A
REPORT ON VISIT TO
NATIONAL BUILDING CONSTRUCTION
CORPORATION LTD.
ON – GRID SOLAR POWER PLANT OF 10KWp
PREPARED BY:
AMITESH KUMAR
VISIT TO NBCC ON-GRID 10KWp SOLAR POWER PLANT | Amitesh
DATE: 11 NOV 2014
Site Name: National Buildings Construction Corporation Ltd. (NBCC) Ghitorni, New Delhi – 110003
Latitude: 29º01' Degree North
Longitude: 77º38' Degree East
Figure: 1 Side View of the plant Installed at NBCC, Ghitorni having a capacity of 10KWp
The installation of on-grid solar power plant at NBCC, Ghitorni has a capacity of 10KWp. It is a fixed installation
facing towards south and an installation angle (β) of 30ᵒ.
Electrical Specifications:
Module PM – 170.
No. of modules in Series – 20.
Parallel Combination – 3.
No. of FJB – 3.
Module wire – 1x4 Sq.mm.
Conduit Wiring – P.V.C conduit 32mm.
Civil foundation - Angle Bar – 50x50x6 (structure and legs)
Pile – 1x1 Foot.
Data Obtained From Inverter Display at 1:20 PM
DC Side V (Volt) I (Amps) V (Volt) I (Amps)
String 1 617 6.4 To Grid 241 8.1
String 2 598 3.0
String 3
VISIT TO NBCC ON-GRID 10KWp SOLAR POWER PLANT | Amitesh
Balance of System (BOS) Described:
1. SPV ARRAY
The SPV array of 10 KWp capacity consist of 60no. Of modules of PM160 wired in 20 series- 3 parallel
configuration. The modules shall be fixed on corrosion resistantMS structures. The SPV module has 72 number
of crystalline silicon solar cells connected in series and hermetically sealed with high transmission toughened
glass on top and suitable lamination material on back using state-of-the-art technology. The laminates are
framed using anodized aluminum channels. A terminal block is fixed on the frames for taking the electrical
output. The SPV array is grouted on Galvanized MS support structure on the ground near the buildings.
2. INVERTER
The SUNNY TRIPOWER solar inverters characterize the technology and are optimally suitable for use in small
and mid-range systems. These inverters have first class efficiency, user-friendliness and reliability and come with
innovative technologies such as OptiTrac and H5-Topology. These make the device even more efficient and
therefore ensure a very good solar yield. Automatic grid voltage detection and an integrated DC disconnect
switch simplifies installation, ensuring safety as well as saving time. These models feature galvanic isolation and
can be used with all types of modules. The die-cast aluminium enclosure, with the OptiCool active temperature
management system, guarantees the highest yields possible and a long service life, even under extreme
conditions.
Figure: 1 Sunny TriPower Inverter (Left) & LCD Display (Right)
VISIT TO NBCC ON-GRID 10KWp SOLAR POWER PLANT | Amitesh
3. GROUNDING OF THE SPV ARRAY
All the non-current carrying panel structures are connected with the earth pit. Apart from this, all other non-
current carrying metallic parts such as FJB and Inverter have also been earthed.
Figure: 2 Interconnection between Structures for grounding (Left) & Earth Pit (Right)
4. SUPPORT STRUCTURES
The modules are mounted on support structures fabricated from Mild steel, which are fixed on the ground as
shown in the drawing. The structures are hot dip galvanized to make them non-corrosive and long lasting.
Twelve Structures Carry 5 Modules each (Total Modules 60 Nos.). The structures are designed so as to withstand
a horizontal wind speed of 150 KMPH.
Figure: 3 Pile Single bolt foundation
VISIT TO NBCC ON-GRID 10KWp SOLAR POWER PLANT | Amitesh
5. The technical specifications of the recommended SPV Plant are as follows:
General
SPV Module
SPV Array Power (Total 10 KWp)
Module type Crystalline silicon
Module power PM160 (160Wp-170Wp)
Inverter
Rating 10KW
Mounting Indoor inside control room (provided by Customer)
No. of Inverters 1
Enclosures IP 20
Other accessories
Cables BIS Copper Conductors
Module mounting frame Galvanized MS frame
6. Module Data Sheet:
SOLAR PV MODULE PM 160
ELECTRICAL PARAMETERS
Maximum Power Rating (Wp) 160
Minimum Power Rating (Wp) 150
Rated Current Im (Amps) 4.45
Rated Voltage Vm (Volts) 36
Short Circuit Current Isc (Amps) 5.0
Open Circuit Voltage Voc (Volts) 44
PHYSICAL PARAMETERS
VISIT TO NBCC ON-GRID 10KWp SOLAR POWER PLANT | Amitesh
No. of Cells 72
Dimensions (approx.) 1580(L)x805(W)x42(T)
Weight (Kg) 14.5
ENVIRONMENTAL RATINGS
Nominal Operating Cell Temp.(C) 492
Max. Allowed Module Temp.(C) -40 to + 85
Max. Allowed System Voltage(V) 1000
RH at 85C 85
Temp. Coefficient of Isc +0.0004/K
Temp. Coefficient of Voc -0.0034/K
7. Inverter Specifications
SUNNY TRIPOWER 10000TL
Input (DC) Output (AC)
Max DC Power (@ Cos Ф=
1)
10200 Rated Power (@ 230 V,
50 Hz)
10000 W
Max. Input voltage 1000 Max. Apparent AC power 10000VA
MPP Voltage Range /
Rated input voltage
320 V – 800 V / 600 V Nominal AC voltage
range
160 V – 280 V
Min. Input Voltage / Initial
input voltage
150 A / 180 A AC power frequency /
range
50 Hz, 60Hz / -6 Hz ...
+5 Hz
Max. Input Current Input
A/ Input B
22 A / 11A Rated grid frequency /
rated grid voltage
50 Hz / 230 V
Max. Input Current Per
String Input A/ Input B
33 A / 12.5 A Max. output current 16 A
Number Of Independent
MPP Inputs / Strings per
MPP input
2 / A: 4; B: 1 Adjustable displacement
factor
0.8 over exited ... 0.8
Under exited

