Meester Corporation has an activity-based costing system with three activity cost pook- Machining. Order Filing, and Othec in the fist stage allocations, costs in the two overhead accounts, equipment depreciation and supervisory expense, are allocated to three octivily cost poots based on resource consumption. Data used in the first stage allocatlons follow: Distribution of Resoutce Consumption Across Activity Cost Poolis: Machining costs are assigned to products using machine hours (Mis) and Order Filling costs are asslgned to products using the nunber of ordeis. The costs in the Outher actlvity cost pool are not assigned to products. Activity data for the company's two products follow. Activity: What is the overhead cost assigned to Product H2 under actlvity based costing? (Round your intermediate colculations to 2 decimal places.) Multiple Choice $64.614$46,031$78,330$18,584.