This document summarizes a seminar presentation on pile foundation work for a residential building project in Greater Noida. It describes the project details, including 9 towers of G+22 floors with 4 flats per floor. It then covers Indian standards for pile foundations, basic concepts of pile capacity calculation, equipment used, site specifications, materials, installation process, cage detailing, and column casting process.
1. SEMINAR PRESENTATION
OF
PILE FOUNDATION
MAYANK KUMARMAYANK KUMAR
GAURAV PACHAURIGAURAV PACHAURI
2010-20142010-2014
HINDUSTAN COLLEGE OF SCIENCEHINDUSTAN COLLEGE OF SCIENCE
& TECHNOLOGY , FARAH,& TECHNOLOGY , FARAH,
MATHURAMATHURA
2. S.D.S PRIVATE INFRATECHS.D.S PRIVATE INFRATECH
LTD.LTD.
NRI CITY PARI CHOWKNRI CITY PARI CHOWK
GREATER NOIDAGREATER NOIDA
3. PROJECT DETAILINGPROJECT DETAILING
NINE TOWER (RESIDENTIAL BUILDING)NINE TOWER (RESIDENTIAL BUILDING)
EACH TOWER HAVE G+22 FLOOREACH TOWER HAVE G+22 FLOOR
EACH FLOOR HAVE FOUR FLATSEACH FLOOR HAVE FOUR FLATS
PROJECT COST IS NEAR ABOUT 600PROJECT COST IS NEAR ABOUT 600
CRORECRORE
6. Indian Standards on PilesIndian Standards on Piles
IS 2911 : Part 1 : Sec 1 : 1979 DrivenIS 2911 : Part 1 : Sec 1 : 1979 Driven
cast in-situ concrete pilescast in-situ concrete piles
IS 2911 : Part 4 : 1985 Load test onIS 2911 : Part 4 : 1985 Load test on
pilespiles
7. BS8004 defines deep foundation with D>BBS8004 defines deep foundation with D>B
or D>3m.or D>3m.
Pile foundation always more expensivePile foundation always more expensive
than shallow foundation but will overcomethan shallow foundation but will overcome
problems of soft surface soils byproblems of soft surface soils by
transferring load to stronger, deepertransferring load to stronger, deeper
stratum, thereby reducing settlements.stratum, thereby reducing settlements.
Top layers of soil are highly compressibleTop layers of soil are highly compressible
for it to supportfor it to support
Why Pile Foundations Prefer
8.
9. W
Qu
Qb
Qs
Basic ConceptBasic Concept
The ultimate bearing capacity (QThe ultimate bearing capacity (Quu )of a pile)of a pile
may be assessed using soil mechanicsmay be assessed using soil mechanics
principles. The capacity is assumed to be theprinciples. The capacity is assumed to be the
sum of skin friction and end-bearingsum of skin friction and end-bearing
resistance, i.eresistance, i.e
QQuu =Q=Qbb+Q+Qss-W-W ……………………………………………….(1).(1)
wherewhere
QQuu total pile resistance,total pile resistance,
QQbb is the end bearing resistance andis the end bearing resistance and
QQss is side friction resistanceis side friction resistance
10. EQUIPMENT USED IN PILEEQUIPMENT USED IN PILE
FOUNDATION WORKFOUNDATION WORK
1- WINCH MACHINE1- WINCH MACHINE
14. 6-CASING PIPE6-CASING PIPE
7-CHAIN WITH HIGH WEIGHT AT LOWER7-CHAIN WITH HIGH WEIGHT AT LOWER
SIDESIDE
15. SPECIFICATIONS USED ATSPECIFICATIONS USED AT
SITESITE
Min cement content 400 kg/m3 of concreteMin cement content 400 kg/m3 of concrete
Min bentonite used in water – 2kg/1000lit.Min bentonite used in water – 2kg/1000lit.
Pile head is prepared after 28 days.Pile head is prepared after 28 days.
Min 1m case left above ground level.(LMin 1m case left above ground level.(L
shape)shape)
16. MATERIAL USEDMATERIAL USED
Bentonite (2kg per 1000 lit.)Bentonite (2kg per 1000 lit.)
Concrete (M35 grade)Concrete (M35 grade)
Steel (Fe 415 grade)Steel (Fe 415 grade)
WaterWater
17. Caisson Installation SequenceCaisson Installation Sequence
CenteringCentering
Hole drilled with winch machineHole drilled with winch machine
Casing installed with help of drop hammerCasing installed with help of drop hammer
Washing (water with bentonite)Washing (water with bentonite)
Bottom inspected and testedBottom inspected and tested
Reinforced (Cage lowering)Reinforced (Cage lowering)
Termie pipe loweringTermie pipe lowering
Concrete placement (& casing removal)Concrete placement (& casing removal)
18. DETAILING OF CAGEDETAILING OF CAGE
Steel is used in casing (Fe-500)Steel is used in casing (Fe-500)
Two 9.5 m cage usedTwo 9.5 m cage used
8 no of bars in each case (4-16mm dia8 no of bars in each case (4-16mm dia
and 4-20mm dia)and 4-20mm dia)
Ring used 8mm dia 150mm c/c spacingRing used 8mm dia 150mm c/c spacing
Additional master ring 12mm dia usedAdditional master ring 12mm dia used
1500 c/c spacing1500 c/c spacing
Each ring is welded with main barsEach ring is welded with main bars
19. Lap length 45 time of bigger bar dia (minLap length 45 time of bigger bar dia (min
900mm)900mm)
100mm c/c ring is used at lap length.100mm c/c ring is used at lap length.
21. PROCESS OF COLUMNPROCESS OF COLUMN
CASTINGCASTING Layout of columnLayout of column
Reinforcement (according to drawing)Reinforcement (according to drawing)
ShutteringShuttering
Checking of shuttering in inclination with help ofChecking of shuttering in inclination with help of
plumb-bobplumb-bob
Testing of material at site(cube test, slump test)Testing of material at site(cube test, slump test)
ConcretingConcreting
Needle vibrator used max 1 min. in a placeNeedle vibrator used max 1 min. in a place
22. SPECIFICATIONSPECIFICATION
Lap length 47 time of main bar dia.Lap length 47 time of main bar dia.
Column cover 40mmColumn cover 40mm
1/3 bars to be overlapped at one location1/3 bars to be overlapped at one location
Tie bars dia.- 12mmTie bars dia.- 12mm
Spacing at beam column connection joint-Spacing at beam column connection joint-
100m c/c100m c/c
Column will not be cast much than 2mColumn will not be cast much than 2m
height.height.