Weitere ähnliche Inhalte

Was ist angesagt?

Drawings & Documents Required for Solar Projects
Drawings & Documents Required for Solar ProjectsDrawings & Documents Required for Solar Projects
Drawings & Documents Required for Solar ProjectsGensol Engineering Limited
 
Steinbeis 1MW Grid Connected System design report
Steinbeis 1MW Grid Connected System design reportSteinbeis 1MW Grid Connected System design report
Steinbeis 1MW Grid Connected System design reportShrikant Hiremath
 
Financial analysis of 1 MW Solar PV plant
Financial analysis of 1 MW Solar PV plantFinancial analysis of 1 MW Solar PV plant
Financial analysis of 1 MW Solar PV plantDr Naim R Kidwai
 
PV solar Design and Installtion
PV solar Design and InstalltionPV solar Design and Installtion
PV solar Design and InstalltionEli Israeli
 
Photovoltaic Training - Session 4 - Plant Maintenance
Photovoltaic Training - Session 4 - Plant MaintenancePhotovoltaic Training - Session 4 - Plant Maintenance
Photovoltaic Training - Session 4 - Plant MaintenanceLeonardo ENERGY
 
Study of Large Scale Grid interactive Solar PV power plant
Study of Large Scale Grid interactive Solar PV power plantStudy of Large Scale Grid interactive Solar PV power plant
Study of Large Scale Grid interactive Solar PV power plantShahbaz Makandar A.
 
10 mw solar power plant
10 mw solar power plant10 mw solar power plant
10 mw solar power plantRusiru Sanjaya
 
Engineering Drawings required for Solar Projects
Engineering Drawings required for Solar Projects Engineering Drawings required for Solar Projects
Engineering Drawings required for Solar Projects Gensol Engineering Limited
 
Solar Panel Installation Proposal PowerPoint Presentation Slides
Solar Panel Installation Proposal PowerPoint Presentation SlidesSolar Panel Installation Proposal PowerPoint Presentation Slides
Solar Panel Installation Proposal PowerPoint Presentation SlidesSlideTeam
 
Solar Power Plant System Sizing
Solar Power Plant System SizingSolar Power Plant System Sizing
Solar Power Plant System Sizingfirstgreen
 
Photovoltaic Training - Session 1 - Design
Photovoltaic Training - Session 1 - DesignPhotovoltaic Training - Session 1 - Design
Photovoltaic Training - Session 1 - DesignLeonardo ENERGY
 
