SPECIFICATION
WRITING
BRIEF SPECIFICATION FOR 1ST CLASS BRICKWORK IN CM (1:6)
PropertiesofBricks–Soakinginwater–mortar–Workmanship–measurement–Scaffolding.
 Brick shall be table – moulded, well burnt in approved kiln, copper coloured, free from cracks and with sharp
andsquareedges
 The brick shall be uniform in shape and shall be of standard size and shall give a clear ringing sound when
struckwitheachother.
 Thebrick shallnotabsorb watermore thanonefifth of theirweightafteronehour of soaking inwater.
 Brickshallhavemaximum crushingstrengthof 10.5 N/mm2.
 The bricks shall be well soaked in water for atleast 12 hours before their use, preferably in water tank provided
atsiteof work.
 Theproportion of mortarshallbe 1:6 by volume.
 Thecement shallbe standardquality.
 Thesandshallbe cleanand course.
 The cement mortar shall be prepared in required quantity of not more than one bag of cement at a
timeandthisshall beconsumedin halfanhouraftermixing.
 Themixing ofmortarshall bedoneon awatertightplatformorin asteel trough.
 Thewaterfit fordrinking shallbeusedin preparingmortar.
 Thebrokenbricksshall notbeusedexceptasclosers.
 All cornersshallbetrulyin plumbandsidesshall bein line andlevel.
 Themortarshallbreakforbondingandshallnotexceed10 mm in thickness.
 All jointsshallberakedandfacesofwall shall becleanedattheendofeach dayswork.
 Only skilled masons shall be employed on the work and the work shall be kept well watered for at least 15
days.
 All brickworkshall becarriedoutin sucha waythatnoportionisraisedunduly aboveanother.
 Thelength andheight shallbemeasuredasonatsite.
 Thethicknessofwall shallbepaidforasonebrick,oneandhalfbricks,twobricksandsoon.
 Tofacilitatetheconstructionofbrickwork,necessaryandsuitablescaffoldingshall beprovided.
 Thescaffoldingshall bestrongandsoundandwithsufficientstrongsupports.
 Therateforbrickworkincludesthisnecessaryscaffoldingalso.
DETAILED SPECIFICATION FOR EARTHWORKEXCAVATION
Startingofwork–workmanship–excavatedmaterial–protectiontoexistingservices–measurement–
whattherateincludes.
 The excavation for the foundation trenches shall be carried out in all sorts of soils as per plan and
lining approvedatsite.
 Thesidesofthefoundationtrenchesshall betrulyvertical andbottomshall beuniformlylevelled.
 The excavated material shall be stacked away from the sides of the trenches of the excavation by
atleast2m.
 Thesurplusexcavatedmaterialshall bespreadoutuniformly uptoa leadof 100m.
 All the existing services such as pipes, sewers, electric cables etc., which are met with in foundation
trenchesshall becarefullysupportedandprotectedbycontractorasperinstructionoftheengineer.
 The excavation shall be measured as per exact length and width of the lowest step of footings
accordingtodrawing.
 The rate of excavation includes all timbering and other supports which are necessary for securing the
sidesofthetrenchesandthecontractorshall beresponsiblefortheirsafety.
 Noextraamountshallbepaidtothecontractorfortheexcavationoftheworkingspace.
 Thematerialorvaluablefoundduringexcavationshall bethepropertyoftheowner.
SPECIFICATION FOR MARBLE FLOORING
Quality of marble - samples –anchors and dowels –vertical and horizontal surfaces –
workmanship –finishing –measurement.
 The marble to be used for the work shall be first class quality, free from cracks, non porous, uniform in
colourandcarefullyselectedso astopresent harmoniousveins throughoutthefinished work.
 The samples of each type to be used shall be submitted to show the full range of variation and the work
shall becompletedwith marblesin accordancewiththeapprovedsamplebytheengineer.
 All necessary bronzeorbrassanchors ,dowels,clamps,wires etc,requiredtosecurethe marblesin place
shall havetobeprovidedbythe contractorandbuiltin atnoextracosttotheowner.
 Nomarbleshallbefacescrew.
 The vertical work commencing at floor level shall be allowed to set before the flooring is laid and the
marbleshall extendabout25mm belowthefinishedfloorlevel.
 The vertical and horizontal surfaces shall be laid in cement mortar (1:3) and the joints shall be finished
withwhitecement.
 The vertical marble shall be machine polished in the workshop and the hzl marbles shall be machine
polished afterlaying.
 The marble for dado and skirting shall be set in non staining white cement and of height described in
drawing.
 Theskirtingshallbe plain,roundedorofbevelled edges.
 Marbleworkshall becarriedoutin thebestworkmanshipmanner.
 All necessary precautions shall be taken to prevent staining or discolouration of marble surface due to
anymaterialusedin setting.
 All joints shallshow perfectalignment ofsurfaceandshall begroutedtomatchthecolourofmarble.
 All marble work shall be covered or finished with wax or other protective material as may be necessary
when set.
 The payment shall be made for the actual work done on site on superficial area basis and no extra
amountshall bepaidforwastageofmaterials,anchors,dowels,etc,
 The rate of the marble work shall include any drilling, cutting, fitting or making any special provisions
requiredin themarblework.
SPECIFICATION FOR 12MM THICK CEMENT PLASTER IN CM (1:4)
Preliminary – process of first coat – second coat of sagol finish after six hours of first
coat –watering –three coats ofwhite or colour wash - measurement

