southbound Presidio Interchange/High Viaduct
Contract 4: Southbound Battery Tunnel and At-Grade Detour
P3 Contracts:
Contract 5: Girard Interchange, Low Viaduct
Contract 6: Northbound Battery Tunnel, Main Post Tunnels
Contract 7: Northbound Presidio Interchange/High Viaduct
Contract 8: Landscaping
19. SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE
DRAFT Schedule
Seismic Safety
Achieved – Feb
2011
Contract 1
R/W Activities
Contract 2 Roadway
Complete –
Contract 3
Late 2012
Contract 4
Contract 5
Contract 6
Contract 7
P3
Contract 8
Original Project Schedule Completion – Spring 2014
20. SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE
Existing Site
Golden Gate Bridge Toll Plaza
We are here.
National Historic Park
Historic Buildings
Former Army Base
Presidio Trust
South Access to Golden Gate Bridge
21. SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE
Contract No. 3 – SB Presidio Interchange
Construction Capital $ 130 Million
Begin/End Construction: Oct 2009 - Summer 2011
Design – 100% complete
22. SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE
Contract No. 4 – Southbound Battery
Tunnel/Temporary at-grade detour
Construction Capital $ 110 Million
Begin/End Construction: Dec. 2009 – Summer 2011
Traffic Shift for Seismic Safety – February 2011
Design – 95% complete
23. SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE
DOYLE DRIVE
Construction Contracts for
P3 Procurement
24. SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE
Contract No. 5 – Tunnels
Construction Capital $ 233 Million
Begin/End Construction: Summer 2011- Early 2013
Design – 50% complete
25. SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE
Contract No. 6 – Girard Interchange
Construction Capital $144 Million
Begin/End Construction: Summer 2011 – Early 2013
Design – 50% complete
26. SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE
Contract No. 7 – NB Presidio Interchange
Construction Capital $103 Million
Begin/End Construction: Summer 2011 - Early 2013
Design – 55% complete
27. SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE
Contract No. 8 – Landscaping
Construction Capital $ 9 Million
Begin/End: Early 2013 – 2016
28. SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE
DOYLE DRIVE
Constraints, Conditions,
Limitations
29. SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE
Fixed Design Elements
Horizontal and vertical alignments
Cross-sections (lane and shoulder widths,
horizontal clearances)
Design Exceptions
Tunnel limits and portal shape
High Viaduct: Aesthetic, span
lengths/column location and structure type.
Fire Life Safety requirements for Tunnel
Contract 3 and 4 completed facility tie-ins.
30. SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE
Fixed Design Elements
ST-10 Barrier
31. SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE
Environmental/Regulatory Requirements
Final Environmental Impact Report/Statement (FEIR/S)
Record of Decision
Programmatic Agreement / Section 106
Water Quality Certification (RWQCB)
Nationwide Permit (USACOE)
Wetland Mitigation Monitoring Program
General Biological Monitoring Program
Migratory Bird Act
Bay Conservation and Development Commission (BCDC)
requirements
National Pollution Discharge Elimination System (NPDES)
32. SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE
DOYLE DRIVE
Maintenance
33. SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE
Maintenance - Roadway
Highway Signs and Traffic Control Devices
Pavement Striping and Delineation
Sweeping
Removal of all Debris and Objects
Drainage
Pavement
34. SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE
Maintenance - Roadside
Landscape
Guard Rail, Safety Devices, Bridge Rail
Maintenance
Tunnels
Pumping Plants
Electric and Mechanical Substations
Lighting
35. SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE
Maintenance - Facility
Structures
Substructures and superstructures
Graffiti Removal
36. SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE
DOYLE DRIVE
Operations
37. SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE
Operations
Day-To-Day Coordination:
Caltrans/CHP Transportation Management Center
(24/7/365 )
Bay Area 511 Traveler Information
City/County of San Francisco:
Signals & roadway maintenance
Golden Gate Bridge & Highway District:
Incident management & roadway maintenance
CHP: Homeland Security
38. SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE
Operations
Traffic Control:
Roadway/Lane Closure Charts
Seven days advance request
Approval process
Late pick-up penalties
Incident Management:
Tow Service:
Project Limits + Approaches on Park Presidio (Hwy 1), Lombard
Street, Marina Boulevard
TBD in coordination with:
• Golden Gate Bridge
• Bay Area Freeway Service Freeway Service Program
39. SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE
Operations
Other Coordination Required for:
Encroachment Permits: Utilities, Filming,
Special Events
Transportation Permits: Extra-Legal Loads
& Commercial Vehicles
Safety & Operational Investigations
40. SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE
Questions?