Solar Project Management
Solar Project ManagementSolar Project Management
Solar Project Managementfirstgreen
 
Proposal for a 2MW fspv system and e-transport
Proposal for a 2MW fspv system and e-transportProposal for a 2MW fspv system and e-transport
Proposal for a 2MW fspv system and e-transportAnkit Singh
 
Solar Panel Installation And Maintenance PowerPoint Presentation Slides
Solar Panel Installation And Maintenance PowerPoint Presentation SlidesSolar Panel Installation And Maintenance PowerPoint Presentation Slides
Solar Panel Installation And Maintenance PowerPoint Presentation SlidesSlideTeam
 
Photovoltaic Training Course - Module 2.7 - Commissioning tests
Photovoltaic Training Course - Module 2.7 - Commissioning testsPhotovoltaic Training Course - Module 2.7 - Commissioning tests
Photovoltaic Training Course - Module 2.7 - Commissioning testsLeonardo ENERGY
 
1 MW solar Power plant project Scheduling and Tracking
1 MW solar Power plant project Scheduling and Tracking1 MW solar Power plant project Scheduling and Tracking
1 MW solar Power plant project Scheduling and TrackingATUL RAJ
 
Ppt on design of solar photovoltaic generation for residential building
Ppt on design of solar photovoltaic generation for residential buildingPpt on design of solar photovoltaic generation for residential building
Ppt on design of solar photovoltaic generation for residential buildingSiya Agarwal
 

Was ist angesagt? (20)

Guide to Solar Project Implementation
Guide to Solar Project ImplementationGuide to Solar Project Implementation
Guide to Solar Project Implementation
 
Drawings & Documents Required for Solar Projects
Drawings & Documents Required for Solar ProjectsDrawings & Documents Required for Solar Projects
Drawings & Documents Required for Solar Projects
 
Steinbeis 1MW Grid Connected System design report
Steinbeis 1MW Grid Connected System design reportSteinbeis 1MW Grid Connected System design report
Steinbeis 1MW Grid Connected System design report
 
Financial analysis of 1 MW Solar PV plant
Financial analysis of 1 MW Solar PV plantFinancial analysis of 1 MW Solar PV plant
Financial analysis of 1 MW Solar PV plant
 
PV solar Design and Installtion
PV solar Design and InstalltionPV solar Design and Installtion
PV solar Design and Installtion
 
Photovoltaic Training - Session 4 - Plant Maintenance
Photovoltaic Training - Session 4 - Plant MaintenancePhotovoltaic Training - Session 4 - Plant Maintenance
Photovoltaic Training - Session 4 - Plant Maintenance
 
Study of Large Scale Grid interactive Solar PV power plant
Study of Large Scale Grid interactive Solar PV power plantStudy of Large Scale Grid interactive Solar PV power plant
Study of Large Scale Grid interactive Solar PV power plant
 
10 mw solar power plant
10 mw solar power plant10 mw solar power plant
10 mw solar power plant
 
Engineering Drawings required for Solar Projects
Engineering Drawings required for Solar Projects Engineering Drawings required for Solar Projects
Engineering Drawings required for Solar Projects
 
Solar Training 20100208
Solar Training 20100208Solar Training 20100208
Solar Training 20100208
 
Solar Panel Installation Proposal PowerPoint Presentation Slides
Solar Panel Installation Proposal PowerPoint Presentation SlidesSolar Panel Installation Proposal PowerPoint Presentation Slides
Solar Panel Installation Proposal PowerPoint Presentation Slides
 
Solar Power Plant System Sizing
Solar Power Plant System SizingSolar Power Plant System Sizing
Solar Power Plant System Sizing
 
Jakson_report_Final
Jakson_report_FinalJakson_report_Final
Jakson_report_Final
 
Photovoltaic Training - Session 1 - Design
Photovoltaic Training - Session 1 - DesignPhotovoltaic Training - Session 1 - Design
Photovoltaic Training - Session 1 - Design
 
Solar Project Management
Solar Project ManagementSolar Project Management
Solar Project Management
 
Proposal for a 2MW fspv system and e-transport
Proposal for a 2MW fspv system and e-transportProposal for a 2MW fspv system and e-transport
Proposal for a 2MW fspv system and e-transport
 