Weitere ähnliche Inhalte

Ähnlich wie UNIT 2.pptx

Sample copy of IT PPT.pptx
Sample copy of IT PPT.pptxSample copy of IT PPT.pptx
Sample copy of IT PPT.pptxHimanshumangal12
 
Detailed specifications
Detailed specificationsDetailed specifications
Detailed specificationsSimran Vats
 
Buiding construction (part ii)
Buiding construction (part ii)Buiding construction (part ii)
Buiding construction (part ii)Waqas Aslam
 
CASE STUDY of remedial measure of civil works
CASE STUDY of remedial measure of civil worksCASE STUDY of remedial measure of civil works
CASE STUDY of remedial measure of civil worksKumarS250747
 
CASE STUDY. on Restoration and rehabilitation
CASE STUDY. on Restoration and rehabilitationCASE STUDY. on Restoration and rehabilitation
CASE STUDY. on Restoration and rehabilitationKumarS250747
 
Waterproffing.pptx
Waterproffing.pptxWaterproffing.pptx
Waterproffing.pptxPrituJadhav1
 
Aggrigatemortor 170209141826
Aggrigatemortor 170209141826Aggrigatemortor 170209141826
Aggrigatemortor 170209141826ram saran
 
Building materials, Basic civil engineering ,unit-1
Building materials, Basic civil engineering ,unit-1Building materials, Basic civil engineering ,unit-1
Building materials, Basic civil engineering ,unit-1Parimal Jha
 
cf_Special Concrete SHOTCRETE PRESENTATION_124_CE60021543644600-1.pptx
cf_Special Concrete SHOTCRETE PRESENTATION_124_CE60021543644600-1.pptxcf_Special Concrete SHOTCRETE PRESENTATION_124_CE60021543644600-1.pptx
cf_Special Concrete SHOTCRETE PRESENTATION_124_CE60021543644600-1.pptxKavithaSuresh31
 

Ähnlich wie UNIT 2.pptx (20)

Roof Specifications
Roof SpecificationsRoof Specifications
Roof Specifications
 
Finishing of cement
Finishing of cementFinishing of cement
Finishing of cement
 
2_2._BOQ.pdf
2_2._BOQ.pdf2_2._BOQ.pdf
2_2._BOQ.pdf
 
Proportions of concrete
Proportions of concreteProportions of concrete
Proportions of concrete
 
Sample copy of IT PPT.pptx
Sample copy of IT PPT.pptxSample copy of IT PPT.pptx
Sample copy of IT PPT.pptx
 
Detailed specifications
Detailed specificationsDetailed specifications
Detailed specifications
 
Buiding construction (part ii)
Buiding construction (part ii)Buiding construction (part ii)
Buiding construction (part ii)
 
Imp Aspect of road.ppt
Imp Aspect of road.pptImp Aspect of road.ppt
Imp Aspect of road.ppt
 
CASE STUDY of remedial measure of civil works
CASE STUDY of remedial measure of civil worksCASE STUDY of remedial measure of civil works
CASE STUDY of remedial measure of civil works
 
CASE STUDY. on Restoration and rehabilitation
CASE STUDY. on Restoration and rehabilitationCASE STUDY. on Restoration and rehabilitation
CASE STUDY. on Restoration and rehabilitation
 
Waterproffing.pptx
Waterproffing.pptxWaterproffing.pptx
Waterproffing.pptx
 
rcc.pptx
rcc.pptxrcc.pptx
rcc.pptx
 
Aggrigatemortor 170209141826
Aggrigatemortor 170209141826Aggrigatemortor 170209141826
Aggrigatemortor 170209141826
 
construction study project sjce ctm
construction study project sjce ctmconstruction study project sjce ctm
construction study project sjce ctm
 
