This is a project management course topic . please help me A project's progress information on 20 June 2022 is given per table below. (2 p) By calculating Schedule Performance Indicator (SPI) which can be concluded? Select one alternative The project is on schedule The project is over 20% delayed The project is less than 10% delayed The project's delay is between 10% to 20%.