Solar Panel Installation And Maintenance PowerPoint Presentation Slides
Solar Panel Installation And Maintenance PowerPoint Presentation SlidesSolar Panel Installation And Maintenance PowerPoint Presentation Slides
Solar Panel Installation And Maintenance PowerPoint Presentation Slides
 
Photovoltaic Training Course - Module 2.7 - Commissioning tests
Photovoltaic Training Course - Module 2.7 - Commissioning testsPhotovoltaic Training Course - Module 2.7 - Commissioning tests
Photovoltaic Training Course - Module 2.7 - Commissioning tests
 
1 MW solar Power plant project Scheduling and Tracking
1 MW solar Power plant project Scheduling and Tracking1 MW solar Power plant project Scheduling and Tracking
1 MW solar Power plant project Scheduling and Tracking
 
Ppt on design of solar photovoltaic generation for residential building
Ppt on design of solar photovoltaic generation for residential buildingPpt on design of solar photovoltaic generation for residential building
Ppt on design of solar photovoltaic generation for residential building
 

Ähnlich wie A Report on solar power plant installation

25 KWp SOLAR POWER PLANT IN BIET
25 KWp SOLAR POWER PLANT IN BIET25 KWp SOLAR POWER PLANT IN BIET
25 KWp SOLAR POWER PLANT IN BIETsuraj chowdhury
 
DPR - 500KWp Solar PV Grid Connected Plant for CUJ june 2023.pdf
DPR - 500KWp Solar PV Grid Connected Plant for CUJ june 2023.pdfDPR - 500KWp Solar PV Grid Connected Plant for CUJ june 2023.pdf
DPR - 500KWp Solar PV Grid Connected Plant for CUJ june 2023.pdfsmsksolar
 
Solar_IT_03_101.pdf
Solar_IT_03_101.pdfSolar_IT_03_101.pdf
Solar_IT_03_101.pdfAntyMouda
 
Masterpact innovations.ppt
Masterpact innovations.pptMasterpact innovations.ppt
Masterpact innovations.pptelninoes1
 
Solar PV Codes and Standards
Solar PV Codes and StandardsSolar PV Codes and Standards
Solar PV Codes and StandardsSolarReference
 
Bergh 42.585 KW Planset - Final
Bergh 42.585 KW Planset - FinalBergh 42.585 KW Planset - Final
Bergh 42.585 KW Planset - FinalDavid Hults
 
SOLAR BASED WATER PUMP EMPLOYING Z -SOURCE INVERTER
SOLAR BASED WATER PUMP EMPLOYING Z -SOURCE INVERTERSOLAR BASED WATER PUMP EMPLOYING Z -SOURCE INVERTER
SOLAR BASED WATER PUMP EMPLOYING Z -SOURCE INVERTERIRJET Journal
 
Grid-Connected Solar Microinverter Reference Design Webinar.pdf
Grid-Connected Solar Microinverter Reference Design Webinar.pdfGrid-Connected Solar Microinverter Reference Design Webinar.pdf
Grid-Connected Solar Microinverter Reference Design Webinar.pdflequanqthuan
 
Solar PV Codes and Standards
Solar PV Codes and StandardsSolar PV Codes and Standards
Solar PV Codes and StandardsSolar Reference
 
Iaetsd design, engineerning and analysis
Iaetsd design, engineerning and analysisIaetsd design, engineerning and analysis
Iaetsd design, engineerning and analysisIaetsd Iaetsd
 
Nidec asi wind farm applications
Nidec asi wind farm applicationsNidec asi wind farm applications
Nidec asi wind farm applicationsNidec Corporation
 
1500V String Inverter Utility PV System Solution 2021.pdf
1500V String Inverter Utility PV System Solution 2021.pdf1500V String Inverter Utility PV System Solution 2021.pdf
1500V String Inverter Utility PV System Solution 2021.pdfgoangagoanga99
 
Fuji thiet bi dien-elcbfuji-160413044256 dienhathe.org
Fuji thiet bi dien-elcbfuji-160413044256 dienhathe.orgFuji thiet bi dien-elcbfuji-160413044256 dienhathe.org
Fuji thiet bi dien-elcbfuji-160413044256 dienhathe.orgDien Ha The
 