Work check list
Work check listWork check list
Work check list
 
Building materials, Basic civil engineering ,unit-1
Building materials, Basic civil engineering ,unit-1Building materials, Basic civil engineering ,unit-1
Building materials, Basic civil engineering ,unit-1
 
Damp proofing
Damp proofingDamp proofing
Damp proofing
 
Basic Details (1).pptx
Basic Details (1).pptxBasic Details (1).pptx
Basic Details (1).pptx
 
cf_Special Concrete SHOTCRETE PRESENTATION_124_CE60021543644600-1.pptx
cf_Special Concrete SHOTCRETE PRESENTATION_124_CE60021543644600-1.pptxcf_Special Concrete SHOTCRETE PRESENTATION_124_CE60021543644600-1.pptx
cf_Special Concrete SHOTCRETE PRESENTATION_124_CE60021543644600-1.pptx
 
Dishant ppt
Dishant pptDishant ppt
Dishant ppt
 

Mehr von Anbarasan Sivaraj

prestressgrouppresentation-140202022807-phpapp02.pptx
prestressgrouppresentation-140202022807-phpapp02.pptxprestressgrouppresentation-140202022807-phpapp02.pptx
prestressgrouppresentation-140202022807-phpapp02.pptxAnbarasan Sivaraj
 
sm-ich-1-150513173810-lva1-app6891.pptx
sm-ich-1-150513173810-lva1-app6891.pptxsm-ich-1-150513173810-lva1-app6891.pptx
sm-ich-1-150513173810-lva1-app6891.pptxAnbarasan Sivaraj
 
Introduction_of_Soil_Mechanics.pptx
Introduction_of_Soil_Mechanics.pptxIntroduction_of_Soil_Mechanics.pptx
Introduction_of_Soil_Mechanics.pptxAnbarasan Sivaraj
 
portal-frame-160216003349.pdf
portal-frame-160216003349.pdfportal-frame-160216003349.pdf
portal-frame-160216003349.pdfAnbarasan Sivaraj
 
Statically-Indeterminate-Beams-.pdf
Statically-Indeterminate-Beams-.pdfStatically-Indeterminate-Beams-.pdf
Statically-Indeterminate-Beams-.pdfAnbarasan Sivaraj
 
typesofloads-180410052323.pdf
typesofloads-180410052323.pdftypesofloads-180410052323.pdf
typesofloads-180410052323.pdfAnbarasan Sivaraj
 
Chainsurveying 170820112206-converted
Chainsurveying 170820112206-convertedChainsurveying 170820112206-converted
Chainsurveying 170820112206-convertedAnbarasan Sivaraj
 

Mehr von Anbarasan Sivaraj (12)

prestressgrouppresentation-140202022807-phpapp02.pptx
prestressgrouppresentation-140202022807-phpapp02.pptxprestressgrouppresentation-140202022807-phpapp02.pptx
prestressgrouppresentation-140202022807-phpapp02.pptx
 
DESIGN OF FOOTINGS.pptx
DESIGN OF FOOTINGS.pptxDESIGN OF FOOTINGS.pptx
DESIGN OF FOOTINGS.pptx
 
footing.pdf
footing.pdffooting.pdf
footing.pdf
 
20160716_WATER SUPPLY.ppt
20160716_WATER SUPPLY.ppt20160716_WATER SUPPLY.ppt
20160716_WATER SUPPLY.ppt
 
MADRAS TERRACE ROOF.ppt
MADRAS TERRACE ROOF.pptMADRAS TERRACE ROOF.ppt
MADRAS TERRACE ROOF.ppt
 
sm-ich-1-150513173810-lva1-app6891.pptx
sm-ich-1-150513173810-lva1-app6891.pptxsm-ich-1-150513173810-lva1-app6891.pptx
sm-ich-1-150513173810-lva1-app6891.pptx
 
Introduction_of_Soil_Mechanics.pptx
Introduction_of_Soil_Mechanics.pptxIntroduction_of_Soil_Mechanics.pptx
Introduction_of_Soil_Mechanics.pptx
 
portal-frame-160216003349.pdf
portal-frame-160216003349.pdfportal-frame-160216003349.pdf
portal-frame-160216003349.pdf
 
Statically-Indeterminate-Beams-.pdf
Statically-Indeterminate-Beams-.pdfStatically-Indeterminate-Beams-.pdf
Statically-Indeterminate-Beams-.pdf
 
typesofloads-180410052323.pdf
typesofloads-180410052323.pdftypesofloads-180410052323.pdf
typesofloads-180410052323.pdf
 