Fuji thiet bi dien-elcbfuji-160413044256
Fuji thiet bi dien-elcbfuji-160413044256Fuji thiet bi dien-elcbfuji-160413044256
Fuji thiet bi dien-elcbfuji-160413044256Thuan Kieu
 
Design, Test and Demonstration of Saturable- Core Reactor HTS Fault Current L...
Design, Test and Demonstration of Saturable- Core Reactor HTS Fault Current L...Design, Test and Demonstration of Saturable- Core Reactor HTS Fault Current L...
Design, Test and Demonstration of Saturable- Core Reactor HTS Fault Current L...Franco Moriconi
 
Final Report -Group-41
Final Report -Group-41Final Report -Group-41
Final Report -Group-41Habib Ali Khan
 

Ähnlich wie A Report on solar power plant installation (20)

ABB 太阳能解决方案_ENG
ABB 太阳能解决方案_ENGABB 太阳能解决方案_ENG
ABB 太阳能解决方案_ENG
 
25 KWp SOLAR POWER PLANT IN BIET
25 KWp SOLAR POWER PLANT IN BIET25 KWp SOLAR POWER PLANT IN BIET
25 KWp SOLAR POWER PLANT IN BIET
 
DPR - 500KWp Solar PV Grid Connected Plant for CUJ june 2023.pdf
DPR - 500KWp Solar PV Grid Connected Plant for CUJ june 2023.pdfDPR - 500KWp Solar PV Grid Connected Plant for CUJ june 2023.pdf
DPR - 500KWp Solar PV Grid Connected Plant for CUJ june 2023.pdf
 
Solar_IT_03_101.pdf
Solar_IT_03_101.pdfSolar_IT_03_101.pdf
Solar_IT_03_101.pdf
 
Masterpact innovations.ppt
Masterpact innovations.pptMasterpact innovations.ppt
Masterpact innovations.ppt
 
Report training 2012
Report training 2012Report training 2012
Report training 2012
 
Solar PV Codes and Standards
Solar PV Codes and StandardsSolar PV Codes and Standards
Solar PV Codes and Standards
 
Bergh 42.585 KW Planset - Final
Bergh 42.585 KW Planset - FinalBergh 42.585 KW Planset - Final
Bergh 42.585 KW Planset - Final
 
SOLAR BASED WATER PUMP EMPLOYING Z -SOURCE INVERTER
SOLAR BASED WATER PUMP EMPLOYING Z -SOURCE INVERTERSOLAR BASED WATER PUMP EMPLOYING Z -SOURCE INVERTER
SOLAR BASED WATER PUMP EMPLOYING Z -SOURCE INVERTER
 
Grid-Connected Solar Microinverter Reference Design Webinar.pdf
Grid-Connected Solar Microinverter Reference Design Webinar.pdfGrid-Connected Solar Microinverter Reference Design Webinar.pdf
Grid-Connected Solar Microinverter Reference Design Webinar.pdf
 
Solar PV Codes and Standards
Solar PV Codes and StandardsSolar PV Codes and Standards
Solar PV Codes and Standards
 
07 - ELCB - Fuji Electric
07 - ELCB - Fuji Electric07 - ELCB - Fuji Electric
07 - ELCB - Fuji Electric
 
Iaetsd design, engineerning and analysis
Iaetsd design, engineerning and analysisIaetsd design, engineerning and analysis
Iaetsd design, engineerning and analysis
 
Nidec asi wind farm applications
Nidec asi wind farm applicationsNidec asi wind farm applications
Nidec asi wind farm applications
 
1500V String Inverter Utility PV System Solution 2021.pdf
1500V String Inverter Utility PV System Solution 2021.pdf1500V String Inverter Utility PV System Solution 2021.pdf
1500V String Inverter Utility PV System Solution 2021.pdf
 
Fuji thiet bi dien-elcbfuji-160413044256 dienhathe.org
Fuji thiet bi dien-elcbfuji-160413044256 dienhathe.orgFuji thiet bi dien-elcbfuji-160413044256 dienhathe.org
Fuji thiet bi dien-elcbfuji-160413044256 dienhathe.org
 
Fuji thiet bi dien-elcbfuji-160413044256
Fuji thiet bi dien-elcbfuji-160413044256Fuji thiet bi dien-elcbfuji-160413044256
Fuji thiet bi dien-elcbfuji-160413044256
 
Design, Test and Demonstration of Saturable- Core Reactor HTS Fault Current L...
Design, Test and Demonstration of Saturable- Core Reactor HTS Fault Current L...Design, Test and Demonstration of Saturable- Core Reactor HTS Fault Current L...
Design, Test and Demonstration of Saturable- Core Reactor HTS Fault Current L...
 
Suntech 300w solar panel
Suntech 300w solar panelSuntech 300w solar panel
Suntech 300w solar panel
 
Final Report -Group-41
Final Report -Group-41Final Report -Group-41
Final Report -Group-41
 

Mehr von Amitesh Kumar

Phoebus energie leaflet
Phoebus energie leaflet Phoebus energie leaflet
Phoebus energie leaflet Amitesh Kumar
 
Automation of cstr using microcontroller gp11
Automation of cstr using microcontroller gp11Automation of cstr using microcontroller gp11
Automation of cstr using microcontroller gp11Amitesh Kumar
 
Industrial instrumentation
Industrial instrumentationIndustrial instrumentation
Industrial instrumentationAmitesh Kumar
 
Presentation on inplant training and instrumentation in bhel
Presentation on inplant training and instrumentation in bhelPresentation on inplant training and instrumentation in bhel
Presentation on inplant training and instrumentation in bhelAmitesh Kumar
 

Mehr von Amitesh Kumar (6)

Phoebus energie leaflet
Phoebus energie leaflet Phoebus energie leaflet
Phoebus energie leaflet
 
Solar radiation -
Solar radiation - Solar radiation -
Solar radiation -
 
Automation of cstr using microcontroller gp11
Automation of cstr using microcontroller gp11Automation of cstr using microcontroller gp11
Automation of cstr using microcontroller gp11
 
Industrial instrumentation
Industrial instrumentationIndustrial instrumentation
Industrial instrumentation
 
Presentation on inplant training and instrumentation in bhel
Presentation on inplant training and instrumentation in bhelPresentation on inplant training and instrumentation in bhel
Presentation on inplant training and instrumentation in bhel
 
Heat exchanger
Heat exchangerHeat exchanger
Heat exchanger
 

Kürzlich hochgeladen

Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)simmis5
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdfankushspencer015
 
Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfRagavanV2
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . pptDineshKumar4165
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdfKamal Acharya
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VDineshKumar4165
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfKamal Acharya
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756dollysharma2066
 

Kürzlich hochgeladen (20)

Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 
Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdf
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 