UNIT 1.PPTX
UNIT 1.PPTXUNIT 1.PPTX
UNIT 1.PPTX
 
Chainsurveying 170820112206-converted
Chainsurveying 170820112206-convertedChainsurveying 170820112206-converted
Chainsurveying 170820112206-converted
 

Kürzlich hochgeladen

Fostering Friendships - Enhancing Social Bonds in the Classroom
Fostering Friendships - Enhancing Social Bonds  in the ClassroomFostering Friendships - Enhancing Social Bonds  in the Classroom
Fostering Friendships - Enhancing Social Bonds in the ClassroomPooky Knightsmith
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdfQucHHunhnh
 
Towards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptxTowards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptxJisc
 
The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxheathfieldcps1
 
Understanding Accommodations and Modifications
Understanding  Accommodations and ModificationsUnderstanding  Accommodations and Modifications
Understanding Accommodations and ModificationsMJDuyan
 
Sociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning ExhibitSociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning Exhibitjbellavia9
 
Salient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functionsSalient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functionsKarakKing
 
Application orientated numerical on hev.ppt
Application orientated numerical on hev.pptApplication orientated numerical on hev.ppt
Application orientated numerical on hev.pptRamjanShidvankar
 
Vishram Singh - Textbook of Anatomy Upper Limb and Thorax.. Volume 1 (1).pdf
Vishram Singh - Textbook of Anatomy  Upper Limb and Thorax.. Volume 1 (1).pdfVishram Singh - Textbook of Anatomy  Upper Limb and Thorax.. Volume 1 (1).pdf
Vishram Singh - Textbook of Anatomy Upper Limb and Thorax.. Volume 1 (1).pdfssuserdda66b
 
How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17Celine George
 
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...christianmathematics
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfciinovamais
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfagholdier
 
ICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxAreebaZafar22
 
ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.MaryamAhmad92
 
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdfUGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdfNirmal Dwivedi
 
Single or Multiple melodic lines structure
Single or Multiple melodic lines structureSingle or Multiple melodic lines structure
Single or Multiple melodic lines structuredhanjurrannsibayan2
 
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptxHMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptxEsquimalt MFRC
 
Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...Association for Project Management
 

Kürzlich hochgeladen (20)

Fostering Friendships - Enhancing Social Bonds in the Classroom
Fostering Friendships - Enhancing Social Bonds  in the ClassroomFostering Friendships - Enhancing Social Bonds  in the Classroom
Fostering Friendships - Enhancing Social Bonds in the Classroom
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdf
 
Towards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptxTowards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptx
 
The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptx
 
Understanding Accommodations and Modifications
Understanding  Accommodations and ModificationsUnderstanding  Accommodations and Modifications
Understanding Accommodations and Modifications
 
Sociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning ExhibitSociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning Exhibit
 
Salient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functionsSalient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functions
 
Application orientated numerical on hev.ppt
Application orientated numerical on hev.pptApplication orientated numerical on hev.ppt
Application orientated numerical on hev.ppt
 
Vishram Singh - Textbook of Anatomy Upper Limb and Thorax.. Volume 1 (1).pdf
Vishram Singh - Textbook of Anatomy  Upper Limb and Thorax.. Volume 1 (1).pdfVishram Singh - Textbook of Anatomy  Upper Limb and Thorax.. Volume 1 (1).pdf
Vishram Singh - Textbook of Anatomy Upper Limb and Thorax.. Volume 1 (1).pdf
 
How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17
 
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdf
 
ICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptx
 
ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.
 
Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024
 
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdfUGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
 
Single or Multiple melodic lines structure
Single or Multiple melodic lines structureSingle or Multiple melodic lines structure
Single or Multiple melodic lines structure
 
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptxHMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
 
Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...
 