A Report on solar power plant installation

  • 1. A REPORT ON VISIT TO NATIONAL BUILDING CONSTRUCTION CORPORATION LTD. ON – GRID SOLAR POWER PLANT OF 10KWp PREPARED BY: AMITESH KUMAR
  • 2. VISIT TO NBCC ON-GRID 10KWp SOLAR POWER PLANT | Amitesh DATE: 11 NOV 2014 Site Name: National Buildings Construction Corporation Ltd. (NBCC) Ghitorni, New Delhi – 110003 Latitude: 29º01' Degree North Longitude: 77º38' Degree East Figure: 1 Side View of the plant Installed at NBCC, Ghitorni having a capacity of 10KWp The installation of on-grid solar power plant at NBCC, Ghitorni has a capacity of 10KWp. It is a fixed installation facing towards south and an installation angle (β) of 30ᵒ. Electrical Specifications: Module PM – 170. No. of modules in Series – 20. Parallel Combination – 3. No. of FJB – 3. Module wire – 1x4 Sq.mm. Conduit Wiring – P.V.C conduit 32mm. Civil foundation - Angle Bar – 50x50x6 (structure and legs) Pile – 1x1 Foot. Data Obtained From Inverter Display at 1:20 PM DC Side V (Volt) I (Amps) V (Volt) I (Amps) String 1 617 6.4 To Grid 241 8.1 String 2 598 3.0 String 3
  • 3. VISIT TO NBCC ON-GRID 10KWp SOLAR POWER PLANT | Amitesh Balance of System (BOS) Described: 1. SPV ARRAY The SPV array of 10 KWp capacity consist of 60no. Of modules of PM160 wired in 20 series- 3 parallel configuration. The modules shall be fixed on corrosion resistantMS structures. The SPV module has 72 number of crystalline silicon solar cells connected in series and hermetically sealed with high transmission toughened glass on top and suitable lamination material on back using state-of-the-art technology. The laminates are framed using anodized aluminum channels. A terminal block is fixed on the frames for taking the electrical output. The SPV array is grouted on Galvanized MS support structure on the ground near the buildings. 2. INVERTER The SUNNY TRIPOWER solar inverters characterize the technology and are optimally suitable for use in small and mid-range systems. These inverters have first class efficiency, user-friendliness and reliability and come with innovative technologies such as OptiTrac and H5-Topology. These make the device even more efficient and therefore ensure a very good solar yield. Automatic grid voltage detection and an integrated DC disconnect switch simplifies installation, ensuring safety as well as saving time. These models feature galvanic isolation and can be used with all types of modules. The die-cast aluminium enclosure, with the OptiCool active temperature management system, guarantees the highest yields possible and a long service life, even under extreme conditions. Figure: 1 Sunny TriPower Inverter (Left) & LCD Display (Right)
  • 4. VISIT TO NBCC ON-GRID 10KWp SOLAR POWER PLANT | Amitesh 3. GROUNDING OF THE SPV ARRAY All the non-current carrying panel structures are connected with the earth pit. Apart from this, all other non- current carrying metallic parts such as FJB and Inverter have also been earthed. Figure: 2 Interconnection between Structures for grounding (Left) & Earth Pit (Right) 4. SUPPORT STRUCTURES The modules are mounted on support structures fabricated from Mild steel, which are fixed on the ground as shown in the drawing. The structures are hot dip galvanized to make them non-corrosive and long lasting. Twelve Structures Carry 5 Modules each (Total Modules 60 Nos.). The structures are designed so as to withstand a horizontal wind speed of 150 KMPH. Figure: 3 Pile Single bolt foundation
  • 5. VISIT TO NBCC ON-GRID 10KWp SOLAR POWER PLANT | Amitesh 5. The technical specifications of the recommended SPV Plant are as follows: General SPV Module SPV Array Power (Total 10 KWp) Module type Crystalline silicon Module power PM160 (160Wp-170Wp) Inverter Rating 10KW Mounting Indoor inside control room (provided by Customer) No. of Inverters 1 Enclosures IP 20 Other accessories Cables BIS Copper Conductors Module mounting frame Galvanized MS frame 6. Module Data Sheet: SOLAR PV MODULE PM 160 ELECTRICAL PARAMETERS Maximum Power Rating (Wp) 160 Minimum Power Rating (Wp) 150 Rated Current Im (Amps) 4.45 Rated Voltage Vm (Volts) 36 Short Circuit Current Isc (Amps) 5.0 Open Circuit Voltage Voc (Volts) 44 PHYSICAL PARAMETERS
  • 6. VISIT TO NBCC ON-GRID 10KWp SOLAR POWER PLANT | Amitesh No. of Cells 72 Dimensions (approx.) 1580(L)x805(W)x42(T) Weight (Kg) 14.5 ENVIRONMENTAL RATINGS Nominal Operating Cell Temp.(C) 492 Max. Allowed Module Temp.(C) -40 to + 85 Max. Allowed System Voltage(V) 1000 RH at 85C 85 Temp. Coefficient of Isc +0.0004/K Temp. Coefficient of Voc -0.0034/K 7. Inverter Specifications SUNNY TRIPOWER 10000TL Input (DC) Output (AC) Max DC Power (@ Cos Ф= 1) 10200 Rated Power (@ 230 V, 50 Hz) 10000 W Max. Input voltage 1000 Max. Apparent AC power 10000VA MPP Voltage Range / Rated input voltage 320 V – 800 V / 600 V Nominal AC voltage range 160 V – 280 V Min. Input Voltage / Initial input voltage 150 A / 180 A AC power frequency / range 50 Hz, 60Hz / -6 Hz ... +5 Hz Max. Input Current Input A/ Input B 22 A / 11A Rated grid frequency / rated grid voltage 50 Hz / 230 V Max. Input Current Per String Input A/ Input B 33 A / 12.5 A Max. output current 16 A Number Of Independent MPP Inputs / Strings per MPP input 2 / A: 4; B: 1 Adjustable displacement factor 0.8 over exited ... 0.8 Under exited