UNIT 2.pptx

  • 2. BRIEF SPECIFICATION FOR 1ST CLASS BRICKWORK IN CM (1:6) PropertiesofBricks–Soakinginwater–mortar–Workmanship–measurement–Scaffolding.  Brick shall be table – moulded, well burnt in approved kiln, copper coloured, free from cracks and with sharp andsquareedges  The brick shall be uniform in shape and shall be of standard size and shall give a clear ringing sound when struckwitheachother.  Thebrick shallnotabsorb watermore thanonefifth of theirweightafteronehour of soaking inwater.  Brickshallhavemaximum crushingstrengthof 10.5 N/mm2.  The bricks shall be well soaked in water for atleast 12 hours before their use, preferably in water tank provided atsiteof work.  Theproportion of mortarshallbe 1:6 by volume.  Thecement shallbe standardquality.  Thesandshallbe cleanand course.
  • 3.  The cement mortar shall be prepared in required quantity of not more than one bag of cement at a timeandthisshall beconsumedin halfanhouraftermixing.  Themixing ofmortarshall bedoneon awatertightplatformorin asteel trough.  Thewaterfit fordrinking shallbeusedin preparingmortar.  Thebrokenbricksshall notbeusedexceptasclosers.  All cornersshallbetrulyin plumbandsidesshall bein line andlevel.  Themortarshallbreakforbondingandshallnotexceed10 mm in thickness.  All jointsshallberakedandfacesofwall shall becleanedattheendofeach dayswork.
  • 4.  Only skilled masons shall be employed on the work and the work shall be kept well watered for at least 15 days.  All brickworkshall becarriedoutin sucha waythatnoportionisraisedunduly aboveanother.  Thelength andheight shallbemeasuredasonatsite.  Thethicknessofwall shallbepaidforasonebrick,oneandhalfbricks,twobricksandsoon.  Tofacilitatetheconstructionofbrickwork,necessaryandsuitablescaffoldingshall beprovided.  Thescaffoldingshall bestrongandsoundandwithsufficientstrongsupports.  Therateforbrickworkincludesthisnecessaryscaffoldingalso.
  • 5. DETAILED SPECIFICATION FOR EARTHWORKEXCAVATION Startingofwork–workmanship–excavatedmaterial–protectiontoexistingservices–measurement– whattherateincludes.  The excavation for the foundation trenches shall be carried out in all sorts of soils as per plan and lining approvedatsite.  Thesidesofthefoundationtrenchesshall betrulyvertical andbottomshall beuniformlylevelled.  The excavated material shall be stacked away from the sides of the trenches of the excavation by atleast2m.  Thesurplusexcavatedmaterialshall bespreadoutuniformly uptoa leadof 100m.  All the existing services such as pipes, sewers, electric cables etc., which are met with in foundation trenchesshall becarefullysupportedandprotectedbycontractorasperinstructionoftheengineer.
  • 6.  The excavation shall be measured as per exact length and width of the lowest step of footings accordingtodrawing.  The rate of excavation includes all timbering and other supports which are necessary for securing the sidesofthetrenchesandthecontractorshall beresponsiblefortheirsafety.  Noextraamountshallbepaidtothecontractorfortheexcavationoftheworkingspace.  Thematerialorvaluablefoundduringexcavationshall bethepropertyoftheowner.
  • 7. SPECIFICATION FOR MARBLE FLOORING Quality of marble - samples –anchors and dowels –vertical and horizontal surfaces – workmanship –finishing –measurement.  The marble to be used for the work shall be first class quality, free from cracks, non porous, uniform in colourandcarefullyselectedso astopresent harmoniousveins throughoutthefinished work.  The samples of each type to be used shall be submitted to show the full range of variation and the work shall becompletedwith marblesin accordancewiththeapprovedsamplebytheengineer.  All necessary bronzeorbrassanchors ,dowels,clamps,wires etc,requiredtosecurethe marblesin place shall havetobeprovidedbythe contractorandbuiltin atnoextracosttotheowner.  Nomarbleshallbefacescrew.
  • 8.  The vertical work commencing at floor level shall be allowed to set before the flooring is laid and the marbleshall extendabout25mm belowthefinishedfloorlevel.  The vertical and horizontal surfaces shall be laid in cement mortar (1:3) and the joints shall be finished withwhitecement.  The vertical marble shall be machine polished in the workshop and the hzl marbles shall be machine polished afterlaying.  The marble for dado and skirting shall be set in non staining white cement and of height described in drawing.  Theskirtingshallbe plain,roundedorofbevelled edges.  Marbleworkshall becarriedoutin thebestworkmanshipmanner.  All necessary precautions shall be taken to prevent staining or discolouration of marble surface due to anymaterialusedin setting.
  • 9.  All joints shallshow perfectalignment ofsurfaceandshall begroutedtomatchthecolourofmarble.  All marble work shall be covered or finished with wax or other protective material as may be necessary when set.  The payment shall be made for the actual work done on site on superficial area basis and no extra amountshall bepaidforwastageofmaterials,anchors,dowels,etc,  The rate of the marble work shall include any drilling, cutting, fitting or making any special provisions requiredin themarblework.
  • 10. SPECIFICATION FOR 12MM THICK CEMENT PLASTER IN CM (1:4) Preliminary – process of first coat – second coat of sagol finish after six hours of first coat –watering –three coats ofwhite or colour wash - measurement